You are on page 1of 44

Alcatel BSS

A9130 BSC Evolution Commissioning

BSC & TC Document Commissioning Manual Release B9

3BK 17422 3121 RJZZA Ed.20P08

BLANK PAGE BREAK

Status Short title

IN PREPARATION mxbsccom
All rights reserved. Passing on and copying of this document, use and communication of its contents not permitted without written authorization from Alcatel/Evolium.

2 / 44

IN PREPARATION

3BK 17422 3121 RJZZA Ed.20P08

Contents

Contents
Preface . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1 Overview . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1.1 Presentation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1.1.1 Hardware Description - Rack Configurations . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1.1.2 Cases . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1.1.3 Options . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1.1.4 Restrictions . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1.1.5 Grouped Task Sequence . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1.2 Preparation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1.2.1 Prerequisites . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1.2.2 Site-Specific Information . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1.3 Scheduling . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1.4 Resources . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1.4.1 Tools . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1.4.2 Supplies . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1.4.3 Applicable Documents . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . A9130 BSC Evolution Commissioning . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2.1 Before Going on Site . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2.2 Before You Start (On Arrival at the Site) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2.2.1 Checks . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2.2.2 Required Knowledge . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2.3 Complete BSC Configuration . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2.3.1 Install Boards in ATCA Shelf . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2.3.2 Check Boards Position in LIU Shelf . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2.3.3 Check the ATCA-LIU Ethernet Cables . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2.3.4 Check the JSXLIU Shelf Address . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2.3.5 Connect PCM Cables to JSXLIU Shelf . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2.4 Hardware Checks . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2.4.1 Check the Equipment Configuration . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2.4.2 Check the JAXPC Address . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2.4.3 Check the JBXFAN Switch Position . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2.5 Powering Up the BSC Rack . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2.5.1 Check the Customer Power Panel . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2.5.2 Check Polarity of DC Cables on BSC Side . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2.5.3 Powering Up the BSC Rack . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2.5.4 Check Power Line Redundancy . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2.6 Check BIOS Settings . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2.7 Software Installation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2.8 Check the Firmware Version . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2.9 Commissioning Tests . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2.9.1 Option: LMT Installation (O1) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2.9.2 Connect the LMT to the BSC . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2.9.3 Option: Connect O&M cables from MFS to BSC (O2) . . . . . . . . . . . . . . . . . . . . . . 2.9.4 Perform the Rack Inventory . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2.10 Connect the OMC-R . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2.11 Option: Check the Connection with the CBC . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2.11.1 Open a Telnet Session . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2.11.2 Ping the CBC . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2.12 End of Commissioning . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5 7 8 8 11 12 12 13 14 14 14 15 16 16 16 17 19 20 20 20 20 21 21 25 27 29 30 31 31 31 33 34 34 34 36 37 38 38 38 39 39 39 40 41 41 42 42 43 43

3BK 17422 3121 RJZZA Ed.20P08

IN PREPARATION

3 / 44

Contents

4 / 44

IN PREPARATION

3BK 17422 3121 RJZZA Ed.20P08

Preface

Preface
Purpose Whats New
This document describes the configuration and verification procedures to be carried out when commissioning the A9130 BSC Evolution in release B9.

In Edition 20
The reference to IO 114 was removed. Figures 2, 3, 12 , 15 and 18 were updated. Description update in Powering Up the BSC Rack (Section 2.5.3).

In Edition 01
First official release of the document.

Audience

This document is addressing to the following: Site administrators Supervisors Project managers Field service technicians Occasional users

Assumed Knowledge

The personnel involved must be familiar with: Commissioning tools Personal Computers using the Windows 2000/XP environment Digitals UNIX operating system environment.

3BK 17422 3121 RJZZA Ed.20P08

IN PREPARATION

5 / 44

Preface

6 / 44

IN PREPARATION

3BK 17422 3121 RJZZA Ed.20P08

1 Overview

1 Overview
This Overview gives information needed by project managers and foremen, for presentation to the customer and for site planning.

3BK 17422 3121 RJZZA Ed.20P08

IN PREPARATION

7 / 44

1 Overview

1.1 Presentation
1.1.1 Hardware Description - Rack Configurations
The following figure shows the rack layout for an A9130 BSC Evolution in 600 TRX configuration.

JSXPDU

Free Space (ATCA Shelf 4)

CLOSED

OPEN

H/S

OOS

CLOSED

OPEN

H/S

OOS

CLOSED

OPEN

H/S

OOS

CLOSED

OPEN

H/S

OOS

Not Used

Not Used
XLIU XLIU
4A

JBXOMCP

JBXOMCP

JBXSSW

Not Used

JBXSSW

JBXCCP

JBXCCP

JBXCCP

1234567890123456789 Air inlet 1234567890123456789 1234567890123456789


Free space (LIU Shelf 2)
1
XPEM

2 3 4
XLIU XLIU XLIU

5 6 7 8
XLIU XLIU XLIU XLIU

9 10 11 12 13 14 15 16 17 18 19 20 21
XLIU XMUX XMUX XLIU XLIU XLIU XLIU XLIU XLIU XPEM

LIU Shelf 1

JBXCCP

48 / 60 VDC

48 / 60 VDC

4A

Figure 1: Example of A9130 BSC Evolution Rack Layout - Front View

8 / 44

IN PREPARATION

Not Used

JBXTP

JBXTP

ATCA Shelf 3

3BK 17422 3121 RJZZA Ed.20P08

1 Overview

The following figure shows the rack layout for an A9130 BSC Evolution 600 TRX configuration /A9130 MFS Evolution 9 JBXGPU configuration in case of rack shared configuration.

