APD(N)L OML-123 ADS 11H COMPLETION PROGRAM

Revision 0 Page 1 of 32

Addax Petroleum Development (Nigeria) Ltd

ADS 11H Completion Program


OML 123

0 July 24, 07 Rev Date

Draft Copy For Review Reason for Issue REVISION HISTORY

EEI Orig.

DS Chkd.

N/a Appr.

Prepared By: Ifediora Emmanuel

APD(N)L OML-123 ADS 11H COMPLETION PROGRAM

Revision 0 Page 2 of 32

TABLE OF CONTENTS REVISION DETAIL TABLE....................................................................................................2 1.0 SIGNATURE/APPROVAL PAGE......................................................................................3 2.0 INTRODUCTION.................................................................................................................4
1.1PREAMBLE ...............................................................................................................................4 1.2PURPOSE....................................................................................................................................4 1.3OBJECTIVE................................................................................................................................4 1.4GENERAL INFORMATION......................................................................................................5

3.0 CASING & CEMENTING INFORMATION .....................................................................5 4.0 PROPOSED PRODUCTION INTERVAL ..........................................................................5 5.0 GENERAL OPERATIONAL INSTRUCTIONS ................................................................6 6.0 PIPE RABITTING ...............................................................................................................7 7.0 GASLIFT MANDREL PLACEMENT.................................................................................7 8.0 TUBULAR SPECIFICATIONS ..........................................................................................8 9.0 ON SITE OPERATIONAL RESPONSIBILITIES .............................................................8 10.0 HOLE CONDITIONING ...................................................................................................9 11.0 7 LINER ASSEMBLY ...................................................................................................10
Figure-A..........................................................................................................................................12

12.0 3 COMPLETION ASSEMBLY ..................................................................................17


Figure-B..........................................................................................................................................20

13.0 REFERENCE....................................................................................................................25 14.0 ATTACHMENT...............................................................................................................26 REVISION DETAIL TABLE Rev . 0 Details of Changes Initial draft copy.

Prepared By: Ifediora Emmanuel

APD(N)L OML-123 ADS 11H COMPLETION PROGRAM

Revision 0 Page 3 of 32

1.0

SIGNATURE/APPROVAL PAGE Name


Ifediora Emmanuel Guus Nobbenhuis John Lowder Richard Knox Amarquaye Martey

Action
Prepared By:

Area of Responsibility
Snr. Completion Engineer Drilling Superintendents Head, Drilling Engineering Deputy Asset Manager, OML 123 Drilling Manager Production Manager Deputy GM Asset Management

Signature

Date

Reviewed By:

Approved By:

Horace B. Awi Emmanuel Ukegbu Monday Otabor

Prepared By: Ifediora Emmanuel

APD(N)L OML-123 ADS 11H COMPLETION PROGRAM

Revision 0 Page 4 of 32

2.0
1.1

INTRODUCTION
PREAMBLE

The well Adanga South 11H was spudded from slot B1a in EBUGHU North East PP with the 36 conductor pipe driven to 384 ft md. The ADS 11H producer is contingent on the ADS 11P1 appraisal result. It is planned to produce oil from the P5.2 reservoir in the southern part of Adanga South Block A structure. A dual bore (splitter) starter head technology will be used. The wellhead consists of Drill-Quip Dual Bore Starter Head and Unitized 13 5M, 2 step wellhead housing for landing 9 casing and the 3 tubing hangers.
1.2 PURPOSE

The purpose of this document is to present a detailed procedure for completing Adanga South 11H well to achieve its primary objective.
1.3 OBJECTIVE

The objective of this proposal is to optimally complete ADS-11H as a single string oil producer in the P-5.2 reservoir of the Adanga South A block and to complete the horizontal section with minimum formation damage. A 7" pre-drilled liner assembly will be run in the open hole section and blank liner overlapping inside 9 casing to about 55 degrees (6,400ft md) using Baker model SC-1R packer assembly. The blank sections of the liner will equally overlapped into the open hole with at least 40 ft. The lateral section will be cleaned with Organic solvents via the wash pipe to remove filter cakes. In the event of a geological compartmentalization resulting in gas or water being traversed, zonal isolation would be required. The pre-drilled and blank 7 liner assembly will be run in the open hole section with Swell packer(s) placed for the zonal isolations. The assembly will be run with blank liner overlapping inside 9 casing to about 55 degrees using Baker model SC-1R packer assembly. After recovering SBM and displacing hole to Seawater, the lateral section will be displaced to organic (cal) acid and then the 9-5/8 casing section circulated clean with detergent. The tubing string will be 3 9.3 ppf N-80 EUE tubing equipped with Baker Model TE5 sub-surface safety valve (TE-5 SCSSSV), gas lift mandrels, Locator seal assembly and other well completion accessories. The end of the tubing (EOT) would be positioned between 2-5ft above the KOIV depth after landing the string. The knock out isolation valve will be broken with slick line tool afterwards.

Prepared By: Ifediora Emmanuel

APD(N)L OML-123 ADS 11H COMPLETION PROGRAM

Revision 0 Page 5 of 32

1.4

GENERAL INFORMATION

Well Name: Target Name: Target TVD: Total Depth (MD): Maximum Inclination: Water Depth: RKB-MSL Elevation: RKB-WH Elevation: 3.0

Adanga South 11H ADS P-5.2 Reservoir 6,175 ft-tvd 9,193 ft 90 deg 53 ft MSL 104 ft 69.87 ft

CASING & CEMENTING INFORMATION

A 36 conductor pipe was driven from a slot B-1a, Ebughu East production platform to 433 ft-md. A 16 surface hole section was directionally drilled to 2,718ft-md (2,596 fttvd). The 13 68ppf N-80, BTC casing was cemented in place with 15.8ppg cement slurry. The 12 build section was drilled horizontally and landed in the P-5.2 reservoir at 7,779ft-md (6,175 ft-tvd). A 9 47ppf N-80 BTC casing will be set at TD and cemented inside 13 casing with 11.8ppg lead and 15.8ppg tail cement slurries. From the 9 casing shoe, an 8 hole will be drilled with about 1,417 ft of lateral to TD at 9,193 ft-md maintaining TVD of 6,175 ft-tvd) in the P-5.2 reservoir. The 7" 23ppf K-55 BTC pre-drilled liner will be run in the open hole section to TD with 7" 29ppf K-55 BTC blank liner overlapped in the 9 casing to at most 74 degrees. The liner assembly will be hung off using Baker model SC-1R packer assembly. As a contingency, the 7 pre-drilled/blank liners and Swell Packer(s) will be spaced out such as to provide required isolation in the 8 hole. Note: - The blank liner in the 9- casing section will be overlapped into the open hole section with a minimum of 1 joint to reduce shock around the casing shoe due to production. - Final liners (pre-drilled & Blank) and Swell Packer (if required) placements will be determined after drilling the lateral section. PROPOSED PRODUCTION INTERVAL P-5.2 7,776 9,193 ft-md (1,417 ft) 6,175 ft 2,200psia (0.3563psi/ft) 188degF

4.0

Reservoir: Interval: TVD-RKB: BHP: BHT:

Prepared By: Ifediora Emmanuel

APD(N)L OML-123 ADS 11H COMPLETION PROGRAM

Revision 0 Page 6 of 32

5.0

GENERAL OPERATIONAL INSTRUCTIONS

NOTE: - This program is a work instruction. The line of COMMUNICATION with the rig will be via the Drilling Superintendent. The Drilling Manager and/or OML-123/124 Asset Manager shall approve any fundamental change prior to implementation. Meetings should be conducted with relevant personnel considering following: Introduction of key personnel. Highlight every critical stage of the job. Identify areas of possible failure and ensure adequate preventative steps are taken. Discuss on known hole conditions such as doglegs, tight spots, hole angle, high drilling torques and any problems encountered while drilling. Highlight consequences of any failure. Ensure that all relevant personnel understand all processes / steps required for each stage of the job. Assign responsibility where possible and stress on accountability. Ensure teamwork principle. Establish and Pick up the required HWDP to provide enough weight to push the liner to bottom. The DC and HWDP should be positioned immediately in the vertical section of the hole at about 44 deg. Rabbit all drill pipes on wiper trip before running liner. Prior to pulling out of the hole on the last wiper trip, if a special wiper trip is made, i.e. hole opener/bull nose run, drop 2.5 OD rabbit with 100ft of wire attached to enhance recovery should it stick in a restricted joint. Avoid drifting completion tubing while RIH, but where not avoidable, ensure one drift is used at a time and should be seen prior to making up and running in hole with any of the drifted joints Do not use Teflon drifts. Use API steel drifts. It is recommended that all the Liner joints, Tubing joints and completion equipment be cleaned and drifted on the deck. Ensure Addax Drilling Supervisor/Completion Engineer witness all drifting.

