Professional Documents
Culture Documents
CHAPTER 8
What IflChecklist
What If
Preparation
Assemble drawings.
Assign nodes.
Prepare checklist.
Assemble Team
Explain process.
Commence Analysis
Add additional checklist items at the end of review of individual nodes.
9DYADEM
© 2003 by CRC Prcss LLC
What IflChecklist 8 -2
Advantages
Pitfalls
)DYADEM
© 2003 by CRC Prcss LLC
What IfIChecklist 8-3
Checklist
Available checklists, other data and your own experience may be used to create Checklists.
Failing that, or in addition, you can use the following to assist with the preparation:
1. What does the equipment actually do? In what ways can the equipment actually
fail?
2. What are the major hazards associated with the material being handled by the
equipment?
7. Could individual component failures, e.g., control valves, level switches, give
problems?
12. Are there adequate protective systems? If so, how about redundancy?
3 DYADEM
© 2003 by CRC Prcss LLC
What lflchecklist 8 -4
Power failure?
Iilstruinent air failure?
Cooling water failure?
Steam failure'?
Have effects of all of these been considered in relation to flare system
sizing?
Equipment isolation?
Drainage?
Venting?
Blinding?
Emergency interlocks?
16. Have you considered any special operations, e.g., yreszrlfiding, on-site cata1j)st
loading/unloading, on-site regeneratiorz, etc. ?
2 DYADEM
© 2003 by CRC Prcss LLC
What IflChecklist 8-5
The following are some general what if questions for the Furnace Oil Heater:
2 DYADEM
© 2003 by CRC Prcss LLC
What lflchecklist 8-6
2. Major Hazards
4. Control
a. What are the mitigation steps taken to reduce the effects of fire box explosion?
b. What are the mitigation steps taken to reduce the effects of tube rupture?
c. What are the mitigation steps taken to reduce the effects of vapor cloud
explosion?
6. Supporting Utilities
7 . Process Side
)DYADEM
© 2003 by CRC Prcss LLC
What IfIChecklist 8-7
a. Are there any controls to regulateldetect high pressure on tube side? Are they fail
safe?
b. Could heater be source of ignition for the vapor cloud release of flammable?
)DYADEM
© 2003 by CRC Prcss LLC
What lfichecklist 8-8
a. Are flow control valves fail safe on loss of actuating medium (e.g., instrument air
failure)?
e. If relief valve could plug or coke up, is a purge stream (e.g., steam) included?
j. Are there spectacle blinds provided at all process inlets and outlets?
1. Are there adequate highllow pressure alarms on fuel gas & pilot gas provided?
m. What if reverse flow into the firebox occurs in the event of tube failure?
o. If burner tip is plugged, could atomizing stream cause higher pressure than fuel?
r. What mitigation steps are taken to reduce the effects of tube rupture in the
furnace?
What If Example
Figure 8-1: P&ID of Ammonia Refrigeration Unit
2DYADEM
© 2003 by CRC Prcss LLC
What lflchecklist 8-10
), DYADEM
© 2003 by CRC Prcss LLC
What IfIChecklist 8-1 1
M 80.19 1.112 R M S.284 20.04 (LO73 847.3 0.0387 1.0746 38.00 0.39%
60 107.6 1.120 0.02587 &R1 81.28 2818.1 848.4 03814 18888 38.W O m
m 128.8 1.118 0.02634 2.812 4X.M 608.8 MIS 08848 1.0482 98.00 0.4325
80 1638 1.188 0.02683 1.868 M.08 4S8.7 56e.8 0.1041 1.0283 37.48 OH16
90 180.8 1.147 O.OPmt 1.881 66.66 488.6 664.1 0.12110 18188 35.W 0.6018
m& I 1 1 0~?668 I . . . . . 1 1
1 I
1857 ..... (886) 0 .... ..... ..... 14.6 ......
'Dttrhom~dS~CirCOL(IYn142 B w Te:- 32F.
(smThe (igutes m pclraattuui~swen calcu*tsd tm empirical equsths givsa in BWP Df S~lndardsScienMc ppan IDS.
313 sad 316 ad -dm
abtsinsd b l srtmpobtk k q w d lha nass caacsd In the ergshlatsl wwk.