JSXPDU
CLOSED / OPEN H/S OOS CLOSED / OPEN H/S OOS CLOSED / OPEN H/S OOS CLOSED / OPEN H/S OOS

JBXOMCP

JBXOMCP

Not Used

Not Used

Not Used JBXGPU


XLIU XLIU XPEM
48 / 60 VDC 4A

1234567890123456789 1234567890123456789 Air inlet 1234567890123456789 1234567890123456789


CLOSED / OPEN H/S OOS CLOSED / OPEN H/S OOS H/S CLOSED / OPEN OOS CLOSED / OPEN H/S OOS

JBXOMCP

JBXOMCP

JBXSSW

JBXSSW

JBXGPU

JBXGPU

JBXGPU

JBXGPU

JBXGPU

JBXGPU

JBXGPU

JBXGPU

1234567890123456789 1234567890123456789 Air inlet 1234567890123456789 1234567890123456789


1 2 3 4
XLIU

5 6 7 8
XLIU XLIU

9 10 11 12 13 14 15 16 17 18 19 20 21
XLIU XMUX XMUX XLIU XLIU XLIU XLIU XLIU XLIU

LIU Shelf 2

XPEM

XLIU

XLIU

XLIU

XLIU

48 / 60 VDC

4A

2 3 4
XLIU XLIU XLIU

5 6 7 8
XLIU XLIU XLIU XLIU

9 10 11 12 13 14 15 16 17 18 19 20 21
XLIU XMUX XMUX XLIU XLIU XLIU XLIU XLIU XLIU XLIU XLIU XPEM

LIU Shelf 1

XPEM

48 / 60 VDC

48 / 60 VDC

4A 4A

graphics/174223121003.cgm

Figure 2: Example of A9130 BSC Evolution Rack Layout - Front View

JBXGPU

ATCA Shelf 3

Not Used

JBXSSW

JBXSSW

JBXCCP

JBXCCP

JBXCCP

JBXCCP

JBXTP

JBXTP

ATCA Shelf 4

3BK 17422 3121 RJZZA Ed.20P08

IN PREPARATION

9 / 44

1 Overview

The following figure shows the rack layout in case of rack shared by two A9130 BSCs Evolution 600 TRX configuration.

JSXPDU
CLOSED / OPEN H/S OOS CLOSED / OPEN H/S OOS CLOSED / OPEN H/S OOS CLOSED / OPEN H/S OOS

JBXOMCP

JBXOMCP

Not Used

Not Used

Not Used Not Used


XLIU XLIU XPEM
48 / 60 VDC 4A

1234567890123456789 1234567890123456789 Air inlet 1234567890123456789 1234567890123456789


CLOSED / OPEN H/S OOS CLOSED / OPEN H/S OOS CLOSED / OPEN H/S OOS CLOSED / OPEN H/S OOS

JBXOMCP

JBXOMCP

Not Used

Not Used

1234567890123456789 1234567890123456789 Air inlet 1234567890123456789 1234567890123456789


1 2 3 4
XLIU

5 6 7 8
XLIU XLIU

9 10 11 12 13 14 15 16 17 18 19 20 21
XLIU XMUX XMUX XLIU XLIU XLIU XLIU XLIU XLIU

XPEM

XLIU

XLIU

XLIU

XLIU

LIU Shelf 2
48 / 60 VDC 4A

1
XPEM

2 3 4
XLIU XLIU XLIU

5 6 7 8
XLIU XLIU XLIU XLIU

9 10 11 12 13 14 15 16 17 18 19 20 21
XLIU XMUX XMUX XLIU XLIU XLIU XLIU XLIU XLIU XLIU XLIU XPEM

LIU Shelf 1
48 / 60 VDC 48 / 60 VDC 4A 4A

graphics/174223121006.cgm

Figure 3: Example of Two A9130 BSC Evolution Rack Layout - Front View

10 / 44

IN PREPARATION

Not Used

JBXSSW

JBXSSW

JBXCCP

JBXCCP

JBXCCP

JBXCCP

JBXTP

JBXTP

ATCA Shelf 3

Not Used

JBXSSW

JBXSSW

JBXCCP

JBXCCP

JBXCCP

JBXCCP

JBXTP

JBXTP

ATCA Shelf 4

3BK 17422 3121 RJZZA Ed.20P08

1 Overview

The following figure shows the back rack layout for an A9130 BSC Evolution in any configuration.

12345678901234567890 12345678901234567890 Air outlet 12345678901234567890 12345678901234567890


JAXSSW

ATCA Shelf 3 (rear side)


JBXPS
(POWER)

JAXSSW
JAXSMM

JAXSMM
OOS OK ACT

JBXPS
(POWER)

JBXPS JBXPS
(POWER) (POWER)

Telco Alarms & Relays

OK ACT

Alarm/ Reset H/S

Alarm/ Reset H/S

+(RETURN)

+(RETURN)

+(RETURN)

+(RETURN)

Handle

Closed Open

Closed Open

H/S

OOS

OOS

H/S

OK

Handle

Telco Alarms & Relays

OOS

JAXPC JAXPC
JAXPC JAXPC

GND
OK

graphics/174223121002.cgm

Figure 4: Example of A9130 BSC Evolution Rack Layout - Rear View

1.1.2 Cases
None.

3BK 17422 3121 RJZZA Ed.20P08

IN PREPARATION

11 / 44

1 Overview

1.1.3 Options
The following option applies: O1: Install LMT O2: Connect O&M cables from MFS to BSC, in rack shared configuration

1.1.4 Restrictions
None.

12 / 44

IN PREPARATION

3BK 17422 3121 RJZZA Ed.20P08

1 Overview

1.1.5 Grouped Task Sequence


The following figure shows the task sequence for the A9130 BSC Evolution commissioning.

