You are on page 1of 7

case updates

Engineer’s non-final decision of considerable concern and notwithstanding the possibility


enforced by unanimous ICC uncertainty under both pre-arbitral that at the end they may be revised
arbitral award procedures has been what value, if any, or set aside in arbitration or by a
is to be given to the binding decision of further agreement to the contrary,
Christopher R Seppälä
an Engineer or a DAB? If such decision there is no reason why in the
White & Case LLP, Paris is not respected, are there any means face of such a breach the arbitral
by which it can be enforced? tribunal should refrain from an
An ICC arbitral tribunal, in an interim
The recently-published ICC immediate judgment giving the
award in ICC Case No 10619 (see
award referred to above expressly Engineer’s decisions their full
(2008) 19(2) ICC Int’l Ct of Arb Bull
addresses the issue and provides a force and effect. This simply is the
85-90), has unanimously decided that
most welcome solution. law of the contract.
an Engineer’s non‑final decision on a
By an interim award in ICC Case
dispute under Clause 67 of the FIDIC [Para 22, emphasis added]
No 10619, a tribunal of three
conditions of contract for works of
arbitrators, sitting in Paris, Thus, an arbitral tribunal may and,
civil engineering construction (the
unanimously held, at the request of when requested to do so, should
‘FIDIC Conditions’), fourth edition,
the claimant  (Contractor), that enforce decisions of the Engineer
1987 should be enforced by an
certain decisions of the Engineer under Clause  67 by an interim
arbitral award.
under the FIDIC Conditions, award under the ICC Rules ordering
Since the Dispute Adjudication
fourth edition, 1987 which awarded the other party immediately to pay
Board (DAB) has replaced the
sums to the claimant  Contractor, their amount even though one or
Engineer as a decider of disputes
could be enforced by such an award both parties have given a notice of
under the current (1999) editions
under the ICC Rules of Arbitration, intention to commence arbitration
of the FIDIC forms of contract for
even though one of the parties (the with respect to them.
major works (the ‘1999 FIDIC
claimant  Contractor, in fact, who As, in this case, one of the parties
Books’), the author can see no
was seeking to enforce the had given such a notice of intention
reason why the same principle
decisions) had given a notice of to commence arbitration, the
should not apply to a non-final
intention to commence arbitration dispositive section of the interim
decision of a DAB under the
with respect to the decisions. award expressly reserved the rights
current editions.
The arbitrators held that such of the parties as to the merits of the
The ICC arbitral tribunal’s
decisions can be given effect to by case until the tribunal’s final award.
decision is briefly described below.
such an interim award – which, under In this author’s view, the tribunal’s
As readers of Construction Law
the ICC Rules, is final as to the matters approach is entirely consistent with
International will know, FIDIC
decided  – because Clause  67 of the the way Clause  67 of the FIDIC
construction contracts before
FIDIC Conditions expressly provides Conditions was intended to operate.
publication of the 1999 FIDIC
that a decision of the Engineer under ICC arbitral tribunals had
Books provided for the referral of
that Clause is binding on the parties previously ordered payment of
disputes between the Contractor
notwithstanding that either or both ‘final and binding’ decisions of the
and the Employer to the Engineer
of them have given a notice of Engineer under Clause  67 of the
for decision and that, only if a party
intention to commence arbitration. FIDIC Conditions, second edition
expressed dissatisfaction with the
In this connection, the second (1969), that is, decisions which had
decision, in a specified way, could
paragraph of Sub‑Clause  67.1 not been the subject of any notice
the dispute be referred to
provides: of intention to commence
arbitration. Unless and until
‘… the Contractor and the arbitration within the contractually
revised in arbitration (or by an
Employer shall give effect stipulated time limit (90 days under
amicable settlement), that decision
forthwith to every such decision the second edition) at all (see ICC
was deemed to be binding on the
of the Engineer unless and Case Nos. 3790/3902/4050/4051/
parties and, thus, settled the matter
until the same shall be revised, 4054 (joined cases), summarised in
provisionally at least.
as hereinafter provided, in an Abdul Hamid El‑Ahdab, Arbitration
In the 1999 FIDIC Books, FIDIC
amicable settlement or an arbitral with the Arab Countries (Kluwer,
replaced the Engineer as the
award.’ Deventer, 1990) at 889‑891).
decider of disputes by a DAB. But
However, the interim award in Case
otherwise the pre-arbitral procedure The tribunal stated as follows:
No 10619 is the first example of a
for the settlement of disputes is ‘If the above Engineer’s decisions
published award of which this
essentially unchanged. have an immediate binding
author is aware where an arbitral
However, as construction effect on the parties so that the
tribunal has ordered payment by
arbitrations frequently take several mere fact that any party does
an interim award of the amount of
years and are often not even begun not comply with them forthwith
an Engineer’s decision which is
until near the end of a project, an issue is deemed a breach of contract,
‘binding’ but not ‘final’; that is,

