Professional Documents
Culture Documents
OF THE
UNIVERSITY OF CALIFORNIA.
Class
OF THE
UNIVERSITY
OF
s -
II
Estimating
A
Guide
to
SYSTEMATIC METHODS IN TAKING OFF QUANTITIES AND MAKING UP ESTIMATES OF COST IN BUILDING OPERATIONS, WITH QUOTATIONS OF CURRENT PRICES FOR MATERIALS AND LABOR
By
EDWARD NICHOLS
Architect, Boston, Mass.
ILLUSTRATED
<***
GENERAL
COPYRIGHT
1907
BY
Foreword
recent years, such marvelous advances have been
made
in the engineering
and
scientific fields,
and
practical
size
and low
cost,
embodying the
To
fill
this
acknowledged
need,
this
is
volume belongs.
series, it
as distinguished
from mere
or academic discussion.
Each volume
is
and
is
methods
field,
purposes of
self-
home
study.
The utmost
bring the treatment of each subject within the range of the com-
196470
mon
technically trained expert, but also to the beginner and the self-
taught practical
progress.
man who
is
wishes
to
The language
without
sacrificing
any of
the
requirements
is
of
practical
instruction;
reader along
by easy
it
make
is
that
employed so successfully
for
many
years.
It is not
an experiment,
all tests
which
for the
to be the best
Table of Contents
PRELIMINARY PRINCIPLES
Variation
in
.
.
...
Percentage
....
Duplication
of
Page
Prices
Profit
Parts
Transportation
the
Estimating by
Rules
Square;
by
Preparatory
Steps
Units
and
Tables
Measurement
tents of Solids.
-\
Page 13
(Cut
Wages
in
Various
Trades
Excavation
Stonework
Window
Sets,
Sandstone,
Setting of Cut
Seam-Faced Granite)
Brickwork (Mortar,
Mason's Supplies
Vitrified Pipe
7
Face Brick)
Cellar
Concrete
Columns
Car-
pentry
Board Measure
Door-Frames)
Shingling
Lumber (Dimension, Floor and Finish, Inside Frame Floors Outside Walls the Calculating
V
Roofing
Studding
Windows
Doors
Cost
of
Inside
Finish
(by
the
Window-Frames
ductors
Stairs
Day's
Work
Labor
Exterior Finish
ConMetal,
Hardware
Nails
Roofing
(Shingles,
Plastering
Lathing
Paint-
Hot-Water)
Plumbing
Drainage
Water Supply (Boiler, Waste-Cocks, etc.) Capacity of Cisterns and Electric Lavatories Tanks Sinks Gasfitting Laundry Trays
Work
...-,.
...
Carpentry
Page 59
Staking-Out and
Setting
Batter-Boards
Plaster-
Water Supply during Construction Excavation Stonework ing Walls with Cement Cesspools, Dry Wells, and Drains
Brick-
work
Stairs
Flue-Linings
Concreting
Plastering
Electric
Work
Electric^
Hardware
Fixtures
Heating
Painting
for
Plumbing
Schedules
Wiring
of
Lighting
(Analysis
Carpentry
Work)
Outlets.
Memoranda
Heating Estimate
INDEX
.....'.
Page
109
FRONT AND REAR VIEWS OF RESIDENCE OF MR. H. T. LOOMIS, MAGNOLIA DRIVE, CLEVELAND, OHIO Watterson & Schneider, Architects, Cleveland, Ohio.
Cost, about $35,000.
Made
at Akron, Ohio.
Koofs of
Combination Red
Tile.
ESTIMATING
PART
Introductory.
