M A R C H
1 3 ,
2 0 0 6 F I N A L
V E R S I O N :
1
_/opt/scribd/conversion/tmp/scratch2708/78005259.doc
Revision History
Version 1.0 1.1 1.2 1.3 1.4 1.5 1.6 Date 01/18/2006 02/06/06 02/15/06 02/16/06 2/27/06 2/28/06 3/13/06 Description of Revisions Initial Draft Added Names and communication strategies Defined team & finalized communications area Revised document Added Org Chart and minor typos Updated Sponsors reporting processes Final comments/revisions Author Roman Roman Roman Sheri Sheri, Roman & Shaun Roman Team
Revision Notice
Version Control is used to track progress and changes to the SRIP Communication Plan. Comments and questions should be directed to Sheri Nees or Roman Martushev.
2
_/opt/scribd/conversion/tmp/scratch2708/78005259.doc
Table of Contents
Revision History......................................................................................................................................2
1 Introduction.......................................................................................................................4
1.1 Purpose...................................................................................................................................................4 1.2 Scope......................................................................................................................................................4 1.3 Assumptions ..........................................................................................................................................4 1.4 Project Information.................................................................................................................................4 1.5 Electronic Distribution............................................................................................................................4
6 Issue Management..........................................................................................................16
3
_/opt/scribd/conversion/tmp/scratch2708/78005259.doc
1 Introduction
1.1 Purpose
In order for change management to be successful, clear and concise communications among all stakeholders is essential. This plan will act as a road map and outline the basis for open communications during the State Recruitment Improvement Project (SRIP). The SRIP project will operate as an enterprise wide project requiring shared resources amongst state agencies. This will occur under the direction of the Sponsors along with the support of the Advisory Committee in conjunction with Agency Representatives.
1.2 Scope
This communication plan relates to the planning, designing, development, operations, status reporting, controlling, closing, and maintenance of the project. It also encompasses how we communicate (including ad-hoc) to the following groups: Enterprise, Sponsors (Executive Committee), Advisory Committee, Agency Representatives, Stakeholders, and the Project Team.
1.3 Assumptions
This project will transform the way we do business for state recruitments. Therefore, the communication plan will be a very important element in the way we distribute timely and accurate information to all stakeholders. For enterprise wide projects that cross multiple agencies, this plan will serve in providing open communication among all stakeholders. Communication is a key element in the success of a shared service.
4
_/opt/scribd/conversion/tmp/scratch2708/78005259.doc
5
_/opt/scribd/conversion/tmp/scratch2708/78005259.doc
3 Organization Chart
Susan Wilson, Human Resource Services Division Administrator (Sponsor) Jennifer Lara, Statewide Training, Development and Recruitment Manager (Sponsor) Roman Martushev, Project Leader Sheri Nees, SRIP Business Analyst Shaun Hansen, SRIP Research Analyst Laurie Grenya, Classification Analyst - (MQ/SOC) Jeannette Miley, PPDB Analyst Donna Lantz, PPDB Information Manager Tom Perry, Labor Relations Manager Craig Cowan, Labor Relations Manager Rebecca Gray, Rules & Policy Analyst IT Staff: Appl/Cert System Analysts TeamSite Developer - EDS Greg Hickman, Employment Department Deputy Director Velva Warden, iMatchSkills Program Manager Greg Pelton, iMatchSkills Technician, Analyst & Testing Lead Tracy Olander, iMatchSkills Business Analyst Mary Wood, iMatchSkills Data Specialist (SOC/Skills) ITS Staff: System Architect iMatchSkills Lead Systems Analyst Database Administrator Network & Security Analyst
6
_/opt/scribd/conversion/tmp/scratch2708/78005259.doc
DAS
OED