26 Construction Law International Volume 4 No 3 September 2009


which had been challenged, within Twenty-six minutes late Important points raised by the
the contractually stipulated time tender was properly rejected judgment include the following.
period, by one or other or both of
Rupert Choat and Siobhan Costello
the parties.
Equal treatment/ rectifying
The same result should obtain, CMS Cameron McKenna LLP, London
errors
the author submits, in the case of a
In J B Leadbitter & Co Ltd v Devon
decision of a DAB under Clause 20 The ITT provided that tenderers
County Council [2009] EWHC
of the 1999 FIDIC Books as the would be given an opportunity,
930 (Ch) [2009] CILL 2713, a
arbitral tribunal in Case No 10619 after the deadline, to rectify errors
judgment delivered on 1 May
found applies in the case of a in tenders which were submitted
2009, the English High Court
decision of the Engineer under before the deadline and accepted
decided that a contracting entity
Clause 67 of the FIDIC Conditions, by Devon CC. While the claimant
for the purposes of the public
fourth edition. This should be so accepted it did not submit its entire
procurement rules was entitled
because the relevant language of tender before the deadline, it
to reject a tender for a framework
Clause  67 of the fourth edition argued that Devon CC should have
agreement where part of the
(quoted above) and of Clause 20 of waived strict compliance with the
tender was submitted 26 minutes
the 1999 FIDIC Books is to the ITT and allowed it to correct its
late. The Cour t decided this
same effect. Sub‑Clause 20.4 of the error (by submitting the case studies
was neither disproportionate
1999 FIDIC Books provides as after the deadline so the tender
nor was it unequal treatment or
follows: would not be rejected). It argued
discrimination. The judgment
‘The decision [of a DAB] shall be that not permitting this would
gives important guidance
binding on both Parties, who shall constitute unequal treatment and
on the application of tender
promptly give effect to it unless discrimination against it.
rules, particularly timing, and
and until it shall be revised in an The Court disagreed. The Court
also considers the viability of
amicable settlement or an arbitral did not find that the failure to
proportionality arguments in
award as described below.’ include the case studies was an
procurement challenges.
‘error’ as provided for in the ITT;
Accordingly, even if one or both The tender in question required
rather, the claimant’s tender was
parties have given a notice of at least four case studies to be
substantially incomplete. The
dissatisfaction (which is equivalent to submitted as part of the tender.
Court’s view was that this part of
the notice of intention to commence The invitation to tender (ITT)
the ITT neither obviated the need
arbitration under the fourth clearly stated that each tenderer
to submit a complete tender nor
edition of the FIDIC Conditions) would have only one opportunity
did it provide a means by which
with respect to a decision of a to submit documents to the
tenderers could supply substantial
DAB, each party is bound to give contracting authority’s portal (and
documents or substantial sections
effect to that decision (unless and thereby submit its bid). The tender
of documents after the deadline so
until overturned by a subsequent documentation also clearly stated
as to complete tenders. Devon CC’s
amicable settlement or arbitral the remaining tender rules.
failure to waive strict compliance
award) and, if that decision calls, for The claimant, J B Leadbitter &
with the ITT was applied equally to
example, for a payment to be made Co Ltd, submitted its tender before
all tenderers. Indeed, the Court’s
by one party to the other, then that the 1500 hrs deadline on the
opinion was that a waiver of terms
decision may be enforced directly relevant date, but before 1500 it
which are stated as applying
by an interim award pursuant to the realised it had failed to include the
without exception carries the very
ICC Rules of Arbitration. That is the case studies with the rest of its
risks of unequal treatment,
logical conclusion to draw from the tender. It then attempted to submit
discrimination and a lack of
interim award in Case No. 10619. the case studies to the portal before
transparency which the contracting
1500 but was unable to do so as the
authority is required to avoid.
system only permitted one loading
of documents by each tenderer
Christopher R Seppälä is a Partner in and the claimant was now on its Proportionality
White & Case LLP, Paris, and Legal Advisor second attempt. The claimant then
to the FIDIC Contracts Committee. A The claimant further alleged that,
e-mailed the case studies at 1526
shorter version of this article was first as a general principle of European
(ie, 26 minutes after the deadline).
published in Global Arbitration Review in Community law, Devon CC owed an
The contracting authority (Devon
June 2009. An article discussing the obligation to act proportionately in
interim award in ICC Case No 10619 in County Council) rejected the
the treatment of the tender and,
detail will be published in The International claimant’s tender on the basis that
in not doing so, it was in breach
Construction Law Review later in 2009. it had not submitted a complete
of this obligation. Proportionality
tender by the deadline.

