Background:
Provide new facility housing the Police Department Headquarters; Fire De-
partment Headquarters, City Emergency Communications Center (911); City
Emergency Operations Center; Traffic Signal System Operations, Data Center
Information Technology Consolidation; Building Maintenance Administration
for Avery C. Upchurch Complex, Large Assembly Hall for staff and Com-
munity use; and a Public Gallery & Café. Project is being designed to attain
LEED Gold certification.
Cost:
Estimated cost of this projects is $226,070,000.00
Construction Management
2
City of Raleigh
Economic Stimulus Projects
Background:
The Wilders Grove Solid Waste Service Center Facility is one of the initial
service facility elements targeted for development and is currently under de-
sign. The Wilders Grove Solid Waste Service Center Facility is approximately
20,000 SF in size and will accommodate over 240 Solid Waste staff and op-
erations personnel at the new site. The new facility will encompass approxi-
mately 14 acres when completed and will provide 300 parking spaces for em-
ployees and the public. The facility will provide for new solid waste vehicle
wash and fuel facilities and parking for solid waste vehicle fleet of over 150
vehicles. The facility shall be designed to attain LEED Silver certifications.
Cost:
Estimated cost of this projects is $18,000,000.00
Construction Management
3
City of Raleigh
Economic Stimulus Projects
Background:
Upfit existing building for Building maintenance operations center serving
Downtown General Government office and operations buildings and Central
Area Parks and Recreation Facilities. Facility renovation shall be designed to
attain LEED Certification.
Cost:
Total estimated cost of this project is $ 2,350,000. This includes $1,600,000
for land purchase and $750,000 for renovations and upfit.
Construction Management
4
City of Raleigh
Economic Stimulus Projects
Background:
The remote operations network operation network planed for this site will
include new facilities for Street Maintenance, Vehicle Fleet Services, Traffic
Engineering, Parks and Recreation and Building Maintenance. The program
needs are projected at over 215,000 SF of building and shops and 233,000
SF of storage. Over 160 employees will eventually be located at the site with
parking and with over 360 City vehicles being assigned to the site. Total site
requirements are projected to be approximately 30 acres. Facility construction
shall be designed to attain LEED Silver certification.
Cost:
Total estimated cost of this project including design and construction is
$80,000,000.00.
Construction Management
5
City of Raleigh
Economic Stimulus Projects
Background:
New facilities are planned for 4 nodes of the City, located in high growth
areas. The networks have been identified as the Downtown Remote Opera-
tions Facility Site, the Wilders Grove Remote Operations Facility Site, the Mt.
Herman Remote Operations Facility, and the North East Remote Operations
Facility Site: The vehicle fleet network is to include planning, design, engi-
neering and other services to provide for an integrated City wide vehicle fleet
management system at all Remote Operations Facilities. The facilities, equip-
ment, functional areas and operational standards are desired to be of uniform
design for all sites to allow for uniformity and management efficiency across
the entire City network. Facility construction shall be designed to attain
LEED Silver certification.
Cost:
Total estimated cost of this project including design and construction is
$75,000,000.
Construction Management
6
City of Raleigh
Economic Stimulus Projects
Background:
Provide upfit of purchased facility for Downtown Police Field Operations
center and relocate Criminal Evidence Storage to enable demolition for the
Clarence E Lightner facility construction.
Cost:
Total estimated cost of this project including design and construction is
$3,500,000.
Construction Management
7
City of Raleigh
Economic Stimulus Projects
Background:
Provide renovation and upfit of purchased facility for Police Head Quarters
and Detectives Operations center to enable demolition for the Clarence E
Lightner facility construction.
Cost:
Total estimated cost of this project including design and construction is
$2,500,000.00.
Construction Management
8
City of Raleigh
Economic Stimulus Projects
Background:
WCSBC, the premiere athletic facility for the City of Raleigh, is programmed five
nights per week starting in March through mid November and accommodates 36
(+/-) tournaments per year. Current fencing is damaged to the point where replace-
ment is required. This includes bowing, curled edges, peeling coating and lack of
structural integrity. Installed in the early 1990's combined with the amount of use at
these facilities has reached the end of it's life-cycle.
