Professional Documents
Culture Documents
Page 57 of 78
Washington Metropolitan Area Transit Authority Board Action/Information Summary Action Information MEAD Number: Resolution: 103186 Yes No
TITLE Rail Service Adjustments for State of Good Repair PRESENTATION SUMMARY To rebuild the system to a steady state of good repair, Metro continues the aggressive work program it launched in 2011. The outstanding amount of infrastructure and system work cannot be achieved without scheduled service interruptions that span from single tracking on days, nights and weekends to total weekend shutdowns.
PURPOSE To update the Board on the upcoming 2013 service adjustments required to support achieving a state of good repair. DESCRIPTION Key Highlights: Metro has undertaken an aggressive rebuilding program that expends capital funds to ensure a safer system and provide: Improved service reliability Rehabilitated track system infrastructure Smoother ride quality Continued completion of National Transportation Safety Board (NTSB) recommendations BACKGROUND AND HISTORY In 2011, Metro moved forward to rebuild the regions transit system investing $5 billion over the next six years to produce a better service for customers, made possible through funding support from the District of Columbia, Maryland, Virginia and the Federal government. The $5 billion investment covers over a 100 projects including: New generation of rail cars to replace the oldest cars Replacement of 60 miles of rail over the next six years
Page 58 of 78
This major investment is already showing results in the form of improved reliability on Metrorail and improved safety. Last May Metro completed the installation of the Guarded No. 8 switches throughout the system, one of the NTSB recommendations.
DISCUSSION The Fiscal 2013 Capital Budget continues to accelerate efforts to rebuild Metro, with nearly a billion dollars ($997M) in investment. Over the next three months Metro has scheduled 43 single tracking/11 shutdowns to accomplish: Rehabilitation of station platforms Rehabilitation of 3rd rail Repair/replacement of insulators, fasteners, ties and turnouts Operational testing for the Silver Line Installation of Neutral Host cable Replacement of track circuits Rail welding Replacement of track Replacement of #10 turnouts Repair of tunnel leaks Radio remediation Greenbelt test track
A chronological listing of upcoming single tracking outages and shutdowns is provided in the attached Appendix. Outages have been planned to complete the project work in the shortest time while minimizing customer impact. This is accomplished by multiple projects working in parallel during outages. Further review of required maintenance and infrastructure work is ongoing to assess the need for additional outages. There are no planned shutdowns during: Martin Luther King/Presidential Inauguration Cherry Blossoms 4th of July Thanksgiving Christmas Metro has conducted a proactive and aggressive customer outreach campaign to ensure that as part of the Metro Forward Campaign the public is aware of upcoming work and closures through: Electronic display screens at kiosk in every station Station banners, signs, murals, take ones Station announcements Social media messages, videos Web site postings Metro alerts/customers advisories
Page 59 of 78
Call Center (on-hold) recordings Added personnel on-site Community briefings, outreach Outreach to local Departments of Transportation News media advisories Newspapers, radio advertisements
ALTERNATIVES None FUNDING IMPACT All projects are funded in the FY13 approved Capital budget. MEAD AMOUNT $0 TIMELINE Previous Actions Anticipated Actions After Presentation Provided the Board an update July 2012 The Board and public will continue to be informed regarding upcoming work through the Metro Forward Campaign and Customer Outreach.
Page 60 of 78
Page 61 of 78
Page 62 of 78
No planned shutdowns during Martin Luther King/Presidential Inauguration weekend No planned shutdowns during Cherry Blossoms, 4th of July, y , y, Thanksgiving and Christmas Veterans Day and other holiday weekend shutdowns being evaluated
Page 63 of 78
Page 64 of 78
APPENDIX
Page 65 of 78
Finish
January12,2013
Line
Red
Type
3rd Rail
Location
Friendship Heights MedicalCenter
January10,2013
January17,2013
Blue
Station Dome
January10,2013
January28,2013
Green
FenceInstallation
January 10,2013
January 12,2013
Red
PlatformRehab
RhodeIslandAve Takoma
January11,2013
January14,2013
Green
FenceInstallation
January11,2013
January 14,2013
Red