Prepared By: Ifediora Emmanuel

APD(N)L OML-123 ADS 11H COMPLETION PROGRAM

Revision 0 Page 7 of 32

All drift sizes used should be recorded and reported in the Daily completion report. Keep an accurate tubing tally. All lengths, IDs, coupling OD's and thread types of all down hole completion items must be known and recorded. It is critical that the tally is as accurate as possible. Ensure hole is covered all the time to avoid working tools or any other item dropping in the hole. In the event working tools or any other items drop in hole, report type of fish that is lost in hole to the Addax Drilling Supervisor/Completion Engineer Ensure availability of equipment back-ups. Ensure availability of completed and signed-off QA/QC data sheet and checklists.

6.0

PIPE RABITTING

The purpose of this is to ensure that possible rust; debris is cleared off the pipe and to determine the minimum acceptable passage required for each pipe or assembly. The following pipes / tubing joints should be drifted with the minimum corresponding drift size. Minimum Drift Size Requirement 6.059 5.50 2.50 2.867 2.867 2.165 Table: 1 GASLIFT MANDREL PLACEMENT Liner/DP/Tbg 7 Liner Swell Packer 5 Drill pipe / HWDP 3 Tubing 3 Tubing Hanger 2 Tubing (Wash pipe)

7.0

The Gas Lift Mandrels will be run with pre-installed Live and orifice valves as shown in the table below. The plan is to make up the mandrels onto pup joints and pressure test in town. Ensure that each GLM has been tested to at least 5,000psi before running in hole. This is to be confirmed with pressure test charts. The Gas Lift Mandrels will be labeled at Weatherford with #1 mandrel as the first to run and #3 mandrel the last in hole. The Drilling Supervisor should check and ensure that mandrel labeling is correct and run accordingly. Also, the mandrels should carry the test values and dates of test.

Prepared By: Ifediora Emmanuel

APD(N)L OML-123 ADS 11H COMPLETION PROGRAM

Revision 0 Page 8 of 32

Number as Stenciled on GLM GLM #3 GLM #2 GLM #1 8.0


Size (in) 2 3 7 9 Wt (ppf) 8.7 9.3 23 29 47

MD

(ft)

TVD (ft) 1,420 2,144 2,437

Inclinatio n (deg) 10 25.52 35.04

Dummy Live Live ORIFICE Table: 2


Coupl OD (in) 3.500 4.250 7.656 7.656 10.625 Recommended Make-up 3,000 ft-lb 3,200 ft-lb Base Triangle Base Triangle of of

1,429 2,184 2,522

TUBULAR SPECIFICATIONS
Grade N-80 N-80 K-55 N-80 N-80 Thrd PH6 EUE BTC BTC BTC ID (in) 2.259 2.992 6.366 6.184 8.681 Drift (in) 2.165 2.867 6.241 6.059 8.525 Cap (bpf) 0.0058 0.0087 0.0394 0.0371 0.0732 Coll (psi) 15300 10530 3270 7020 4760 Burst (psi) 15000 10160 4360 8160 6870 Yield (kips) 180.3 207 366 676 1085

Table: 3 9.0 ON SITE OPERATIONAL RESPONSIBILITIES In the execution process of this program, responsibilities have been assigned as follows to avoid possible operational conflict: Drilling Supervisor: Is the overall boss in-charge of the overall operation throughout the execution of this program. He oversees every aspect of this operation and supervises all the subsupervisors. He will call for toolbox meeting on each of operational stage by involving every relevant personnel and delegate responsibility to sub-supervisors after clear understanding of the operation by all involved. He ensures that operators are working according to approved checklist. Running of the rig and completion tools as per instruction of the Drilling Supervisor and Sub-operational supervisors. Is one of the main Sub-operational supervisors. He will supervise and be responsible for the making up and running of the Liner and Upper completion assemblies. He should ensure that the tallies and every other measurement are properly taken and

Toolpusher / Driller: Baker Engineer:

Prepared By: Ifediora Emmanuel

APD(N)L OML-123 ADS 11H COMPLETION PROGRAM

Revision 0 Page 9 of 32

recorded. At the end of well completion, he should ensure that a complete, correct and detailed well completion schematic (Field Copy) is delivered to the Drilling Supervisor before leaving the rig. Baker Systems Engineer: Is also one of the Sub-operational supervisors responsible for SCSSSV running and control line. He should inspect and report any damage on the control line while running. He should be present throughout the periods of running, and operating of the SCSSSV (closing and opening of the valve). Is another Sub-operational supervisor responsible for the making up of tubing hanger, landing hanger, landing off Xmas tree and testing same. He will be in-charge of running and pulling of Two-way check valve, and wear bushing. He will also work with the safety systems engineer in termination of the control line on the wellhead. Sub-operational supervisor responsible for slick line activities in testing the string integrity. Is a Sub-operational supervisor responsible for proper preparation and composition of casing cleanout detergent and the packer fluid. He should ensure that pumping procedure is established.

DrillQuip Engineer:

Geoservices Supervisor:

Mud Engineer:

Note: It is obligatory for all service providers to ensure that a copy of QA/QC data sheet and checklist signed-off with Addax QA/QC personnel in town is presented to the Drilling Supervisor prior to commencement of operation. Sections of the checklist that require further completion on the rig site will be signed off by the Drilling supervisor thereafter. 10.0 10.1 Note: HOLE CONDITIONING MU/RIH with hole clean out assembly (8 hole opener / bull nose and 9 casing scraper) in tandem. Ensure the assembly is spaced out such that the casing scraper will run down about 85 degrees when the hole opener assembly would be at TD.

Prepared By: Ifediora Emmanuel

APD(N)L OML-123 ADS 11H COMPLETION PROGRAM

Revision 0 Page 10 of 32

10.2

Condition mud (9.0-10.0ppg)/hole and scrape casing with the assembly and ascertain hole condition. Ensure that hole is adequately clean (circulate minimum 2.5 bottoms up). Report any losses in BPH and Total in the morning report.

10.3 POOH to 9- casing shoe. Pump sweep and circulate bottoms up at the shoe. Note: Ensure hole is cleaned of cuttings. 10.4 10.5 10.6 11.0 11.1: Continue POOH (without pumping). L/D 8 hole opener / 9 casing scraper assembly. Prepare to run Liner assembly. Rig up elevators and tongs. 7 LINER ASSEMBLY
PRIMARY CONCEPT

The plan in this concept is to run the pre-drilled liner in the lateral section with blank overlapping inside the 9- casing and hanging off with Baker model SC-1R packer assembly at about 74 degrees. A 1-7/16 Stainless Steel ball will be dropped and allowed to gravitate down to the ball seat at the bottom of the liner running tool. There will be 3 pressure setting stages, 1,800psi, 2,200psi and 2,500psi to set the packer. The ball seat will be sheared with + 15% of 3,872psi. 11.2
SECONDARY CONCEPT

This is a contingent approach to the above concept whereby zonal isolation will be required in the lateral section. In this case, one or two 6 24ppf L80 13% Cr base pipe Swell packer(s) spaced out with blank liners as required to provide isolation in the lateral open hole section will be run as part of the liner assembly. The assembly will be run and hung off inside 9 casing with an overlap to about 74 degrees inclination using Baker model SC-1R packer assembly. 11.3
GENERAL OVERVIEW

In both scenarios, Baker model SC-1R type packer will be used to anchor the open hole assembly. SC-1R packer is a fully retrievable retainer production packer with a rotationally locked setting mechanism. Although this packer is primarily used for gravel pack applications, it may also be used as a standard completions packer where a retrievable retainer production packer is required. This will be run with an SC hydraulic setting tool. The purpose is to provide an effective sealing in the 9 casing annulus and anchor the liner string in the hole. A 1-7/16 Stainless Steel ball will be dropped and allowed to gravitate down to the ball seat at the bottom of the liner running tool. There will be 3 pressure setting stages, 1800psi, 2200psi and 2500psi to set the packer. The ball seat will be sheared with + 15% of 3,872psi.