Before going site

Before you start

Boards installation

Hardware check

Set LIU shelf address

Power up rack

Check firmware version

Commisioning test

Connect the OMCR

Check connection to CBC

End commissioning
graphics/174213121opprinc.cgm

3BK 17422 3121 RJZZA Ed.20P08

IN PREPARATION

13 / 44

1 Overview

1.2 Preparation
1.2.1 Prerequisites
The following prerequisites apply: The site must conform to the "Safety rules" (see BSS Methods Handbook). The site must conform to SPP- 59, Specification for Site Preparation A9130-BSC The OMC-R must be operational and ready for connection to the BSC. The router must be configured and ready for connection (if applicable).

1.2.2 Site-Specific Information


Network information: BSC Id and name External Host name, external IP address and netmask for each OMCP station IP address of the alias host name for active station ("station_BSC") IP address for the default gateway for external network used for connection BSC - OMC IP address for the CBC User name and password for external router between BSC and CBC Ports in external router where to connect the Ethernet cables Routing configuration between OMC-R and BSC Local network sockets position to plug in the OMCP Servers network cables (if applicable) Position of cables connection on the CISCO router to plug in the OMCP Servers network cables (if applicable). BSC configuration: Number of CCP boards.

14 / 44

IN PREPARATION

3BK 17422 3121 RJZZA Ed.20P08

1 Overview

1.3 Scheduling
The following table gives the duration for each task. Task Preliminary checks Preparation before leaving for the site Before starting (on arrival at the site) Boards installation Hardware check Set LIU shelf address Powering up the BSC rack Check the power panel Check the polarity on the BSC side Powering up the BSC rack Check power line redundancy Check firmware version Commissioning tests Option: LMT installation Connecting LMT to the BSC Software installation Perform rack inventory Connecting the OMC-R Option: Check the connection with the CBC End of commissioning Total Table 1: Scheduling 20 2 65 15 10 5 10 4h10 5 10 5 10 30 15 10 20 10 5 Duration (min)

3BK 17422 3121 RJZZA Ed.20P08

IN PREPARATION

15 / 44

1 Overview

1.4 Resources
1.4.1 Tools
1.4.1.1 Hardware Tools
The following table is used to check, at base, the availability of the necessary tools. SeeTools Catalogue for Field Activity for checking the content. Kit name Basic kit Test cables and plugs (BSC) Utility PC (IMT) Digital multimeter Reference OUT 001 OUT 013 DES 002 DES 001 Calibration NO NO NO NO

1.4.1.2 Software Tools


The following table is used to check, at base, the availability and the version of the necessary software. Refer to the corresponding document for checking the SW version. Name Windows 2000/XP Netscape Communicator 4.78 Version checking -

1.4.1.3 Forms
None.

1.4.2 Supplies
None.

16 / 44

IN PREPARATION

3BK 17422 3121 RJZZA Ed.20P08

1 Overview

1.4.3 Applicable Documents


The following list is used to check, at base, the availability of the necessary documents. Catalogue of Technical and Logistic Information (ITL), 3DF 00462 0004 AAAGA Catalogue of Instruction Operation (IO), 3DF 00300 0004 UAZZA B9 BSS Methods Handbook, 3BK 17422 0002 PCZZA CI 08 - Site Equipment Inventory, 3BK 17257 0001 RJZZA Tools Catalogue for Field Activity, 3BK 20458 0001 RJZZA SPP-59, Specification for Site Preparation A9130 MFS/BSC Evolution, 8BL 00704 0076 DRZZA BSS site premises inspections, post handover, 8BL 00704 0016 DRBRA Site Premises Inspection Form (CEL), 8BL 00704 0015 DRBRA A9130 BSC Evolution Software Installation, 3BK 17422 3126 RJZZA A9130 BSC Evolution Firmware Upgrade, 3BK 17422 3106 RJZZA.

3BK 17422 3121 RJZZA Ed.20P08

IN PREPARATION

17 / 44

1 Overview

18 / 44

IN PREPARATION

3BK 17422 3121 RJZZA Ed.20P08

2 A9130 BSC Evolution Commissioning

2 A9130 BSC Evolution Commissioning


This section describes the tasks to be performed during A9130 BSC Evolution commissioning.

3BK 17422 3121 RJZZA Ed.20P08

IN PREPARATION

19 / 44

2 A9130 BSC Evolution Commissioning

2.1 Before Going on Site


Before going on site you must check the following: All Prerequisites (Section 1.2.1) are fulfilled The customer has been informed of the Date and time Site name and address Purpose of the operation. Personnel are available and ready for operation (refer to Scheduling (Section 1.3) Site-Specific Information (Section 1.2.2) is available Tools (Section 1.4.1) are available and ready for operation Software Tools (Section 1.4.1.2 ) are available and ready for operation Applicable Documents (Section 1.4.3) are available.

2.2 Before You Start (On Arrival at the Site)


2.2.1 Checks
Before you start, perform the following operations: Check that all Prerequisites (Section 1.2.1) are fulfilled Check applicable notifications and operating instructions (refer to the Applicable Notifications List and Applicable Operation Instructions List) Check the availability of all necessary tools and supplies. Refer to BSS site premises inspections, post handover and complete the Site Premises Inspection Form (CEL). Check that the safety precautions have been taken in accordance with the safety instructions described in the B9 BSS Methods Handbook. Check which Cases (Section 1.1.2) or Options (Section 1.1.3) apply Complete the header field of the CCL. The CCL is completed as each instruction is carried out.

