Professional Documents
Culture Documents
Samee Bhangu 2
Presented by
Mr. Samee Bhangu
Samee Bhangu 3
A project is a unique endeavor to
produce a set of deliverables within
clearly specified time, cost and quality
constraints.
Projects are different from standard
business operational activities as they:
Are unique in nature.
Have a defined timescale.
Have an approved budget.
Have limited resources.
Involve an element of risk.
Achieve beneficial change.
Samee Bhangu 5
● A unique, one-time operational activity or effort
● Requires the completion of a large number of
interrelated activities
● Established to achieve specific objective
● Resources, such as time and/or money, are
limited
● Typically has its own management structure
● Need leadership
Samee Bhangu 6
constructing houses, factories, shopping
malls, athletic stadiums or arenas
developing military weapons systems,
aircrafts, new ships
launching satellite systems
constructing oil pipelines
developing and implementing new
computer systems
planning concert, football games, or
basketball tournaments
introducing new products into market
Samee Bhangu 7
Project
Management is the skills, tools
and management processes required
to undertake a project successfully. It
incorporates:
A set of skills.
A suite of tools.
A series of processes.
Samee Bhangu 8
Samee Bhangu 9
President
Human Quality
Sales Finance Engineering Production
Factors Control
Project 1 Project
Manager
Propulsion Test
Physiologist Technician
Engineer Engineer
Project 2 Project
Manager
Structural Inspection
Psychologist Technician
Engineer Technician
Samee Bhangu 10
Payne & Turner categorized into 4 types in 1999
= of capital of
1. Major Projects Organization
2. Large Projects =1/10 of capital of
3. Medium Organization
te r s of
r ea ce
G an ss
Ch cce
Su 16-12 Samee Bhangu
Project planning
Project scheduling
Project control
Project team
made up of individuals from various areas and
departments within a company
Matrix organization
a team structure with members from functional
areas, depending on skills required
Project Manager
most important member of project team
Samee Bhangu 13
Scope statement
a document that provides an understanding, justification,
and expected result of a project
Statement of work
written description of objectives of a project
Organizational Breakdown Structure
a chart that shows which organizational units are
responsible for work items
Responsibility Assignment Matrix
shows who is responsible for work in a project
Samee Bhangu 14
Samee Bhangu 16
Figure 5: Full circle and arrow diagram for the computer
project we are using as an example
Samee Bhangu 17
Where one activity cannot start until another has
been completed, we start the arrow for the
dependent activity at the completion event circle
of the previous activity. An example of this is
shown below:
Samee Bhangu 18
A different case is shown below
Samee Bhangu 19
Activity Description Duration
1-2 Social work team to live in village 5w
1-3 Social research team to do survey 12w
3-4 Analyse results of survey 5w
2-4 Establish mother & child health program 14w
3-5 Establish rural credit programme 15w
4-5 Carry out immunization of under fives 4w
4
2
1 5
Samee Bhangu 20
Project Leader
The Team
Work Methods and Procedures
Work Plan
Samee Bhangu 21
Establishing objectives
Defining project
Creating work breakdown structure
Determining resources
Forming organization
Samee Bhangu 22
Resource Availability and/or Limits
Due date, late penalties, early completion
incentives
Budget
Activity Information
Identify all required activities
Estimate the resources required (time) to
complete each activity
Immediate predecessor(s) to each activity
needed to create interrelationships
Samee Bhangu 23
Gantt chart
Critical Path Method (CPM)
Program Evaluation & Review
Technique (PERT)
Network Diagrams
Samee Bhangu 25
Gantt Chart
Graph or bar chart with a bar for each project activity that shows passage of time
Provides visual display of project schedule
Samee Bhangu 26
Critical Path Method (CPM)
E I Du Pont de Nemours & Co. (1957) for construction
of new chemical plant and maintenance shut-down
Deterministic task times
Activity-on-node network construction
Repetitive nature of jobs
Project Evaluation and Review Technique
(PERT)
U S Navy (1958) for the POLARIS missile program
Multiple task time estimates (probabilistic nature)
Activity-on-arrow network construction
Non-repetitive jobs (R & D work)
Samee Bhangu 27
PERT-Program Evaluation and Review
Technique, for planning and
coordinating large projects and is
concern about scheduling of activities
CPM-Critical Path Method, for planning
and coordinating large projects and is
concern about importance of activities
Samee Bhangu 28
Learning Objectives
Aware and Understand the Concepts and
Principles of PERT/CPM
Analyze Business Problem and Relate to
the Applicability Of the Use of
PERT/CPM
Identify Business Problems and Use
PERT/CPM in its solution
Solve Business Problems Using PERT/CPM
Samee Bhangu 29
Path
A connected sequence of activities leading
from the starting event to the ending event
Critical Path
The longest path (time); determines the
project duration
Critical Activities
All of the activities that make up the critical
path
Samee Bhangu 30
Earliest Start Time (ES)
earliest time an activity can start
ES = maximum EF of immediate predecessors
Earliest finish time (EF)
earliest time an activity can finish
earliest start time plus activity time
EF= ES + t
Backward Pass
Latest Start Time (LS)
Latest time an activity can start without delaying critical path time
LS= LF - t
Latest finish time (LF)
latest time an activity can be completed without delaying critical path time
LS = minimum LS of immediate predecessors
Samee Bhangu 31
Draw the CPM network
Analyze the paths through the network
Determine the float for each activity
Compute the activity’s float
float = LS - ES = LF - EF
Float is the maximum amount of time that this activity
can be delay in its completion before it becomes a
critical activity, i.e., delays completion of the project
Find the critical path is that the sequence of activities and
events where there is no “slack” i.e.. Zero slack
Longest path through a network
Find the project duration is minimum project completion
time
Samee Bhangu 32
CPM Network
f,f, 15
15
g,
g, 17
17 h, 9
a, 6
i,i, 66
b, 8
d,
d, 13
13 j,j, 12
c,
c, 55
e,
e, 99
Samee Bhangu 33
PERT is based on the assumption that an activity’s
duration follows a probability distribution instead of
being a single value
Three time estimates are required to compute the
parameters of an activity’s duration distribution:
pessimistic time (tp ) - the time the activity would
take if things did not go well
most likely time (tm ) - the consensus best
estimate of the activity’s duration
optimistic time (to ) - the time the activity would
take if things did go well
T = 40 50 X mz = 0 2.0 Z
Samee Bhangu 16-37
Draw the network.