ODOT DOR OED DAS PERS DCBS DHS ODFW State Lands Lottery
HRSD/IRMD
iMS /ITS
EDS
TeamSite Analyst
Other
Agency Representatives
7
_/opt/scribd/conversion/tmp/scratch2708/78005259.doc
4 Contact List
State Recruitment Improvement Project Contact List
Team Member Susan Wilson Jennifer Lara Roman Martushev Sheri Nees Shaun Hansen Tom Perry Rebecca Gray Jeanette Miley Donna Lantz Laurie Grenya Craig Cowan Joe Adelman Kathy Flynn Velva Warden Greg Pelton Tracy Olander Mary Wood Rashmi Joshi DAS DCBS DHS DOR ODOT ODFW OED PERS State Lands Div. Lottery Role Administrator Statewide Training, Development & Recruitment Program Manager Project Leader SRIP Business Analyst Research Analyst - Temp Labor Relations Rules & Policy Analyst PPDB Analyst HR Sys/Svc/Audit backup State Class Analyst Labor Relations Appl/Cert System Analyst System Analyst iMatchSkills Program Mgr iMS Technician iMS Technician State jobs SOC Specialist System Architect Jerry Korson (Mgr ) Belinda Teague (Mgr) Twyla Lawson (Interim) Sandra McLernan (Mgr) Blair Johnson Jonathan Herman (HR Mgr) Cheri Tebeau-Harrell Helen Bamford Darrell Bennett Sheryl Warren Email Phone (503) 378-3020 (503) 378-3869 (503) 373-7572 (503) 378-8347 (503) 378-2287 (503) 378-4201 (503) 378-8301 (503) 378-8548 (503) 378-3145 (503) 373-7431 (503) 378-5611 (503) 378-4946 x470 (503) 373-7484 (503) 947-1973 (503) 947-1974 (503) 947-1236 (503) 947-1975 (503) 947-1849 (503) 378.4006 (503) 947-7292 (503) 945-6137 Salem (971) 673-1296 Portld (503) 945-8554 (503) 986-4057 (503) 947-6063 (503) 947-1319 (503) 603 7707 (503) 378-3805 x249 (503) 540-1135
Project Oversight
Susan.Wilson@das.state.or.us Jennifer.C.Lara@das.state.or.us Roman.Martushev@state.or.us Sheri.Nees@das.state.or.us Shaun.D.Hansen@das.state.or.us Tom.S.Perry@das.state.or.us Rebecca.Gray@das.state.or.us Jeanette.Miley@das.state.or.us Donna.L.Lantz@das.state.or.us Laurie.L.Grenya@das.state.or.us Craig.L.Cowan@das.state.or.us Joe.F.Adelman@das.state.or.us Kathy.Flynn@das.state.or.us Velva.C.Warden@state.or.us Gregory.M.Pelton@state.or.us Tracy.G.Olander@state.or.us Mary.M.Wood@state.or.us Rashmi.N.Joshi@state.or.us Jerry.F.Korson@das.state.or.us Belinda.g.teague@state.or.us Twyla.Lawson@state.or.us Sandra.L.Mclernan@state.or.us Blair.Johnson@state.or.us Jonathan.C.Herman@state.or.us
Cheri.Tebeau-HARRELL@state.or.us
DAS - HRSD
Advisory Committee
8
_/opt/scribd/conversion/tmp/scratch2708/78005259.doc
(503) 947-7296 (503) 947-7288 (503) 945-5693 (503) 945-6851 (503) 945-8552 (503) 378-6796 (503) 986-4057 (503) 947-6057 (503) 947-6061 (503) 947-1469 (503) 947-1319 (503) 603 7550 (503) 603 7707 (503) 378-3805 x249 (503) 540-1322 (503) 540-1135 (503) 229-5119
Back-up
9
_/opt/scribd/conversion/tmp/scratch2708/78005259.doc
5 Communications
5.1 Internal Program Communications
Program communications are internal communications between DAS HRSD and Employment Department regarding the State Recruitment Improvement Project. Relevant project documentation (hard copy) located in the Project Leaders office. All related project documents are located in the SRIP Project Folder at DAS HRSD. Description / Purpose Provide Sponsor(s) with timely project status Responsibility Project Leader provides updates SRIP Business Analyst Distribution Sponsors Project Team Media MS Word, electronic via Email Timing Bi-Monthly around 1st and the 15th of each month. Starting April 1st Weekly Tuesdays @ 10:00 AM Templates Standards Status Report template
Team Meetings
Project Schedule
Progress reports, schedule review, task assignments, major issues & risks, action items, roundtable discussions Shows project schedule interdependencies with the complete set of project tasks and duration as well as the concurrent work activities
Project Leader facilitates DAS and OED Project Team Project Leader maintain, apply updates, post on web
Project Team
Facilitated meeting, MS Word, electronic via Email MS Project, electronic via Email
10
_/opt/scribd/conversion/tmp/scratch2708/78005259.doc
Description / Purpose Identify new risks Review and update risk assessments Review and update Risk Management Plan
11
_/opt/scribd/conversion/tmp/scratch2708/78005259.doc
Project Schedule
Task list of all activities required to complete the project Includes tasks, dependencies, durations, start & finish dates, concurrent work activities, and responsible resources Track issues for reporting and resolution - project team, stakeholders and agencies
Project Schedule
Issue Log
Ongoing
12
_/opt/scribd/conversion/tmp/scratch2708/78005259.doc