2.2.2 Required Knowledge


You must be familiar with the following: The safety rules and precautions given in the B9 BSS Methods Handbook. How to document faults and anomalies as described in the B9 BSS Methods Handbook.

20 / 44

IN PREPARATION

3BK 17422 3121 RJZZA Ed.20P08

2 A9130 BSC Evolution Commissioning

2.3 Complete BSC Configuration


2.3.1 Install Boards in ATCA Shelf
To install the boards: 1. Check the configuration requested by the customer. Refer to Site-Specific Information (Section 1.2.2) for details.

Note:

Shelf filling is done from center to shelf sides. The following tables gives the JBXCCP boards allocation in ATCA shelf. Physical slots 1 2 3 4 x 5 x x x 6 7 8 9 10 x x x 11 x x 12 13 14 -

Boards

Configuration (No. of TRX)

JBXCCP

200 400 600

Table 2: JBXCCP Position in ATCA Shelf The ATCA configuration is described in the following figure:
CLOSED / OPEN H/S OOS CLOSED / OPEN H/S OOS

CLOSED

OPEN

H/S

OOS

CLOSED

OPEN

H/S

OOS

Physical 1 slot

9 10 11 12 13 14

JBXOMCP

JBXOMCP

Not Used

Not Used

123456789012345678901234567890121 123456789012345678901234567890121 Air inlet 123456789012345678901234567890121 123456789012345678901234567890121 123456789012345678901234567890121


graphics/174223121004.cgm

Figure 5: ATCA Shelf Boards

Not Used

Not Used
21 / 44

JBXCCP

JBXCCP

JBXSSW

JBXSSW

JBXCCP

3BK 17422 3121 RJZZA Ed.20P08

JBXCCP

JBXTP

JBXTP

IN PREPARATION

2 A9130 BSC Evolution Commissioning

2. Put on an ESD wrist strap and connect it to the shelf by attaching the front or rear ESD jack. 3. Ensure that the lower and upper handles are in the outward position. 4. Insert the board into the shelf by placing the top and bottom edges of the board in the card guides of the shelf. Ensure that the guiding module of shelf and board are aligned properly. Press the lower and upper parts of the handle together.

graphics/174213111018.cgm

Figure 6: Insert the Board 5. Slide the board into the shelf until you feel resistance.

22 / 44

IN PREPARATION

3BK 17422 3121 RJZZA Ed.20P08

2 A9130 BSC Evolution Commissioning

6. Simultaneously move the top and bottom handles to the inward position to lock the board to the shelf.

graphics/174213111blade.cgm

Figure 7: Board in ATCA Shelf, Secured with Handles to the Inward Position

3BK 17422 3121 RJZZA Ed.20P08

IN PREPARATION

23 / 44

2 A9130 BSC Evolution Commissioning

7. Install one by one all the boards for the requested configuration. During boards insertion: Holes on back side of the board must be in line with guiding pins on the back plane

graphics/174213111008.gif

Figure 8: Holes in Line with Guiding Pins EMI stripes must not be damaged when inserting the boards

graphics/174213111009.gif

Figure 9: EMI Stripes 8. Tighten the front plate screws to secure the board to the shelf. 9. Insert a filler (JBXFILL) in each unused slot. 10. Tighten the front plate screws to secure the filler to the shelf.

24 / 44

IN PREPARATION

3BK 17422 3121 RJZZA Ed.20P08

2 A9130 BSC Evolution Commissioning

2.3.2 Check Boards Position in LIU Shelf


Check the configuration requested by the customer. Refer to Site-Specific Information (Section 1.2.2) for details. In case of 200 and 400 TRX configurations check that there are boards on slots 19 and 20 (for slot numbering, see Figure 2), otherwise you must replace the JBXDUM fillers from slots 19 and 20 with the JBXLIU boards from slots 8 and 9, using the procedure below. The following table shows the boards correspondence in case of replacing JBXLIU with JBXDUM: JBXLIU Slot No. in LIU Shelf 8 9 Table 3: Boards Correspondence To move the boards from slots 8 and 9 to slots 19 and 20, in LIU shelf: 1. Put on an ESD wrist strap and connect it to the shelf by attaching the front or rear ESD jack 2. Unfasten the top and the bottom screws of the JBXDUM fillers. 3. Remove the JBXDUM fillers. 4. Unfasten the top and the bottom screws of the JBXLIU boards. The bottom screw is located under the handle. 5. Using the board handle, remove the JBXLIU boards. 6. Using the board handle, insert the JBXLIU boards to the corresponding slots, until you feel resistance (for boards correspondence see Table 3). 7. Fasten the top and the bottom screws of the JBXLIU boards. 8. Insert the JBXDUM fillers in the empty slots. 9. Fasten the top and the bottom screws of the JBXDUM fillers. The following figures show the LIU shelf for different A9130 BSC Evolution 200 and 400 TRX configurations.
JBXPEM JBXLIU JBXLIU JBXLIU JBXLIU JBXLIU JBXLIU JBXDUM JBXDUM JBXMUX JBXMUX JBXDUM JBXDUM JBXDUM JBXDUM JBXDUM JBXDUM JBXLIU JBXLIU JBXPEM

JBXDUM 19 20

48 / 60 VDC

48 / 60 VDC

4A 4A

graphics/174213121001.cgm

Figure 10: LIU Shelf for BSC with 200 and 400 TRX Configuration

3BK 17422 3121 RJZZA Ed.20P08

IN PREPARATION

25 / 44

2 A9130 BSC Evolution Commissioning

The following figures show the LIU shelf for different A9130 BSC Evolution 600 TRX configuration.
JBXPEM JBXLIU JBXLIU JBXLIU JBXLIU JBXLIU JBXLIU JBXLIU JBXLIU JBXMUX JBXMUX JBXLIU JBXLIU JBXLIU JBXLIU JBXLIU JBXLIU JBXLIU JBXLIU JBXPEM

