BS INTERIOR DESIGN OJT REPORT

Daily Log of Training Experience


Date: Name of Student: Reyes,
Family Name

April 02 Obar
Middle Name

, 2012

Rincess
First Name

Office/Company Name: Novelle Office Furniture Incorporation th Address: Unit 403 4 Flr. Toyama Group Center #22 Timog Ave. Brgy. Laging Handa Q.C. Project Title: Relocation of Novelle Office Space & Showroom Project Description: Furniture Project Location: G/F MGF Champaca Bldg, # 156 Amorsolo St., Legaspi Village, Makati City Assigned Work Task: Sketch-up Time In Time Out : : 8:00 a.m 5:00 p.m Sunny Total No. of Hour/s Spent: Site Condition: 8 hours Office Site Others, pls. specify

Weather Condition:

Work Activities Performed: Company Orientation Furniture Designing o Office Workstation with Google Sketch-up

Personal Observations at the Project Site:

Report/s Submitted, if any:

Lesson/s Learned:

I learned how to use the component and group command in google sketch-up.

Picture/s Taken, if any:

Certified True and Correct by:

Noted by:

Mentor
(Signature above Printed Name)

IDr. Billie Jean Dumlao-Dela Cruz, piid


Faculty OJT Coordinator

Date: April 02

, 2012

Date: ________________ , 2012

POLYTECHNIC UNIVERSITY OF THE PHILIPPINES

COLLEGE OF ARCHITECTURE AND FINE ARTS DEPARTMENT OF INTERIOR DESIGN


PUP Engineering and Architecture BuildingNDC Compound, Anonas cor. Pureza Sts., Sta. Mesa, Manila Tel: (632) 713 9304

BS INTERIOR DESIGN OJT REPORT

Daily Log of Training Experience


Date: April 03 , 2012

Name of Student:

Reyes,
Family Name

Rincess
First Name

Obar
Middle Name

Office/Company Name: Novelle Office Furniture Incorporation th Address: Unit 403 4 Flr. Toyama Group Center #22 Timog Ave. Brgy. Laging Handa Q.C. Project Title: Relocation of Novelle Office Space & Showroom Project Description: Furniture Project Location: G/F MGF Champaca Bldg, # 156 Amorsolo St., Legaspi Village, Makati City Assigned Work Task: Time In Time Out : : Sketch-up 8:00 a.m 5:00 p.m Sunny Total No. of Hour/s Spent: Site Condition: 8 hours Office Site Others, pls. specify

Weather Condition:

Work Activities Performed: Furniture Designing o Office Workstation with Google Sketch-up

Personal Observations at the Project Site:

Report/s Submitted, if any

Lesson/s Learned:

I learned how to become faster and easier in making office furniture using google sketch-up.

Picture/s Taken, if any:

Certified True and Correct by:

Noted by:

Mentor

IDr. Billie Jean Dumlao-Dela Cruz, piid

Signature above Printed Name)

Faculty OJT Coordinator

Date: April 03

, 2012

Date: ________________ , 2012

POLYTECHNIC UNIVERSITY OF THE PHILIPPINES

COLLEGE OF ARCHITECTURE AND FINE ARTS DEPARTMENT OF INTERIOR DESIGN


PUP Engineering and Architecture BuildingNDC Compound, Anonas cor. Pureza Sts., Sta. Mesa, Manila Tel: (632) 713 9304

BS INTERIOR DESIGN OJT REPORT

Daily Log of Training Experience


Date: April 04 , 2012

Name of Student:

Reyes,
Family Name

Rincess
First Name

Obar
Middle Name

Office/Company Name: Novelle Office Furniture Incorporation th Address: Unit 403 4 Flr. Toyama Group Center #22 Timog Ave. Brgy. Laging Handa Q.C. Project Title: Relocation of Novelle Office Space & Showroom Project Description: Furniture Project Location: G/F MGF Champaca Bldg, # 156 Amorsolo St., Legaspi Village, Makati City Assigned Work Task: Furniture Marking Time In Time Out : : 8:00 a.m 5:00 p.m Total No. of Hour/s Spent: Site Condition: Sunny 8 hours Office Site Others, pls. specify

Weather Condition:

Work Activities Performed: Ocular Inspection Site Visit Furniture Marking Area measurement

Personal Observations at the Project Site:

White paint is use in marking furniture. After marking, the white paint must measure again to final the size of the furniture.

Report/s Submitted, if any:

Lesson/s Learned:

In actual space, the floor layout must be drawn in the floor of the interior just to see the real space.

Picture/s Taken, if any:

Certified True and Correct by:

Noted by:

Mentor
(Signature above Printed Name)

IDr. Billie Jean Dumlao-Dela Cruz, piid


Faculty OJT Coordinator

Date: April 04

, 2012

Date: ________________ , 2012

POLYTECHNIC UNIVERSITY OF THE PHILIPPINES

COLLEGE OF ARCHITECTURE AND FINE ARTS DEPARTMENT OF INTERIOR DESIGN


PUP Engineering and Architecture BuildingNDC Compound, Anonas cor. Pureza Sts., Sta. Mesa, Manila Tel: (632) 713 9304

BS INTERIOR DESIGN OJT REPORT

Daily Log of Training Experience


Date: April 10 , 2012

Name of Student:

Reyes,
Family Name

Rincess
First Name

Obar
Middle Name

Office/Company Name: Novelle Office Furniture Incorporation th Address: Unit 403 4 Flr. Toyama Group Center #22 Timog Ave. Brgy. Laging Handa Q.C. Project Title: Relocation of Novelle Office Space & Showroom Project Description: Furniture Project Location: G/F MGF Champaca Bldg, # 156 Amorsolo St., Legaspi Village, Makati City Assigned Work Task: Furniture Quotation Time In Time Out : : 8:00 a.m 5:00 p.m Sunny Total No. of Hour/s Spent: Site Condition: 8 hours Office Site Others, pls. specify

Weather Condition:

Work Activities Performed: Furniture Quotation Material Searching

Personal Observations at the Project Site:

Report/s Submitted, if any:

Lesson/s Learned:

I learned that in quotation the material, size, color and cost of the furniture are specify.

Picture/s Taken, if any:

Certified True and Correct by:

Noted by:

Mentor
(Signature above Printed Name)

IDr. Billie Jean Dumlao-Dela Cruz, piid


Faculty OJT Coordinator

Date: April 10

, 2012

Date: ________________ , 2012

POLYTECHNIC UNIVERSITY OF THE PHILIPPINES

COLLEGE OF ARCHITECTURE AND FINE ARTS DEPARTMENT OF INTERIOR DESIGN


PUP Engineering and Architecture BuildingNDC Compound, Anonas cor. Pureza Sts., Sta. Mesa, Manila Tel: (632) 713 9304

BS INTERIOR DESIGN OJT REPORT

Daily Log of Training Experience


Date: April 11 , 2012

Name of Student:

Reyes,
Family Name

Rincess
First Name

Obar
Middle Name

Office/Company Name: Novelle Office Furniture Incorporation th Address: Unit 403 4 Flr. Toyama Group Center #22 Timog Ave. Brgy. Laging Handa Q.C. Project Title: Bank of Commerce Katipunan Branch Project Description: Furniture

Project Location: Katipunan Ave. cor Mangyan Road, La Vista Subd. Loyola Hgts. Q.C. Assigned Work Task: Furniture Specification Time In Time Out : : 8:00 a.m 5:00 p.m Sunny Total No. of Hour/s Spent: Site Condition: 8 hours Office Site Others, pls. specify

Weather Condition:

Work Activities Performed: Furniture Material Searching Furniture Material Specification

Personal Observations at the Project Site:

Report/s Submitted, if any:

Lesson/s Learned:

I learned that in furniture material specification all the color and size that used are indicated; Like what we did in furniture specification.