I
The
ability to estimate
may
be considered as the
never "hang
dividing line between the journeyman and the master builder, for,
no matter how
skilful
a mechanic
out his shingle" and invite patronage in his distinctive line of work, unless he becomes able to make reliable estimates of material and
labor to be furnished.
and quickness
in figures or a
needed;
namely: experience and judgment, an understanding of the more or less complicated details which go to make up a building, and a knowledge of current prices and discounts in the trade. It is the object of this paper to point the way toward the acquirement of such of these needs as may be imparted by words or figures; that is, to put in con-
estimates are
to
made
which are
be avoided.
and materials are constantly shifting, must be taken only as proportionate, to in this paper those quoted be used in comparison with known quantities and methods. All
Prices.
As
prices of labor
in Boston, Mass., in December, 1906, prices given are as current account of the variaand are subject to immediate change.
On
bleness in price of labor and materials, it is better, in general, to make estimates on the basis of days or hours, and quantities of materials, so that they may be used for comparison in future work.
To
estimates should be carefully labelled and filed away This should be done whether the bids were for future reference.
this
end
all
successful or otherwise.
to
good
compare the estimates of cost of the different items, opportunity with the actual cost of execution; and if a bid fails to win the job,
and experience may be gained by noting the items which may have been priced too high or too low. This data may be of great
satisfaction
every case.
ESTIMATING
Catalogues and price lists of all standard articles are easily obtained and should be kept at hand, properly indexed, for ready reference, as they contain a great deal of specific information.
Catalogues.
figuring, however, it will not do to rely upon these prices, amounts of trade discounts are not always included. These vary greatly from time to time, and often there are two or more discounts, a trade discount, a cash discount, and a variation in discounts
For close
as the
made by different merchants, all of which the contractor must become aware of to obtain bottom pricesAll data of this sort should be carefully tabulated for constant form that it may be easily revised and kept, so far as possible, up to date.
reference, in such a
time of payments
it
is
a matter to be considered
will
permit the contractor to take advantage make a great difference in the cost of
the actual price of labor and materials must be added common method the profit and this will need careful consideration. is to add a lump sum to the estimated cost of labor and materials,
Profit.
To
varying with locality and customer, with the probable sharpness of competition and the circumstances of the contractor. This is a careless
method, as
it
leaves
no means
for future
knowledge of just what the profits of a given job are. better way is to base the profits upon a perPercentage. centage of the estimated cost. This will vary, in ordinary cases, from
tain
expected two or three thousand dollars; but for large work, where there is a great duplication of parts and processes, it will be enough in most
cases.
ten to fifteen per cent, ten per cent being the least that should be on any work, and this is not enough for small contracts of
Some
contractors,
whose workmen are required to perform per cent on all labor and ten
matter of duplication
is
Duplicate Parts.
The
an important
is often made if large either worked or unworked, are required ; this of material, quantities such as doors and windows, is especially true in manufactured parts,
columns, balustrades,
etc.
of dupli-
together
ESTIMATING
similar parts
more quickly and cheaply than variable members. Transportation. The distance of the work from the shop of the
from centers of manufacture,
will ?iflect the cost to a
contractor, or
marked
If
degree, as
much
time
is
consumed
in
in handling material a
number
it
of time?.
site
be
site
made
reference, subject to
study should each different building and the data kept for future
A careful
and amounts
be transported.
These are some of the more important matters which require preliminary consideration as affecting all estimates, and are only a
small part of the real questions involved, as different localities and
customs require different treatment, and numerous questions will arise to confront the contractor, all of which may be successfully
met, as
we have
seen,
Methods.
the contractor,
depending upon the degree of accuracy required, the capability of and the character of the building. A broad division
estimates and accurate detailed
estimates, only the latter of which should be considered when it is the intention to actually carry out the work under a definite contract.