Prepared By: Ifediora Emmanuel

APD(N)L OML-123 ADS 11H COMPLETION PROGRAM

Revision 0 Page 11 of 32

Note: In the event of losses, prior to setting the SC-1R packer, the ball seat with max. 8 shear screws rated at 484psi/screw for a shear value of 3,872psi may shear out at 3,491psi + 15%, i.e. between minimum of 2,967psi and maximum of 4,015psi. This is as a result of the overbalance of 381psi, created by the hydrostatic head of 10.0ppg drilling fluid over the reservoir pressure. A back-up 1.75 Bakerlite ball is available in case the setting sequence of the packer is not completed with the primary ball. The backup ball seat cannot be Address: 188deg F sheared out and circulation can only be regained after2,200 psi reversing out the ball. 6 Fatai Durosinmi Etti Street Victoria Island Extra caution is necessary in reversing out Annex backup9,193 since reversing ball 6,175' Lagos, Nigeria the Baker Nigeria Limited 90 90 N/A pressure can adversely affect the reservoir stability. PLEASE REVIEW 8.6ppg Inhibited Sea SITUATION Addax WITH TOWN (Drilling Superintendent)Water 7" Pre-Drilled Liner BEFORE DROPPING BACK A Emmanuel Ifediora 8-1/2" Open Hole 7,776' - 9,193' (1,417') UP BALL.
BHP BHT MD TVD INHIBITOR MAX. DEVIATION ZONE DEVIATION SAND SIZE OPERATOR COMPLETION FLUID (WEIGHT AND TYPE) SCREEN SIZE COMPANY REP. PERFORATIONS FIELD WELL NO. SIZE WEIGHT GRADE THREAD

PROPOSED WELL SCHEMATIC

ADS Offshore
RIG NAME

11 H
COUNTRY

CASING PRE-DRILLED LINER

9-5/8" 7"

47 ppf 23 ppf

N-80 K-55

BTC BTC

The Swell Packer is Craighead on the swellingBLANK LINER based properties 7"of rubber in hydrocarbons. 26 PPF N-80 BTC Tommy Thermodynamic absorption expansion is continuous. The Swell ppf TUBING 2-7/8" 8.7 Packer will swell to N-80 PH-6 26-Jul-07 1 expand and seal the annulus around a pipe. It can be used in open or cased holes. Ogbeide John
DATE REVISionION NO. PREPARED BY

Nigeria

No.

Depth

Length

O.D.

I.D.

Description

Special Note:

SC-1R Packer and Pre-Drilled Liner Assembly

7,200.0 5.0 8.440 4.750 C 1. Remove 1 Lamiflex protection withoutModel SC-1R Packer, Size 96A4-47, withwith Box touching the rubber 7" BTC knife rather Down

remove protection by 1.5 pulling tape 5.000by hand. off Size 7" KnockOut Isolation Valve w/7" New Vam Box X Pin 3 7,225.0 7.656
D 2

7,205.0

20.0

7.625

6.184

Retrieving Extension, Size 7" x 25 ft., with 7" BTC Pin x Pin

2. Drift the OD 7,226.5 packer(s) with and OD gauge.7", with 7" Buttress Box x Pin of the 589.5 4 7.656 6.276 Blank Liner, Size 3. Avoid prolonged contact with base oil,Buttress Boxor other oil-based fluids. If packer diesel x Pin
E

5 6 7

7,816.0 9,177.0 9,192.0 9,193.0

1361.0 15.0 1.0

7.656 7.656 7.656

6.276 2.875 ---

Pre-Drilled Liner, Size 7", with (114) 3/8" Holes Per Foot, with 7" Casing Pup, Size 7" w/ Insert Drillable Packoff Bushing f/ Baker Cement filled Shoe, Size 7", with 7" Buttress Box Up

2.875" off with Stinger, BTC is exposed to any of the above fluids, wipe Polished Slicka cloth. Box x Pin F End of Assembly 4. Make up with crossover pup joint for handling in town.

Rental Tool 5. Swell Gpacker start setting by swelling after 3 days in contact Assembly with SBM or diesel. A B C D E F G H I J K 3.0 3.0 0.9 1.5 1.0 6.0
As Required

I 5

1.0
As Required

1.0 10.0

7.130 6.000 3.900 3.500 3.365 3.365 3.365 3.910 3.365 3.365 3.500

2.500 2.441 2.441 2.441 2.441 2.441 2.441 2.441 2.441 2.441 2.441

Model "SC" Hydraulic Setting Tool, Size 86, with 3-1/2" IF Box x Hydro-Set Adapter Kit Crossover 3-1/2 CSHydril Box X 2-7/8 EU 8rd Pin Swivel Sub with 2-7/8 EU 8rd Box X Pin X-Over 2-7/8 EU 8rd Box X 2-7/8 CS Hydril Pin Pup Joint, Size 2-7/8" x 6 ft., with 2-7/8" Hydril CS Box x Pin 2-7/8 Pup Joints w/2-7/8 CS Hydril Box X Pin Crossover 2-7/8" Hydril CS Box x 2-7/8 Hydril PH-6 Pin Tubing, Size 2-7/8", with 2-7/8" PH-6 Box x Pin X-Over 2-7/8 Hydril PH-6 Box X 2-7/8 CS Hydril Pin Polished Stinger, Size 2-7/8", 14 ft. Long, with 2-7/8 CS Hydril Box Up

11.4

7 LINER ASSEMBLY SCHEMATIC

Prepared By: Ifediora Emmanuel NOTES:


1) 2) 3)

APD(N)L OML-123 ADS 11H COMPLETION PROGRAM

Revision 0 Page 12 of 32

Figure-A 11.5 Assembl y No.


SUMMARY OF 7 LINER ASSEMBLY MAKE-UP

No. In Description Drawing

Prepared By: Ifediora Emmanuel

APD(N)L OML-123 ADS 11H COMPLETION PROGRAM

Revision 0 Page 13 of 32

Figure-A (Items: 9 5)

Pin.

Baker Size 7 Shoe with 7 Buttress Box up. Casing Pup Joint, Size 7 x 15 ft with 7 BTC Box x

Figure-A (Items: J G)

3 4

Figure-A (Items: 4 1)

(Items: FA)

Size 7 x 2.875, Drillable Pack-off Bushing. About 887 ft of 7 29ppf N-80 BTC Predrilled Liner, with 7 BTC Box x Pin. Optional: 6 24ppf 13% Cr BTC Swell Packer assembly* About 1,426 ft, 7 29ppf N-80 BTC Blank Liner, with 7 BTC Box x Pin. Polished Slick Stinger, Size 2 OD with 2 CSH Box up. X-Over sub, size 2-7/8 PH-6 Hydrill Box x CSH pin. About 2500 ft of 2 Wash Pipe, with 2 8.7ppf PH-6 Hydrill Box x Pin. X-Over sub, size 2-7/8 CSH Box x PH-6 Hydrill pin Pup joints (as required to space out), 2 CSH box x Pin. Crossover sub, 5-1/2 LTC box x 7 BTC pin. Model C KOIV, size 7 LTC Box x Pin Crossover sub, 7- BTC box x 7 BTC pin. Mill out extension sub Size 7- x 20ft with 7- BTC box x Pin. Model SC-1R Gravel pack Packer assembly, size 96A4-60, max O.D. of 8.44 with 6 bore for 9 43.5 - 47ppf casing. (Following sub-assemblies already made-up with packer in town); Pup joint, size 2-7/8 CSH Box x pin. X-Over sub, size 2-7/8 EU 8rd box x 2-7/8 CSH pin. Swivel Sub, Size 4.5, with 2 EU 8rd Box x Pin. Model BSCR Hydro-Set Adapter kit, size 190-60, with 2- EUE pin down. Model SC Hydraulic Setting Tool, size 86, w/3- IF Box up. Crossover Sub, with 4- IF Box x 3- IF Pin. 5 Drill Pipe pup joint with 4- IF Box x pin.

11.6

DETAILED PROCEDURE FOR RUNNING 7 LINER ASSEMBLY Rig Up 7 liner running tools. Hold pre-job safety meeting.

11.6.1. 11.6.2. 11.6.3.

Pick up the Assembly No. 1 (Open Hole pre-drilled Liner) as per attached schematic.

Prepared By: Ifediora Emmanuel

APD(N)L OML-123 ADS 11H COMPLETION PROGRAM

Revision 0 Page 14 of 32

Note: *The swell packer is not part of the schematic, but will only be run should zonal isolation will be required, otherwise skip item. Swell packer placement will be advised by the Completion Engineer / Drilling Superintendent. 11.6.4. With the Open Hole 7" liner assembly (Assembly No.1) hanging in the rotary, rig up and run Assembly No. 2 (inner string concentric/wash pipe assembly) inside the liner assembly and sting into the drillable pack-off bushing.