Picture/s Taken, if any:

Certified True and Correct by:

Noted by:

Mentor
(Signature above Printed Name)

IDr. Billie Jean Dumlao-Dela Cruz, piid


Faculty OJT Coordinator

Date: April 11

, 2012

Date: ________________ , 2012

POLYTECHNIC UNIVERSITY OF THE PHILIPPINES

COLLEGE OF ARCHITECTURE AND FINE ARTS DEPARTMENT OF INTERIOR DESIGN


PUP Engineering and Architecture BuildingNDC Compound, Anonas cor. Pureza Sts., Sta. Mesa, Manila Tel: (632) 713 9304

BS INTERIOR DESIGN OJT REPORT

Daily Log of Training Experience


Date: Name of Student: Reyes,
Family Name

April 12 Obar
Middle Name

, 2012

Rincess
First Name

Office/Company Name: Novelle Office Furniture Incorporation th Address: Unit 403 4 Flr. Toyama Group Center #22 Timog Ave. Brgy. Laging Handa Q.C. Project Title: Relocation of Novelle Office Space & Showroom Project Description: Furniture Project Location: G/F MGF Champaca Bldg, # 156 Amorsolo St., Legaspi Village, Makati City Assigned Work Task: Material Searching Time In Time Out : : 8:00 a.m 5:00 p.m Office Site Others, pls. specify

Balintawak Home Depot Total No. of Hour/s Spent: Site Condition: Sunny 8 hours

Weather Condition:

Work Activities Performed: Furniture Material Searching

Personal Observations at the Project Site:

Report/s Submitted, if any:

Lesson/s Learned:

I learned that in material searching the quality and the price must consider.

Picture/s Taken, if any:

Certified True and Correct by:

Noted by:

Mentor
(Signature above Printed Name)

IDr. Billie Jean Dumlao-Dela Cruz, piid


Faculty OJT Coordinator

Date: April 12

, 2012

Date: ________________ , 2012

POLYTECHNIC UNIVERSITY OF THE PHILIPPINES

COLLEGE OF ARCHITECTURE AND FINE ARTS DEPARTMENT OF INTERIOR DESIGN


PUP Engineering and Architecture BuildingNDC Compound, Anonas cor. Pureza Sts., Sta. Mesa, Manila Tel: (632) 713 9304

BS INTERIOR DESIGN OJT REPORT

Daily Log of Training Experience


Date: April 13 , 2012

Name of Student:

Reyes,
Family Name

Rincess
First Name

Obar
Middle Name

Office/Company Name: Novelle Office Furniture Inc. th Address: Unit 403 4 Flr. Toyama Group Center #22 Timog Ave. Brgy. Laging Handa Q.C. Project Title: Relocation of Novelle Office Space & Showroom Project Description: Furniture Project Location: G/F MGF Champaca Bldg, # 156 Amorsolo St., Legaspi Village, Makati City Assigned Work Task: Time In Time Out : : Sketch up 8:00 a.m 5:00 p.m Sunny Total No. of Hour/s Spent: Site Condition: 8 hours Office Site Others, pls. specify

Weather Condition:

Work Activities Performed: Google Sketch-up o Office Workstation

Personal Observations at the Project Site:

Report/s Submitted, if any:

Lesson/s Learned:

I learned that in making office workstation in google sketch-up it is much easier if you dont make it more complicated like making a depth.

Picture/s Taken, if any:

Certified True and Correct by:

Noted by:

Mentor
(Signature above Printed Name)

IDr. Billie Jean Dumlao-Dela Cruz, piid


Faculty OJT Coordinator

Date: April 13

, 2012

Date: ________________ , 2012

Furniture

Weekly Log

POLYTECHNIC UNIVERSITY OF THE PHILIPPINES

COLLEGE OF ARCHITECTURE AND FINE ARTS DEPARTMENT OF INTERIOR DESIGN


PUP Engineering and Architecture BuildingNDC Compound, Anonas cor. Pureza Sts., Sta. Mesa, Manila Tel: (632) 713 9304

BS Interior Design On-the-Job Training ON-THE-JOB TRAINING WEEKLY ACCOMPLISHMENT REPORT


Name of Student: Reyes,
Family Name,

Rincess
First Name

Obar
Middle Name

Student No.2009-02004-MN-0 Employed by: Novelle Office Furniture Incorporation Address: Unit 403 4th Flr. Toyama Group Center #22 Timog Ave. Brgy. Laging Handa Q.C. Reporting Period from: 02 April 20 12 to 04 April 2012
Day Month Day Month Percentage of Assigned Work Completed

Item No.

Field of Practice Project Title/Description/Location (Brief Description)

No. of Hours

100% = Full Completion

Relocation of Novelle Office Space & Showroom/ Furniture/ G/F MGF Champaca Bldg, # 156 Amorsolo St., Legaspi Village, Makati City Relocation of Novelle Office Space & Showroom/ Furniture/ G/F MGF Champaca Bldg, # 156 Amorsolo St., Legaspi Village, Makati City Relocation of Novelle Office Space & Showroom/ Furniture/ G/F MGF Champaca Bldg, # 156 Amorsolo St., Legaspi Village, Makati City Relocation of Novelle Office Space & Showroom/ Furniture/ G/F MGF Champaca Bldg, # 156 Amorsolo St., Legaspi Village, Makati City

Google Sketch-up Office Workstation

16 hours

100 %

Ocular Inspection

2 hours

100 %

3 hours Furniture Marking 100 %

Area Measurement

3 hours

100 %

Item No.

Field of Practice Project Title/Description/Location (Brief Description)

No. of Hours

Percentage of Assigned Work Completed

100% = Full Completion

TOTAL NO. OF HOURS

24 hours

100 %

Recommendations for the Trainees further growth and development:

Checked and Approved by:

Conforme:

Rincess O. Reyes OJT Faculty Coordinator


(Signature above printed name)

Student Trainee
(Signature above printed name)

POLYTECHNIC UNIVERSITY OF THE PHILIPPINES

COLLEGE OF ARCHITECTURE AND FINE ARTS DEPARTMENT OF INTERIOR DESIGN


PUP Engineering and Architecture BuildingNDC Compound, Anonas cor. Pureza Sts., Sta. Mesa, Manila Tel: (632) 713 9304

BS Interior Design On-the-Job Training ON-THE-JOB TRAINING WEEKLY ACCOMPLISHMENT REPORT

Name of Student:

Reyes,
Family Name,

Rincess
First Name

Obar
Middle Name

Student No.2009-02004-MN-0 Employed by: Novelle Office Furniture Incorporation Address: Unit 403 4th Flr. Toyama Group Center #22 Timog Ave. Brgy. Laging Handa Q.C. Reporting Period from: 10
Day

April
Month

20 12

to

13
Day

April
Month

2012

Item No.

Field of Practice Project Title/Description/Location (Brief Description)

No. of Hours

Percentage of Assigned Work Completed

100% = Full Completion

Filinvest Office/ Furniture Furniture Quotation 4 hours 100 %

Relocation of Novelle Office Space & Showroom/ Furniture/ G/F MGF Champaca Bldg, # 156 Amorsolo St., Legaspi Village, Makati City

Furniture Material Searching

17 hours

100 %

Bank of Commerce Katipunan Branch

Furniture Material Specification

3 hours

100 %

Relocation of Novelle Office Space & Showroom/ Furniture/ G/F MGF Champaca Bldg, # 156 Amorsolo St., Legaspi Village, Makati City

Google Sketch-up Office Workstation

8 hours

100 %

Item No.