Cost:
Total estimated cost of this project including design and construction is
$600,000.00.
Parks and Recreation
9
City of Raleigh
Economic Stimulus Projects
Background:
The Parks Division completes an annual inspection of approximately 1/5 of
its wooden structures (i.e bridges, boardwalks, etc.) by a structural engineer-
ing firm. Routine inspections are also completed 3x/year by in-house staff.
The result of these inspections will determine what structures require major
repair or modification or have reached the point where they need to be re-
placed due to structural failure.
Repair and replacement of bridges and/or other structures as determined by
Structural Engineer. The function of the assessment is to identify the current
structural integrity and identify needed repairs. In some instances wholesale
replacement is required to insure users are not at risk in using. Structures are
used to provide access across bodies of water to connect trail segments con-
structed at individual park facilities. Current requiring replacement include:
Lions Park #391
Fallon Park #394 & #395
Durant Nature Park #303
Millbrook Exchange #302
Eastgate #313 & #314
Cost:
Total estimated cost of this project including design and construction is
$260,000.00.
Parks and Recreation
10
City of Raleigh
Economic Stimulus Projects
Background:
Various structures at community Parks require upgrading and improvements.
Many of these projects have been deferred due to budget limitations. This
includes upgrading the picnic shelters at Chavis, Jaycee, Roberts, and Ki-
wanis parks and upgrading comfort stations (restrooms) at Jaycee, Roberts,
and Shelley Lake. In addition, Sgt. Courtney T. Johnson Community Center
is in need of renovations. And the Martin Luther King, Jr. Gardens requires
renovations and expansion. Also, the synthetic turf athletic field requires im-
provements as well.
Cost:
Total estimated cost of all the listed projects is $3,975,000.
Picnic shelter improvements - $500,000
Comfort Stations Improvements - $600,000
Sgt. Courtney T. Johnson Community Center Renovations -
$900,000
Martin Luther King, Jr. Gardens Expansion/Renovations - $625,000
Synthetic Turf Athletic Field - $1,350,000
Parks and Recreation
11
City of Raleigh
Economic Stimulus Projects
Background:
The City of Raleigh has completed the design for this section of the Neuse
River Trail. The City does not adequate funding to complete the entire 26
mile section of non-vehicular greenway from Falls Lake Dam to the Wake/
Johnston County line.:
The project includes paving a 10’ wide non-vehicular trail and replacing a
number of foot bridges to current standards to meet the current requirements.
There are insufficient funds available to complete the Neuse River Greenway
Trail. The Upper Neuse Project is ready to bid and start construction within
6 months and is scheduled to be completed within 14 months of the start.
Cost:
Total estimated cost of this project is $5,800,000.
Parks and Recreation
12
City of Raleigh
Economic Stimulus Projects
Background:
The City of Raleigh currently has a contract with Dewberry & Davis, Inc for
engineering services related to bridge removal and replacement. Construction
plans are nearly 100 complete. The following is a list of the project scope for
each segment of greenway:
Ironwood Trail – Trail relocation, bridge removal, new 500 lf of asphalt
Rocky Branch Trail – Bridge removal, new 65 lf of asphalt
Little Rock – New 10’ x 37’ pedestrian bridge
Lake Park – Bridge removal, 110 lf of new gravel path, new 10’ x 28’
pedestrian bridge
These projects are currently unfunded and the design is nearly complete.
These segments of greenway are in need of repair as the existing bridges are
older wooden bridges and jeopardized by stream bank erosion.
Cost:
Total estimated cost of this project is $330,000.00.
Parks and Recreation
13
City of Raleigh
Economic Stimulus Projects
Background:
Several greenway trails are in need of repaving. Lake Lynn Trail is approxi-
mately 2.2 miles in length and critically needs to be repaved.
The scope of the work includes removing the existing asphalt surfacing, re-
placing/repairing a number of storm drainage structures and repaving the en-
tire trail.
The City has insufficient funds to complete this work in the coming fiscal
year.
Cost:
Total estimated cost of this project is $500,000.00.