Note: Make up the KOIV below the SC-1R packer assembly on the rig before running it because of the possibility of damaging the flapper with the inner string while transporting. ALL wash pipe connections across and below the KOIV sub MUST be either 2- CSH or PH-6. Set the concentric/wash pipe string in a 2 Bowl and Slips on the false rotary table. Space out the wash pipe string so that the polish stinger is stung into the Drillable pack off bushing. 11.6.5. Pick up Assembly No. 3 (pre-assembled SC-1R packer assembly with the service tools already installed). The KOIV should have been made up to the packer assembly. Make up the inner string to the pup joint stick out. Then make up the 7 Liner assembly to the SC-1R packer assembly. Break circulation and do not exceed 800psi. After assembling the above horizontal liner assembly, pick up and RIH with 5 drill pipe, space out HWDPs at an inclination of 44 degrees to maximize the benefit of the HWDP continue RIH joints of 5 DPs to surface, and run in hole to TD at a rate of 1.5 minutes per 90 stand. Dope slightly pin ends only. Monitor the running (S/O) and pulling (P/U) weights and compare trend with the attached Multiple Drag Analysis. In case of rapid change to the predicted weights, work pipe by reciprocating gently while circulating bottoms up prior to landing assembly in the slips for connection (to free the friction). The Drag analysis will be finalized after drilling the lateral section to TD and the result compared with the attached planned report. In case of any significant variance to the attached, a revised analysis report will therefore be forwarded to the rig. Note: Fill up drill pipe on the slips with fill-up hose. DO NOT fill pipe with TDS.

11.6.6.

11.6.7.

Prepared By: Ifediora Emmanuel

APD(N)L OML-123 ADS 11H COMPLETION PROGRAM

Revision 0 Page 15 of 32

At the casing shoe, break circulation. Prior to entering the open hole, record the BHA P/U & S/O weights. During circulation, do not exceed 800psi surface pump pressure. In case of restriction or tight spot, wash through restriction CBU, and continue RIH. At TD record P/U and S/O weight. 11.6.8. 11.6.9. Once at TD, RU surface equipment and test all lines to 5,000psi. Space out with drill pipe pup joints if required to have surface connections close to rig floor. Drop 1-7/16 Stainless Steel setting ball and allow about 30 minutes for ball to gravitate to seat.

11.6.10.

11.6.11. With the ball seated on the ball seat, set Model SC-1R Gravel Pack Packer using the following steps: A. Slowly pressure up to 1,800psi. Hold for 5 minutes and then bleed to 100psi. B. Slowly pressure up to 2,200psi. Hold for 5 minutes and then bleed to 100psi C. Slowly pressure up to 2,500psi. Hold for 5 minutes and then bleed to 100psi Please refer to notes under Section 11.3. 11.6.12. Verify Packer setting by pulling 30,000 lbs over pick-up. Set down 5,000 lbs, close the pipe rams and apply 1,500psi to annulus (backside) for 5 minutes. Bleed pressure to 0psi. If this test fails, repeat step 11.6.11 with 200psi pressure increments to 3100psi max. In case SC-1R packer test fails, Baker model FH packer, for 9-5/8 43.5 47ppf casing size on standby will be run as part of the 3- completion string. As back up to release, holding slight up strain, rotate 12-15 turns to the right at the tool in order to release the service tools from the Liner assembly.

Note:

11.6.13.

11.6.14. Slowly pick at the tool 2-3 ft to verify that the service tool has released from the packer. 11.6.15. Note: With the seals off the sealing bore, pressure the work string +3,872psi to shear ball seat. If a back-up ball was used to set the SC-1R Packer, PU service tools until the polished stinger is out of the pack off bushing to reverse out the ball.

Prepared By: Ifediora Emmanuel

APD(N)L OML-123 ADS 11H COMPLETION PROGRAM

Revision 0 Page 16 of 32

Hole Cleaning and Lateral Section Displacement 11.6.16. Circulate bottoms up. Note: Prior to displacement ensure preparations are made to achieve a continuous displacement process.

HSE ISSUES:
Chemicals should be handled carefully and safely. The appropriate personal protective equipment should be used to prevent the probability of exposure to these solvents. Perform safety meeting and ensure proper understanding of all required safety procedures in handling the above solvents. WW4002 is inflammable, please ensure application of inflammable chemicals procedure handling. 11.6.17. With the slick stinger inside the pack-off bushing, pump 35bbls spacer, followed with 65bbls of Organic Solvent (WW4002) and 5bbls spacer behind. Prepare Spacer with HEC and CaCO3 to 0.5ppg above the density of the SBM.

11.6.18. Displace entire hole to 8.6ppg Seawater and recover SBM and Organic Solvent (WW4002). Monitor losses for 30mins and fill hole with Seawater as may require. Note: Driller to make use of pump stroke count to estimate the time HEC pill will be on surface. Mud engineer to station at the flow line 30 minutes prior to the expected time verifying fluid rheology and provide adequate advise to the Driller. 11.6.19. Pump about 100bbls of Organic acid and displace to the lateral section with 8.6ppg Seawater. The acid is required to dissolve the calcium carbonate filter cake in the lateral section.

Note: Over displace acid as may be required ensuring that it contacted the heel section. Be sure that there is adequate Seawater reserve prior to pumping organic acid. Displace organic acid at maximum pump rate. WW4002 and Organic acid will be pumped from a rented tank. Recalculate the volume of Organic acid based on run-in tally. 11.6.20. Once displacement is completed, pull out of hole slowly with the service tools until they are completely out of the Liner assembly to avoid swabbing.

Prepared By: Ifediora Emmanuel

APD(N)L OML-123 ADS 11H COMPLETION PROGRAM

Revision 0 Page 17 of 32

11.6.21. POOH with wash pipe (service tool) to about 2 joints below the KOIV at 1.52mins per stand while monitoring losses and adequately filling up hole. Record rate of losses and cumulative in the report. Casing Cleaning & Displacement to Packer Fluid (INHIBITED Seawater) 11.6.22. With work string about 2 joints below KOIV, kick-off pump and circulate below KOIV at 4bpm thoroughly before picking up pipe slowly through the KOIV. Stop 5 ft above the KOIV and observe well for losses. Start the pump and pick up string above the SC-1R packer. DO NOT tag KOIV with work string to avoid damage. Pump 141bls of hole cleaning detergent solution (Seawater with 1% Dirt Magnet volume concentration).

Note: 11.6.23.

11.6.24. Displace hole to 8.6ppg Inhibited Seawater (Packer Fluid). Note: Seawater to be treated with 10 gals Tetra-Hib (corrosion inhibitor) per 100bbls and 5gals No-Oxygen (Oxygen Scavenger) per 100bbls. Observe the well for losses.

11.6.25. POOH and rack drill pipes, DCs, HWDPs. LD wash pipe and Baker service tools. 11.6.26. RU to run 3- tubing (upper completion string). 12.0 12.1 3 COMPLETION ASSEMBLY
OVERVIEW

The well will be completed with 3 9.3ppf N-80 EUE 8rd tubing with tubing retrievable safety valve, Gas lift mandrels, Locator seal assembly and nipples installed. 12.2
SUMMARY OF 3 TUBING UPPER COMPLETION ASSEMBLY MAKE-UP

Assembl y No.
I

Nos. In Description Drawings


Figure-B (Items: 36 31)

Model A ratcheting mule shoe, size 190-47 with 3-1/2 EU 8rd Box up Baker model R Seating Nipple, Size 3 x 2.75 x 2.697btm NoGo

Prepared By: Ifediora Emmanuel

APD(N)L OML-123 ADS 11H COMPLETION PROGRAM

Revision 0 Page 18 of 32

II

Figure-B (Items: 29 25)

III Figure-B (Items: 23 21) IV Figure-B (Items: 19 17) V Figure-B (Items: 15 13) VI Figure-B (Items: 7 3)

Baker Flow Coupling 3 9.3ppf EUE 8rd Box x Pin. Baker model S-22 Locator Seal, Size 190-60 with 10 ft seals with 3 9.3ppf EUE 8rd Box x Pin. Pup joint of 3 9.3ppf EUE 8rd Box x Pin. Pup joint of 3 9.3ppf EUE 8rd Box x Pin. Baker Flow Coupling 3 9.3ppf EUE 8rd. Baker model F Top No-Go Seating Nipple, Size 3 x 2.75. Baker Flow Coupling 3 9.3ppf EUE 8rd. Pup joint of 3 9.3ppf EUE 8rd Box x Pin. Pup joint of 3 9.3ppf EUE 8rd Box x Pin. GLM #1 with ORIFICE 3 9.3ppf EUE 8rd Box x Pin. Pup joint of 3 9.3ppf EUE 8rd Box x Pin. Pup joint of 3 9.3ppf EUE 8rd Box x Pin. GLM #2 with LIVE 3 9.3ppf EUE 8rd Box x Pin. Pup joint of 3 9.3ppf EUE 8rd Box x Pin. Pup joint of 3 9.3ppf EUE 8rd Box x Pin. GLM #3 with LIVE 3 9.3ppf EUE 8rd Box x Pin. Pup joint of 3 9.3ppf EUE 8rd Box x Pin. Pup joint of 3 9.3ppf EUE 8rd Box x Pin. Baker Flow Coupling 3 9.3ppf CSH Box x EUE 8rd Pin. Baker model TE-5 Surface Controlled Subsurface Safety Valve, 3 x 2.81with 3 9.3ppf CSH Box x Pin. Baker Flow Coupling 3 9.3ppf 3 9.3ppf CSH Pin x EUE 8rd Box Pup joint of 3 9.3ppf EUE 8rd Box x Pin. Tubing Hanger

VII

Figure-B (Items: 1)

Prepared By: Ifediora Emmanuel

APD(N)L OML-123 ADS 11H COMPLETION PROGRAM

Revision 0 Page 19 of 32

12.3

UPPER COMPLETION SCHEMATIC


BHP BHT

PROPOSED WELL SCHEMATIC

Baker Nigeria Limited


OPERATOR

Address: Plot 6 Fatai Durosinmi Etti St Lagos Nigeria Phone: 4619081-5


COMPLETION FLUID (WEIGHT AND TYPE)

2,200 psi
MD TVD

188 deg F
INHIBITOR

9,193 ft
MAX. DEVIATION

6,175 ft
ZONE DEVIATION SAND SIZE

90 deg
SCREEN SIZE

90 deg

Addax Pet Dev. Nigeria Ltd Emma Ifediora


WELL NO.