Field of Practice Project Title/Description/Location (Brief Description)

No. of Hours

Percentage of Assigned Work Completed

100% = Full Completion

TOTAL NO. OF HOURS

32 hours

100 %

Recommendations for the Trainees further growth and development:

Checked and Approved by:

Conforme:

Rincess O. Reyes OJT Faculty Coordinator


(Signature above printed name)

Student Trainee
(Signature above printed name)

Furniture

Certificate of Completion

Furniture

Evaluation Form

Architecture

Architecture

Company Profile

Architecture

Certificate of Acceptance

Architecture

Employers Guidelines

Architecture

Licensed

Architecture

Daily Log

POLYTECHNIC UNIVERSITY OF THE PHILIPPINES

COLLEGE OF ARCHITECTURE AND FINE ARTS DEPARTMENT OF INTERIOR DESIGN


PUP Engineering and Architecture BuildingNDC Compound, Anonas cor. Pureza Sts., Sta. Mesa, Manila Tel: (632) 713 9304

BS INTERIOR DESIGN OJT REPORT

Daily Log of Training Experience


Date: April 16 , 2012

Name of Student:

Reyes,
Family Name

Rincess
First Name

Obar
Middle Name

Office/Company Name: Vincent To Ng/Vincent Ng Architectural Services Address: Unit 4 # 8 Binmaka St., Brgy. Manresa Quezon City Project Title: Mariano Ho Project Location: G. Raymundo Avenue Pasig City Assigned Work Task: Time In Time Out : : As-Built 8:00 a.m 5:00 p.m Total No. of Hour/s Spent: Site Condition: Sunny 8 hours Office Site Others, pls. specify Project Description: Architecture

Weather Condition: Work Activities Performed: Convert CADD Files to PDF Mariano Ho o o Area measurement As-Built

Personal Observations at the Project Site:

The steel are exposed so that if the owner wants to extend their space they dont have to tear down the wall.

Report/s Submitted, if any:

Lesson/s Learned:

I learned that in measuring space, you must have a reference point.

Picture/s Taken, if any:

Certified True and Correct by:

Noted by:

Mentor
(Signature above Printed Name)

IDr. Billie Jean Dumlao-Dela Cruz, piid


Faculty OJT Coordinator

Date: April 16

, 2012

Date: ________________ , 2012

POLYTECHNIC UNIVERSITY OF THE PHILIPPINES

COLLEGE OF ARCHITECTURE AND FINE ARTS DEPARTMENT OF INTERIOR DESIGN


PUP Engineering and Architecture BuildingNDC Compound, Anonas cor. Pureza Sts., Sta. Mesa, Manila Tel: (632) 713 9304

BS INTERIOR DESIGN OJT REPORT

Daily Log of Training Experience


Date: April 17 , 2012

Name of Student:

Reyes,
Family Name

Rincess
First Name

Obar
Middle Name

Office/Company Name: Vincent To Ng/Vincent Ng Architectural Services Address: Unit 4 # 8 Binmaka St., Brgy. Manresa Quezon City Project Title: Project Location: Mariano Ho G. Raymundo Avenue Pasig City CADD 8:00 a.m 5:00 p.m Sunny Total No. of Hour/s Spent: Site Condition: 8 hours Office Site Others, pls. specify Project Description: Architecture

Assigned Work Task: Time In Time Out : :

Weather Condition:

Work Activities Performed: CADD o o o Ground Floor Plan (As-Built) 2nd Floor Plan (As-Built) 3rd Floor Plan (As-Built)

Personal Observations at the Project Site:

Report/s Submitted, if any:

Lesson/s Learned:

I learned that in making floor plan in CADD, you must have a reference point so that you know where the start and end of the line.

Picture/s Taken, if any:

Certified True and Correct by:

Noted by:

Mentor
(Signature above Printed Name)

IDr. Billie Jean Dumlao-Dela Cruz, piid


Faculty OJT Coordinator

Date: April 17

, 2012

Date: ________________ , 2012

POLYTECHNIC UNIVERSITY OF THE PHILIPPINES

COLLEGE OF ARCHITECTURE AND FINE ARTS DEPARTMENT OF INTERIOR DESIGN


PUP Engineering and Architecture BuildingNDC Compound, Anonas cor. Pureza Sts., Sta. Mesa, Manila Tel: (632) 713 9304

BS INTERIOR DESIGN OJT REPORT

Daily Log of Training Experience


Date: Name of Student: Reyes,
Family Name

April 18 Obar
Middle Name

, 2012

Rincess
First Name

Office/Company Name: Vincent To Ng/Vincent Ng Architectural Services Address: Unit 4 # 8 Binmaka St., Brgy. Manresa Quezon City Project Title: Project Location: Mariano Ho G. Raymundo Avenue Pasig City CADD 8:00 a.m 5:00 p.m Sunny Total No. of Hour/s Spent: Site Condition: 8 hours Office Site Others, pls. specify Project Description: Architecture

Assigned Work Task: Time In Time Out : :

Weather Condition:

Work Activities Performed: CADD o o o Proposed Ground Floor Plan Proposed 2nd Floor Plan Proposed 3rd Floor Plan

Personal Observations at the Project Site:

Report/s Submitted, if any:

Lesson/s Learned:

I learned that making a plan in CADD, you should indicate the entire dimension so the constructor knew.

Picture/s Taken, if any:

Certified True and Correct by:

Noted by:

Mentor
(Signature above Printed Name)

IDr. Billie Jean Dumlao-Dela Cruz, piid


Faculty OJT Coordinator

Date: April 18

, 2012

Date: ________________ , 2012

POLYTECHNIC UNIVERSITY OF THE PHILIPPINES

COLLEGE OF ARCHITECTURE AND FINE ARTS DEPARTMENT OF INTERIOR DESIGN


PUP Engineering and Architecture BuildingNDC Compound, Anonas cor. Pureza Sts., Sta. Mesa, Manila Tel: (632) 713 9304

BS INTERIOR DESIGN OJT REPORT

Daily Log of Training Experience


Date: April 19 , 2012

Name of Student:

Reyes,
Family Name

Rincess
First Name

Obar
Middle Name

Office/Company Name: Vincent To Ng/Vincent Ng Architectural Services Address: Unit 4 # 8 Binmaka St., Brgy. Manresa Quezon City Project Title: Three Storey Residence Project Description: Architecture

Project Location: Paltok Street Quezon City Assigned Work Task: Choosing color palette Time In Time Out : : 8:00 a.m 5:00 p.m Sunny Total No. of Hour/s Spent: Site Condition: 8 hours Office Site Others, pls. specify

Weather Condition:

Work Activities Performed: Three Storey Residence o o Choosing the Architectural Color Palette in Davies Swatch Paint.

Alvin Ang Choosing the Architectural Color Palette in Davies Swatch Paint.

Personal Observations at the Project Site:

Report/s Submitted, if any:

Lesson/s Learned:

I learned that in choosing color palette in architectural design you must consider that it has contrast and the color that will use didnt hurt the eyes.

Picture/s Taken, if any:

Certified True and Correct by:

Noted by:

Mentor
(Signature above Printed Name)

IDr. Billie Jean Dumlao-Dela Cruz, piid


Faculty OJT Coordinator

Date: April 19

, 2012

Date: ________________ , 2012

POLYTECHNIC UNIVERSITY OF THE PHILIPPINES

COLLEGE OF ARCHITECTURE AND FINE ARTS DEPARTMENT OF INTERIOR DESIGN


PUP Engineering and Architecture BuildingNDC Compound, Anonas cor. Pureza Sts., Sta. Mesa, Manila Tel: (632) 713 9304

BS INTERIOR DESIGN OJT REPORT

Daily Log of Training Experience


Date: April 20 , 2012

Name of Student:

Reyes,
Family Name

Rincess
First Name

Obar
Middle Name

Office/Company Name: Vincent To Ng/Vincent Ng Architectural Services Address: Unit 4 # 8 Binmaka St., Brgy. Manresa Quezon City Project Title: Six Unit Three Storey Town House Project Location: Project Description: Architecture

#47 Mapagkumbaba Street, Sikatuna Property, Quezon City CADD 8:00 a.m 5:00 p.m Sunny Total No. of Hour/s Spent: Site Condition: 8 hours Office Site Others, pls. specify

Assigned Work Task: Time In Time Out : :

Weather Condition:

Work Activities Performed: CADD o o Lot Plan Proposed Floor Plan

Personal Observations at the Project Site:

Report/s Submitted, if any:

Lesson/s Learned:

I learned that in CADD it have a layer where the thickness of the line are specify.