48 / 60 VDC

48 / 60 VDC

4A 4A

.cgm

Figure 11: LIU Shelf for BSC with 600 TRX Configuration

26 / 44

IN PREPARATION

3BK 17422 3121 RJZZA Ed.20P08

2 A9130 BSC Evolution Commissioning

2.3.3 Check the ATCA-LIU Ethernet Cables


Shelves used for A9130 BSC Evolution configurations are: ATCA shelf 3 with LIU shelf 1 ATCA shelf 4 and LIU shelf 2. Therefore the inter-shelves Ethernet cables are always connected between: ATCA shelf 3 and LIU shelf 1 ATCA shelf 4 and LIU shelf 2. To connect ATCA-LIU Ethernet cables: 1. Connect the first JLCAT6 Ethernet cable (1AB 22983 0005) on ATCA shelf 3/4, JAXSSW1, Ethernet port 2. See Figure 12.
ETH 1

ETH 1

ETH 2
ETH 3 ETH 4 ETH 5 ETH 6 ETH 7 ETH 8 OOS

ETH 2
ETH 3 ETH 4 ETH 5 ETH 6 ETH 7 ETH 8 OOS

OK

OK

ACT

ACT

ATCA Shelf 3 Rear side


HS HS

JAXSSW2 JAXSSW1 JLCAT6 Ethernet cables 1AB 22983 0005

JBXLIU JBXLIU JBXMUX JBXDUM JBXMUX JBXLIU JBXLIU

Test

Test

GbE

GbE

LIU Shelf 1 Front side

.cgm

Figure 12: JLCAT6 Cable Connection

3BK 17422 3121 RJZZA Ed.20P08

IN PREPARATION

27 / 44

2 A9130 BSC Evolution Commissioning

2. Run the cable under the JSXLIU shelf 1

ATCA Shelf 4

ATCA Shelf 3

FRONT
Free Space (LIU Shelf 2)

REAR

LIU Shelf 1

123456789012345678 123456789012345678
graphics/174213111014.cgm

Figure 13: JLCAT6 Cable Routing 3. Connect the first JLCAT6 Ethernet cable (1AB 22983 0005) to the GbE port on JBXMUX1 (slot 10) in JSXLIU shelf 1/2. See Figure 12. 4. Connect the second JLCAT6 Ethernet cable (1AB 22983 0005) on ATCA shelf 3/4, JAXSSW2, Ethernet port 2. See Figure 12. 5. Run the cable under the JSXLIU shelf 1. See Figure 13. 6. Connect the second JLCAT6 Ethernet cable (1AB 22983 0005) to the GbE port on JBXMUX2 (slot 12) in JSXLIU shelf 1/2. See Figure 12. To connect the OMC-R Ethernet cables: 1. Identify the OMC-R Ethernet cables 2. Connect the first OMC-R Ethernet cable to the ATCA shelf 3/4 JAXSSW1, Ethernet port 3 3. Label the cables near the connectors.

28 / 44

IN PREPARATION

3BK 17422 3121 RJZZA Ed.20P08

2 A9130 BSC Evolution Commissioning

2.3.4 Check the JSXLIU Shelf Address


To check the JSXLIU shelf address: 1. Remove the dummy panel from the slot 11 in JSXLIU shelf 2. On the slot 11 check that the shelf address is set to 1, jumper from position 1 is removed
1 2 3 4 5 6 7 8

MUX A

PEM A

LIU 16

LIU 10

LIU 14

LIU 12

LIU 13

LIU 15

MUX B

10

11

12

13

14

15

16

17

18

19

20

graphics/174213111001.cgm

Figure 14: Slot 11 Back Panel Jumper Numbering 3. If the shelf address is set to 1 continue with step 8 4. If the shelf address is not set to 1, set it following the next steps 5. Remove the JBXMUX boards and some JBXLIU boards to have better access to the back panel 6. On the slot 11 on back panel remove the jumper from position 1, if equipped, in order to set the shelf address to "1 (See Figure 14) 7. Insert the JBXLIU and JBXMUX boards and secure it with the screws 8. Fix the dummy panel on slot 11 and fix it with the screws.

PEM B

LIU 11

LIU 6

LIU 4

LIU 7

LIU 8

LIU 2

LIU 3

LIU 5

LIU 9

LIU 1

21

3BK 17422 3121 RJZZA Ed.20P08

IN PREPARATION

29 / 44

2 A9130 BSC Evolution Commissioning

2.3.5 Connect PCM Cables to JSXLIU Shelf


To connect the PCM cables to the JSXLIU shelf: 1. Connect the cables to the JBXLIU boards 2. Check that there is a good connection of the cables 3. Close the front door to check if the cables are not stressed by it 4. Open the front door and arrange the cables if necessary 5. Attach the cables to the rack 6. Label the cables near the connectors.

30 / 44

IN PREPARATION

3BK 17422 3121 RJZZA Ed.20P08

2 A9130 BSC Evolution Commissioning

2.4 Hardware Checks


2.4.1 Check the Equipment Configuration
The hardware check is done to see if the equipment configuration corresponds to the customers order. Check the presence and position of the boards according to the requested configuration. Refer to the Site-Specific Information and Hardware Description - Rack Configurations sections.