8.6ppg Inhibited Cacl2


PERFORATIONS SIZE

7" Pre-Drilled Liner


WEIGHT GRADE THREAD

COMPANY REP.

8-1/2" Open Hole 7,776'-9,193' (1,417ft) 11H


COUNTRY

FIELD

ADS
STATE RIG NAME

CASING

9-5/8" 7" 7" 3-1/2"

47 ppf 23 ppf 26 ppf 9.3 ppf

N-80 N-80 N-80 N-80

BTC BTC BTC EU 8rd

Nigeria Noble Tommy Craighead


REVISION NO. DATE PREPARED BY

PRE-DRILLED BLANK LINER

26th July 2007 Length

1 O.D. I.D.

TUBING SHT. STRING

John Ogbeide No. Depth

Description 9-5/8" x 3-1/2" Production Tubing Assembly

0.000 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 69.9 71.9 289.1 295.1 301.1 307.1 313.1 319.1 1423.0 1429.0 1433.0 1439.0 2178.0 2184.0 2188.0 2194.0 2516.0 2522.0 2526.0 2532.0 5888.0 5894.0 5900.0 5902.0 5908.0 5914.0 7193.0 7199.0 7200.0

69.9 2.0 217.2 6.0 6.0 6.0 6.0 6.0 1103.9 6.0 4.0 6.0 739.0 6.0 4.0 6.0 322.0 6.0 4.0 6.0 3356.0 6.0 6.0 2.0 6.0 6.0 1279.0 6.0 1.0 13.0 4.500 4.500 4.500 5.380 4.500 4.500 4.500 4.500 5.500 4.500 4.500 4.500 5.500 4.500 4.500 4.500 5.500 4.500 4.500 4.500 4.500 4.500 4.500 4.500 4.500 4.500 6.250 6.000 2.992 2.992 2.992 2.992 2.812 2.992 2.992 2.992 2.992 2.937 2.992 2.992 2.992 2.937 2.992 2.992 2.992 2.937 2.992 2.992 2.992 2.992 2.750 2.992 2.992 2.992 2.992 3.000 3.000

Elevation Tubing Hanger, Size 3-1/2", with 3-1/2" 9.3 ppf EU 8rd Pin Down 7 Jts of Tubing, Size 3-1/2", with 3-1/2" 9.3 ppf EU 8rd Box x Pin Pup Joint, Size 3-1/2" x 6 ft., with 3-1/2" 9.3 ppf EU 8rd Box x Pin Flow Coupling, Size 3-1/2" x 6 ft., with 3-1/2" 9.3 ppf EU 8rd Box x 3-1/2" 9.3 ppf Hydril CS Pin Model "TE-5" Surface Controlled Subsurface Safety Valve, Size 3-1/2" x 2.812, with 3-1/2" 9.3 ppf Hydril CS Box x Pin Flow Coupling, Size 3-1/2" x 6 ft., with 3-1/2" 9.3 ppf Hydril CS Box x 3-1/2" 9.3 ppf EU 8rd Pin Pup Joint, Size 3-1/2" x 6 ft., with 3-1/2" 9.3 ppf EU 8rd Box x Pin 35 Jts of Tubing, Size 3-1/2", with 3-1/2" 9.3 ppf EU 8rd Box x Pin Pup Joint, Size 3-1/2" x 6 ft., with 3-1/2" 9.3 ppf EU 8rd Box x Pin Side Pocket Gas Lift Mandrel, Size 3-1/2", #1 with Live Valve, with 3-1/2" 9.3 ppf EU 8rd Box x Pin (# 3 Live) Pup Joint, Size 3-1/2" x 6 ft., with 3-1/2" 9.3 ppf EU 8rd Box x Pin 24 Jts of Tubing, Size 3-1/2", with 3-1/2" 9.3 ppf EU 8rd Box x Pin Pup Joint, Size 3-1/2" x 6 ft., with 3-1/2" 9.3 ppf EU 8rd Box x Pin Side Pocket Gas Lift Mandrel, Size 3-1/2", #2 with Live Valve, with 3-1/2" 9.3 ppf EU 8rd Box x Pin (# 2 Live) Pup Joint, Size 3-1/2" x 6 ft., with 3-1/2" 9.3 ppf EU 8rd Box x Pin 10 Jts of Tubing, Size 3-1/2", with 3-1/2" 9.3 ppf EU 8rd Box x Pin Pup Joint, Size 3-1/2" x 6 ft., with 3-1/2" 9.3 ppf EU 8rd Box x Pin Side Pocket Gas Lift Mandrel, Size 3-1/2", #2 with Live Valve, with 3-1/2" 9.3 ppf EU 8rd Box x Pin (# 1 Orifice) Pup Joint, Size 3-1/2" x 6 ft., with 3-1/2" 9.3 ppf EU 8rd Box x Pin 1 Jts of Tubing, Size 3-1/2", with 3-1/2" 9.3 ppf EU 8rd Box x Pin Pup Joint, Size 3-1/2" x 6 ft., with 3-1/2" 9.3 ppf EU 8rd Box x Pin Flow Coupling Size 3-1/2 X 6' w/3-1/2 EU 8rd Box X Pin Model "F" Top No-Go Seating Nipple, Size 3-1/2" x 2.750, with 3-1/2" 9.3 ppf EU 8rd Box x Pin Flow Coupling Size 3-1/2 X 6' w/3-1/2 EU 8rd Box X Pin Pup Joint, Size 3-1/2" x 6 ft., with 3-1/2" 9.3 ppf EU 8rd Box x Pin 41 Jts of Tubing, Size 3-1/2", with 3-1/2" 9.3 ppf EU 8rd Box x Pin Pup Joint, Size 3-1/2" x 6 ft., with 3-1/2" 9.3 ppf EU 8rd Box x Pin Model "S-22" Locator Seal Sub, Size 190-60, with 3-1/2" 9.3 ppf EU 8rd Box Up Model "S-22" Seal Assembly, Size 190-60, with 10 feet of Seals, with 3-1/2" 9.3 ppf EU 8rd Pin Down

NOTES: 1) 2) 3)

Prepared By: Ifediora Emmanuel

APD(N)L OML-123 ADS 11H COMPLETION PROGRAM

Revision 0 Page 20 of 32

Address: Plot 1676 O ladele O lashore St. Victoria Island, Lagos, Nigeria

BHP

BHT

2,200 psi
MD TVD

188 deg F
INHIBITOR

9,193 ft
MAX. DEVIATION

6,175 ft
ZONE DEVIATION SAND SIZE

Baker Nigeria Lim ited


OPERATOR

Phone: 234-1-262-2121
COMPLETION FLUID (WEIGHT AND TYPE)

90 deg
SCREEN SIZE

90 deg

Addax Pet Dev. Nigeria Ltd


COMPANY REP.

8.6ppg Inhibited Cacl2


PERFORATIONS WELL NO. SIZE

7" Pre-Drilled Liner


WEIGHT GRADE THREAD

Emma Ifediora
FIELD

8-1/2" Open Hole 7,776'-9,193' (1,417ft) 11H


COUNTRY

ADS
STATE RIG NAME

CASING LINER LG STRING .

9-5/8" 7" 7" 3-1/2"

47 ppf 23 ppf 26 ppf 9.3 ppf

N-80 N-80 N-80 N-80

BTC BTC BTC EU 8rd

Noble Tommy Craighead


DATE REVISION NO.