Picture/s Taken, if any:

Certified True and Correct by:

Noted by:

Mentor
(Signature above Printed Name)

IDr. Billie Jean Dumlao-Dela Cruz, piid


Faculty OJT Coordinator

Date: April 20

, 2012

Date: ________________ , 2012

POLYTECHNIC UNIVERSITY OF THE PHILIPPINES

COLLEGE OF ARCHITECTURE AND FINE ARTS DEPARTMENT OF INTERIOR DESIGN


PUP Engineering and Architecture BuildingNDC Compound, Anonas cor. Pureza Sts., Sta. Mesa, Manila Tel: (632) 713 9304

BS INTERIOR DESIGN OJT REPORT

Daily Log of Training Experience


Date: April 23 , 2012

Name of Student:

Reyes,
Family Name

Rincess
First Name

Obar
Middle Name

Office/Company Name: Vincent To Ng/Vincent Ng Architectural Services Address: Unit 4 # 8 Binmaka St., Brgy. Manresa Quezon City Project Title: Six Unit Three Storey Town House Project Description: Architecture

Project Location: #47 Mapagkumbaba Street, Sikatuna Property, Quezon city Assigned Work Task: Time In Time Out : : CADD 8:00 a.m 5:00 p.m Sunny Total No. of Hour/s Spent: Site Condition: 8 hours Office Site Others, pls. specify

Weather Condition:

Work Activities Performed: CADD o o Proposed Floor Plan Proposed Reflected Ceiling Plan

Personal Observations at the Project Site:

Report/s Submitted, if any:

Lesson/s Learned:

I learned how the Architect makes their reflected ceiling plan it is slightly different in Interior Designer.

Picture/s Taken, if any:

Certified True and Correct by:

Noted by:

Mentor
(Signature above Printed Name)

IDr. Billie Jean Dumlao-Dela Cruz, piid


Faculty OJT Coordinator

Date: April 23

, 2012

Date: ________________ , 2012

POLYTECHNIC UNIVERSITY OF THE PHILIPPINES

COLLEGE OF ARCHITECTURE AND FINE ARTS DEPARTMENT OF INTERIOR DESIGN


PUP Engineering and Architecture BuildingNDC Compound, Anonas cor. Pureza Sts., Sta. Mesa, Manila Tel: (632) 713 9304

BS INTERIOR DESIGN OJT REPORT

Daily Log of Training Experience


Date: April 24 , 2012

Name of Student:

Reyes,
Family Name

Rincess
First Name

Obar
Middle Name

Office/Company Name: Vincent To Ng/Vincent Ng Architectural Services Address: Unit 4 # 8 Binmaka St., Brgy. Manresa Quezon City Project Title: Six Unit Three Storey Town House Project Description: Architecture

Project Location: #47 Mapagkumbaba Street, Sikatuna Property, Quezon City Assigned Work Task: Time In Time Out : : CADD 8:00 a.m 10:00 a.m Sunny Total No. of Hour/s Spent: Site Condition: 2 hours Office Site Others, pls. specify

Weather Condition:

Work Activities Performed: CADD o Proposed Reflected Ceiling Plan

Personal Observations at the Project Site:

Report/s Submitted, if any:

Lesson/s Learned:

I learned how to layout in 20x30 using CADD.

Picture/s Taken, if any:

Certified True and Correct by:

Noted by:

Mentor
(Signature above Printed Name)

IDr. Billie Jean Dumlao-Dela Cruz, piid


Faculty OJT Coordinator

Date: April 24

, 2012

Date: ________________ , 2012

Architecture

Weekly Log

POLYTECHNIC UNIVERSITY OF THE PHILIPPINES

COLLEGE OF ARCHITECTURE AND FINE ARTS DEPARTMENT OF INTERIOR DESIGN


PUP Engineering and Architecture BuildingNDC Compound, Anonas cor. Pureza Sts., Sta. Mesa, Manila Tel: (632) 713 9304

BS Interior Design On-the-Job Training ON-THE-JOB TRAINING WEEKLY ACCOMPLISHMENT REPORT


Name of Student: Reyes,
Family Name,

Rincess
First Name

Obar
Middle Name

Student No.2009-02004-MN-0 Employed by: Vincent To Ng/Vincent Ng Architectural Service Address: Unit 4 # 08 Binmaka Street Brgy. Manresa Quezon City Reporting Period from:
Day

16
Month

April

2012

to
Day

20
Month

April

2012
Percentage of Assigned Work Completed

Item No.

Field of Practice Project Title/Description/Location (Brief Description)

No. of Hours

100% = Full Completion

Mariano Ho/ Architecture/ G. Raymundo Avenue Pasig City

Area Measurement (As-Built)

8 hours

100 %

Mariano Ho/ Architecture/ G. Raymundo Avenue Pasig City

CADD Ground, 2 , and rd 3 Floor Plan (As-Built)

nd

8 hours

100 %

Mariano Ho/ Architecture/ G. Raymundo Avenue Pasig City

CADD Proposed Ground, nd rd 2 and 3 Floor Plan

8 hours

100 %

4 Three Storey Residence/ Architecture/ Paltok Street Quezon City 5 Alvin Ang/ Architecture Choosing Color Palette Choosing Color Palette

4 hours 100 %

100 % 4 hours

Six Unit Three Storey Town House/ Architecture/ #47 Mapagkumbaba Street, Sikatuna Property, Quezon City

CADD Lot Plan and Proposed Floor Plan

8 hours

40 %

Item No.

Field of Practice Project Title/Description/Location (Brief Description)

No. of Hours

Percentage of Assigned Work Completed

100% = Full Completion

TOTAL NO. OF HOURS

40 hours

90 %

Recommendations for the Trainees further growth and development:

Checked and Approved by:

Conforme:

Rincess O. Reyes OJT Faculty Coordinator


(Signature above printed name)

Student Trainee
(Signature above printed name)

POLYTECHNIC UNIVERSITY OF THE PHILIPPINES

COLLEGE OF ARCHITECTURE AND FINE ARTS DEPARTMENT OF INTERIOR DESIGN


PUP Engineering and Architecture BuildingNDC Compound, Anonas cor. Pureza Sts., Sta. Mesa, Manila Tel: (632) 713 9304

BS Interior Design On-the-Job Training ON-THE-JOB TRAINING WEEKLY ACCOMPLISHMENT REPORT

Name of Student:

Reyes,
Family Name,

Rincess
First Name

Obar
Middle Name

Student No.2009-02004-MN-0 Employed by: Vincent To Ng/Vincent Ng Architectural Service Address: Unit 4 # 08 Binmaka Street Brgy. Manresa Quezon City Reporting Period from:
Day

23
Month

April

2012

to
Day

24
Month

April

2012
Percentage of Assigned Work Completed

Item No.

Field of Practice Project Title/Description/Location (Brief Description)

No. of Hours

100% = Full Completion

Six Unit Three Storey Town House/Architecture/ #47 Mapagkumbaba Street, Sikatuna Property, Quezon City

CADD Continuation of Proposed Floor Plan and Proposed Reflected Ceiling Plan

10 hours

100 %

Item No.

