You are on page 1of 39

Putting Earned Value Into Action

Pete Arnold & Neal Morgan


Lewis & Fowler, LLC

Copyright 2007 , All Rights Reserved

Outline
What is Earned Value Management
Why use Earned Value Management
Prerequisites
The Formulas
Collecting Data
Analyzing Data
Taking Corrective Action

Copyright 2007 , All Rights Reserved

History of Earned Value - Timeline

http://www.acq.osd.mil/pm/historical/Timeline/EV%20Timeline.htm
Copyright 2007 , All Rights Reserved

timeline from www.acq.osd.mil website

What is Earned Value Management?

ANSI / EIA 748


spells out the
criteria for
using an
Earned Value
Management
System

Copyright 2007 , All Rights Reserved

Objective
Combines scope, cost and schedule
Measures project performance against
the original plan
Helps forecast project cost and
schedule variances using statistical
projections

Why Should We Use Earned Value


Management?

Copyright 2007 , All Rights Reserved

It Measures Progress, not Activity


Activity is routinely measured on projects
Two dimensional (Planned Value, Actual
Cost)
As long as we are spending what we
planned, we look good

Copyright 2007 , All Rights Reserved

An Activity Example
Plan is to build 5 widgets this month
Each widget is expected to take 100 hours to build
At the end of the month I am expecting to utilize 500
hours building widgets
At the end of the month, I spent 500 hours working on
widgets
Well, Ive spent 500 hrs ,
Does that mean Ive
accomplished 500 hrs
of Work?

Copyright 2007 , All Rights Reserved

Incorporating Progress

Here the 3
widgets
represents
the Earned
Value

Copyright 2007 , All Rights Reserved

Plan is 500 hours to make 5 widgets in a month


I Spent 500 hours, but only made 3 widgets
Each widget cost me 167 hours, instead of the planned
100
Im two widgets short for the month
Yikes! Im over budget ,
and behind schedule!

It is a Leading, not Lagging,


Indicator
Past performance, in Earned Value
terms, has been measured as a
successful predictor of future
performance
DoD Research on Hundreds of Projects#
Predictability at 15% Cost Expended
Stability in Cost Index (CPI) at 20% Cost Expended
Typically doesnt vary more than .10
Rarely gets better, often gets worse

Copyright 2007 , All Rights Reserved

Fleming, Q., & Koppelman, J. (2005) Earned Value Project Management.

It is Useful in Decision Making


Objective
Early identification of trends,
problems and risks
Basis for course corrections

Copyright 2007 , All Rights Reserved

10

It may be Required in Some


Instances

ANSI / EIA
748 spells
out the
Earned Value
Management
System
criteria

Copyright 2007 , All Rights Reserved

Department of Defense Projects


NASA Projects
Department of Energy Projects
US Office of Management &
Budget projects

11

What are the Prerequisites?


Full scope defined (WBS)
A Performance
Management
Baselinesm will
provide the basis
for Earned Value
Management

Sequentially scheduled project


Time phased budget baseline
Method & tool to collect and record
actual costs
Method to determine % complete
Change control process

Copyright 2007 , All Rights Reserved

12

What are the Formulas?

Copyright 2007 , All Rights Reserved

13

Definition of Basic Earned Value


Management Measures
Measure

Other Acronym

Budget at
Completion (BAC)

Well utilize
the shorter
acronyms in
this
presentation
(PV, AC, EV)

What is the total budgeted cost of


the planned work?

Planned Value (PV)

Budgeted Cost of Work


Scheduled (BCWS)

How much work should be


complete at this point in time?

Actual Cost (AC)

Actual Cost of Work


Performed (ACWP)

How much did the work cost (that


was completed)?

Physical %
Complete
Earned Value (EV)

Estimate at
Completion (EAC)

Copyright 2007 , All Rights Reserved

Questions

What percentage of the work is


complete?
Budgeted Cost of Work
Performed (BCWP)

What is the value of the work Ive


completed at this point in time?
What do we estimate as the total
job cost at this point in time?

