Presentation

on
Industrial Case Study
CONSTRUCTION OF SLAB CULVERT
Submitted by
Tushar M. Tiple
(CE13017)
BE VII Semester
Under the guidance of
Mr. R. K. Parve
Assistant Professor

2016-17
DEPARTMENT OF CIVIL ENGINEERING
KAVIKULGURU INSTITUTE OF
TECHNOLOGY AND SCIENCE
1
RAMTEK- 441106

CONTENT
INTRODUCTION
DESCRIPTION OF PROJECT
WORK EXPERIENCE
OBSERVATION AND DISCUSSION
References
2

INTRODUCT
ION
INDUSTRIAL CASE STUDY
OBJECTIVE OF INDUSTRIAL CASE STUDY
DURATION
30TH MAY 2016 TO 15TH JUNE 2016

DESCRIPTION OF
PROJECT
Details of Project:
Name of the project

: Upgradation of Washi to

Girgaon
Road
Location

: Between Washi to Girgaon,


Hinganghat

Type of Structure
Name of Project Manager

: RCC Slab Culvert


: Mr. Harshal Madamwar

Name of the Site Engineer : Mr. Praphul Sabal


Cost of the Project

: Approximately 50 Lakhs

Duration

: 3 months

Ownership Details:
Name of the Department

: Swayambhu Construction Pvt. Ltd.

Address of the Department

: Yeshwant Nagar, Hinganghat-

442301
Financial Authority

: Public Work Department, Wardha

Sanction Authority

: Public Work Department, Wardha

Management Structure:
Pradhan Mantri Gram Sadak Yojana
Swayambhu Construction Pvt. Ltd.
Contractor
Project Manager
Site Engineer
Site Supervisor
6
Labours

Construction Details of Project


Drawing

PCC LAYER
SAND FILLING

ELEVATION OF CULVERT
7

8
PLAN OF CULVERT

Structural Details
Raft foundation details:
Depth
Length
Concrete grade

: 1500 mm
: 16440mm
: M15

Abutment details:
Height

: 1600mm

Width at top

: 750mm

Width at bottom

: 1330 mm

Gradient

: 1 in 5
9

Pier details:
Height

: 1600 mm

Width at top

: 750 mm

Width at bottom

: 1330mm

Gradient

: 1 in 10

Cap details
Height

: 300mm

Width

: 750 mm

10

Reinforcement
Details
Diameter of steel for Raft Foundation

: 10 mm,

12 mm,

16mm and 20mm


Diameter of steel for Abutment and Piers

: 10 mm

and 12 mm
11

Diameter of steel for Abutment and Pier cap : 10 mm

12

13

Material

Cement PPC, Birla Gold, Grade:43


Sand Fine granular sand
Aggregate -10 mm and 20 mm
Steel -10 mm,12 mm,16 mm,20 mm and 25 mm
Water-Clean
Concrete- PCC-M10
Raft foundation-M20
Pier and Abutment-M15
Cap-M30
14

Construction Tools

1.Iron Pan (Ghamela)


2.Shovel (Phawda)
3.Bar Bending Rod

15

Equipment Used

1. Needle vibrators
2. Concrete mixer
3. Excavator Machineries

16

Methodology

1.Excavation of site was done.


2.Founded soil was removed.
3.Filling of sand bedding compaction up to 900 mm was done
with 100% saturation.
4.Laying of PCC of 100 mm thick.
5.Construction of RCC Raft 350 mm thick.
6.Construction of Abutment and Pier.
7.Construction of cap
17

Human Resources
Labors No
Ladies 10

Wags Per Day


Rs 200

Men

Rs 250

13

Operato 3

Rs 500

Rs 300

Forema
n

18

WORK EXPERIENCE
Day 1 (30.05.2016)
On the first day of training, visited to office of Swayambhu
Construction Pvt. Ltd. Hinganghat. Met to the project manager and
submitted application for permission of summer training
Day 2 (31.05.2016)
On the second day, Assistant Engineer gave the permission and
explained

about the construction which was going on the site.

19

Location of Construction Site

Day 3 (01.06.2016)
On third day, excavation was going on for raft foundation work at a depth of 1.5 m.
Day 4 (02.06.2016)
Next day, filling of sand bedding and compaction up to 900 mm going on with 100 %
saturation.
Day 5 (03.06.2016)
After the sand filling over that 10 cm PCC layer was laid of M10 grade concrete.
Concrete was mix in concrete mixer and it was compacted by Rammer. With that, tie
of reinforcement was carried for further work of raft foundation.
Day 6 (04.06.2016)
Next day, the reinforcement was laid that is 12 mm diameter bars at 220 mm c/c
spacing and also 12
mm diameter bent up bars provided at a spacing of 220 mm c/c spacing. Then
concreting work is
carried out by using M20 grade concrete, concrete is mix at site only by concrete mixer.
20

Raft Foundation Reinforcement


Concrete Mixer

21

Day 7 (05.06.2016)
As the reason of Sunday, Construction was close so only curing of
constructed part was done.
Day 8 (06.06.2016) and Day 9 (07.06.2016)
On this two day the form work arrangement for pier and abutment
by metal shutters was going on with reinforcement arrangement.
Difference between pier and abutment is 5 m c/c and pier and pier is
also 5 m c/c.
Day 10 (08.06.2016) and Day 11 (09.06.2016)
After shuttering to abutment and pier concreting was going on, for
concreting M15 grade concrete was used. Concrete mixing is done in
concrete mixer. To compact the concrete tamping was done by
bamboo.

22

Concreting of Pier
Constructed Pier

23

Day 12 (10.06.2016)
Curing of the constructed part was done and checked the level at
top of the pier and at raft foundation was done by using auto
level.
Day 13 (11.06.2016)
On next day tie of reinforcement was going on for abutment and
cap as per shown in plan. For caping 10 mm diameter steel bar
are used.

24

Reinforcement of Abutment Cap

Day 14 (12.06.2016)
Next day is Sunday so construction work was closed
but curing to previous concrete work was carried out.
Day 15 (13.06.2016)
The reinforcement arrangement for the pier cap was
going on. The thickness of the pier cap was of 300
mm. also formwork also going on for pier of
reinforcement cap.

25

Cap Reinforcement on Abutment

Cap

Day 16 (14.06.2016) and Day 17


(15.06.2016)
On last two day only concreting was done
for cap of pier and abutment by using M30
grade concrete with proper compaction.

26

Project Site

OBSERVATION AND
DISCUSSION
OBSERVATION
AND
DISCUSSION

27

REFERENCES

Arora K. R.(2011), Soil Mechanics and Foundation


Engineering, Standard Publication Delhi-110006
IS 456-(2000), Code of Practice for Plain Reinforced
Concrete Bureau Of Indian Standard, New Delhi.
Sheety M. S.(2003), Concrete Technology, S.
Chand Publication, New Delhi.
Gupta B.L.(2011) and Gupta Amit(2011), Roads,
Railway, Bridges, Tunnels and Harbour-Dock
Engineering, Standard Publishers Distributors
Delhi-110006
28

THANK
YOU

THANK YOU