Department of Technical Education

Andhra Pradesh
Name :V.Siva Rama Prasad
Designation : Lecturer
Branch : Civil Engineering
Institute : S.S Government Polytechnic,
Zaheerabad
Year/semester : IVsemester
Subject : Construction Practice
Subject Code : C406
Topic : Roofs and Floorings.
Duration : 50 min
Sub -Topic : Floorings
Teaching Aids : PPT, Animations
Revised by : GVVL Satyanarayana
9C406.34 1
Objectives

Upon completion of this period, you will be able to

• Know construction of cement concrete floorings.

9C406.34 2
Recap

In the previous period, we discussed

• Flooring

• Different parts of flooring

• Requirement of a good floor

9C406.34 3
Discussion on floorings

• Where will be a flooring provided ?

• Can you name some types of flooring ?

• What type of floor you have at your home?

• Can you name the type flooring in our class room?

• Guess how many layers does of a floor have?

• Do you know the steps involved in its construction?

9C406.34 4
Various materials used for flooring

• Asphalt
• Brick
• Cement concrete
• Cement plaster
• Cork
• Granolithic
• Glass

9C406.34 5
Various materials used for flooring

• Linoleum

• Marble

• Moorum

• Mosaic

• Mud

• Plastic or P.V.C
9C406.34 6
Various materials used for flooring

• Stone

• Terrazzo

• Tile

• Timber

• Vitrified Tiles, etc..

9C406.34 7
Steps in Construction of a floor

Construction of any type of flooring consists

• Preparation of floor base


• Construction of floor covering

9C406.34 8
Cement Concrete Flooring

It is most commonly used in


• Residential
• Commercial and
• Industrial buildings

9C406.34 9
CEMENT CONCERTE

LEAN CONCRETE

RAMMED EARTH

CEMENT CONCRETE FLOORING

Fig. (1) 9C406.34 10


Components of CC flooring

• CC floor consists of two components

BASE CONCRETE TOPPING

9C406.34 11
Preparation of sub base

• Granular inert material like sand ,gravel or quarry dust is

filled in the plinth in layers not more than 150mm

• The layers are well compacted and watered

• Lean concrete mix (1:3:6 or 1:4:8) of thick ness 100 to

150mmis laid above the sub grade.

9C406.34 12
Preparation of sub base

• The concrete bed is thoroughly compacted by hand

rammers

• It should be kept wet for 2-3 days

9C406.34 13
Laying of CC floor

• The whole surface is divided into small square or


rectangular panels of side not more than 1.5m

• On the edges of these panels aluniminium strips are


placed with the help of mortar screeds

• Before laying topping, the sub base shall be wetted


thoroughly and cleaned

9C406.34 14
Laying of CC floor

• Proper slope shall be maintained before


concreting is started
• Alternate panels (diagonally opposite) are laid
first
• Remaining panels are laid in succession
• Thickness of Concrete will be 20 to 40 mm

9C406.34 15
Laying of CC floor contd..

• While laying in panels concrete is spread with straight


edge and consolidated with wooden floats
• Finished with steel trowels
• The surface is cured for a period of 7 to 14 days

9C406.34 16
Advantages of CC flooring

• Durable
• Non-absorbent
• Smooth
• Economical
• Easy to construct
• Good appearance
• Easy to maintain and clean

9C406.34 17
Disadvantages of CC flooring

• Any modifications are difficult after construction


• Not suitable for repair for patch work

9C406.34 18
Summary

In this period, you have learnt

• Construction of cement concrete Flooring

9C406.34 19
Quiz

1. Number of components in a floor are

a. One
b. two
c. three
d. four

9C406.34 20
2. In cement concrete floor the wearing surface
is made of

a. Flag stone
b. Marble
c. Cement plaster
d. Cement concrete

9C406.34 21
3. Cement concrete flooring is used in buildings of

a. Residential

b. Commercial

c. Industrial

d. All the above

9C406.34 22
Frequently asked questions

1) Describe the method of constructing cement concrete


flooring

9C406.34 23