2 DYADEM
© 2003 by CRC Prcss LLC
What lflchecklist 8-12
- --- -- --- -- - -- * - - -
- i *a
k
Operating ConditionsIParameters: 138 psig, 76°F
*:%eK~%f&W=%$&b*b,
SXb ?tYb> "&%L&WL%%&W\B~B%&
AS&?
%
i
$ m W ~ w ~ @ qP ~
$ a ~~ & ~ & +A@&*VL
?k ~ % s W% 6 5' 9%
What If Responsibilitie
S
, -- -- - -
I . Overfilling? Anna D
Nigel W
3. Pressure Steve L
exceeds design
specifications?
Anna D
9DYADEM
© 2003 by CRC Prcss LLC
What IfIChecklist 8-13
into condenser
do not result in
I
S / L RR
, -- ""-" -.-- - - - -
' i ,3--
"
2. Level too 2.1. LV-20 1 or 2.1. 1" 2.1. Level 3. Acc~uinulator / Geoff B
low? controller LC- Accumulator G a ~ ~ g e / should be large
20 1 tends to einpty (LG- 102) I enough to ensure the
malfunctioning fill1 contents of the
j receiver.
2.2. Damage to 1 16. Level Alann Low Geoff B
Piimp 1 (LAL- 201)
I
3. Pressure 3.1. Fire case 3.1. Release of 3.1. High 14. Ensure fire Steve L
exceeds design ammonia point vent monitors and
specifications? through relief 1
extinguishers are
system ; nearby
3.2. Some fire
hazard in
vicinity 15. Locate relief valve Anna D
1 vents in a safe
3.3. Hazard to ! location.
personnel in
vicinity
4. Level gauge 4. I. Physical
(LG- impact from
4.1. Hazard to
personnel in
4. I. None 1 6. Provide annor
plated level gauges
Nigel W
5. Low 5.1. 5.1. Steel can 5.1. None 8. Check need for Geoff B
temperature Depressuring to shatter if ' Charpee Tested
embrittlement? atmosphere on ~mpactedby Carbon Steel
pressure let wrench I
--- - - -- * I
down during
5.2. Hazard to I
inaintenance i
personnel in
. . . I
r " -
6. Toxic or 6. I. Release 6.1. Hazard to 6.1. None i 9. Self contalned Nigel W
hazardous from joints or personnel in 1 breathing apparatus
" - -
' service? flanges during vicinity
- *
maintenance
1 10. Biiddy system Nigel W
' 1 1. Develop Anna D
/1 operational
procedures
" " -
1
Recommendation Drawing
Is
Establish operational procedures for inventory control of ammonia ARU-A 1
Design to ensure that inventories of ammonia in receiver and accumulator plus piping are ARU-A 1
compatible and do not result in flooding.
(Accumulator should be large enough to ensure the full contents of the receiver. I MU-A 1
4. 1 Ensure fire monitors and extinguishers are nearby I ARU-A 1
Locate relief valve vents in a safe location.
Provide armor plated level gauges IARu-A 1
No action required.
Install high-limit stops on all control valves: TV-301, 302, FV 30 1,302 ARU-
A1
Operating procedure for setting temperature controls TIC-301, 302
9DYADEM
© 2003 by CRC Prcss LLC
SUGGESTED READING (URLs current at time of publication)
"Guidelines for Hazard Evaluation Procedures" by AIChE, CCPS, 2'Id edition, 1992 plus
"Guidelines for Hazard Evaluation Procedures" by AIChE, CCPS, 1st edition, 1985
www.aiche.or~!pubcat/~eac1tl.as~~'!Act=C~&C~ate.~ory=S~ct3&Mi1i=20
"Use 'What i f method for process hazard analysis" by L.Zoller, J.P.Esping, Hydrocarbon
Processing, January 1993, pages 132-B to 1 32-G
www.hvdl~ocurbonprocessing.com/co~itents
'pub1 ications::'hpi
"Speed Your Hazard Analysis with the Focused What If?" by L.Goodman, Chemical
Engineering Progress, July 1996, pages 75 to 79
www.cepniagazinc.org/
"Process Safety Review Checklist", University of Florida, (Website)
t l~caltli/~~rocess
I~tt~:!lpie.cl~e.ii~l.ed~1/g~1i~1~~~s;~f checklist.html
"Process Hazards Analysis" by I.Sutton, published by SWISutton & Associates, 2002
prlia.slltml
ht tp://www.swbooks.cc~~n~!L~ooks/bool
)
,, DYADEM
© 2003 by CRC Prcss LLC