Parks and Recreation
14
City of Raleigh
Economic Stimulus Projects
Background:
The City of Raleigh has funding for the design of the Neuse River Trail ex-
tending from Falls of Neuse Road at Falls of Neuse Dam south to the Wake
Johnston County Line. This trail length is 28 miles long. Most of this trail
will require approximately 2 years to complete engineering drawings and se-
cure needed permits. The section from Skycrest Drive south to Anderson
Point Park is 4.2 miles in length and will be ready for construction within
one year .
The project includes paving a 10’ wide non-vehicular trail and replacing a
number of foot bridges to current standards to meet the current requirements.
The design for this project is funded but the construction is unfunded. Plans
and permits can be completed within one year so that construction can begin.
Cost:
Total estimated cost of this project is $2,810,000.00.
Parks and Recreation
15
City of Raleigh
Economic Stimulus Projects
Background:
The Neuse River Wastewater Treatment Plant (NRWWTP) is a regional
plant that treats wastewater from Raleigh, Garner, Knightdale, Wendell,
Rolesville, and parts of Wake Forest, North Carolina with a current treatment
capacity of 60 MGD. An NPDES permit has been issued to expand the
treatment capacity to 75 MGD. The 15 MGD expansion project is currently
under design.
The design plans for the electrical improvements are 98 complete. Design is
scheduled to be complete in January 2009. Design costs have already been
encumbered.
Cost:
The estimated construction cost is $7,100,000. Funds are not currently avail-
able for the construction costs.
Public Utilities
16
City of Raleigh
Economic Stimulus Projects
Background:
The East Neuse Parallel Sewer Interceptor project includes installation of ap-
proximately 12,200 LF of 48” sanitary sewer main on the east side of the
Neuse River from south of Buffaloe Road up to the Harris Creek Interceptor
that provides sewer service for the Town of Rolesville. The sewer interceptor
will provide gravity sewer service to the east side of the Neuse River and help
accommodate projected growth in the Rolesville and east Raleigh service ar-
eas. The interceptor will also provide relief to the existing sewer interceptor
main on the west side of the river, and accommodate abandonment of a pri-
vate packaged wastewater treatment plant that serves a mobile home park.
The project is completely designed, and all easements have been obtained.
All environmental permits and approvals have been obtained including the
FONSI. The project is ready for bidding.
Cost:
The estimated construction cost is $8,000,000. Funds are not currently avail-
able for construction.
Public Utilities
17
City of Raleigh
Economic Stimulus Projects
Background:
Widening and realignment of existing Falls of Neuse Road to a multi-lane
section with sidewalks and streetlights between Raven Ridge Road to existing
New Falls of Neuse Road, including a new bridge crossing of the Neuse
River.
Cost:
Estimated Additional Funding Needed: $4.0 million (assuming current design
proposal presented to Council at 12/2/08 Public Hearing)
Public Works
18
City of Raleigh
Economic Stimulus Projects
Background:
Widening of existing Rock Quarry Road to a five-lane section with sidewalks
and streetlights between Sunnybrook Road and New Hope Road.
Cost:
Estimated Additional Funding Needed: $7.2 million
Public Works
19
City of Raleigh
Economic Stimulus Projects
Background:
Add curb and gutter, sidewalks and streetlights to Wade Avenue between
Ridge Road and Faircloth Street.
Cost:
Estimated Additional Funding Needed: $864,000
Public Works
20
City of Raleigh
Economic Stimulus Projects
Background:
Widening of Buck Jones Road to a three-lane section with sidewalks and
streetlights between Farmgate Road to Xebec Way.
Cost:
Estimated Additional Funding Needed: $6.8 million
Public Works
21
City of Raleigh
Economic Stimulus Projects
Background:
Addition of multi-use path along west side and turn lane additions at two in-
tersections along Lake Wheeler Road between Tryon Road and the I-40 in-
terchange.
Current Funding: $0 (Programmed with FY 09 CIP for first, and only, year
funding in FY 10)
Cost:
Estimated Additional Funding Needed: $2.0 million (based upon FY 09 CIP
funding projection plus right-of-way cost estimate not previously included)
Public Works
22
City of Raleigh
Economic Stimulus Projects
Background:
Complete conversions of South Street and Lenoir Street to two-way opera-
tion in those areas where they are still one-way operation between South
Saunders Street and East Street.