RhodeIslandAve FortTotten
y , January11,2013
January 14,2013 y ,
Red
Finish
January 24,2013
Line
Red
Type
3rd Rail
Location
Friendship Heights MedicalCenter
January14,2013
January17,2013
Red
NeutralHost
FarragutNorth JudiciarySquare
January19,2013
January22,2013
NoSingleTracking MartinLuther King/PresidentialInauguration Blue Turnouts DTPOperational Testing PlatformRehab/ FastenerRenewal FenceInstallation StadiumArmory Morgan Blvd
January22,2013
January31,2013
January25,2013
January28, 2013
Orange
EastFallsChurch WestFallsChurch
January25,2013
January28,2013
Orange
January25,2013
January28,2013
Green
Finish
February 07,2013
Line
Red
Type
PlatformRehab
Location
RhodeIslandAve Takoma
January28,2013
February 02,2013
Red
FastenerRenewal
VanNess FriendshipHeights
February1,2013
February4,2013
Green
TestTrackProject
February1,2013
February4,2013
Red
February1,2013
February4,2013
Orange
February4,2013
February7,2013
Orange
February4,2013
February7,2013
Red
JointElimination
Finish
February14,2014
Line
Blue Green/ Yellow Orange
Type
Turnout CamerasandCeiling TileInstallation JointElimination/Rail &FastenerRenewal PlatformRehab/ / FastenerRenewal TestTrackProject
Location
StadiumArmory MorganBlvd
February 6,2014
February212014
February 8,2013
February11, 2013
Ballston WestFallsChurch
February11, 2013 F b 11
Orange O
February 8,2013
February11, 2013
Green
February 8,2013
February11, 2013
Red
PlatformRehab
Twinbrook ShadyGrove
February 8,2013
February11, 2013
Red
PlatformRehab
RhodeIslandAve Takoma
Finish
February 14,2013
Line
Red
Type
FastenerRenewal
Location
VanNess FriendshipHeights
February11,2013
February28,2013
Red
PlatformRehab
RhodeIslandAve Takoma
February 15,2013
February19, 2013
Red
PlatformRehab
RhodeIslandAve Takoma
February19,2013
February21,2013
Platform Rehab
Twinbrook ShadyGrove
February19,2013
February22,2013
DomeRehab
EasternMarket toStadiumArmory
February19,2013
March28,2013
3rd Rail
NationalAirport BraddockRoad
y , February22,2013
February25,2013 y ,
PlatformRehab
RhodeIslandAve Takoma
Finish
February25,2013
Line
Orange
Type
PlatformRehab/ FastenerRenewal TestTrackProject
Location
Stadium Armory Cheverly
February22,2013
February25,2013
Green
February22,2013
February25,2013
Red
RailRenewal DTPOperational DTP Operational Testing DomeRehab CamerasandCeiling TileInstallation PlatformRehab/ FastenerRenewal F t R l
February 25,2013
February 28.2013
February 25,2013
March 1,2013
EasternMarket toStadiumArmory
February 25,2013
March 14,2013
, March 1,2013
March4,2013 ,
Finish
March11,2013
Line
Orange
Type
PlatformRehab/ FastenerRenewal PlatformRehab/ FastenerRenewal Fastener Renewal
Location
Stadium Armory Cheverly
March 15,2013
March18,2013
Orange
Total Shutdowns
Start
January11,2013
Finish
January14,2013
Line
Blue
Location
Rosslyn Pentagon
January19,2013
January22,2013
NoShutdown MartinLutherKing/PresidentialInauguration Red DupontCircle RhodeIslandAvenue p Federal CenterSW Cheverly&Benning Road StadiumArmory Cheverly &LargoTown y y g Center CollegePark Greenbelt
y , January25,2013
January28,2013 y ,
February01,2013
February04,2013
Blue/Orange
February15,2013 F b 15 2013
February19,2013 F b 19 2013
Blue/Orange Bl / O
February15,2013
February19,2013
Green
Total Shutdowns
Start
February 22,2013
Finish
February25,2013
Line
Orange
Location
Ballston Vienna
March01,2013
March04,2013
Blue/Yellow
, March01,2013
March04,2013 ,
Red
March08,2013
March11, 2013
Blue/Orange
March15, M h 15 2013
March18, M h 18 2013
Red R d
March15, 2013
March18, 2013
Green
March22,2013
March25,2013
Total Shutdowns
Start
March29,2013
Finish
April1,2013
Line
Location
No Shutdown CherryBlossoms y No Shutdown CherryBlossoms No Shutdown CherryBlossoms Ch Bl
April5,2013
April8,2013
p , April 12,2013
April15,2013 p ,
April19,2013
April22,2013
Orange
Rosslyn VirginiaSquare
Red R d
NoMaGallaudetU Takoma N M G ll d t U T k
May3,2013
May6,2013
Green
CongressHeights BranchAvenue
May10,2013
May13,2013
Orange
Ballston Vienna
Total Shutdowns
Start
May17,2013
Finish
May20,2013
Line
Green
Location
CollegePark Greenbelt
May17, 2013
May20, 2013
Orange
Clarendon EastFallsChurch
y , May24,2013
May 28,2013 y ,
Orange g
EastFallsChurch Vienna
May24,2013
May28, 2013
Red
Twinbrook ShadyGrove
June3,2013 J 3 2013
Red R d
MetroCenter W dl P k Z M t C t WoodleyParkZoo
June7,2013
June10,2013
Green/Yellow
ShawHowardU GeorgiaAve
June14,2013
June17,2013
Red
Takoma ForestGlen
Total Shutdowns
Start
June21, 2013
Finish
June24,2013
Line
Red
Location
Takoma ForestGlen
June28,2013
July 1,2013
Green
y , July3,2013
July5,2013 y ,