Construction Law International Volume 4 No 3 September 2009 27


case updates

involves an authority (1) acting to a time where there are signs of clause) is a common feature in many
suit the purpose of their powers; an increasing number of tender standard form contracts used in
(2) achieving that purpose by means challenges in the UK. This increase the construction and engineering
least burdensome to those affected; may be due to a combination of two industry, such as the appointment
and (3) imposing burdens that are things: first, short-term financial of an architect or an engineer
proportionate to the intended goal. need outweighing the fear for some published by RIBA or ACE, for
The Court found that the of disputing tenders and, secondly, example.
principle of proportionality is accelerated public spending on If there is a problem with a
capable of applying to the projects that risks breaching construction project resulting in a
implementation of a procurement procurement rules (although there loss, this may well be the fault of
process (as well as the selection of are reports that this is stuttering in more than one of the parties
tender criteria). However, the some areas). designing or constructing the
Court made clear that it will not Expect further cases in this project. The party suffering the
intervene on this point unless the developing area. No one involved in loss can sue any of the parties at
decision is unjustifiable. Authorities the procurement of public projects fault and each will be 100 per cent
have a ‘margin of appreciation’ to can afford to be left behind. liable for damages, whatever their
act proportionately (unlike for share of the blame. A net
breaches of the equal treatment, Rupert Choat is an Partner and Solicitor
contribution clause tries to change
non-discrimination and Advocate and Siobhan Costello an this position – it generally states
transparency requirements) so that Associate with CMS Cameron McKenna that the liability of each party will
the court will only disturb an LLP, based in London. This note originally be limited to the amount which
authority’s decision where it has appeared on www.law-now.com. would be apportioned to that party
committed a ‘manifest error’. Reproduced by permission. by a court and/or which it is just
In this case, the Court found that and reasonable for them to pay.
the ITT could not have been Instead of the party who suffered
clearer on the requirement for a the loss suing one party at fault,
The first UK court decision
single upload and submission and leaving it to them to claim
on net contribution clauses
before the deadline – the against any other people jointly
implication being that Devon CC’s Emmanuel Ninos liable, a net contribution clause
decision to reject the claimant’s also puts the onus on the party who
Shadbolt LLP, London
tender was justifiable and it did not has suffered a loss and who wishes
act disproportionately in doing so. The recent Scottish Court of Session to recoup all of its losses to claim
case of Langstane v Riverside & Others against all parties potentially at
[2009] CSOH 52 is the first case in fault.
Acceptance of late submissions
the UK to question whether net It has in the past been argued
The Court noted the lack of clarity contribution clauses are effective. that where a net contribution
in this area. It went on to state that The case looked specifically at clause is included in a standard
there may be circumstances where whether a Housing Association form contract the ‘reasonableness
proportionality will, exceptionally, (Langstane) had appointed a test’ found in the Unfair Contract
require the acceptance of late consulting engineer (Ramsay & Terms Act 1977 would apply,
submission of the whole or Chalmers, who were the second resulting in the net contribution
significant portions of a tender, defendant) on the ACE conditions clause being rendered invalid. This
most obviously where it results from and, if so, which version (1988 or case considered that argument.
fault on the part of the procuring 1998). The distinction is important,
authority. But, in general, even if as the 1998 version contains a net
The facts of the case
there is a discretion to accept late contribution clause. The Court
submissions, there is no requirement found, on the facts, that Ramsay Langstane was seeking to recover
to do so, particularly where, as in was appointed on the 1998 version from Ramsay losses suffered as a
this case, it results from a fault on – so the Court then turned to look result of the partial collapse of a
the part of the tenderer. at the applicability of the net property on which Ramsay had been
contribution clause itself. involved in renovation works and
which arose from an alleged breach
Conclusion
of contract and/or negligence. The
What is a net contribution
Proportionality may provide fertile net contribution clause purported to
clause?
ground for challenging authorities’ restrict the damages that Langstane
selection of tender criteria and A net contribution clause (also could recover from Ramsay.
their implementation. This is at known as a proportional liability