Field of Practice Project Title/Description/Location (Brief Description)

No. of Hours

Percentage of Assigned Work Completed

100% = Full Completion

TOTAL NO. OF HOURS

10 hours

100 %

Recommendations for the Trainees further growth and development:

Checked and Approved by:

Conforme:

Rincess O. Reyes OJT Faculty Coordinator


(Signature above printed name)

Student Trainee
(Signature above printed name)

Architecture

Certificate of Completion

Architecture

Evaluation Form

Interior Design

Interior Design

Licensed

Interior Design

Daily Log

POLYTECHNIC UNIVERSITY OF THE PHILIPPINES

COLLEGE OF ARCHITECTURE AND FINE ARTS DEPARTMENT OF INTERIOR DESIGN


PUP Engineering and Architecture BuildingNDC Compound, Anonas cor. Pureza Sts., Sta. Mesa, Manila Tel: (632) 713 9304

BS INTERIOR DESIGN OJT REPORT

Daily Log of Training Experience


Date: Name of Student: Reyes,
Family Name

April 24 Obar
Middle Name

, 2012

Rincess
First Name

Office/Company Name: Vincent To Ng/Vincent Ng Architectural Services Address: Unit 4 # 8 Binmaka St., Brgy. Manresa Quezon City Project Title: Six Unit Three Storey Town House Project Description: Interior Design

Project Location: #47 Mapagkumbaba Street, Sikatuna Property, Quezon City Assigned Work Task: Time In Time Out : : CADD 10:00 a.m 5:00 p.m Sunny Total No. of Hour/s Spent: Site Condition: 6 hours Office Site Others, pls. specify

Weather Condition:

Work Activities Performed: CADD o o Proposed Ground Floor Plan with Furniture Layout Proposed 2nd Floor Plan with Furniture Layout

Personal Observations at the Project Site:

Report/s Submitted, if any:

Lesson/s Learned:

I learned that the Floor Plan and Floor Plan with Furniture Layout are place separate so all the dimension is seen properly.

Picture/s Taken, if any:

Certified True and Correct by:

Noted by:

Leah T. Chua PIID, PRC 705 Mentor


(Signature above Printed Name)

IDr. Billie Jean Dumlao-Dela Cruz, piid


Faculty OJT Coordinator

Date: April 24

, 2012

Date: ________________ , 2012

POLYTECHNIC UNIVERSITY OF THE PHILIPPINES

COLLEGE OF ARCHITECTURE AND FINE ARTS DEPARTMENT OF INTERIOR DESIGN


PUP Engineering and Architecture BuildingNDC Compound, Anonas cor. Pureza Sts., Sta. Mesa, Manila Tel: (632) 713 9304

BS INTERIOR DESIGN OJT REPORT

Daily Log of Training Experience


Date: April 25 , 2012

Name of Student:

Reyes,
Family Name

Rincess
First Name

Obar
Middle Name

Office/Company Name: Vincent To Ng/Vincent Ng Architectural Services Address: Unit 4 # 8 Binmaka St., Brgy. Manresa Quezon City Project Title: Six Unit Three Storey Town House Project Description: Interior Design

Project Location: #47 Mapagkumbaba Street, Sikatuna Property, Quezon City Assigned Work Task: Time In Time Out : : CADD 8:00 a.m 5:00 p.m Sunny Total No. of Hour/s Spent: Site Condition: 8 hours Office Site Others, pls. specify

Weather Condition:

Work Activities Performed: CADD o o o o Proposed 3rd Floor Plan with Furniture Layout Proposed Ground Lighting Layout Proposed 2nd Floor Lighting Layout Proposed 3rd Floor Lighting Layout

Personal Observations at the Project Site:

Report/s Submitted, if any:

Lesson/s Learned:

I learned what kind of layer that will use in wall, light, electrical, and callouts.

Picture/s Taken, if any:

Certified True and Correct by:

Noted by:

Leah T. Chua PIID, PRC 705 Mentor


(Signature above Printed Name)

IDr. Billie Jean Dumlao-Dela Cruz, piid


Faculty OJT Coordinator

Date: April 25

, 2012

Date: ________________ , 2012

POLYTECHNIC UNIVERSITY OF THE PHILIPPINES

COLLEGE OF ARCHITECTURE AND FINE ARTS DEPARTMENT OF INTERIOR DESIGN


PUP Engineering and Architecture BuildingNDC Compound, Anonas cor. Pureza Sts., Sta. Mesa, Manila Tel: (632) 713 9304

BS INTERIOR DESIGN OJT REPORT

Daily Log of Training Experience


Date: April 26 , 2012

Name of Student:

Reyes,
Family Name

Rincess
First Name

Obar
Middle Name

Office/Company Name: Vincent To Ng/Vincent Ng Architectural Services Address: Unit 4 # 8 Binmaka St., Brgy. Manresa Quezon City Project Title: Brand & Lifestyle Development Partners, Inc. Office Project Description: Interior Design Project Location: G/F One E-Com Center Ocean Drive cor. Sunset Ave. SM Central Business Park, Pasay City Assigned Work Task: Time In Time Out : : As-Built 8:00 a.m 5:00 p.m Sunny Total No. of Hour/s Spent: Site Condition: 8 hours Office Site Others, pls. specify

Weather Condition:

Work Activities Performed: Fitness First Office o o Area Measurement As-Built

Personal Observations at the Project Site:

Report/s Submitted, if any:

Lesson/s Learned:

I learned that in getting the as built of the space all the existing lighting and power are obtain.

Picture/s Taken, if any:

Certified True and Correct by:

Noted by:

Leah T. Chua PIID, PRC 705 Mentor


(Signature above Printed Name)

IDr. Billie Jean Dumlao-Dela Cruz, piid


Faculty OJT Coordinator

Date: April 26

, 2012

Date: ________________ , 2012

POLYTECHNIC UNIVERSITY OF THE PHILIPPINES

COLLEGE OF ARCHITECTURE AND FINE ARTS DEPARTMENT OF INTERIOR DESIGN


PUP Engineering and Architecture BuildingNDC Compound, Anonas cor. Pureza Sts., Sta. Mesa, Manila Tel: (632) 713 9304

BS INTERIOR DESIGN OJT REPORT

Daily Log of Training Experience


Date: April 27 , 2012

Name of Student:

Reyes,
Family Name

Rincess
First Name

Obar
Middle Name

Office/Company Name: Vincent To Ng/Vincent Ng Architectural Services Address: Unit 4 # 8 Binmaka St., Brgy. Manresa Quezon City Project Title: Brand & Lifestyle Development Partners, Inc. Office Project Description: Interior Design Project Location: G/F One E-Com Center Ocean Drive cor. Sunset Ave. SM Central Business Park, Pasay City Assigned Work Task: Time In Time Out : : CADD 8:00 a.m 5:00 p.m Sunny Total No. of Hour/s Spent: Site Condition: 8 hours Office Site Others, pls. specify

Weather Condition:

Work Activities Performed: CADD o o Floor Plan (As-Built) Proposed Floor Plan with Furniture Layout

Personal Observations at the Project Site:

Report/s Submitted, if any:

Lesson/s Learned:

I learned some techniques and shortcut in CADD.

Picture/s Taken, if any:

Certified True and Correct by:

Noted by:

Leah T. Chua PIID, PRC 705 Mentor


(Signature above Printed Name)

IDr. Billie Jean Dumlao-Dela Cruz, piid


Faculty OJT Coordinator

Date: April 27

, 2012

Date: ________________ , 2012

POLYTECHNIC UNIVERSITY OF THE PHILIPPINES

COLLEGE OF ARCHITECTURE AND FINE ARTS DEPARTMENT OF INTERIOR DESIGN


PUP Engineering and Architecture BuildingNDC Compound, Anonas cor. Pureza Sts., Sta. Mesa, Manila Tel: (632) 713 9304

BS INTERIOR DESIGN OJT REPORT

Daily Log of Training Experience


Date: April 30 , 2012

Name of Student:

Reyes,
Family Name

Rincess
First Name

Obar
Middle Name

Office/Company Name: Vincent To Ng/Vincent Ng Architectural Services Address: Unit 4 # 8 Binmaka St., Brgy. Manresa Quezon City Project Title: Brand & Lifestyle Development Partner, Inc. Office Project Description: Interior Design Project Location: G/F One E-Com Center Ocean Drive cor. Sunset Ave. SM Central Business Park, Pasay City Assigned Work Task: Time In Time Out : : CADD 8:00 a.m 5:00 p.m Sunny Total No. of Hour/s Spent: Site Condition: 8 hours Office Site Others, pls. specify

Weather Condition:

Work Activities Performed: CADD o o Proposed Floor Plan with Furniture Layout Proposed Reflected Ceiling Plan

Personal Observations at the Project Site:

Report/s Submitted, if any:

Lesson/s Learned:

I learned how to make furniture more visible to see and become accent.