14

Calculating Earned Value


Needed
Budget at Completion (BAC)
% Complete

Earned Value (EV) or (BCWP) = % Complete x


Budget at Completion (BAC)
If my budget is $50,000
And Im 50% complete
Ive earned $25,000 in value

Copyright 2007 , All Rights Reserved

15

Indices & Variances


Cost Performance Index (CPI) = EV / AC
Generally
speaking, the
higher the value
of a variance or
index number,
the better off
you are

>1.0 is under budget


<1.0 is over budget

Schedule Performance Index (SPI) = EV / PV


>1.0 is ahead of schedule
<1.0 is behind schedule

Cost Variance (CV) = EV AC


> 0 is under budget
< 0 is over budget

Schedule Variance (SV) = EV PV


> 0 is ahead of schedule
< 0 is behind schedule

Copyright 2007 , All Rights Reserved

16

Estimate At Completion

ETC =
Estimate to
Completion
iEAC =
Independent
Estimate at
Completion

Copyright 2007 , All Rights Reserved

EAC is an update to the BAC


EAC is the new estimate of what the project
will cost when complete
EAC = AC + ETC
iEAC = AC + [(BAC EV) / CPI]
Other Performance Factors
Worst Case: CPI x SPI
SPI
(.8xCPI)x(.2XSPI)

17

Summary of Major Formulas

Copyright 2007 , All Rights Reserved

EV = % Comp x BAC
CPI = EV / AC
SPI = EV / PV
CV = EV - AC
SV = EV - PV
EAC = AC + ETC
iEAC = AC + [(BAC EV) / CPI]

18

How to Determine % Complete


Fixed Formula
Applies a % complete to the start and finish
of an activity.
0/100 or 50/50 or 25/75

Apportioned Milestones
Assigns a % complete for a portion of a
task with observable results

Subjective % Complete
Team members determines % complete
based on experience, etc.

Copyright 2007 , All Rights Reserved

Pros and Cons of Each % Complete


Method

Copyright 2007 , All Rights Reserved

Method

Pros

Cons

Fixed Formula

Good for short term


tasks
Very clean
Observable criteria

Not as effective on
longer tasks
Could see lag in
crediting value

Apportioned
Milestones

Works well for long


term tasks
Observable criteria

More complex
Requires detailed
tracking of tasks
Not worth the effort
for shorter tasks

Subjective %
Complete

Very easy
Very quick

Subjective measure
Unreliable
Lacks accuracy

20

Building A Deck: Collecting Data, Analyzing Data


& Taking Corrective Action

Copyright 2007 , All Rights Reserved

21

New Deck project

Copyright 2007 , All Rights Reserved

Having a BBQ in 7 days


Need a new deck built for the BBQ
Hired a contractor for $25/Hr
There are 6 days to complete the
project

22

Contractors Plan
Day 1
Contractor will
work 8 hours a
day and plans to
finish in 5 days.
No additional
resources
needed.
All materials
provided.

Concrete patio removed 4 hrs


Post holes dug 4 hrs

Day 2
Posts cemented in ground 4 hrs
Joists measured and cut 4 hrs

Day 3
Joists hung 4 hrs
Floor boards measured and cut 4 hrs

Day 4
Floor boards secured 4 hrs
Deck floor sanded 4 hrs

Day 5
1st coat of stain applied 4 hrs
2nd coat of stain applied 4 hrs

Day 6
No work planned (Float)
Copyright 2007 , All Rights Reserved

23

The Project in Earned Value Terms


Budget at Completion (BAC) = 40 hours at
$25/hr or $1000
Planned Value (PV) = 8 hrs x $25 or $200 per
day
Work is all discrete tasks
Taking progress well use 0/100%
Incomplete tasks worth 0%
Completed tasks worth 100%

Copyright 2007 , All Rights Reserved

24

Contractors Plan For Day 1


Plan for Day 1
Concrete patio removed 4 hrs
Post holes dug 4 hrs

Planned Value for Day 1 = $200 (8 x


$25/hr)

Copyright 2007 , All Rights Reserved

25

Contractors Results After Day 1


Actual results from Day 1
Planned Value = $200
Actual Cost = $200

Copyright 2007 , All Rights Reserved

Concrete patio removed 7 hours


Started post holes 1 hour

Day 1 is done 20% complete!