28 Construction Law International Volume 4 No 3 September 2009


Langstane sought to establish and the relevant clause of the Act of English law – in the past
that the Unfair Contract Terms Act did not apply. Parliament itself has reviewed the
1977 (the Act) applied to the The decisions reached on the above principle and declined to amend it
contract, and so the net two points meant that the Court did – and this Scottish case does not
contribution clause was itself not have to decide whether the net over-ride Parliament. The decision
subject to the terms of the Act. If contribution clause was fair and may represent a persuasive
the Act applied, the clause could reasonable in the circumstances. authority for the English courts,
potentially be excluded from the However, the Court said (obiter) but we do not know what decision
contract. that they would hold the clause to they would reach in similar
In trying to establish this, a be fair and reasonable in any event. circumstances.
number of points were looked at, The reasons given for this were If a party contracts on its own
of which the following are the most threefold: individual standard terms, which
pertinent: 1) Although such clauses have incorporate a net contribution
• If the net contribution clause attracted controversy, this has clause, then it will be much harder
was shown to exclude or restrict not stopped them being used. to argue that the Act does not
liability then under clause 2) Langstane had shown willingness apply. As such, the party will have
16 of the Act the term would to contract on the basis of the to prove that the clause is fair and
have no effect if it was not fair ACE conditions. reasonable in all the circumstances.
and reasonable to incorporate 3) Also, importantly, it was open to Do not assume that net
the ter m into the contract. Langstane to ensure that proper contribution clauses drafted by
So, did the clause exclude or insurance was in place in the ACE, RIBA or similar professional
restrict the liability of Ramsay? event that one or more of the bodies are appropriate in all cases
Unsurprisingly, Langstane said it contractors or consultants was in – there will be projects where such
did, and Ramsay said it did not. breach of contract or duty. If clauses should be amended or
Ramsay said it simply sought to such insurance is in place, then struck out, in order to represent a
ensure that they were only held it should be possible in the event fair balance between the parties.
liable for the consequences of of insolvency of the contractor In any event, it is good practice
their own breaches of duty and or consultant to go against the for all parties in a project (but
were not held liable (under the insurer. The Court saw nothing particularly a client) to consider
principle of joint and several unfair or unreasonable in the what would happen if one member
liability) for breaches of duty by client taking a risk that it had of the professional team were to
other contractors and consultants. adequately covered itself against enter insolvency, and check
The Court agreed with Ramsay. the possible insolvency of those whether appropriate insurance is
• The Court also had to consider whom it had itself appointed. in place.
whether the parties were dealing
on the basis of Ramsay’s written Emmanuel Ninos is an Associate at
Practical points
standard terms of business. If Shadbolt LLP, London. This article was
they were, then under clause 17 This case was decided on its originally published on www.lexology.
of the Act any term would have no particular facts – it does not establish com. Reproduced by permission.
effect for the purpose of enabling generally accepted principles. The
a party to the contract who is in judge was specifically addressing the
breach of a contractual obligation question of whether the clause was
EU/UK procurement – the
to exclude or restrict any of its so unreasonable as to fall foul of the
three month rule
liability to the ‘customer’ in Act. The judgment has already come
respect of that breach, if it was not in for some criticism, and should Jeremy Glover
fair and reasonable to incorporate not be taken as judicial approval
Fenwick Elliott LLP, London
the terms in the contract. of net contribution clauses in all
• The Court agreed with the circumstances. It is well known that claims brought
argument put forward by Ramsay You may, however, find that for a breach of the 2006 Public
that this clause did not apply people refer to this case to bolster Contracts Regulations must be
because they were not dealing on arguments for the inclusion of a made within a tight three month
their standard terms of business net contribution clause – in fact, time limit. There have been two
– the terms were drafted and the ACE itself does just that in its recent cases, Brent London Borough
promulgated by the ACE and new suite of appointments. We do Council v Risk Management Partners
used widely within the profession. need to remember that this is not Ltd [2009] EWCA Civ 490 and
• This meant that Langstane was really justified. Joint and several Amar yllis v HM Treasur y [2009]
not a ‘customer’ under the Act, liability is an established principle EWHC 962 (TCC) which have