Picture/s Taken, if any:

Certified True and Correct by:

Noted by:

Leah T. Chua PIID, PRC 705 Mentor


(Signature above Printed Name)

IDr. Billie Jean Dumlao-Dela Cruz, piid


Faculty OJT Coordinator

Date: April 30

, 2012

Date: ________________ , 2012

POLYTECHNIC UNIVERSITY OF THE PHILIPPINES

COLLEGE OF ARCHITECTURE AND FINE ARTS DEPARTMENT OF INTERIOR DESIGN


PUP Engineering and Architecture BuildingNDC Compound, Anonas cor. Pureza Sts., Sta. Mesa, Manila Tel: (632) 713 9304

BS INTERIOR DESIGN OJT REPORT

Daily Log of Training Experience


Date: May 02 , 2012

Name of Student:

Reyes,
Family Name

Rincess
First Name

Obar
Middle Name

Office/Company Name: Vincent To Ng/Vincent Ng Architectural Services Address: Unit 4 # 8 Binmaka St., Brgy. Manresa Quezon City Project Title: Project Location: Trinoma Assigned Work Task: Time In Time Out : : CADD 8:00 a.m 5:00 p.m Sunny Total No. of Hour/s Spent: Site Condition: 8 hours Office Site Others, pls. specify Traffic Store Project Description: Interior Design

Weather Condition:

Work Activities Performed: CADD o o o Proposed Lighting Layout of Fitness First Office Floor Plan with Furniture Layout (As-Built) Reflected Ceiling Plan (As-Built)

Personal Observations at the Project Site:

Report/s Submitted, if any:

Lesson/s Learned:

I learned some light fixture that can use in retail design.

Picture/s Taken, if any:

Certified True and Correct by:

Noted by:

Leah T. Chua PIID, PRC 705 Mentor


(Signature above Printed Name)

IDr. Billie Jean Dumlao-Dela Cruz, piid


Faculty OJT Coordinator

Date: May 02

, 2012

Date: ________________ , 2012

POLYTECHNIC UNIVERSITY OF THE PHILIPPINES

COLLEGE OF ARCHITECTURE AND FINE ARTS DEPARTMENT OF INTERIOR DESIGN


PUP Engineering and Architecture BuildingNDC Compound, Anonas cor. Pureza Sts., Sta. Mesa, Manila Tel: (632) 713 9304

BS INTERIOR DESIGN OJT REPORT

Daily Log of Training Experience


Date: Name of Student: Reyes,
Family Name

May 03 Obar
Middle Name

, 2012

Rincess
First Name

Office/Company Name: Vincent To Ng/Vincent Ng Architectural Services Address: Unit 4 # 8 Binmaka St., Brgy. Manresa Quezon City Project Title: Project Location: Trinoma Assigned Work Task: Time In Time Out : : CADD 8:00 a.m 5:00 p.m Sunny Total No. of Hour/s Spent: Site Condition: 8 hours Office Site Others, pls. specify Traffic Store Project Description: Interior Design

Weather Condition:

Work Activities Performed: CADD o o Module Specification Wall Elevation (As-Built

Personal Observations at the Project Site:

Report/s Submitted, if any:

Lesson/s Learned:

I learned some method in making elevation via CADD.

Picture/s Taken, if any:

Certified True and Correct by:

Noted by:

Leah T. Chua PIID, PRC 705 Mentor


(Signature above Printed Name)

IDr. Billie Jean Dumlao-Dela Cruz, piid


Faculty OJT Coordinator

Date: May 03

, 2012

Date: ________________ , 2012

POLYTECHNIC UNIVERSITY OF THE PHILIPPINES

COLLEGE OF ARCHITECTURE AND FINE ARTS DEPARTMENT OF INTERIOR DESIGN


PUP Engineering and Architecture BuildingNDC Compound, Anonas cor. Pureza Sts., Sta. Mesa, Manila Tel: (632) 713 9304

BS INTERIOR DESIGN OJT REPORT

Daily Log of Training Experience


Date: May 04 , 2012

Name of Student:

Reyes,
Family Name

Rincess
First Name

Obar
Middle Name

Office/Company Name: Vincent To Ng/Vincent Ng Architectural Services Address: Unit 4 # 8 Binmaka St., Brgy. Manresa Quezon City Project Title: Project Location: Trinoma Assigned Work Task: Time In Time Out : : CADD 8:00 a.m 5:00 p.m Sunny Total No. of Hour/s Spent: Site Condition: 8 hours Office Site Others, pls. specify Traffic Store Project Description: Interior Design

Weather Condition:

Work Activities Performed: CADD o Wall Elevation (As-Built)

Personal Observations at the Project Site:

Report/s Submitted, if any:

Lesson/s Learned:

I learned how to create text in CADD.

Picture/s Taken, if any:

Certified True and Correct by:

Noted by:

Leah T. Chua PIID, PRC 705 Mentor


(Signature above Printed Name)

IDr. Billie Jean Dumlao-Dela Cruz, piid


Faculty OJT Coordinator

Date: May 04

, 2012

Date: ________________ , 2012

POLYTECHNIC UNIVERSITY OF THE PHILIPPINES

COLLEGE OF ARCHITECTURE AND FINE ARTS DEPARTMENT OF INTERIOR DESIGN


PUP Engineering and Architecture BuildingNDC Compound, Anonas cor. Pureza Sts., Sta. Mesa, Manila Tel: (632) 713 9304

BS INTERIOR DESIGN OJT REPORT

Daily Log of Training Experience


Date: Name of Student: Reyes,
Family Name

May 07 Obar
Middle Name

, 2012

Rincess
First Name

Office/Company Name: Vincent To Ng/Vincent Ng Architectural Services Address: Unit 4 # 8 Binmaka St., Brgy. Manresa Quezon City Project Title: Project Location: Trinoma Assigned Work Task: Time In Time Out : : CADD 8:00 a.m 5:00 p.m Sunny Total No. of Hour/s Spent: Site Condition: 8 hours Office Site Others, pls. specify Bellabianca Project Description: Interior Design

Weather Condition:

Work Activities Performed: CADD o o o Traffic Store Wall Elevation (As-Built) Bellebianca Floor Plan with Furniture Layout (As-Built) Bellebianca Reflected Ceiling Plan (As-Built)

Personal Observations at the Project Site:

Report/s Submitted, if any:

Lesson/s Learned:

I learned how to layout floor plan, reflected ceiling, elevation, and module in 20x30 using CADD.