8 hours of work planned
8 hours of work complete
Im on schedule

26

Earned Value After Day 1

Instead of
being 20%
complete, Im
only 10%
complete
(% Complete = EV /
BAC)

Copyright 2007 , All Rights Reserved

Contractors Plan For Day 2


Plan for Day 2
Finish digging post holes spillover
Posts cemented into ground 4 hrs
Joists measured and cut 4 hrs

Planned Value for Day 2 = $200 (8 x


$25/hr)

Copyright 2007 , All Rights Reserved

28

Contractors Results After Day 2


Actual results from Day 2
Planned Value = $400
Actual Cost = $475

Finish digging post holes 4 hours (addl)


Posts cemented into ground 6 hours
Joists measured and cut 1 hour

Day 2 is done worked extra hours


8 hours of work planned
11 hours of work complete
Im ahead schedule

Copyright 2007 , All Rights Reserved

29

Earned Value After 2 Days

I should be
40%
complete,
but Im only
30%
complete
(% Complete =
EV / BAC)

Copyright 2007 , All Rights Reserved

After 2 Days, What is My EAC?


Traditional Method (AC + ETC)
BAC EV
represents the
Planned Value
of the
remaining
work

$475 + $600 = $1075

iEAC (AC + [(BAC EV) / CPI]


$475 + [($1000 - $300) / .63] = $1586

At the current rate of performance, this


will cost me $586 more than planned

Copyright 2007 , All Rights Reserved

31

Earned Value Chart for Deck Build

Were
projecting to be
well over
budget and
somewhat
behind
schedule after 5
days

Copyright 2007 , All Rights Reserved

CV

SV

32

CPI & SPI Trending for Deck Project

Project
performance is
improving over
the two days,
but well below
1.00

Copyright 2007 , All Rights Reserved

33

What Do We Know About Our


Project?

Copyright 2007 , All Rights Reserved

34

How to Address Schedule & Cost


Issues

Copyright 2007 , All Rights Reserved

Schedule

Cost

Fast track the schedule


concurrent tasks, eliminate float

Use overtime if unpaid

Crash the schedule: more people,


more hours, unpaid OT

Find cheaper resources (will it take


them longer?)

Use up contingency (time


contingency)

Use up contingency (cost


contingency)

Change the scope

Change the scope

Change the quality (e.g. reduce


testing)

Change the quality (e.g. less


documentation)

Request new dates from


stakeholders

Use less costly facilities, equipment

Obtain better resources (can they


do the work faster)

Can better resources get the job


done for less total money?

Employ technical innovations which


could speed up the process

Employ technical innovations that


are more cost effective

Make sure you are not gold plating Make sure you are not gold plating
instead of just meeting
instead of just meeting
35
requirements
requirements

How We Fixed Our Deck Project


Schedule

Cost

Hired a 2nd, cheaper worked to


crash the schedule

Cheaper resource brought total


cost down

Worked on 6th day (using up


contingency)

Extra day of work increased


cost

Eliminated 2nd coat of stain


reducing overall scope

Helped bring down cost as well

Used sprayer for 1st coat of


Reduce overall cost because it
stain instead of brush (technical took less time to stain
innovation)
Still over on cost, we borrowed
money from the BBQ project
to pay for the overrun

Copyright 2007 , All Rights Reserved

36

Finished Deck, Successful BBQ!

Copyright 2007 , All Rights Reserved

37

In Summary
Earned Value Management helps PMs identify
problems early and take corrective action
A Performance Management Baselinesm is
needed to do Earned Value Management

Full scope
Sequentially scheduled with time phased budget
Collection of actual costs
Determine % complete

Earned Value Management wont SOLVE


project issues you have do that based on the
information
YOU can start using Earned Value
Management today
Copyright 2007 , All Rights Reserved

38

Lewis & Fowler, LLC


Pete Arnold
parnold@lewisandfowler.com
303-478-4253
Neal Morgan
nmorgan@lewisandfowler.com
303-618-9980

Copyright 2007 , All Rights Reserved

39

You might also like