26th July 2007


PREPARED BY

1 O.D. I.D.

CO NC. STRING SHT. STRING

John Ogbeide No. Depth

Length

Description

30 31 32 33

7213.0 7217.8 7219.1 7223.1 7225.4

4.8 1.3 4.0 2.3

5.500 4.500 4.500 4.730

2.992 2.697 2.992 3.000

Flow Coupling Size 3-1/2 X 6' w/3-1/2 EU 8rd Box X Pin M odel "R" Bottom No-Go Seating Nipple, Size 3-1/2" x 2.750, w ith 2.697" No-Go ID, w 3-1/2" 9.3 ppf EU 8rd Box x Pin ith Pup Joint, Size 3-1/2" x 6 ft., w 3-1/2" 9.3 ppf EU 8rd Box x Pin ith M odel "A" Ratcheting M uleshoe, Size 190-47, with 3-1/2" 9.3 ppf EU 8rd Box Up x 1/2 M uleshoe EOT

NOTES: 1) 2) 3)

Figure-B

Prepared By: Ifediora Emmanuel

APD(N)L OML-123 ADS 11H COMPLETION PROGRAM

Revision 0 Page 21 of 32

12.4

UPPER COMPLETION RUNNING PROCEDURE

12.4.1. 12.4.2. 12.4.3. 12.4.4. Note:

RU and recover Wear bushing

RU 3 completion running tools. Hold pre-job safety meeting Pick up Assembly No. I (Guide shoe, Model R Seating Nipple and Locator Seal assembly) already made up in town. Ensure the length of the tailpipe measured from the Locator to EOT is 23ft less than that measured from SC-1R packer top to the KOIV flapper.

CONTINGENT: In case SC-1R packer was not positively tested, the contingent packer 9- x 3- FH packer will be made to the string at this point. 12.4.5. Continue running in hole with 3 9.3ppf EUE 8rd Tubing until sufficient depth has been reached to ensure the Baker Model F Seating Nipple set about 5,900 ft when landed. Pick up and RIH with Assembly No. II (Model F Nipple assembly).

12.4.6.

Tubing Integrity Test 12.4.7. 12.4.8. 12.4.9. RU slick line unit and pressure test lubricator to 2,500psi Make a 2.72 gauge cutter run to the R-nipple. POOH with gauge cutter. MU Tee connection on the tubing hanger landing joint with TIW valve installed.

12.4.10. RU surface lines to the tubing and annulus. Test lines to 2,500psi. 12.4.11. RU slick line unit and pressure test lubricator to 2,500psi. 12.4.12. Make up and RIH with RB-2 equalizing plug on slick line to test the string. Set plug in R seating nipple. Pressure test internally to 2,000psi for 30 minutes. Chart pressure reading. Bleed off pressure. Note: If the pressure drop is not more than 5% within 30 minutes (100psi) the test is then acceptable. If final test pressure is 1900psi, test is ok. 12.4.13. Pick up on plug to shear the equalizing shear pins. Wait for 1-2 minutes for pressure to equalize across the valve before pulling free the RB-2 equalizing check valve. 12.4.14. POOH with RB-2 equalizing valve. RD slick line.

Prepared By: Ifediora Emmanuel

APD(N)L OML-123 ADS 11H COMPLETION PROGRAM

Revision 0 Page 22 of 32

12.4.15. If leak is observed while performing step 12.4.12, POOH and fix leak, otherwise skip to step 12.4.16. Gas Lift Mandrels Placement 12.4.16. Continue run 3 9.3ppf EUE 8rd Tubing until sufficient depth has been reached to ensure the Gas Lift Mandrel at depth as per engineering design. 12.4.17. RIH with Gas lift mandrels (Assembly Nos. III VI) as per engineering design with 3 9.3ppf EUE 8rd Tubing joints as specified in Gas lift Mandrel section above. Set mandrels at the depths from rotary table as shown in table 2 (page 8) spacing out with tubing joints.

Surface Control Sub-Surface Safety Valve 12.4.18. Run 3 9.3ppf EUE 8rd Tubing until sufficient depth has been reached to ensure the Safety valve at depth +300.

12.4.19. RU slick line unit and lubricator. 12.4.20. Make a 2.83 gauge cutter run to the F-nipple. POOH with gauge cutter. RD slickline and lubricator.

Note: The No go on the FB-2 is 2.802, therefore the tubing should be drifted with a gauge cutter higher than the no go. However, the 2.83 GC is bigger than the 2.81 Safety valve profile, hence the two-step drifting. 12.4.21. Note: 12.4.22. Note: Pick up Assembly No. VII (Tubing Retrievable Safety Valve assembly) and make up control Line connection. Record the SCSSSV part number, nipple profile and confirm the valve is a TE-5 model. The part number of Baker TE-5 SCSSSV is H824-83-2810. Function test Safety valve 3 times and monitor Control Line returns. Control line must not have intermediate connections (DO NOT Splice Control line).

12.4.23. RIH with Safety Valve assembly and maintain 5,000psi on Control Line to keep valve in the open position. Note: Strap control line at three places on each joint (one below the box, one above and one halfway) with Baker safety system plastic straps. Ensure control line pressure is monitored on the SCSSSV while strapping and running in. Report number of straps installed.

Prepared By: Ifediora Emmanuel

APD(N)L OML-123 ADS 11H COMPLETION PROGRAM

Revision 0 Page 23 of 32

Position slips carefully to avoid crushing SCSSSV control line. Prior to running in hole after making-up, PU string and inspect control line for possible damage. In case of any observed damage control line, please pull and replace control line. String Spacing out 12.4.24. Continue RIH with 3 9.3ppf EUE 8rd Tubing and locate into the SC-1R packer bore with Locator seal assembly Note: The loss in string weight and flicking of the weight indicator is a good indication of the seals entrance into the packer Seal Bore. Ensure that the seals are actually inside the packer bore with the locator sub properly landed on top of the SC-1R Packer prior to spacing out of the tubing. Space out string by calculating required pipe + length below Tubing Hanger for space out at Landing such that the locator will be placed about 1 ft above the packer. POOH excessive joints, install Space out joints (pup joints).

12.4.25.

12.4.26. Prepare to MU tubing hanger. Landing String Hanger in Unitized Wellhead after Spacing Out 12.4.27. Note: 12.4.28. P/U Assembly No. VIII (tubing hanger) and make up to string. Drill Quip Engineer to supervise Tubing Hanger operations according to Drill Quip procedures. Wrap control line around hanger neck four times. Bleed off from control line. Connect NPT nipple with control line extension on top of hanger control line port. Flush port and connect control line below hanger. Pressure up to 5,000psi to open valve and to test connection for leaks. Keep SCSSSV open.

12.4.29. MU tubing hanger running tool and landing joint 12.4.30. RIH to about 3 below rotary table. Drain Stack. Land hanger and Lock hanger in place. Tubing and Annulus Integrity Test 12.4.31. MU Tee connection on the tubing hanger landing joint with TIW valve installed. 12.4.32. RU surface lines to the tubing and annulus. Test lines to 2,500psi.

Prepared By: Ifediora Emmanuel

APD(N)L OML-123 ADS 11H COMPLETION PROGRAM

Revision 0 Page 24 of 32

12.4.33. RU slick line unit and pressure test lubricator to 2,500psi. 12.4.34. Make a 2.83 drift cutter run to the Safety Valve. POOH with gauge cutter. 12.4.35. Make up and RIH with FB-2 equalizing plug on slick line to test the string. Set plug in F seating nipple. Pressure test internally to 2,000psi and hold pressure for 30 minutes. Chart pressure reading. Bleed off pressure. Note: If the pressure drop is less than 5% within 30 minutes the test is then acceptable. 12.4.36. While holding 2,000psi in the tubing, pressure up annulus and test, packer/seal assembly and hanger seals to 1,500psi. Hold pressure for 30 minutes. Monitor tubing pressure during test. Chart pressure readings. Bleed off pressure from annulus recording volume returned. 12.4.37. Pick up on plug to shear the equalizing shear pins. Wait for 1-2 minutes for pressure to equalize across the valve before pulling free the FB-2 equalizing check valve. 12.4.38. If leak is observed while pressure testing, check hanger seals and possibly POOH with tubing to Seal Assembly and fix leak, otherwise, skip and continue with step 12.4.39. 12.4.39. POOH with FB-2 plug and running tool. RD slick line. Wellhead Handling (BOPs & Xmas Tree) 12.4.40. Close Sub surface safety valve (SCSSSV). 12.4.41. Remove the tubing hanger landing joint and lay down landing joint. 12.4.42. Install Two Way Check Valve on the hanger. 12.4.43. Nipple Down BOPs. 12.4.44. Install single Drill-Quip Xmas tree - consisting of 2 master valves, 1 swab valve, 1 wing valve, actuated safety valve on the wing and choke box. 12.4.45. Test the tree void to 3,000psi and function test all the tree valves. Note: Ensure that production representative witnesses all the tree tests. 12.4.46. Retrieve Two Way Check Valve.