Construction Law International Volume 4 No 3 September 2009 29


case updates

considered this principle. authority must follow before (vii) On 7 March 2007 a repre-
Regulation 47(7) makes it clear entering into a contract with a sentative of Brent told RMP,
that there is a two step process: supplier of goods or services... informally, that Brent’s
‘(7) Proceedings under this It follows that a failure by the insurance would be dealt with
regulation must not be brought contracting authority to comply through LAML. In response
unless – with any step in the required RMP looked at Brent’s website
procedure involves a breach and located the decision of 13
(a) the economic operator
of duty sufficient to support a November 2006;
bringing the proceedings has
claim under the Regulations. (viii) RMP sought formal con-
informed the contracting
Moreover, because the procedure firmation by letter of 19 March
authority... of the breach or
governs the whole process from 2007, and received it by letter
apprehended breach of the duty
the formation of the intention from Brent of 27 March;
owed to it… and of its intention
to procure goods or services to (ix) Brent made payments to LAML
to bring proceedings under this
the award of the contract and is from 16 March onwards;
regulation in respect of it; and
structured in a way that is intended (x) By letter of 4 May 2007 RMP’s
(b) those proceedings are brought to ensure equal treatment and solicitors raised with Brent
promptly and in any event within transparency throughout, a failure the question of breach of the
3 months from the date when the to comply with the procedure at regulations;
grounds for the bringing of the any stage inevitably undermines (xi) Proceedings were begun on 6
proceedings first arose unless the the integrity of all that follows.’ June 2007.
court considers that there is good Brent submitted that grounds for
In doing so, he expressly recognised
reason for extending the period the bringing of proceedings first
the problem that whilst grounds for
within which the proceedings may arose in November 2006 when they
bringing proceedings may exist well
be brought.’ resolved to approve participation
before the procedure reaches the
in LAML or, alternatively, on 18
award of a contract, the Regulations
January 2007 when they became a
Brent London Borough Council v do not expressly identify the point at
member of LAML. Brent said that
Risk Management Partners Ltd which that will occur. The relevant
either time runs or it does not
chronology was as follows:
The Brent case came before the and a claimant cannot (if out of
(i) On 9 October 2006, Brent
English Court of Appeal. Here time from the date a breach has
resolved in principle to
RMP claimed that certain contracts been apprehended) improve his
participate in LAML;
of insurance had been awarded position by waiting for the actual
(ii) On 7 November 2006, the
by Brent Authority to the London breach to occur.
RMP were told by Brent’s
Mutual Ltd (LAML) outside of The judge at first instance,
brokers that Brent ‘had
a tender process in which they Stanley Burnton LJ, held that:
committed to going into the
participated. It is important to note ‘In my judgment, therefore, for
Mutual’ but that there was
that RMP were only making a claim the purposes of the Regulations
uncertainty whether it would
for damages. Among other issues, in the present case “grounds for
be ready by the next renewal
Brent said that the claims were the bringing of the proceedings”
date (1 April 2007) and there
started more than three months after first arose when the breach which
would be some insurance that
the date on which the grounds for forms the subject of the claim
would be sought outside it
bringing the proceedings first arose. occurred. It would have been
anyway. Accordingly there was
In particular, Brent submitted that different if the claim were for an
to be a full tender exercise;
grounds for bringing proceedings injunction to restrain a breach of
(iii) At a meeting on 13 November
existed (and that time therefore the Regulations; but it is not.
2006, Brent resolved to approve
started to run) in November 2006
participation in LAML; ‘It is therefore necessar y to
when RMP were told that Brent
(iv) In December 2006 Brent determine when the breach of
was obtaining insurance elsewhere.
invited tenders for cover the Regulations first occurred.
Proceedings were not commenced
generally from 1 April 2007; It seems to me it was when
until 6 June 2007. If Brent was right,
(v) On 18 January 2007, Brent the appellant abandoned the
RMP were well out of time.
began membership with LAML; tender process and awarded
Pill LJ noted that:
(vi) Because incorrect docu- the contracts to LAML. That
“When considering when grounds
mentation had been used, a occurred in March 2007. Until
for proceedings first arose it is
replacement invitation to then, it could have lawfully
necessary to bear in mind that
tender was issued on 1 February awarded the insurance contracts
the Regulations prescribe the
2007. RMP tendered in time; to a company participating in the
procedure which a contracting
LAML did not participate; tender process.’