Description / Purpose Collect information to assist with providing advice and guidance Report progress, delays and the impact over timeline Advisory Role to the Team Leads Share resources consumed for the project duration Track agency or program requests for project changes to scope or new system capabilities Includes description of the impact and actions to implement change Report to DAS Executives Business/Administrativ e Mgrs Large Agency Heads Small Agency Heads Provide project information relevant to any stakeholder Provide monthly updates of project status Provide monthly updates of project status
Responsibility Project Leader SRIP Business Analyst Sponsors iMS Program Manager
Sponsors DAS & OED business analysts Advisory Committee Project Team DAS Executives Admin Managers Agency Heads
Quarterly
Project Leader & SRIP Business Analyst Sponsor (J. Lara) Sponsor (J. Lara) Project Leader or SRIP Business Analyst
DAS/HR/SRIP project page List Serves SRIP com list List Serves SRIP com list
Web page
24/7 access
As approved
E-mails E-mails
13
_/opt/scribd/conversion/tmp/scratch2708/78005259.doc
Description / Purpose Formal sessions where Advisory Committee might need to review direction or decision for approval Formal sign-off on selected decisions or deliverables by Sponsors Increase focus on service, quality, promote collaboration, highlight successes, ensure clear understanding of expectations and enable the entire SRIP team to deliver against those expectations.
Responsibility Project Leader (oversight) SRIP Business Analyst execute Sponsors & iMS Program Manager Project Leader methodology & oversight Project Team strive for excellence & high quality work Advisory Committee for assurance
Timing As required
Quality Assurance
Ongoing As required
14
_/opt/scribd/conversion/tmp/scratch2708/78005259.doc
Issue Updates
Excel Spreadsheet
Issue Closure
Excel Spreadsheet
15
_/opt/scribd/conversion/tmp/scratch2708/78005259.doc
6 Issue Management
Standard issue management and tracking is described in the Issue Management Plan document. Issues become an item of escalation when the regular channels of communication fail to deliver the expected results or when the identified concern could result in immediate procedural or financial harm for the State of Oregon or the SRIP Project. When an issue is created, it is assigned a priority number as described in the following table. Issues are also assigned a critical due date. Depending on the issue priority level, the critical due date should be within the number of days allowed for resolution of the reported issue. Priority Number 1 Description High An issue assigned priority level 1 has the potential to ultimately cause procedural or financial harm to the project and/or client if not resolved. A delay in resolution will ultimately impact the projects scope, schedule, quality, cost or resources. Medium An issue is assigned priority level 2 if it has limited procedural impact on the project and/or client. A delay in resolution may impact the projects scope, schedule, quality, cost, or resources. Low An issue is assigned priority level 3 if it has no procedural or financial impact on the project and/or client. A delay in resolution will not impact the projects scope, schedule, quality, cost or resources. Enhancement An issue could be assigned as ENH if it is determined to be an enhancement of the current scope of work and requires additional work in order to resolve it. This issue/enhancement will need to follow the change management process for approval in order to be considered for this project. A resolution might potentially impact one or more of the following: projects scope, schedule, quality, cost or resources. Resolution Period 1 working day or less
2 - 5working days
ENH
Issues that are not resolved and closed by the critical due date or within the resolution period should be immediately escalated to the Project Leader. See next page for escalation contacts.
Escalation Contacts
Position Project Leader SRIP Business Analyst Business Sponsor Executive Sponsor iMatchSkills iMatchSkills Program Manager
Escalation Point Initial Initial Backup Business Processes Executive & Final
Area of Focus Project Issues Project Issues Program Management Overall Management
Phone and Email (503) 373-7572 Roman.Martushev@das.state.or.us (503) 378-8347 Sheri.Nees@das.state.or.us (503) 378-3869 Jennifer.C.Lara@das.state.or.us (503) 378-3020 Susan.Wilson@das.state.or.us
iMS Program
Program Management