Picture/s Taken, if any:

Certified True and Correct by:

Noted by:

Leah T. Chua PIID, PRC 705 Mentor


(Signature above Printed Name)

IDr. Billie Jean Dumlao-Dela Cruz, piid


Faculty OJT Coordinator

Date: May 07

, 2012

Date: ________________ , 2012

POLYTECHNIC UNIVERSITY OF THE PHILIPPINES

COLLEGE OF ARCHITECTURE AND FINE ARTS DEPARTMENT OF INTERIOR DESIGN


PUP Engineering and Architecture BuildingNDC Compound, Anonas cor. Pureza Sts., Sta. Mesa, Manila Tel: (632) 713 9304

BS INTERIOR DESIGN OJT REPORT

Daily Log of Training Experience


Date: Name of Student: Reyes,
Family Name

May 08 Obar
Middle Name

, 2012

Rincess
First Name

Office/Company Name: Vincent To Ng/Vincent Ng Architectural Services Address: Unit 4 # 8 Binmaka St., Brgy. Manresa Quezon City Project Title: Project Location: Trinoma Assigned Work Task: Time In Time Out : : CADD 8:00 a.m 5:00 p.m Sunny Total No. of Hour/s Spent: Site Condition: 8 hours Office Site Others, pls. specify Bellebianca Project Description: Interior Design

Weather Condition:

Work Activities Performed: CADD o o Module Specification Wall Elevation (As-Built)

Personal Observations at the Project Site:

Report/s Submitted, if any:

Lesson/s Learned:

I learned how to edit the dimension line.

Picture/s Taken, if any:

Certified True and Correct by:

Noted by:

Leah T. Chua PIID, PRC 705 Mentor


(Signature above Printed Name)

IDr. Billie Jean Dumlao-Dela Cruz, piid


Faculty OJT Coordinator

Date: May 08

, 2012

Date: ________________ , 2012

POLYTECHNIC UNIVERSITY OF THE PHILIPPINES

COLLEGE OF ARCHITECTURE AND FINE ARTS DEPARTMENT OF INTERIOR DESIGN


PUP Engineering and Architecture BuildingNDC Compound, Anonas cor. Pureza Sts., Sta. Mesa, Manila Tel: (632) 713 9304

BS INTERIOR DESIGN OJT REPORT

Daily Log of Training Experience


Date: May 09 , 2012

Name of Student:

Reyes,
Family Name

Rincess
First Name

Obar
Middle Name

Office/Company Name: Vincent To Ng/Vincent Ng Architectural Services Address: Unit 4 # 8 Binmaka St., Brgy. Manresa Quezon City Project Title: Project Location: Trinoma Assigned Work Task: Time In Time Out : : CADD 8:00 a.m 5:00 p.m Sunny Total No. of Hour/s Spent: Site Condition: 8 hours Office Site Others, pls. specify Bellebianca Project Description: Interior Design

Weather Condition:

Work Activities Performed: CADD o Wall Elevation (As-Built)

Personal Observations at the Project Site:

Report/s Submitted, if any:

Lesson/s Learned:

I learned how to measure the length of the line in CADD.

Picture/s Taken, if any:

Certified True and Correct by:

Noted by:

Leah T. Chua PIID, PRC 705 Mentor


(Signature above Printed Name)

IDr. Billie Jean Dumlao-Dela Cruz, piid


Faculty OJT Coordinator

Date: May 09

, 2012

Date: ________________ , 2012

POLYTECHNIC UNIVERSITY OF THE PHILIPPINES

COLLEGE OF ARCHITECTURE AND FINE ARTS DEPARTMENT OF INTERIOR DESIGN


PUP Engineering and Architecture BuildingNDC Compound, Anonas cor. Pureza Sts., Sta. Mesa, Manila Tel: (632) 713 9304

BS INTERIOR DESIGN OJT REPORT

Daily Log of Training Experience


Date: Name of Student: Reyes,
Family Name

May 10 Obar
Middle Name

, 2012

Rincess
First Name

Office/Company Name: Vincent To Ng/Vincent Ng Architectural Services Address: Unit 4 # 8 Binmaka St., Brgy. Manresa Quezon City Project Title: Project Location: Trinoma Assigned Work Task: Time In Time Out : : CADD 8:00 a.m 5:00 p.m Sunny Total No. of Hour/s Spent: Site Condition: 8 hours Office Site Others, pls. specify Bellebianca Project Description: Interior Design

Weather Condition:

Work Activities Performed: CADD o o Wall Elevation (As-Built) Air conditioning Specification

Personal Observations at the Project Site:

Report/s Submitted, if any:

Lesson/s Learned:

I learned how to change the layer into another layer in an easy way.

Picture/s Taken, if any:

Certified True and Correct by:

Noted by:

Leah T. Chua PIID, PRC 705 Mentor


(Signature above Printed Name)

IDr. Billie Jean Dumlao-Dela Cruz, piid


Faculty OJT Coordinator

Date: May 10

, 2012

Date: ________________ , 2012

POLYTECHNIC UNIVERSITY OF THE PHILIPPINES

COLLEGE OF ARCHITECTURE AND FINE ARTS DEPARTMENT OF INTERIOR DESIGN


PUP Engineering and Architecture BuildingNDC Compound, Anonas cor. Pureza Sts., Sta. Mesa, Manila Tel: (632) 713 9304

BS INTERIOR DESIGN OJT REPORT

Daily Log of Training Experience


Date: May 11 , 2012

Name of Student:

Reyes,
Family Name

Rincess
First Name

Obar
Middle Name

Office/Company Name: Vincent To Ng/Vincent Ng Architectural Services Address: Unit 4 # 8 Binmaka St., Brgy. Manresa Quezon City Project Title: Digital Walker Project Description: Interior Design

Project Location: Robinsons Magnolia Town Center Aurora Boulevard, Quezon City Assigned Work Task: Time In Time Out : : CADD 8:00 a.m 5:00 p.m Sunny Total No. of Hour/s Spent: Site Condition: 8 hours Office Site Others, pls. specify

Weather Condition:

Work Activities Performed: CADD o o o o o Digital Walker Floor Plan Crumpler Floor Plan Crumpler Fire Protection Plan Crumpler Airconditioning Plan Crumpler Mechanical Plan

Personal Observations at the Project Site:

Report/s Submitted, if any:

Lesson/s Learned:

I learned how to estimate some dimension so the space is fit.

Picture/s Taken, if any:

Certified True and Correct by:

Noted by:

Leah T. Chua PIID, PRC 705 Mentor


(Signature above Printed Name)

IDr. Billie Jean Dumlao-Dela Cruz, piid


Faculty OJT Coordinator

Date: May 11

, 2012

Date: ________________ , 2012

Interior Design

Weekly Log

POLYTECHNIC UNIVERSITY OF THE PHILIPPINES

COLLEGE OF ARCHITECTURE AND FINE ARTS DEPARTMENT OF INTERIOR DESIGN


PUP Engineering and Architecture BuildingNDC Compound, Anonas cor. Pureza Sts., Sta. Mesa, Manila Tel: (632) 713 9304

BS Interior Design On-the-Job Training ON-THE-JOB TRAINING WEEKLY ACCOMPLISHMENT REPORT


Name of Student: Reyes,
Family Name,

Rincess
First Name

Obar
Middle Name

Student No.2009-02004-MN-0 Employed by: Vincent To Ng/Vincent Ng Architectural Service Address: Unit 4 # 08 Binmaka Street Brgy. Manresa Quezon City Reporting Period from:
Day

24
Month

April

2012

to
Day

27
Month

April

2012
Percentage of Assigned Work Completed

Item No.

Field of Practice Project Title/Description/Location (Brief Description)

No. of Hours

100% = Full Completion

Six Unit Three Storey Town House/ Interior Design/ #47 Mapagkumbaba Street, Sikatuna Property, Quezon City

CADD Proposed nd rd Ground, 2 and 3 Floor Plan with Furniture Layout and Lighting Layout

14 hours

100 %

Brand & Lifestyle Development Partners, Inc. Office/ Interior Design/ G/F One E-Com Center Ocean Drive cor. Sunset Ave. SM Central Business Brand & Lifestyle Development Partners, Inc./ Interior Design/ G/F One E-Com Center Ocean Drive cor. Sunset Ave. SM Central Business

Area Measurement (As-Built)

8 hours

100 %

CADD Floor Plan (AsBuilt) and Proposed Floor Plan with Furniture Layout

8 hours

45 %

Item No.