Prepared By: Ifediora Emmanuel

APD(N)L OML-123 ADS 11H COMPLETION PROGRAM

Revision 0 Page 25 of 32

12.4.47. Open SCSSSV and observe tubing pressure (if any). Close in well on X-mas tree master valves open SCSSSV with 5,000psi, bled down pressure and maintain at 3,000psi. Breaking of KOIV 12.4.48. Apply a pressure of 3,000psi in the completion string to break the KOIV. This would rupture the disc. The KOIV is at a high deviation. Note: This should be performed with coil tubing in hole. If the KOIV cannot be broken by pressure as a result of sand on top the KOIV, CT should be run to wash off sand from the top of KOIV, then the KOIV would be broken with Hammer. 12.4.49. RU 1.5 CT and test CT. RIH to wash sand on top the KOIV. POOH. 12.4.50. MU 2.25 OD Tapered disc breaker x 2-1/8 Rotor Hammer, 2-1/8 Intensifier and Motor head assembly on CT. 12.4.51. Open well on X-mas tree and ensure that the SCSSSV is in Open position.

12.4.52. RIH with the Hammer BHA and tag the KOIV flapper recording drag every 1,000 ft. 12.4.53. Hammer down and break flapper of top KOIV. Tag bottom KOIV and break flapper. 12.4.54. POOH with hammer BHA and prepare to perform well cleanup. 12.4.55. Secure well on the X-mas tree. 12.4.56. Perform well clean up in line with clean up program. Note: The clean up program for this well will be provided by Production Technology and would be supervised by the Drilling Supervisor. 12.4.57. Handover well to Production Department. Note: Ensure well is signed off to Production and copies of signed-off form sent to Drilling Superintendent, Asset team leader and completion Engineer. 12.4.58. Rig down and prepare to skid rig. 13.0 REFERENCE ADS 11H Drilling Program. ADS 11H Application to Drill

Prepared By: Ifediora Emmanuel

APD(N)L OML-123 ADS 11H COMPLETION PROGRAM

Revision 0 Page 26 of 32

Addax Drilling Manual.

14.0

ATTACHMENT

ADS 11H Liner Multiple Drag Analysis


Slack-Off BHA Depth (Ft) 100 500 1000 1500 2000 2500 3000 3500 4000 4500 5000 5500 6000 6500 7000 7500 8000 8500 9000 9193 66147 73,916 83,328 92,728 102,603 111,736 119,668 128,098 136,097 143,587 151,024 158,059 164,212 181,084 174,982 192,144-200000 -250000 0 186,090 180,504 172,784 170,138 67,750 75,578 85,545 96,046 107,683 119,392 130,553 143,470 157,205 171,284 185,904 200,626 214,670 239,267 S-O W /O R otation A xial 257,609 263,092 -100000 -150000 -50000 0 265,643 266,562 268,513 270,254 Pick-UP

D rag
50000 100000

-5000

A xial

M .D . (ft)
Sin -10000

H lx

Prepared By: Ifediora Emmanuel


-15000

A xial D rag (lbf)

APD(N)L OML-123 ADS 11H COMPLETION PROGRAM

Revision 0 Page 27 of 32

Torque and drag Analysis Chart. It shows Assembly was successfully run to bottom with an open hole friction factor of 0.25. There was no Buckling and lockup. This result will be verified with the actual pick up and slack off weights after the hole is drilled and during deployment

API Tubing Running and Handling Procedure NOTE: Addax recommends API modified thread compound for all 8 round connections like Weatherford Lube Seal.

Prepared By: Ifediora Emmanuel

APD(N)L OML-123 ADS 11H COMPLETION PROGRAM

Revision 0 Page 28 of 32

1. The DSV to ensure that the tong operator use the correct make up torque before commencing the job. 2. All tubular connections shall be thoroughly cleaned and dried at the rig prior to running or inspection. 3. Drift the pipe with a clean, properly sized mandrel. If pipe is dirty inside, clean before drifting. 4. Thread protectors should always remain in place when moving or handling tubular. 5. By visual inspection ensure that all running equipment are available and in good condition. 6. Use slip type elevators. Ensure that the slips are of correct size to accommodate the size, weight and length of the tube. 7. Ensure that the safety clamp is of the correct size and in serviceable condition. NOTE: The safety clamp should be used above the table slips for the first 20 joints. 8. Check for traveling block alignment and rotary hole alignment. 9. Ensure that the power tong snub line is at 90o and level with the tong. NOTE: Ensure that an accurate torque monitoring device (Martin-Decker torque gauge) is available, the load cell is for use in the require torque range, and the load cell has been calibrated within the past four (4) months. 10. Joints should be moved to the V-door via a crane. 11. Drift the pipe with a clean, properly sized mandrel. Use Elevators, single joint elevator to lift the joint up in the Derrick. 12. As each length is suspended vertically, remove the thread protectors and the drift, clean both pin and box connectors to be made-up. 13. Visually inspect to assure no damage to either connector has occurred. 14. After the connection is clean and dry, apply a light, even coating of the thread compound to the pin connector. 15. Stab the pin connector into the box connector carefully to avoid damage to the connectors. 16. Back-up tongs should be placed below the coupling. 17. Position the power tongs approximately 7" above the coupling. 18. Before making up, back out the tubing until the threads jumps and are aligned. Make up the connection power-tight using a make-up speed between 5 and 14 RPM.

Prepared By: Ifediora Emmanuel

APD(N)L OML-123 ADS 11H COMPLETION PROGRAM

Revision 0 Page 29 of 32

Item No. RIG 1 2 3 3 4

ADS 11H Well Completion Equipment List


Descriptions 5" DP (19.2 ppf, 5" OD, 4-1/2" IF connection) 5" HWDP (5" OD, with 4-1/2" IF Connection) 6 DC 4-1/2" IF box x 4-1/2" Reg. pin 4-1/2" IF pin x 4-1/2" Reg. pin Quantity 135 joints 48 joints N/A 1 1 Supplier HI9 rig HI9 rig HI9 rig HI9 rig HI9 rig Location On board HI9 On board HI9 On board HI9 On board HI9 On board HI9 Remarks

OTHERS 1 7" Predrilled Liner 29# N-80 BTC 2 7" Blank Liner, 29# N-80 BTC 3 3-1/2" 9.3# EUE 8-rd Tubing 4 Tetra Hib (Corrosion Inhibitor) 5 No-Oxygen (Oxygen Scavenger) 6 Dirt Magnet 7 8-1/2" Hole Opener with bull nose 8 WW4002 (Organic Solvent) 9 Organic Acid 10 Calcium Chloride (CaCl2) 11 2-7/8" N-80 PH Tubing (Wash String) 12 9-5/8" Casing Scraper 13 8-1/2" PDC bit RR.

1,500 ft 1,000 ft 7,500 ft 135 gals 65 gals 5 drums 1 80bbls 140bbls 2,900 ft 1 1

Addax Addax Addax BHI BHI BHI AOS/Orwell Water wells MI BHI Addax Baker Addax

Port Harcourt Calabar Calabar Port Harcourt Port Harcourt Port Harcourt Port Harcourt Warri Port Harcourt Port Harcourt Calabar Port Harcourt On board TC

400 ft excess 1000 ft excess 300 ft excess 50% excess 50% excess 50% excess 20% excess 20% excess 150 ft excess

XMAS TREE 1 Tubing Hanger: 13-5/8" x 11" x 3-1/2" EUE 2 2 Tubing bonnet 2 3 Complete Xmas Tree: 3-18" 5M Xmas tree 2 made up of four (4) 3-1/2" 5M gate valves with two on the tree stem as lower and upper master valves, top valve acting as swab valve and one as wing valve, 3-1/8" 5M pneumatic actuated gate valve, 3-1/8" positive choke

Addax/DQ Addax/DQ Addax/DQ

Calabar / Port Harcourt Calabar / Port Harcourt Calabar/Port Backup inclusive Harcourt

