Professional Documents
Culture Documents
MRP :A system of planning and scheduling the time-phased materials requirement for production operations Reactive system ( What should I do now ) to what will I be needing in the future how much and when?
to successful production and operations management is balancing of requirements and capacities Objectives
Inventory
MRP
reduction
enables the manager to produce that component as it is needed avoiding costs of excessive inventory
Reduction
unplanned interruption
requires
system for accurate inventory and product build up information A realistic master production schedule Discipline and commitment by schedulers, supervisors, managers and shop floor employees to make the system work Keep the system honest accurate and believable
dependency
to which the demand for some item is associated with the demand for another item Thus if one is known the other can be predicted (if the demand for the end product is known the demand for sub components can be predicted)
Independent
Demand
demand
Reactive
inventory control system (order quantity reorder point systems) ignore the distinction between dependent and independent demand
Output Planning
Operations
Capacity planning
Aggregate output Aggregate output planning Planning Master Production Scheduling MRP Loading
Aggregate Capacity Planning Rough cut capacity planning Detailed capacity planning
Sequencing
Detailed scheduling
Expediting
to the MRP system Developed from firm customer orders or demand forecast Identifies the quantity of each end product and when it needs to be produced during each future period in the production planning horizon Orders for replacement (service) components are also entered as end items in MPS Provides focal information for the MRP
Components
2F
E
3G
2H
identifying levels in product structure brings out the relationship among components Each item is given a unique identification number Thus scheduling and time phasing the orders for correct lower level components in the product structure becomes possible
Status file
Provides
accurate information about the availability of every item controlled by MRP system Contains the following information on each component
the
identification number Quantity on hand Safety stock level Quantity disbursed / allocated Lead time
Processing Logic
Accepts
the master schedule and determines the component schedule for successively lower level items of the product structure It calculates for each item in each product structure and for each time period (typically one week ) in the planning horizon how many of that item are needed ( gross requirements ) How much inventory is available Planned order receipts Planned order releases
Order Receipts
quantity of an item that is planned to be ordered so that it will be received at the beginning of the time period to meet net requirements for the period. The order has not yet been placed
Planned
order release
Quantity
of an item that is planned to be ordered and the planned period for releasing this order that will result in the order being received when needed Planned order receipt offset in time by the items lead time. When this order is placed (released), It becomes a scheduled receipt and is delete from planned order receipts and planned order releases.
the order is placed (released) it becomes a scheduled release and is deleted from planned order receipts and planned order releases
Scheduled
The
Receipts
quantity of an item that will be received from suppliers as a result of orders that have been placed (open orders) Net requirements
Net
quantity of an item that must be acquired to meet the scheduled output for the period calculated as gross requirements minus scheduled receipt for the period minus amounts available from the previous period
quantity of an item in inventory that has been committed for use and is not available for future requirements
Gross
Requirements
Over all quantity of an item needed at the end of a period to meet planned output levels. Planned output for end items is obtained from the MPS. Planned output for the lower level items is obtained from the MRP system
Schedule
The
Receipts
quantity of an item that will be received at the beginning of a time period from suppliers as a result of orders that have been placed (open orders)
Quantity
quantity of an item expected to be available at the end of a time period for meeting requirements in the succeeding periods. Calculated as
receipts + planned order receipts gross requirements for the period + amounts available from the previous period
Scheduled
processing Sequence
processing logic is applied first to the high level items (end products) in the product structure and then to items in the next lower level. It continues downwards level by level until it has determined the requirement for all items in the product structure.
Indented
Bill Of Material
Provides
create a parent item we often need multiple units of a lower level item . e.g one unit of H requires four units of E Hence the planned order release of 450 units of H in week 7 must be multiplied by four (4 X 450 = 1800 ) to determine the gross requirement of E in week 7
Low
level Coding
Often
a single item exists in several levels of the product structure. e.g. Item E for example exists at both levels 1 and 2 for end time H. To improve efficiency of calculations MRP assigns the item to the lowest level E is treated as level 2 item gross requirements are determined from the planned order releases of its parent item F,G and H