Professional Documents
Culture Documents
HENRY P. TURALDE
College of Engineering Camarines Sur Polytechnic Colleges Email: engineer_pluss@yahoo.com
Quotable Quotes
2
Introduction
Common Scheme : Cross Slope Alternative Scheme: One Side Slope Designing the Storm Water Drainage Using Box Culvert Using Pipe Culvert Highlights on the Differences of the Common and Alternative Schemes Conclusion
Introduction
4
Land transportation
Principal
means of transporting persons and goods Roads crucial role in economic development Roads as priority infrastructure
Introduction
5
Introduction
6
Do away with non-essentials Eliminate duplicates Rid off redundant Reduce items of works
carriageway slope
sidewalk slope
drainage
drainage
Common Scheme:
carriageway slope
sidewalk slope
drainage
drainage
Common Scheme:
drainage
Alternative Scheme:
One-side slope
2007 PICE NATIONAL CONVENTION
Q CI
1 2 3 1 v ( )R S 2 n
where: Q = run-off rate C = coefficient of run-off I = average rainfall intensity Ad = drainage area
1 2 1 3 Q Ac ( ) R S 2 n
Using Pipe:
Ac = bd = 2d2 P = 2d + b = 2d + 2d = 4d R = Ac / P = 2d2 / 4d = d
Illustrative Example Application Given: Length of the Road = 1000 m Width of the 2-lane road = 7 m
(consider 20 m including sidewalk, planting strip and other)
Distance between manholes = 50 m Coefficient of run-off = 0.85 Rainfall intensity = 224 mm/hr = 0.0622 mm/sec Roughness coefficient = 0.013 Slope = 0.005
0 + 050
0 + 100 0 + 150 0 + 200 0 + 250 0 + 300 0 + 350 0 + 400 0 + 450 0 + 500 0 + 550 0 + 600
1,000
2,000 3,000 4,000 5,000 6,000 7,000 8,000 9,000 10,000 11,000 12,000
500
600 600 700 700 700 750 750 750 800 800 800
500
500 500 500 500 500 500 500 500 500 500 500
600
700 700 800 800 800 800 900 900 900 900 900
500
500 500 500 500 500 500 600 600 600 600 600
0 + 650
0 + 700 0 + 750 0 + 800 0 + 850 0 + 900 0 + 950 1 + 000
13,000
14,000 15,000 16,000 17,000 18,000 19,000 20,000
800
800 850 850 850 850 900 900
500
500 500 500 500 500 500 500
900
1,000 1,000 1,000 1,000 1,000 1,000 1,000
600
600 600 600 600 600 600 600
O.D. + 0.6m
Diameter mm 265
0 + 100
0 + 150 0 + 200 0 + 250 0 + 300 0 + 350 0 + 400 0 + 450 0 + 500 0 + 550 0 + 600
0.053
0.079 0.106 0.132 0.159 0.185 0.212 0.238 0.264 0.291 0.317
265
271 344 374 400 424 446 466 485 502 519
300
300 400 400 400 500 500 500 500 500 600
0.106
0.159 0.212 0.264 0.317 0.370 0.423 0.476 0.529 0.582 0.635
344
351 446 485 519 550 578 604 629 652 673
400
400 500 500 600 600 600 600 700 700 700
0 + 650
0 + 700 0 + 750 0 + 800 0 + 850 0 + 900 0 + 950 1 + 000
0.344
0.370 0.397 0.423 0.450 0.476 0.502 0.529
535
550 564 578 591 604 617 629
600
600 600 600 600 600 700 700
0.688
0.740 0.793 0.846 0.899 0.952 1.005 1.058
694
713 732 750 767 784 800 815
700
800 800 800 800 800 800 900
Using pipes
16
Summary Comparison
Quantities of drainage works
18
For cross-slope:
drainage
Summary Comparison
Quantities of drainage works
20
1,829.37 42.32%
1,194.25 45.54%
374.62 39.96%
33,716.25 39.96%
drainage
Summary Comparison
Quantities of drainage works
22
USING PIPES
Excavation (m3) Cross-slope One-side slope Quantity reduced Reduced (%) 2,256.00 1,463.00 Backfill (m3) 1,827.96 1,111.14
793.00 35.15%
716.82 39.21%
Summary Comparison
Quantities of drainage works
23
USING PIPES
Diameter (mm) 200 Cross-slope Length (m) 100 One-side Slope Length (m) -
300
400 500 600 700 800 900
200
300 500 700 200 -
50
100 100 200 200 300 50
150
200 400 500 0 (300 addition) (50 addition)
75.00%
66.67% 80.00% 71.43% 0.00% -
Total
2000
1000
1000
CONCLUSION
24
urban road project construction costs due to reduction of quantities of drainage works Excavation Backfill Manholes Conveyance materials One-side slope road shortens project execution period Particularly underground works require extra care Savings derived through this alternative scheme Eventually be used to build other roads
Point to Ponder
25
In time of scarcity,
option is a luxury.
26
THANK YOU.
HENRY P. TURALDE Email: engineer_pluss@yahoo.com