Prepared By: Ifediora Emmanuel

APD(N)L OML-123 ADS 11H COMPLETION PROGRAM

Revision 0 Page 30 of 32

4 5 6

Two Way check valve for 3-1/8" Hanger. BPV for 3-1/8" Hanger. Running Tools

2 2 2

DQ DQ DQ

Port Harcourt Port Harcourt Port Harcourt

Backup inclusive Backup inclusive Backup inclusive

9-5/8" Packer, Predrilled Liner and Wash pipe Assembly 1 Size 7 x 2.875, Drillable Pack-off Bushing. 2 3 4 5 6 7 8 9 10 11 12 13 14 Size 9-5/8" x 6" Model "SC-1R" Packer with retrieving extension. Blank Liner Pup Joint, Size 7" x 10 ft, with 7" BTC Box x Pin KOIV size 7 x 5.0 ID with BTC conn. Baker Size 7" Shoe with 7" BTC Box Crossover Sub w/2-7/8" PH-6 Box x 2-7/8" CSH Pin. Swivel with 2- with crossover, 2- EUE 8rd Box x CSH Pin Baker model BSCR Hydro-Set Adapter kit, size 190-60 Size 7" Model "SC" Setting Tool, size 86 Spacer Joint (Mill out extension) SC-1R Packer retrieving tool 5" IF x 15' Drill Pipe Pup with Junk Bonnet Pup Joint, Size 2- with 2- CSH Box x Pin, to extend below the packer. Set of Pup Joints, Size 2-, 2', 4', 6', 8', 10' Lengths, with 2- CSH Box x Pin, to space out inner string (with thread protectors) Size 2- Slick stinger with 2- Hydril CS Box up Primary Setting Ball, Size 1-7/16, Stainless Steel Back Up Setting Ball, Size 1-3/4", Bakelite Bowl and Slips, for 2- Stripping Plate, for 7" Collar and 2- CSH " Inner String Metal Drift, Size 7", for 7" 29 ppf Teflon Drift, Size 2- for 2- 8.7 ppf

2
2 2 2 2 2 1 2 2 2 1 2 2 1

Baker Baker Addax Baker Baker Baker Baker Baker Baker Baker Baker Baker Baker Baker

Port Harcourt Port Harcourt Port Harcourt Port Harcourt Port Harcourt Port Harcourt Port Harcourt Port Harcourt Port Harcourt Port Harcourt Port Harcourt Port Harcourt Port Harcourt Port Harcourt

Backup inclusive Backup inclusive Backup inclusive 1 Backup inclusive Backup inclusive Backup inclusive

Backup inclusive Backup inclusive Backup inclusive Contingent Backup inclusive Backup inclusive Backup inclusive

15 16 17 18 19 20 21

1 1 2 1 1 1 1

Baker Baker Baker Baker Baker BJ BJ

Port Harcourt Port Harcourt Port Harcourt Port Harcourt Port Harcourt Port Harcourt Port Harcourt

Backup inclusive Backup inclusive Backup inclusive

3-1/2" Completion Assembly 1 2 Baker model S-22 Locator Seal, Size 190-47 with 10 ft seals with 3 9.3ppf EUE 8rd. 2 Baker Baker Port Harcourt Port Harcourt Backup inclusive Contingent

Baker model "FH" Double grip single string 1 hydrostatic set production packer, with 3-1/2" 9.3ppf EU 8rd Box x Pin Model "R" Bottom No-Go Seating Nipple, Size 2 3-1/2" x 2.750, with 2.697" No-Go ID, with 3-1/2" 9.3 ppf EU 8rd Box x Pin

Baker

Port Harcourt

Backup inclusive

Prepared By: Ifediora Emmanuel

APD(N)L OML-123 ADS 11H COMPLETION PROGRAM

Revision 0 Page 31 of 32

Flow Coupling, Size 3-1/2" x 6 ft., with 3-1/2" 9.3 ppf EU 8rd Box x Pin (across Nipples) 5 Model "F" Top No-Go Seating Nipple, Size 31/2" x 2.750, with 3-1/2" 9.3 ppf EU 8rd Box x Pin 6 Flow Coupling, Size 3-1/2" x 6 ft., with 3-1/2" 9.3 ppf Hydril CS Box x 3-1/2" 9.3 ppf EU 8rd Pin 7 Model "TE-5" Surface Controlled Subsurface Safety Valve, Size 3-1/2" x 2.812, with 3-1/2" 9.3 ppf Hydril CS Box x Pin 8 Flow Coupling, Size 3-1/2" x 6 ft., with 3-1/2" 9.3 ppf EU 8rd Box x 3-1/2" 9.3ppf Hydril CS Pin 9 6 ft Pup Joint, Size 3-1/2", with 3-1/2" EUE 8rd Box x Pin, (for GLMs) 10 6 ft Pup Joint, Size 3-1/2", with 3-1/2" EUE 8rd Box x Pin, (for SCSSV, seal assy, R & FNipples) 11 Set of Pup Joints, Size 3-1/2", 2', 4', 6', 8', 10' Lengths, with 3-1/2" EUE Box x Pin, (for tubing space out) 12 Model A ratcheting mule shoe, size 190-47 with 3-1/2 EU 8rd Box up 12 Control Line, Size 1/4" x .049, 316L Stainless Steel, Spool of 400 ft. 13 Setting Ball, Size 2-1/2", Kirksite 14 Control Line Stand 15 3-1/2" Teflon/steel drift 7" Liner, 3-1/2" & 2-7/8" Tubular Running Equipment 1 7-5/8" Hydraulic Power Tongs complete with ancillary equipment and integrated hydraulic backup. 2 Hydraulic power units complete ancillary equipment 3 350 Ton Varco spider complete 4 Jaws & Dies for 7-5/8", 6-5/8 5-1/2", 5", 4" & 27/8" 5 Jaws & Dies for 7", 6-5/8, 3-1/2" & 2-7/8" 6 Lifting slings 7 Type J single Joint elevator for 3-1/2" tubing 8 Type J single Joint elevator for 6-5/8 & 7" tubing 9 150 Ton Side door elevator 10 75 Ton YC/YT Elevators 11 500T flush mounted spider 12 500T slip assembly and top guide for 7" 13 YC/MYC Slip assembly and top guide for 3-1/2" 14 Rotary hand Slip for 6-5/8 & 7" Liner 15 Rotary hand Slip for 3-1/2" Tubing 16 Safety Clamp for 7" Liner 17 Safety Clamp for 3-1/2" Tubing

6 2 2 2

Baker Baker Baker Baker

Port Harcourt Port Harcourt Port Harcourt Port Harcourt

Backup inclusive Backup inclusive Backup inclusive Backup inclusive

2 4 6 1 2 2 2 1 1

Baker Addax Addax Addax Baker Baker Baker Baker Baker

Port Harcourt

Backup inclusive Check stock Check stock Check stock

Port Harcourt Port Harcourt Port Harcourt Port Harcourt Port Harcourt

Backup inclusive Backup inclusive Backup inclusive

BJ

Port Harcourt

Backup inclusive

1 2 2 2 2 sets 1 2 2 2 1 1 Set 1 Set 1 1 2 2

BJ BJ BJ BJ BJ BJ BJ BJ BJ BJ BJ BJ BJ BJ BJ BJ

Port Harcourt Port Harcourt Port Harcourt Port Harcourt Port Harcourt Port Harcourt Port Harcourt Port Harcourt Port Harcourt Port Harcourt Port Harcourt Port Harcourt Port Harcourt Port Harcourt Port Harcourt Port Harcourt Backup inclusive -Do-Do-DoBackup inclusive -Do-Do-

Backup inclusive Backup inclusive

Prepared By: Ifediora Emmanuel

APD(N)L OML-123 ADS 11H COMPLETION PROGRAM

Revision 0 Page 32 of 32

18 19 20 21 22

Klepo Gun for 7" Stabbing Guide for 3-1/2" Metal Drift, Size 6-5/8 24# & 7", for 7" 29 ppf Teflon Drift, Size 2- for 2- 8.7 ppf 7" Thread Protectors

6 1 1 1 6

BJ BJ BJ BJ BJ

Port Harcourt Port Harcourt Port Harcourt Port Harcourt Port Harcourt

GASLIFT MANDREL 1 Gas lift Mandrels with pre-installed Dummy valves SLICKLINE EQUIPMENT 1 Slick line Unit 2 Gauge Cutters (2.44 2.50, 2.72, 2.76, 2.83, 2.86) 3 2.2 Tapered Tool 4 2.75 RB-2 Plug 4 2.75 FB-2 Plug 5 2.75 plug redressing seals 6 Knuckle joints 7 1-7/8 Sinker Bars/Stems (2ft, 3ft, 5ft) 8 Jars 9 BOPs and Lubricator CONTENGENT 1 6 ft 6- BTC box x 7 BTC box crossover pup 2 3 6 ft 6- BTC box x 7 BTC pin crossover pup 6- 24ppf 13% Cr BTC Swell Packer

Weatherford Port Harcourt

2 2 2 2 2 1 2 4 2 1

Geoservices Geoservices Geoservices Geoservices Geoservices Geoservices Geoservices Geoservices Geoservices Geoservices

Back-up inclusive Back-up inclusive Back-up inclusive

Back-up inclusive Back-up inclusive Back-up inclusive

1 1 1

Addax Addax Addax

Calabar Calabar Calabar

Usage to be advised Usage to be advised Usage to be advised

Prepared By: Ifediora Emmanuel