Cost:
Estimated Additional Funding Needed: $1.7 million (based upon FY 09 CIP
funding projection)
Public Works
23
City of Raleigh
Economic Stimulus Projects
Background:
The Carolina Pines Dam is classified by the North Carolina Dam Safety Of-
fice as a small, high-hazard dam. If the dam were to fail, it would potentially
pose a risk for loss of life or significant property damage. Based on an analy-
sis of the existing spillway, the dam is expected to overtop in a 10 Annual-
Chance (or 10-year) storm. Currently, the dam does not meet North Caro-
lina Dam Safety standards. This poses a significant risk to both Carolina
Pines Avenue and to the single-family dwellings in Oleander Park Subdivi-
sion. Available records suggest that the dam was built sometime between
1946 and 1952. The City of Raleigh took ownership of the dam in 1978
(DB 2584, page 145). No problems had been experienced with the dam un-
til Hurricane Fran struck 1996, when the dam overtopped. The dam again
overtopped on June 14, 2006 due to Tropical Storm Alberto. The City plans
to replace the three 36-inch concrete pipes, which currently act as the only
spillway for Carolina Pines Lake, with a spillway structure in the lake and a 5'
x 10' concrete culvert. The construction duration is expected to take up to
eleven months.
Cost:
COST ESTIMATE
Stormwater Management
24
City of Raleigh
Economic Stimulus Projects
The proposed improvements call for constructing of additional storm drainage along Myrtle Avenue
(24” and 36” RCP) to alleviate surface flows on Fairview Road and Glenwood Avenue. This proposed
plan also includes adding catch basins on Reid Street and along Myrtle Avenue. In addition to adding
infrastructure, the plans calls of replacing aging and undersized pipes of various materials with appro-
priately sized concrete piping. The existing storm sewer outfall currently crossing Glenwood Avenue
and daylighting on the backside of a privately owned retaining wall to an existing open channel would
be increased to a size of 48”RCP. In order to minimize impacts to existing private property improve-
ments, a new discharge point to the open channel would be added instead of removing and replacing
the existing retaining wall downstream.
The pipe improvements under Glenwood Avenue could be accomplished via open cut or jack and bore
and would require NCDOT approval of the project and we would need to obtain temporary and per-
manent drainage improvements from approximately 4 property owners.
The construction cost for the entire project would be approximately $575,000. Of this total amount,
$134,000 of this amount is for jack and boring of a new 48” encased RCP for 62 LF under Glenwood
Avenue only. The remaining $441,000 would be for the portion of the work outside of the NCDOT
right-of-way and would fall under the City’s financial responsibility.
Additional survey work would be necessary to gather necessary water, sewer, and private utility service
information to property owners along the work area. The outlet of the pipe system downstream does
not affect a blue line stream downstream or any regulated wetland areas. This project could be expe-
dited to begin in 90 to 120 days.
Cost:
1. Engineer’s Estimate: $ 480,000
2. 15 Contingency $ 72,000
3. Easement Purchases $ 3,000
4. Utility Relocations $ 20,000
TOTAL PROJECT ESTIMATE $ 575,000
Stormwater Management
25
City of Raleigh
Economic Stimulus Projects
The proposed improvements call for constructing of additional storm drainage along Myrtle Avenue
(24” and 36” RCP) to alleviate surface flows on Fairview Road and Glenwood Avenue. This proposed
plan also includes adding catch basins on Reid Street and along Myrtle Avenue. In addition to adding
infrastructure, the plans calls of replacing aging and undersized pipes of various materials with appro-
priately sized concrete piping. The existing storm sewer outfall currently crossing Glenwood Avenue
and daylighting on the backside of a privately owned retaining wall to an existing open channel would
be increased to a size of 48”RCP. In order to minimize impacts to existing private property improve-
ments, a new discharge point to the open channel would be added instead of removing and replacing
the existing retaining wall downstream.
The pipe improvements under Glenwood Avenue could be accomplished via open cut or jack and bore
and would require NCDOT approval of the project and we would need to obtain temporary and per-
manent drainage improvements from approximately 4 property owners.