Analyze the paths through the network and find the
critical path.
The length of the critical path is the mean of the
project duration probability distribution which is
assumed to be normal
The standard deviation of the project duration
probability distribution is computed by adding the
variances of the critical activities (all of the
activities that make up the critical path) and taking
the square root of that sum
Probability computations can now be made using
the normal distribution table.
Samee Bhangu 38
PERT (Program Evaluation and Review
Technique)
PERT is a variation on Critical Path Analysis that
takes a slightly more skeptical view of time
estimates made for each project stage.
Use the formula below to calculate the time to
use for each project stage:
Samee Bhangu 39
Probability
Zσ
µ = tp x Time
Samee Bhangu 40
Immed. Optimistic Most Likely Pessimistic
Activity Predec. Time (Hr.) Time (Hr.) Time (Hr.)
A -- 4 6 8
B -- 1 4.5 5
C A 3 3 3
D A 4 5 6
E A 0.5 1 1.5
F B,C 3 4 5
G B,C 1 1.5 5
H E,F 5 6 7
I E,F 2 5 8
J D,H 2.5 2.75 4.5
K G,I 3 5 7
Samee Bhangu 41
PERT Network
A E H J
B I K
F
Samee Bhangu 42
Activity ES EF LS LF Slack
A 0 6 0 6 0 *critical
B 0 4 5 9
5
C 6 9 6 9 0*
D 6 11 15 20 9
E 6 7 12 13 6
F 9 13 9 13
0*
G 9 11 16 18 7
H 13 19 14 20 1
I 13 18 13 18 0*
J 19 22 20 23 1
K 18 23 18 23 0*
Samee Bhangu 43
Vpath = VA + VC + VF + VI + VK
= 4/9 + 0 + 1/9 + 1 + 4/9
= 2
σ path = 1.414
z = (24 - 23)/σ = (24-23)/1.414 = .71
From the Standard Normal Distribution table:
P(z < .71) = .5 + .2612 = .7612
Samee Bhangu 44
➀ Define the project and all of its significant
activities or tasks
➁ Develop relationships among the activities.
(Decide which activities must precede and which
must follow others.)
➂ Draw the network connecting all of the activities
➃ Assign time and cost estimates to each activity
➄ Compute the longest time path through the
network. This is called the critical path
➅ Use the network to help plan, schedule, monitor,
and control the project
Samee Bhangu 49
Project Network
Event
Signals the beginning or ending of an activity
Designates a point in time
Represented by a circle (node)
Network
Shows the sequential relationships among
activities using nodes and arrows
Activity-on-node (AON)
nodes represent activities, and arrows show precedence
relationships
Activity-on-arrow (AOA)
arrows represent activities and nodes are events for points in time
Samee Bhangu 50
3
Lay Dummy
foundation
2 0 Build Finish
3 1 house work
1 2 4 6 7
Design house Order and 3 1
and obtain receive Select 1 1 Select
financing materials paint carpet
5
C
A
C both A and B must finish before C can start
A
C both A and C must finish before either of B or D can
start
B
D
A
B
A must finish before B can start
Dummy both A and C must finish before D can start
C
D Bhangu
Samee 52
3
Lay foundation Lay
Dummy
foundation
2 0
2 3
1
Order material 2 4
Order material
Samee Bhangu 53
Illustration of network analysis of a minor redesign of a product and its associated
packaging.
The key question is: How long will it take to complete this project ?
Samee Bhangu 54
For clarity, this list is kept to a minimum by specifying only immediate
relationships, that is relationships involving activities that "occur near to each
other in time".
Samee Bhangu 55
Is this a Start Activity?
Is this a Finish Activity?
What Activity Precedes this?
What Activity Follows this?
What Activity is Concurrent with this?