2.4.2 Check the JAXPC Address


To check the JAXPC address: 1. Put on an ESD wrist strap and connect it to the shelf by attaching the front or rear ESD jack. 2. Unfasten the screws fixing the JAXPC card to the ATCA shelf. 3. Carefully remove the JAXPC card from the slot. 4. Check if S2 switch is set to 0 and S1 switch is set to 3 for shelf 3 and to 4 for shelf 4 . If different setting is present correct it as follows.

S2

S1

.cgm

Figure 15: Rotary Switches on JAXPC Card

3BK 17422 3121 RJZZA Ed.20P08

IN PREPARATION

31 / 44

2 A9130 BSC Evolution Commissioning

5. On the JAXPC board set the S2 switch to 0. 6. On the JAXPC board set the S1 switch to 3 for shelf 3 and to 4 for shelf 4. See Figure 2 for shelf numbering. 7. Carefully insert the JAXPC card in the slot. 8. Tighten the screws fixing the JAXPC card to the ATCA shelf. 9. Place the JAXPC board handle switch to Closed position.

32 / 44

IN PREPARATION

3BK 17422 3121 RJZZA Ed.20P08

2 A9130 BSC Evolution Commissioning

2.4.3 Check the JBXFAN Switch Position


To check the JBXFAN switch position: 1. Unfasten the screws fixing the JBXFAN cover plate.

graphics/174213111011.gif

Figure 16: JBXFAN Cover Fixing Screws 2. Remove the JBXFAN cover plate.

graphics/174213111012.gif

Figure 17: Remove JBXFAN Cover 3. Check if JBXFAN switch is set to Closed position otherwise set it to Close position. 4. Perform the check for all four JBXFAN units and for all equipped ATCA shelves. 5. Fit back the JBXFAN cover and fasten the fixing screws.

3BK 17422 3121 RJZZA Ed.20P08

IN PREPARATION

33 / 44

2 A9130 BSC Evolution Commissioning

2.5 Powering Up the BSC Rack


Two people are needed for performing this task.

2.5.1 Check the Customer Power Panel


To check the rating of the fuses: 1. On the customer power panel, check for the existence of two DC power supply distribution circuits. Each distribution circuit is provided with a DC circuit breaker (fuse holder). (See Site-Specific Information (Section 1.2.2) ) 2. On the power panel, disconnect the two -48V power supply lines by using the fuse holders for the rack. 3. Check that the fuse ratings are in accordance with the SPP document (See SPP-59).

2.5.2 Check Polarity of DC Cables on BSC Side


To check the connection of the power cables between the site power panel and the power interface on the BSC side: 1. At the customer power panel, make sure the two power lines for the BSC are disconnected (breakers OFF) (See Site-Specific Information (Section 1.2.2) ). 2. At the A9130 BSC, check that the A1 to A5 and B1 to B5 switches, located at the front of the PDU, are OFF. If not, switch them OFF.
A1 A2 A3 A4 A5 B1 B2 B3 B4 B5

I
O

I
O

I
O

I
O

I
O

I
O

I
O

I
O

I
O

I
O

Shelf 4

Shelf 2

Shelf 3

Shelf 1

Shelf 4

Shelf 2

Shelf 3

Shelf 1

graphics/174213111pdu.cgm

Figure 18: PDU on top of A9130 BSC (JSXPDU)

34 / 44

IN PREPARATION

3BK 17422 3121 RJZZA Ed.20P08

2 A9130 BSC Evolution Commissioning

3. At the top of the BSC rack, remove the PDU cover.


Cover (made of two independent parts for branch A and B) 35 mm
2

from power station VBAT

Breaker

BATR

GND

Cables must be fixed on this plane 16 mm


2

to ATCA shelf

cover.cgm

Figure 19: Connections for One Single Breaker 4. Check the power line connections for both lines A and B: Blue cables in the BATA and BATB position Black cables in the BATR position Yellow-green cable in GND position 5. Check that nothing can cause a short circuit between the BATA, BATB and BATR connectors.
Line cable from power station (branch A) 35 mm 2 diameter 14 mm Line cable from power station (Branch B) 35 mm 2 diameter 14 mm

BATA BATR

BATB BATR

Earthing (GND)

75A

10A

75A

10A

75A

75A

10A

75A

10A

75A

Racking braket

Battery return connection plate (BATR)

con.cgm

Figure 20: Connections from Power Station to PDU

3BK 17422 3121 RJZZA Ed.20P08

IN PREPARATION

35 / 44

2 A9130 BSC Evolution Commissioning

6. On the site power panel, connect the power supply line, using fuse holder A first. Circuit A is connected. 7. Test the A circuit. Check with the multimeter the presence of -48V and the polarity between BATA and BATR. 8. On the site power panel, disconnect the power supply line, using fuse holder A. 9. Repeat the previous operations for circuit B. Check the presence of -48V and the polarity between BATA/B and BATR on each circuit, then leave the circuits disconnected. 10. Replace the PDU cover plate.

2.5.3 Powering Up the BSC Rack


In the following steps power up only the shelves used by the installed configuration. To power up the BSC rack: 1. On the JSXPDU, check that the corresponding switches, Ax and BX are in the OFF position (see Figure 18) where: x is 1 for Shelf 4 x is 3 for Shelf 3 2. Check that switches on JBXPS modules are switched OFF, otherwise set them OFF. 3. On the site power panel, connect the DC power supply lines (circuits A and B). DC Lines A and B are connected.

Power Up ATCA3 Shelf

4. If ATCA3 shelf is used, switch ON (engage) the breakers A3 and B3. 5. Check on each JBXPS front panel that Rev. Power LED is OFF. If Rev. Power LED is ON switch OFF the breakers A3 and B3 and check power polarity on JBXPS terminals. 6. Switch ON the breaker on all JBXPS modules.