The construction cost for the entire project would be approximately $575,000. Of this total amount,
$134,000 of this amount is for jack and boring of a new 48” encased RCP for 62 LF under Glenwood
Avenue only. The remaining $441,000 would be for the portion of the work outside of the NCDOT
right-of-way and would fall under the City’s financial responsibility.
Additional survey work would be necessary to gather necessary water, sewer, and private utility service
information to property owners along the work area. The outlet of the pipe system downstream does
not affect a blue line stream downstream or any regulated wetland areas. This project could be expe-
dited to begin in 90 to 120 days.
Cost:
1. Engineer’s Estimate: $ 480,000
2. 15 Contingency $ 72,000
3. Easement Purchases $ 3,000
4. Utility Relocations $ 20,000
TOTAL PROJECT ESTIMATE $ 575,000
Stormwater Management
26
City of Raleigh
Economic Stimulus Projects
Background:
The City of Raleigh would like to construct a high-speed optical fiber net-
work to connect many of its critical buildings together. This network would
benefit the City of Raleigh’s internal operations by lowering operational costs
and providing higher speed network connections to city staff. More impor-
tantly, however, it will enhance the interoperability of public safety agencies,
the ability for essential departments to operate in the event of a disaster, pro-
vide opportunities to extend wireless broadband to the community, and allow
for enhanced collaboration with other government agencies in the fu-
ture. Construction of the network would include placing conduit and fiber
underground as well as aerial installation of fiber when necessary.
Cost:
Funding in the amount of $2 million if the estimated project cost.
Jonathan Minter
Assistant IT Director - Enterprise Infrastructure Management
Information Technology
27
City of Raleigh
Economic Stimulus Projects
Generators
Goal:
Acquire funding to purchase generators to
protect critical police facilities for the Raleigh
Police Department
Need/Purpose:
The Raleigh Police Department strives to
ensure the safety and property of citizens in
our community. In order to guarantee this
safety, the department needs the ability to protect critical police facilities, reduce the
exposure to liability and minimize community disruption.
Public safety offers a line of communication to access external resources. The pro-
ficiency in retrieving and safeguarding sensitive documents during these hazards is
essential. Without power, the ability to dispense emergency equipment is impeded.
The City of Raleigh has two major watershed and is in close proximity to the
Shearon Harris Nuclear Facility. Six hazards have been rated moderate to high risk
in this are. It includes floods, severe storm/tornadoes, hurricanes/coastal storms,
winter storms/freezes, drought/heat waves and wildfires. The police department
requires the ability to respond to those emergencies expeditiously when disasters
occur.
In summary, the funds will allow each facility to sustain police activities without
disruption and deliver critical police services to citizens of Raleigh.
Cost:
Funding in the amount of $1,500,000.00 is the estimated project cost for the pur-
chase of generators and engineering/administrative fees for the police facilities.
Belinda C. Barrow
Grants Manager
110 S. McDowell St.
Raleigh, NC 27602
(919) 996‐1112
28
City of Raleigh
Economic Stimulus Projects
Need/Purpose:
The Raleigh Police Department requires funding to
build a new Firing Range Support Building at the
Battlebridge Training Facility. The photo shown to
the right is the current building in use by the de-
partment. This building was constructed in 1978.
Fund for the project would include a new range house for RPD’s firing
range, upgrades of the site fencing and
necessary repairs to the grounds. The
building will house some training staff
and provide classroom seating for up to
50 officers. Additionally, it will provide
restrooms and storage space for range
maintenance equipment and training
supplies. The building to the right is an il-
lustration of the proposed request.
Cost:
Funding in the amount of $900,000.00 is required to build a new facility
and necessary repairs and upgrades.
