(Take all Dimensions in feet), its works for M10, M15, M20, M25 Grade of Concrete.
Formula is Called
Like for a column (1022 feet) and M20 (1:1.5:3) Grade of Concrete 1st Multiply 1022 = 40 (volume) 2nd Divide 40/5.5 = 7.27 --- (sum of grade Ration 1+1.5+3= 5.5) 3rd multiply 7.27 1.25 = 9
So 9 bag of cement required for column of (1022 feet) if we use M20 Grade of Cement.
If you use dimensions in meter then convert volume cubic meter to cubic feet by multiply 35.31