Power Up ATCA4 Shelf

7. If ATCA4 shelf is used, switch ON (engage) the switches A1 and B1. 8. Check on each JBXPS front panel that Rev. Power LED is OFF. If Rev. Power LED is ON switch OFF the breakers A1 and B1 and check power polarity on JBXPS terminals. If two shelves are used for the MFS, both shelves must be powered up. 9. Switch ON the breaker on all JBXPS modules.

Power Up JSXLIU1 Shelf 10. Switch ON (engage) the switches A4 and B4, if JSXLIU1 shelf is used.
Power LED on JBXPEMs in JSXLIU shelf switches ON.

Power Up JSXLIU2 Shelf 11. Switch ON (engage) the switches A2 and B2, if JSXLIU2 shelf is used.
Power LED on JBXPEMs in JSXLIU shelf switches ON.

36 / 44

IN PREPARATION

3BK 17422 3121 RJZZA Ed.20P08

2 A9130 BSC Evolution Commissioning

2.5.4 Check Power Line Redundancy


2.5.4.1 Check Power Redundancy for ATCA Shelves
To check the power line redundancy for ATCA shelves: 1. On the power distribution unit (JSXPDU), switch OFF the -48 V DC power supply lines A3 (if ATCA shelf 3 is used) or A1 (if ATCA shelf 4 is used) using the corresponding fuse holders. If two shelves are used for the MFS, A3 and A1 lines must be switched OFF. 2. Check that the ATCA shelves remain powered up and the boards are not affected (check the LED states). 3. Switch ON the -48 V DC power supply lines A3 (if ATCA shelf 3 is used) or A1 (if ATCA shelf 4 is used). No boards are affected and lines A3 and A1 are connected. If two shelves are used for the MFS, A3 and A1 lines must be switched ON. 4. On the power distribution unit (JSXPDU), switch OFF the -48 V DC power supply lines B3 (if ATCA shelf 3 is used) or B1 (if ATCA shelf 4 is used) using the corresponding fuse holders. If two shelves are used for the MFS, B3 and B1 lines must be switched OFF. 5. Check that the ATCA shelves remain powered up and the boards are not affected (check the LED states). 6. Switch ON the -48 V DC power supply lines B3 (if ATCA shelf 3 is used) and B1 (if ATCA shelf 4 is equipped) No boards are affected and lines B3 and B1 are connected. If two shelves are used for the MFS, B3 and B1 lines must be switched ON.

2.5.4.2 Check Power Redundancy for LIU Shelf


To check the power line redundancy for JSXLIU shelf: 1. On the power distribution unit (JSXPDU), disconnect the -48 V DC power supply line A4 (if JSXLIU shelf 1 is used) or A2 (if JSXLIU 2 is used). 2. Check that the boards in JSXLIU shelf remain powered up and are not affected (The LED on the left JBXPEM front plate is orange). 3. Reconnect the -48 V DC power line A4 (if JSXLIU shelf 1 is used) or A2 (if JSXLIU 2 is used). No boards are affected and line A4 or A2 are connected. 4. On the power distribution unit (JSXPDU), disconnect the -48 V DC power supply line B4 (if JSXLIU shelf 1 is used) or B2 (if JSXLIU 2 is used). 5. Check that the boards in JSXLIU shelf remain powered up and are not affected (The LED on the right JBXPEM front plate is orange). 6. Reconnect the -48 V DC power line B4(if JSXLIU shelf 1 is used) or B2 (if JSXLIU 2 is used). No boards are affected and line B4 or B2 are connected.

3BK 17422 3121 RJZZA Ed.20P08

IN PREPARATION

37 / 44

2 A9130 BSC Evolution Commissioning

2.6 Check BIOS Settings


Perform the following steps for both OMCP1 and OMCP2 boards. To check System Date & Time and Boot Sequence on the OMCPs: 1. Connect to OMCP console: For WinXP: telnet 172.17.y.8 <port number> Port number is 4503 for OMCP1 Port number is 4504 for OMCP2 y is 3 if the subrack is in lower y is 4 if the subrack is in upper For Win2000: telnet set term vt100 open 172.17.y.8 <port number> Port number is 4503 for OMCP1 Port number is 4504 for OMCP2 y is 3 if the subrack is in lower y is 4 if the subrack is in upper 2. Reset the OMCP board: reboot 3. In order to enter in OMCP BIOS use the sequence ESC+2 from the installation PC keyboard. You must enter this sequence during the station reboot with OMCP console window selected. 4. Check that the System date and time are the current ones, otherwise you must correct it. 5. Check that in the boot sequence, the Hard drive is on the first position, otherwise you must modify it. 6. Save the changes you made and exit the BIOS.

position position

position position

2.7 Software Installation


To install the A9130 BSC Evolution software, refer to the A9130 BSC Evolution Software Installation document (3BK 17422 3126 RJZZA). After finishing the software installation perform the commissioning tests.

2.8 Check the Firmware Version


For checking the Firmware Version please refer to A9130 BSC Evolution Firmware Upgrade.

38 / 44

IN PREPARATION

3BK 17422 3121 RJZZA Ed.20P08

2 A9130 BSC Evolution Commissioning

2.9 Commissioning Tests


2.9.1 Option: LMT Installation (O1)
For B9 Release: If you have not already installed the LMT, refer to the A9130 BSC Evolution Terminal User Guide for how to install and configure the LMT.