Belinda C. Barrow
Grants Manager
110 S. McDowell St.
Raleigh, NC 27602
(919) 996‐1112
29
City of Raleigh
Economic Stimulus Projects
Bathroom Kitchen/
15’ c
l Breakroom 18’
o
s
e
15’ t Bathroom
ws RANGE HOUSE 6,904 sq. ft
e t
Equip a o
closet p r 20’
o a
n g
e Courtyard
76’
6’
7’ 5’ 12’ 12’ 12’ 12’ 14’ 24’
c
Armory
Classroom hallway l
46’
to o office office office office 12’
outside s
e
t
cleaning carport/
7’
area mowers
tractors
c equip
Lobby l
o
FATS training
work room storage closet office s 12’
e
t
25’ 14’ 12’ 10’ 32’ 20’ 10’
137’
Belinda C. Barrow
Grants Manager
110 S. McDowell St.
Raleigh, NC 27602
(919) 996‐1112
30
City of Raleigh
Economic Stimulus Projects
Need/Purpose:
The Mobile Command Center is used for
a variety of events. It can act as an incident
command center, disaster recovery or as a
means of crowd control for a local parade.
It can be used in high-crime areas to coor-
dinate operations or even as a mobile sub-
station. Any of these situations can bring a
strong police presence into the commu-
nity.
The Mobile Command Center would be
assigned to the Special Operations Divi-
sion. This is a compact and flexible division of the
Raleigh Police Department that often sees the nature
of its assignments change in response to crime trends
and other identified special needs. The division closely
monitors statistical information, along with intelli-
gence gathered from field operations and other
sources, to specifically target criminal activities and
assist with investigations.
Cost:
Funding in the amount of $750,000.00 is required for the purchase of the Mobile Com-
mand Center and required equipment such as a server, monitors and cameras.
Belinda C. Barrow
Grants Manager
110 S. McDowell St.
Raleigh, NC 27602
(919) 996‐1112
31
City of Raleigh
Economic Stimulus Projects
Background:
CAT currently utilizes an operations and mainte-
nance facility situated on approximately 4 acres.
The existing facility is over 30 years old and was
originally built to support a fleet of 50 buses; this
facility currently houses over 90 buses and support
vehicles. Funding has been secured for the pur-
chase of a 23 acre site for the transit operations and
maintenance facility. An additional 12.2 million in
federal funds are being sought in order to begin
the construction phase of this project. The new
facility has been strategically located in order to
support local and regional transit services. This
project is programmed in the North Carolina Department of Transportation’s State Transporta-
tion Improvement Program and the City of Raleigh’s Capital Improvement Program.
Cost:
Appropriate $12,240,000.00 to construct a new and expanded bus operations and maintenance
facility.
David Eatman
Transit Administrator
222 West Hargett Street, Suite 400
Phone: (919) 996-4040
32
City of Raleigh
Economic Stimulus Projects
Cost:
Appropriate $4,373,000.00 to purchase 14 replacement buses. Appropriate
$3,666,000.00 to purchase 10 expansion buses. Total Bus Request: $8,039,000.00.
David Eatman
Transit Administrator
222 West Hargett Street, Suite 400
Phone: (919) 996-4040
33
City of Raleigh
Economic Stimulus Projects
Background:
CAT’s main transfer terminal in downtown Raleigh, Moore Square, is over 25 years
old. While this facility is perfectly situated within the CBD it is in need of substantial
upgrades and expansion to accommodate existing and future local / regional transit
services. Due to expanded services buses now use peripheral transfer points located on
Blount Street and Wil-
mington Street. Passen-
ger waiting areas, rest-
rooms, and the Capital
Area Transit ticket /
information booth are
all in need of improve-
ment. This project is
programmed in the
North Carolina Depart-
ment of Transporta-
tion’s State Transporta-
tion Improvement Pro-
gram and the City of
Raleigh’s Capital Improvement Program.
David Eatman
Transit Administrator
222 West Hargett Street, Suite 400
Phone: (919) 996-4040
34
City of Raleigh
Economic Stimulus Projects
Cost:
Total estimated cost of the project is $3.8 million. North Carolina and Federal
funds in the amount of $647,000 have previously been committed.
35
City of Raleigh
Economic Stimulus Projects
Background:
Fire Station #12 was designed and built in 1973 to be a one-company (4 personnel)
station. The station is only 3200 sq. ft., including the bay area for apparatus storage,
and is built on a .6 acre lot. Due to development in the area, the need currently exists
to house a second apparatus (aerial device) and a passenger vehicle at this station. Due
to the size of the lot, we are unable to renovate and expand this station. Property is
available nearby that would enable us to relocate this station and build a facility capa-
ble of housing all three apparatus and personnel.
