Dr. K.

Srinivasan
SCE
VIT - Vellore
Door D - 1.2 X 2.1
Window W - 1.2 X 1.2
Length of long wall is = 13.3 m
Length of Short wall = 5.3 m.
Item Description No Length Width Depth Qty Total Remarks
No. . (m) (m) (m) Qty.
1

5
Earth work excavation :-

1. Earth work 2 13.3 1.0 0.9 23.94


Excavation:-
Long Wall
Short Wall 2 5.3 1.0 0.9 9.54 33.48 m3
Sand filling below foundation :-
2. Sand filling :- 2 13.3 1.0 0.15 3.99
Long Wall

Short Wall 2 5.3 1.0 0.15 1.59 5.58 m3


P.C.C layer with mix 1:4:8 below foundation :-
3. P.C.C layer:- 2 13.3 1.0 0.15 3.99
Long Wall

Short Wall 2 5.3 1.0 0.15 1.59 5.58 m3


Brick work in First footing :-
4. Long Wall 2 13.1 0.8 0.3 6.29

Short Wall 2 5.5 0.8 0.3 2.64 8.93 m3


Brick work in Second footing:-

4. Long Wall 2 12.9 0.6 0.3 4.644

Short Wall 2 5.7 0.6 0.3 2.05 6.696 m3


Brick work in Basement:-

5. Long Wall 2 12.8 0.5 0.45 5.76

Short Wall 2 5.8 0.5 0.45 2.61 8.37 m3


D.P.C layer with CM 1:1 over Basement – 50 mm thick:-
6. Long Wall 2 12.8 0.5 - 12.8

Short Wall 2 5.8 0.5 - 5.8 18.6 m2


Basement filling with river sand:-
The length in longer direction - 11.8 m.
Width length in shorter direction = 5.8 m and Depth = 0.3 m.

7. Basement filling with 1 11.8 5.8 0.3 20.53 20.53 m3


sand
Flooring Concrete with P.C.C mix 1:4:8 :-
The length in longer direction - 11.8 m.
Width length in shorter direction = 5.8 m and Depth = 0.15 m.

8. Flooring Concrete with 1 11.8 5.8 0.15 10.27 10.27 m3


Mix 1:4:8
Floor finishing with CM 1:3 :-
The length in longer direction - 12.0 m.
Width length in shorter direction = 6.0 m and Depth = 50 mm.

9. Floor finishing with 1 12.0 6.0 - 72 72 m2


CM 1:3
Brick work in super structure with CM 1:5

10. Long Wall 2 12.6 0.3 3.0 22.68


Short Wall 2 6 0.3 3.0 10.8
Parapet wall Long 2 12.6 0.3 1.0 7.56
wall
Short wall 2 6 0.3 1.0 3.6 44.64 m3

Deductions in Brick
work with CM 1:5
Lintel 1 37.2 0.3 0.15 1.674

Door 1 1.2 0.3 2.1 0.756


Window 5 1.2 0.3 1.2 2.16 4.59 m3
Total Brick work in Super structure and Parapet wall 40.05 m3
R.C.C WITH MIX 1:2:4 - Lintel, sunshade and Roof Slab

11. Lintel – Long Wall 2 12.6 0.3 0.15 1.134 m3

Lintel – Short Wall 2 6 0.3 0.15 0.54 m3


R.C.C LINTEL CUM 6 1.5 0.45 0.125 0.506 m3
SUNSHADE WITH MIX
1:2:4 - SUNSHADE
R.C.C ROOF SLAB WITH 1 12.6 6.6 0.15 12.47 m3 14.65 m3
MIX 1:2:4
12. Inner Plastering work 1 12.0 - 6.0 72.0 m2
with CM 1:3 – 12mm
thick - Ceiling
Plastering
Sunshade plastering 6x 1.5 0.45 - 8.1 m2 80.1 m2
work with CM 1:3 – 12 2
mm thick

13. Inner wall plastering 2 12 - 3.0 72.0 m2


with CM 1:4 – 12 mm
thick Long wall
Inner wall plastering 2 6 - 3.0 36.0 m2
with CM 1:4 – 12 mm
thick Short wall

Outer Plastering work 2 12.6 - 5.025 126.63 m2


with CM 1:4 – 12 mm
thick Long wall
Outer Plastering work 2 6.6 - 5.025 66.33 m2 300.96 m2
with CM 1:4 – 12 mm
thick Short wall
13. Inner wall plastering 108.0 m2
with CM 1:4 – 12 mm
thick
Outer Plastering work 192.96 m2 300.96 m2
with CM 1:4 – 12 mm
thick
Deductions in 1 1.2 - 2.1 2.52 m2
plastering work with
CM 1:4 - Door
Deductions in 5 1.2 - 1.2 7.2 m2 9.72 m2
plastering work with
CM 1:4 - Window
Total Plastering work with CM 1:4, After deductions 291.24 m2
14. Weather proof coarse 1 12.2 - 6.2 75.64 m2 75.64 m2
over roof slab with lime
and brick jelly coarse
finished with tiles
15. White and colour Qty. taken from Item no. 12 and 13 371.34 m2
washing
ABSTRACT ESTIMATE

Sl. Item Qty. Unit Rate Per Cost


No.
1 Earth work in foundation 33.48 m3 m3
2 Sand filling below footing with river sand 0.558 m3 m3
3 P.C.C layer with 1:4:8, below footing 0.558 m3 m3
4 Brick work in I & II footing with CM 1:4 15.62 m3 m3
5 Brick work in Basement wit CM 1:4 8.37 m3 m3