Professional Documents
Culture Documents
Level 1
Deanna Reynolds
Instructor
Class Outline
Creating a Project Plan File
Creating a Work Breakdown Structure
Creating and Assigning Resources
Finalizing the Project Plan
Lesson One:
Creating a Project Plan File
Create a project plan file
Create and assign a project calendar
Add tasks to the project plan file
Display a project summary task
Add a recurring task
Enter duration estimates for tasks
how and whether to make trade-offs between Time, Cost, and Quality.
management.
manager.
True or False?
Microsoft Project can:
Identify the project stakeholders.
False
True or False?
Microsoft Project can:
Create a detailed list of project tasks.
True
True or False?
Microsoft Project can:
Get the project team to sign off on the final budget for
the project.
False
True or False?
Microsoft Project can:
Generate project summary report information.
True
Field Heading
Formatting Toolbar
Project
Guide
Toolbar
Entry Bar
Timescale
Task
Pane
Divide Bar
Table
Gantt Chart
View Area
You can completely customize your Project views. Within each view, you
can choose to display various tables.
With tables, you can control the columns, or fields, that appear in the table.
The Task Entry table is the default display. Here you can see:
Task Name
Duration
Start
Finish
Predecessors
Resource Names
Timescale
Task Pane
Entry Bar
View Area
Divide Bar
Gantt Chart
Entry Table
Project will automatically schedule tasks to begin on the next available day in the
project plan unless you determine otherwise.
By setting a project calendar, you can have more control over the flow of task
completion in your project.
Using these base calendars, you can define working times for:
Add Tasks
Task Name
Duration (the estimated time between the start of a task and its finish)
Project estimates each new task at one day indicated with 1 Day? The ? Indicates the
duration is only a estimate.
You could enter up to one million tasks in Project (but, I wouldnt recommend it).
Generally, youll enter tasks in Gantt Chart View. Then, simply click in the Task Name
field and type the task name. Press enter when finished.
A project summary tasks can be used for quick project analysis, such as determining
the total duration of a project.
Schedule and cost information from subtasks are accumulated at the summary task
level.
The start date of a summary task is determined by the earliest start date of any of its
subtasks.
A project summary task is the highest level of work in a project that represents the
project goal or project objective.
All other project tasks are represented as subtasks beneath the project summary
task.
Duration field.
E = [O + P + (4 * M)]/6
The Most Optimistic Time
The Most Probable Time
The total work for a task is the sum of the work for all
its assignments.
assigned to a task.
The default percentage is 100%.
However, if a resource is going to work only half-time
Lesson Two:
Creating a Work Breakdown Structure
Promote and demote tasks
Link tasks
Identify deliverables within the project plan file by
using notes
Apply a constraint to a task
Set a task deadline
Outline Tasks
Because you may have several tasks related to one another, its a good
idea to organize them into manageable chunks.
Outlining allows you to organize the tasks in your plan into summary tasks
and subtasks.
You can use the Indent (Demote) and Outdent (Promote) buttons on the
Formatting toolbar to organize your tasks into an outline form.
Outline Tasks
Once your tasks have been promoted and demoted to your satisfaction,
you can choose how much or how little of your WBS that youd like to view
by collapsing or expanding the outline.
The duration and other details, such as costs, that are associated with
summary tasks still represent the sum of the subtasks when a group of
tasks has been collapsed.
related.
Task Relationships
Finish-to-Start (default)
Start-to-Start
Finish-to-Finish
Start-to-Finish
With these relationships, you can make tasks overlap or cause a delay
between tasks.
Lead time the overlap between dependent tasks. Lead time is entered as
a negative number.
Lag time the delay between any two dependent tasks that adds waiting
time after a task is completed. Lag time is entered as a positive number.
Identify Deliverables
You may want to add notes to record specifications,
Notes
Constrain Tasks
To control the schedule and to minimize the number of constraints you set,
use task relationships as they allow for greater project flexibility.
Page 58
Constrain Tasks
If you want Project to note the conflict, without considering it when creating the
project schedule:
Tools: Options
Schedule tab
Uncheck Task Will Always Honor Their Constraint Dates
using notes?
Apply a constraint to a task?
Set a task deadline?
Lesson Three:
Creating and Assigning Resources
Enter resources and associated costs into the project
plan file
Create a resource calendar
Assign resources to tasks
Add additional resources to a task
Resolve resource conflicts
Resources
Resources are the people, equipment and material used to complete tasks.
Once your tasks are entered, youll need to determine who will perform the work to
accomplish those tasks.
Before you can assign resources to your tasks, youll need to enter the resource
information into the Resource sheet.
Once your resources have been entered, you can change their order by sorting by
Cost, Name, ID or custom criteria you set.
Resource Calendar
Occasionally, youll have resources that dont work the hours
Assign Resources
To identify who is responsible fro completing the tasks in your project plan,
you need to assign resources to those tasks.
Additionally, Project can help in accounting for resource time and costs if
you assign resources to your tasks and the appropriate cost information is
included in the Resource Sheet.
You can assign resources whether by using the Assign Resources Dialog
Box (Assign Resources button on the Standard toolbar) or by entering the
resource information directly in the Entry table.
Using task types enables you to make one of the following three variables unchangeable in
scheduling calculations.
Duration
Work
Units
Since the duration of each task is determined by the formula Duration = Work/Assignment
Units, you can choose which piece of the equation Project calculates by setting the task
type.
Fixed Unit Default Task Type. By assigning additional resources, the tasks duration is
reduced.
Fixed Duration Changes to work or resources does not impact the tasks duration.
Fixed Work Changes to tasks duration or assigned resources does not impact the work.
By default, all tasks are marked effort-driven which means that when you assign or
remove resources, Project lengthens or shortens the duration for task based on the number
of resources assigned to it. This setting can be changed in the Task Information dialog box.
This occurs because they are either assigned to too many tasks or
because more resource units are assigned to a single task than exists
in the resource list.
resource allocation.
Leveling
Once you have identified any overallocated resources in a project plan, you will
need to determine how you want to resolve them.
Tasks are either split or delayed until the resources assigned are no longer
overloaded.
Leveling does not change resource assignments nor does it add any additional
resources.
By reviewing the slack (amount of time a task can slip before it affects another
tasks dates or the project finish date), task priority, task dependencies, task
constraints and scheduling dates, Project levels overallocated resources.
plan file?
Create a resource calendar?
Assign resources to tasks?
Add additional resources to a task?
Resolve resource conflicts?
Lesson Four:
Finalizing the Project Plan
Display the project plans critical path
Shorten the project duration
Save the project baseline
View project summary information
Tasks on the critical path are called critical tasks and they do not
the critical path, youll need to use the Gantt Chart Wizard.
Set a Baseline
The purpose of a baseline is to give you a point of comparison
You can view the project statistics, after you set the baseline
use reports.