Samee Bhangu 56
Crashing
reducing project time by expending additional
resources
Crash time
an amount of time an activity is reduced
Crash cost
cost of reducing activity time
Goal
reduce project duration at minimum cost
Samee Bhangu 58
Crash cost
Crashing activity
Normal Activity
Normal
cost
Normal
time
Samee Bhangu 59
Crashing costs increase as project duration decreases
Indirect costs increase as project duration increases
Reduce project length as long as crashing costs are less than indirect costs
Time-Cost Tradeoff
Min total cost = Total project cost
optimal project
time Indirect cost
cost
Direct cost
time
Samee Bhangu 60
2 4
12
8
7
1 4
12
3 6
4 5 4
4
Samee Bhangu 61
Activity Normal Normal Crash Crash Allowable slope
time cost Rs time cost Rs crash time
1 12 3000 7 5000 5 400
2 8 2000 5 3500 3 500
3 4 4000 3 7000 1 3000
4 12 50000 9 71000 3 7000
5 4 500 1 1100 3 200
6 4 500 1 1100 3 200
7 4 1500 3 22000 1 7000
75000 110700
Samee Bhangu 62
Crash Action
You may find that you need to
complete a project earlier than your
Critical Path Analysis says is
possible. In this case you need to
take action to reduce the length of
time spent on project stages.
Samee Bhangu 63
Aswith Gantt Charts, in practice project
managers tend to use software tools like
Microsoft Project to create CPA Charts. Not
only do these ease make them easier to
draw, they also make modification of plans
easier and provide facilities for monitoring
progress against plans. Microsoft Project is
reviewed at the top of our left hand title
bar.
Samee Bhangu 64
Learning Objectives
Be Familiar and Understand the Concepts
and Principles of Project Financing and
Budgeting
Know and understand how project cost is
analysed and identify sources of financing
Identify and Analyze Project Costs and
Benefits
Compute for the Financial and Economic
Viability of Projects
Samee Bhangu 66
How much will the project cost
To develop
To operate
To maintain
Canwe sustain project operations
and maintenance?
Samee Bhangu 67
How much is needed to operate and maintain
the project in usable form?
If we can charge user fees, how much should it
be? How much more is needed to collect the
fees (administrative cost of collecting the fees)?
Given the fees, what is the projected number of
users?
If we do not collect the fees, what is the
projected number of users?
If the project cannot be expected to pay for
itself, will the provincial government be willing
to subsidize its operations and maintenance?
By how much?
Samee Bhangu 68
If operations and maintenance of the
project cannot be sustained, either
from project revenues or subsidies
from the province, the project
investment should not be undertaken.
Samee Bhangu 69
Equity (Owner’s Investment)
Co-Financing
Samee Bhangu 70
Budget Budget
Accountability Preparation
Budget Budget
Execution Authorization
Budget
Review
Samee Bhangu 71
?
What is the output of the project?
Output, not outcomes
Characterize the output
Public, private, mixed
Tradeable, nontradeable, partly
tradeable
Samee Bhangu 72
Financialconsiderations are often an
important consideration in selecting
projects
Three primary methods for determining
the projected financial value of projects:
Net present value (NPV) analysis
Return on investment (ROI)
Payback analysis
Samee Bhangu 73
Net present value (NPV) analysis is a
method of calculating the expected net
monetary gain or loss from a project by
discounting all expected future cash
inflows and outflows to the present
point in time
Projects with a positive NPV should be
considered if financial value is a key
criterion
The higher the NPV, the better
Samee Bhangu 74
Note
that
totals
are
Uses
equal,
Excel’s
but
npv
NPVs
function
are
not.
Samee Bhangu 75
Multiply
by the
discount
rate each
year, then
take cum.
benefits –
costs to
get NPV
Samee Bhangu 76
Determine estimated costs and benefits for
the life of the project and the products it
produces
Determine the discount rate (check with
your organization on what to use)
Calculate the NPV (see text for details)
Notes: Some organizations consider the
investment year as year 0, while others
start in year 1. Some people enter costs as
negative numbers, while others do not.
Check with your organization for their
preferences.
Samee Bhangu 77
Determine estimated costs and benefits for
the life of the project and the products it
produces
Determine the discount rate (check with
your organization on what to use)
Calculate the NPV (see text for details)
Notes: Some organizations consider the
investment year as year 0, while others
start in year 1. Some people enter costs as
negative numbers, while others do not.
Check with your organization for their
preferences.
Samee Bhangu 78
Project Sponsorship at executive
level
Good project charter
Strong project management
The right mix of team players
Good decision making structure
Good communication
Team members are working toward
common goals
Samee Bhangu 79
Failure to align project with
organizational objectives
Poor scope
Unrealistic expectations
Lack of executive sponsorship
Lack of project management
Inability to move beyond individual and
personality conflicts
Politics
Samee Bhangu 80
Microsoft Project (Microsoft Corp.)
MacProject (Claris Corp.)
PowerProject (ASTA Development Inc.)
Primavera Project Planner (Primavera)
Project Scheduler (Scitor Corp.)
Project Workbench (ABT Corp.)
Samee Bhangu 82