30 Construction Law International Volume 4 No 3 September 2009


The Court of Appeal agreed. The explanation as to how and why and both Amaryllis’ intentions and
key here was the date when Brent Amaryllis had been unsuccessful. the actual breach complained of
abandoned the tendering process On 23 May 2008, Amaryllis said it were clearly identified. Finally, the
and made payments to LAML. would not be submitting a tender judge said that the adequacy of the
Only then were Brent committed for Lots 2–5 because it had no notice had to be considered against
to taking policies from LAML. confidence that any tender the backdrop of the (lack of)
Before March 2007, RMP had not submissions would be given a fair information provided by HMT.
sustained the damage which was and valid assessment. On 4 June Further, HMT said that Amaryllis
the basis of their claim. It may be 2008, Amaryllis indicated its did not act promptly. The judge
that RMP could earlier have made intentions to bring proceedings, said that the starting point is when
an application for interim relief but but again requested reasons as to the specific breach of the
that did not start time running on why the Lot 1 bid was rejected. regulations actually occurred. That
the claim actually made. Amaryllis were of the view that they will often be when the actual
In any event, in the view of the had to commence proceedings by decision is made to exclude a
Court of Appeal, there was good 16 June 2008, 3 months after they tenderer. However, here the
reason for extending the period received notice of their rejection grounds for bringing the
within which the proceedings on Lot 1. They duly did so even proceedings first arose when the
could have been brought, within though HMT had not provided any irrevocable decision was taken by
the meaning of regulation 47(7) response to the June letter. HMT to exclude Amaryllis on Lot
(b). As late as February 2007, Brent Amaryllis made a number of 1. Therefore, the relevant date was
issued an invitation to tender and, claims. First, it appeared that no the date on which HMT wrote to
late in the month, RMP submitted marks were allocated to section F inform Amaryllis that its bid had
a tender in response within time. which dealt with previous been unsuccessful, 17 March 2008.
Accordingly, Brent should not be experience when the tender Note too that the three month
allowed to defeat, on the ground of information stated that all sections period is intended to be a
delay, the claim brought by RMP at would be marked. Amaryllis also maximum period. Even if the
the time it was. complained that HMT had proceedings have been commenced
evaluated the responses without within that period, it is still
having informed any tenderer as to necessary for the court to consider
Amaryllis v HM Treasury
the relative importance ascribed to whether or not they have been
Here Amaryllis submitted a pre- each question – in particular, the commenced ‘promptly’. Therefore,
qualification questionnaire in importance and weighting to be here, even though proceedings
respect of a framework agreement given to the environmental were brought within the three
for the supply and installation of management issues. The judge month period, the judge had to
furniture on a national basis. The described this as being a bit like review what had actually happened.
agreement was to be divided into being required to do an exam Between 17 March and 22 April
six lots. Amar yllis was informed without knowing what marks were 2008, there was no culpable delay
by letter on 17 March 2008 that it available to any given question. on the part of Amaryllis. It
had come though the first stage on Finally, Amaryllis complained that received a letter at the start of
four of the lots. On 9 April 2008 it was given a zero under a business Easter week and a meeting was
there was a meeting between the heading on the basis that it brought arranged in the first full working
parties at which the question of in furniture rather than week after Easter. Amaryllis then
Amaryllis’s unsuccessful tender on manufacture it itself. wrote on 15 April 2008, receiving
Lot 1 was raised. Although there HMT said that Amaryllis were an inadequate answer on 22 April
was a considerable dispute as to not entitled to bring a claim 2008. HMT focused on the fact
the way in which the topic was because it had not provided notice that between 22 April 2008 and 4
raised, it appeared to Mr Justice of its intentions and had not June 2008, little, if anything,
Coulson to be ‘beyond argument’ brought its claim in time. As stated outwardly happened to progress
that Amaryllis wanted to know why above, under Regulation 47(7)(a) this matter. However, the judge
their bid on Lot 1 was unsuccessful of the Public Contracts Regulations disagreed that nothing relevant
and that HMT did not give them 2006, a party is required to provide happened during this period. The
very much information in response. written notice of the breach and its evidence was clear that Amaryllis
Amaryllis wrote to HMT on 15 April intentions to bring proceedings. was involved in making enquiries
2008 seeking an explanation. HMT Here, Mr Justice Coulson thought with other potential tenderers to
responded on 21 April 2008 in a that adequate notice was provided. try and piece together the possible
letter which the judge again felt The regulations were clearly reasons for their exclusion.
did not provide a clear or cogent identified in the June 2008 letter Amaryllis knew that it had been