Field of Practice Project Title/Description/Location (Brief Description)

No. of Hours

Percentage of Assigned Work Completed

100% = Full Completion

TOTAL NO. OF HOURS

30 hours

81.67 %

Recommendations for the Trainees further growth and development:

Checked and Approved by:

Conforme:

Rincess O. Reyes OJT Faculty Coordinator


(Signature above printed name)

Student Trainee
(Signature above printed name)

POLYTECHNIC UNIVERSITY OF THE PHILIPPINES

COLLEGE OF ARCHITECTURE AND FINE ARTS DEPARTMENT OF INTERIOR DESIGN


PUP Engineering and Architecture BuildingNDC Compound, Anonas cor. Pureza Sts., Sta. Mesa, Manila Tel: (632) 713 9304

BS Interior Design On-the-Job Training ON-THE-JOB TRAINING WEEKLY ACCOMPLISHMENT REPORT

Name of Student:

Reyes,
Family Name,

Rincess
First Name

Obar
Middle Name

Student No.2009-02004-MN-0 Employed by: Vincent To Ng/Vincent Ng Architectural Service Address: Unit 4 # 8 Binmaka St., Brgy. Manresa Quezon City Reporting Period from:
Day

30
Month

April

2012

to
Day

04
Month

May

2012
Percentage of Assigned Work Completed

Item No.

Field of Practice Project Title/Description/Location (Brief Description)

No. of Hours

100% = Full Completion

Brand & Lifestyle Development Partners, Inc. Office/ Interior Design/ G/F One E-Com Center Ocean Drive cor. Sunset Ave. SM Central Business

CADD Continuation of Proposed Floor Plan, Reflected Ceiling Plan and Lighting Layout CADD Floor Plan with Furniture Layout (AsBuilt), Reflected Ceiling Plan (As-Built), Module Specification, Wall Elevation (As-Built)

11 hours

100 %

Traffic Store/ Interior Design/ Trinoma

24 hours

85 %

Item No.

Field of Practice Project Title/Description/Location (Brief Description)

No. of Hours

Percentage of Assigned Work Completed

100% = Full Completion

TOTAL NO. OF HOURS

35 hours

92.5 %

Recommendations for the Trainees further growth and development:

Checked and Approved by:

Conforme:

Rincess O. Reyes OJT Faculty Coordinator


(Signature above printed name)

Student Trainee
(Signature above printed name)

POLYTECHNIC UNIVERSITY OF THE PHILIPPINES

COLLEGE OF ARCHITECTURE AND FINE ARTS DEPARTMENT OF INTERIOR DESIGN


PUP Engineering and Architecture BuildingNDC Compound, Anonas cor. Pureza Sts., Sta. Mesa, Manila Tel: (632) 713 9304

BS Interior Design On-the-Job Training ON-THE-JOB TRAINING WEEKLY ACCOMPLISHMENT REPORT

Name of Student:

Reyes,
Family Name,

Rincess
First Name

Obar
Middle Name

Student No.2009-02004-MN-0 Employed by: Vincent To Ng/Vincent Ng Architectural Services Address: Unit 4 # 8 Binmaka St., Brgy. Manresa Quezon City Reporting Period from: 07 May
Day Month

2012

to

11

May
Day Month

2012
Percentage of Assigned Work Completed

Item No.

Project Title/Description/Location

Field of Practice (Brief Description)

No. of Hours

100% = Full Completion

Traffic Store/Interior Design/ Trinoma

CADD Continuation of Wall Elevation (As-Built)

2 hours

100 %

Bellebianca/Interior Design/ Trinoma

CADD Floor Plan with Furniture Layout (AsBuilt), Reflected Ceiling Plan (As-Built), Module Specification, Wall Elevation (As-Built) CADD Air Condition Specification

28 hours

100 %

Six Unit Three Storey Town House/ Interior Design/ #47 Mapagkumbaba Street, Sikatuna Property, Quezon City Digital Walker/ Interior Design/ Robinsons Magnolia Town Center Aurora Boulevard, Quezon City Crumpler/ Interior Design/ Robinsons Magnolia Town Center Aurora Boulevard, Quezon City

4 hours

100 %

CADD Digital Walker Floor Plan

1 hour 100 %

CADD Floor Plan, Fire Protection Plan, Airconditioning Plan, and Mechanical Plan

7 hours

100 %

Item No.

Field of Practice Project Title/Description/Location (Brief Description)

No. of Hours

Percentage of Assigned Work Completed

100% = Full Completion

TOTAL NO. OF HOURS

42 hours

100 %

Recommendations for the Trainees further growth and development:

Checked and Approved by:

Conforme:

Rincess O. Reyes OJT Faculty Coordinator


(Signature above printed name)

Student Trainee
(Signature above printed name)

Interior Design

Certificate of Completion

Interior Design

Evaluation Form

Portfolio of Works

PORTFOLIO

OF

WORKS

Rincess O. Reyes

INTERIOR DESIGN

BRAND & LIFESTYLE DEVELPOMENT PARTNERS, INC. OFFICE PROPOSED FLOOR PLAN

BRAND & LIFESTYLE DEVELPOMENT PARTNERS, INC. OFFICE PROPOSED LIGHTING LAYOUT

BRAND & LIFESTYLE DEVELPOMENT PARTNERS, INC. OFFICE FLOOR PLAN (AS-BUILT)

MAPAGKUMBABA GROUND FLOOR REFLECTED CEILING PLAN

MAPAGKUMBABA SECOND FLOOR REFLECTED CEILING PLAN

MAPAGKUMBABA THIRD FLOOR REFLECTED CEILING PLAN

MAPAGKUMBABA GROUND FLOOR LIGHTING LAYOUT

MAPAGKUMBABA SECOND FLOOR LIGHTING LAYOUT

MAPAGKUMBABA THIRD FLOOR LIGHTING LAYOUT

MISCELLANEOUS DETAILS FOR AIR-CONDITIONING

DIGITAL WALKER FLOOR PLAN

CRUMPLER FLOOR PLAN

CRUMPLER FIRE PROTECTION PLAN

CRUMPLER MECHANICAL PLAN

CRUMPLER AIRCONDITIONING PLAN

TRAFFIC STORE FLOOR AND REFLECTED CEILING PLAN

TRAFFIC STORE WALL ELEVATION A, B, C, AND D

TRAFFIC STORE MODULE SPECIFICATION

TRAFFIC STORE MODULE SPECIFICATION

BELLEBIANCA FLOOR, REFLECTION CEILING PLAN

BELLEBIANCA WALL ELEVATION A, B, C, AND D

BELLEBIANCA MODULE SPECIFICATION

ARCHITECTURE

MARIANO HO PROPOSED GROUND FLOOR PLAN

MARIANO HO PROPOSED SECOND FLOOR PLAN

MARIANO HO PROPOSED THIRD FLOOR PLAN

MARIANO HO FLOOR PLAN(AS-BUILT)

MARIANO HO FLOOR PLAN (AS-BUILT)

ALVIN ANG AND THREE STOREY RESIDENCE

FURNITURE

OFFICE WORKSTATION

OFFICE WORKSTATION

Final OJT Report

In my first day I was so nervous and i dont know what to do. I was thinking, if what kind of work I will going to accomplish and if Im doing it right. But then I was so happy because I have my friend Karen Salvador whom Im with and it was my first time to have work. It was the first time of the 2(two) company that Im working with to have an apprentice.

After few days in the on the job training my nervous was vanished because my mentors are really nice and friendly, and the activities that they give to me was easy because it was the usual thing that we did in school although I have only basic information in Computer Aided Drafting and Design and Google Sketch-Up. Since everyday Im doing the Computer Aided Drafting and Design and Google Sketch-Up I was getting used to it.

I learned a lot in these on the job training. I learned how to communicate properly and I discover something that Im going to apply in my daily life.