2.9.2 Connect the LMT to the BSC


The LMT cable (with RJ45 connector) must be available at ATCA shelf rear side (shelf 3 or 4). 1. Connect the LMT to the JAXSSW1 (position 7 on used ATCA shelf rear side), port ETH8. See Tools (Section 1.4.1)

ETH 1 ETH 2 ETH 3 ETH 4 ETH 5 ETH 6 ETH 7 ETH 8 OOS

OK

ACT

HS

rtm.cgm

Figure 21: JAXSSW at the ATCA Rear Side

3BK 17422 3121 RJZZA Ed.20P08

IN PREPARATION

39 / 44

2 A9130 BSC Evolution Commissioning

2. Check on the front panel that the LED corresponding to the connection port is lit (for the port Eth8 the corresponding LED is situated on row 8 column C).
A B C

1 2 3 4 5 6 7 8

B A S E

I N T E R F A C E

graphics/174223121005.cgm

Figure 22: Part of JBXSSW Front Plate

2.9.3 Option: Connect O&M cables from MFS to BSC (O2)


In case of rack shared configuration, O&M link can be transported from MFS to OMC-R via BSC. On ATCA rear side, connect the O&M Ethernet cables as follows: 1. Connect the first JLCAT6 cable (1AB229830001) from ATCA Shelf 4 JAXSSW1 port ETH1 to ATCA Shelf 3 JAXSSW1 port ETH1. 2. Connect the second JLCAT6 cable (1AB229830001) from ATCA Shelf 4 JAXSSW2 port ETH1 to ATCA Shelf 3 JAXSSW2 port ETH1.

1234567890123456789 1234567890123456789 1234567890123456789


ETH 1
ETH 2 ETH 3 ETH 4 ETH 5 ETH 6 ETH 7 ETH 8 OOS

ETH 1
ETH 2 ETH 3 ETH 4 ETH 5 ETH 6 ETH 7 ETH 8 OOS

OK

OK

ACT

ACT

ATCA 4 rear side


HS HS

12345678901234567890 Ethernet 12345678901234567890 cables between 12345678901234567890 ATCAs 12345678901234567890 12345678901234567890


ETH 1
ETH 2 ETH 3 ETH 4 ETH 5 ETH 6 ETH 7 ETH 8 OOS

JAXSSW 2

JAXSSW 1

ETH 1
ETH 2 ETH 3 ETH 4 ETH 5 ETH 6 ETH 7 ETH 8 OOS

OK

OK

ACT

ACT

ATCA 3 rear side


HS HS

12345678901234567890 12345678901234567890
graphics/174213111interatca.cgm

JAXSSW JAXSSW 2 1

Figure 23: ATCA Shelf 3,4 rear side

40 / 44

IN PREPARATION

3BK 17422 3121 RJZZA Ed.20P08

2 A9130 BSC Evolution Commissioning

2.9.4 Perform the Rack Inventory


To check the firmware status and the hardware technical level of the hardware by performing a rack inventory: 1. Check the hardware technical level of modules and boards by performing the rack inventory. To perform the A9130 BSC Evolution rack inventory, refer to the CI 08 - Site Equipment Inventory document (3BK 17257 0001 RJZZA). 2. Check that there are no errors reported by the Inventar software regarding the technical level of modules and boards.

2.10 Connect the OMC-R


1. Ask the OMC-R operator to check the network connection to the A9130 Evolution BSC for all the fixed and floating IP addresses (to open for example some telnet sessions). See Site-Specific Information (Section 1.2.2) 2. Ask the OMC-R operator to declare in /etc/hosts all the BSC fixed and floating IP addresses together with the host names of BSC stations and "station_bsc" 3. Wait for OMC-R confirmation that the connection is OK.

Check the Equipment Status

4. Wait for the telecom boards to finish their initialization Check the equipment status.

3BK 17422 3121 RJZZA Ed.20P08

IN PREPARATION

41 / 44

2 A9130 BSC Evolution Commissioning

2.11 Option: Check the Connection with the CBC


2.11.1 Open a Telnet Session
To open a Telnet session: 1. In Windows 2000/XP, select: Start Run 2. In Open window enter: telnet 3. Click on [ Ok ] A telnet window opens. 4. Connect to the station as follows: Under Windows 2000, the connection is done as follows: set term vt100 open 172.17.y.x Under Windows XP, the connection is done as follows: open 172.17.y.x where: x is 3 for OMCP1 x is 4 for OMCP2 y is 3 for Shelf 3 y is 4 for Shelf 4 5. Click on [ Enter ] 6. In the Telnet window enter the login name and password. 7. Connect to the router used for connection with CBC server telnet <IP address of the gateway for LSN> By default IP address of the gateway for LSN1 is 172.17.y.10, for LSN2 is 172.18.y.10 user: password: where: y is 3 for Shelf 3 y is 4 for Shelf 4 8. Press [ Enter ] to start.

42 / 44

IN PREPARATION

3BK 17422 3121 RJZZA Ed.20P08

2 A9130 BSC Evolution Commissioning

2.11.2 Ping the CBC


To ping the CBC: 1. Enter the following command to check the connection between the BSC and the CBC: ping <IP address of the CBC> If answers from the CBC are received, the connection between the BSC and the CBC server is established. 2. Exit from the router: quit 3. Exit from BSC Control Station exit

2.12 End of Commissioning


1. Leave the A9130 Evolution BSC powered up 2. Close the doors of the rack 3. Check the CCL 4. Leave the site tidy: Remove all packaging and unused equipment. Clean the site. 5. Close the site and hand the keys to the key holder 6. Return the completed forms and the inventory files relating to the operation to base.

3BK 17422 3121 RJZZA Ed.20P08

IN PREPARATION

43 / 44

2 A9130 BSC Evolution Commissioning

BLANK PAGE BREAK

44 / 44

IN PREPARATION

3BK 17422 3121 RJZZA Ed.20P08