Construction Law International Volume 4 No 3 September 2009 31


case updates

excluded. It was entitled to gather was anything but prompt. Indeed, Conclusion
what information it could about had it been necessary to consider
Both these cases demonstrate the
the reasons for its exclusion and whether Amaryllis needed any
importance if you intend to make
then balance the results of those extension of time, Mr Justice
a challenge to a publicly procured
researches against the risk of Coulson felt that HMT’s conduct
project, of acting promptly. While
commencing proceedings against during the relevant period was
it is true that both these cases also
a party with whom it had an likely to have been the main cause
suggest that the courts will take a
ongoing commercial relationship. of any delay and that no prejudice
fair and reasonable approach in
Finally no criticism of Amaryllis would have been suffered by HMT
deciding whether the three month
could be made of the period 4 as a consequence of that delay.
time limit has been complied with
June and 16 June 2008, the period Therefore Amaryllis would have
or not, it is important to bear in
where it was awaiting a response to had a real prospect of
mind that they will only do so, if it is
a letter from HMT. demonstrating good reason for any
appropriate in all the circumstances.
In addition, the judge thought it delay, had it been necessary.
fair to compare Amaryllis’ speed of Accordingly, the judge concluded
reaction with HMT’s conduct that Amaryllis was duly entitled to Jeremy Glover is a Partner at Fenwick
during the relevant period. HMT pursue its claim against HMT. Elliott LLP in London.

FROM ICP-NET
a few have had the DAB clause frequently removed by employers,
Deleting DAB Clauses removed.’ although in some countries this is
less likely where the project is
Précis by Elizabeth Slattery Edward invited opinions from
particularly large, complex or
ICP colleagues with experience of
Corbett & Co International Construction prestigious. Those contributors
employers removing DAB clauses,
Lawyers Ltd, London who addressed the enforcement
in particular from those who advise
issue generally took the view that
O n 7 May 2009, Edward
Corbett posted the following
question on ICP-Net in relation
employers on their contracts, asking:
‘Do you think greater
enforceability will lead to more
this situation would not be helped
by greater contractual
enforceability, nor security in
to the enforcement of Dispute frequent deletion? Is the problem
exchange for payment.
Adjudication Board (DAB) on a scale that should make
The experience of Marc Frilet
decisions: FIDIC war y of changing the
from France is that DAB clauses are
‘How many employers will enforcement regime?’
non-existent in domestic French
delete the DAB provision from
Many thoughtful responses were contracts (notwithstanding his own
FIDIC–type contracts if the
received from around the world view that they can be useful in
contract forces them to pay up,
offering differing views and specific situations) and that as a
either by making non-payment
experiences. The overall general rule French contractors
a termination offence or by
impression gained from the are not in favour of a DAB in an
giving the Contractor a right to
contributions is that there is international contract. He says that
a summary award in arbitration?
considerable reluctance on the the position may be different in a
How much difference would it
part of employers (and in some project of great complexity or
make if the Employer has a right
jurisdictions contractors also) to above a certain financial threshold
to security from the Contractor
utilise the DAB provision in a and suggests that the threshold of
in exchange for payment? I see
FIDIC contract. DAB clauses are US$50 million currently advised by
a lot of FIDIC contracts and only

32 Construction Law International Volume 4 No 3 September 2009

You might also like