Cost:
The total cost of both the relocation of Fire State #12 and construction of Fire
Satiation is #29 is estimated to be $1.1 million.
L. Bryant Woodall
Assistant Fire Chief
919-250-2815
36
City of Raleigh
Economic Stimulus Projects
Background:
Due to recent growth in the area, the need exists to construct a fire station in the
northwest quadrant of the city. The area is required to be served by two of our
fire stations (providing response by two pumping engines and one aerial appara-
tus) and we currently only have access to the area by one of our stations. Such a
new facility would house one pumping engine, including personnel, and provide
needed apparatus storage area for our reserve fire apparatus.
Cost:
The total cost of both the relocation of Fire State #12 and construction of Fire
Satiation is #29 is estimated to be $1.1 million.
L. Bryant Woodall
Assistant Fire Chief
919-250-2815
37
City of Raleigh
Economic Stimulus Projects
Cost:
The estimate cost of this project is $2 million.
Barry Furey
ECC Director
222 West Hargett Street, Suit 012
919-996-5015
38
City of Raleigh
Economic Stimulus Projects
Cost:
The projected cost of to modernize the fire dispatching infrastructure is
$560,000.
Barry Furey
ECC Director
222 West Hargett Street, Suit 012
919-996-5015
39
City of Raleigh
Economic Stimulus Projects
Cost:
The estimate cost of improving the Back-up 9-1-1 Center infrastructure is
$524,000.
Barry Furey
ECC Director
222 West Hargett Street, Suit 012
919-996-5015
40
City of Raleigh
Economic Stimulus Projects
Cemetery Branch Sanitary Sewer Interceptor Replacement Project:
This project is for replacement of approximately 5,000 linear feet of 12” and 18”
sanitary sewer mains along Cemetery Branch from Pigeon House Creek at Capi-
tal Boulevard to Oakwood Cemetery. The project is located in the historic Oak-
wood section of the City, one of the original neighborhoods in Raleigh. Design
of the project is complete and the construction permits have been issued by the
regulatory agencies. Easement acquisition is expected to be complete by Decem-
ber 2008. The project will be ready for bidding in January 2009 and is expected
to take 9 months to construct.
Cost:
The estimated cost of construction is $2,000,000.
Robert L. Massengill
Assistant Public Utilities Director
919-857-4543
41
City of Raleigh
Economic Stimulus Projects
Southeast Beaverdam Creek Sanitary Sewer Interceptor Replacement:
This project is for replacement of approximately 5,600 linear feet of 15” and 16”
sanitary sewer mains along the east branch of Beaverdam Creek between Glenwood
Avenue and Wade Avenue. The existing line is in poor structural condition which
has caused several SSO’s in the past. The existing line also crosses Beaverdam
Creek in several locations aerially which are subject to damage from high stream
flows and fallen trees. The replacement line will be installed deeper such that the
aerial creek crossings can be eliminated. Design of the project is complete and the
construction permits have been issued by the regulatory agencies. Easement acquisi-
tion is underway and is expected to be complete by January 2009. The project is
expected to be ready for bidding in January 2009, and is expected to take one year
to construct.
Cost:
The estimated cost of construction is $1,800,000.
Southeast Raleigh Reuse Distribution System Expansion:
City of Raleigh’s Water Supply Plan is construction of a reuse water distribution
system to provide water for nonpotable uses such as irrigation and cooling water for
HVAC chillers, which will reduce demand peaks. The primary source of reuse wa-
ter for Raleigh is the Neuse River Wastewater Treatment Plant (NRWWTP) located
remotely in the eastern part of Wake County. The City has begun construction of a
new reuse water distribution pump station at the NRWWTP as well as a new ele-
vated reuse water tank in southeast Raleigh in accordance the City’s Reuse Water
Master Plan. The initial phase of the transmission mains will convey the reuse water
from the NRWWTP to the elevated tank and the users in Raleigh through 8,600 Lf
of 24” and 23,500 LF of 16” pipes. This phase has been designed, permitted by the
regulatory agencies, and is ready for bidding. All of the transmission mains will be
installed either on City owned property or within existing easements.
Robert L. Massengill
Assistant Public Utilities Director
919-857-4543