Approximate estimates are obtained with varying degrees of accuracy by several methods, the most convenient and reliable of which is the system of cubing; i.e., the cubical
contents of the proposed building is obtained and multiplied by a given price per cubic foot. This rate is obtained by careful com-
Approximate Estimates.
parison of the plans and requirements with similar buildings which like as possible to the con-
under which the proposed building can be erected. Several methods are used to determine the cubical units, depending upon the size and shape of the proposed building. One
is to multiply the square feet in the plan of the building by the height from half-way" the depth of foundations to half-way up the roof. Another system uses the height from the bottom of the
method
ESTIMATING
foundation, and another obtains the actual cubical contents.
of these
Any
is
are subject to important variations which experience and will determine. alone For instance, if the contour of the judgment is with low building very uneven, portions, such as porches and sheds, and high portions, such as towers and cupolas, these must either be
way, but
omitted from the whole and compared separately, or a lump sum be added or subtracted according to the size and elaboration of these
members.
Another variation
partitions
arises in the size of rooms, giving
a ratio of
and
division walls
which
is
building with many duplicate parts will require a different rating from a smaller one, so that the method of estimating by cubing is at best approximate, and its degree of accuracy depends largely
large
upon the experience and judgment of the contractor. Even long experience will afford no safe-guard against unusual elaboration of
interior or exterior, so that
to buildings
and comparisons are only reliable between buildings of like description and uses, as the treatment of even the same materials will vary largely in buildings of varying uses.
of ordinary character,
height of the building will not increase the cube rate proportionately, unless the internal voids are alike, although it is certain that the higher
The
expense
it
requires to
thicker walls
is
This
especially
where the
few
in
number or
is
buildings similar in plan. For one story taken to include the roof, walls, floor,
and
all
and foundations, but for buildings of two or more stories the price per square should be taken separately for each floor, the lower floor
being priced to include the foundations and the top floor to include
the roof.
This method of estimating by the square is not so accurate as cubical contents, but the results are often more convenient and by the tabulation of the square area of the various because adaptable,
floors
may
ESTIMATING
buildings or shops.
floor area in
a school house
means accommodation
a certain number of sittings of machinQS and operatives. staple goods, a certain number
number
is
made
method
of estimating
the approximate cost of such buildings as the above mentioned, i.e., This is also a method by
comparison, the
or calculation,
and
approximate cost of buildings necessary to accommodate a given number of individuals or machines, even before any definite plans have been drawn. All of these methods are approximate, with varying
degrees of accuracy, and should never be advanced as accurate, or used as the basis of a contract, unless the contractor has had a long
and varied experience and feels absolutely certain of his judgment, or unless a proper margin is added for possible variations. Estimating by Quantities. The only sure and correct method
is by taking off the actual quantities in detail and carrythe out ing prices accurately with the cost of labor, the percentage for profit, and contingencies added.
of estimating
accurate and complete drawings and specifications are necessary to give the absolute quantity and quality of materials and The various items are then taken off, similar portions grouped, labor.
For
this,
amount of labor estimated, and a complete and classified schedule prepared and priced at current rates; the cost of transportation, board of men, and any other contingencies noted, a percentage of and a sum total reached which should be correct if profit added,
the
faithfully done.
is
if
a definite contract
is
to
be made.
and
speci-
visit to
tain the nature of the soil, the levels of the lot, the distance
from
rail-
if
a long haul
is
necessary,
and the preparation of the site necessary to receive and dispose of materials. Some knowledge should be obtained of the nature of
ESTIMATING
the sub-soil, the presence of ledges or water below the surface which or costly treatment, etc. Often a deposit of sand
site
if
which
away
of
of proper quality,
may
work.
existing conditions will be of great advantage to the estimator. Regarding underground conditions, there is always an element of
chance, as the most thorough examination will not always reveal hidden perils; the author knows of a case where a mason had contracted for the building of a sewer, and was in a fair way to make a good profit, when a narrow vein of quicksand was uncovered, to over-
all
Ground water
he
is to
it
will
be well
examine
what extent
may have been temporarily stopped or diverted by the operation of building, will sometimes unexpectedly make its presence known
during or after the completion of the work, when
it
may become
source of great annoyance and expense to the contractor if he has agreed to insure a waterproof job. Numerous illustrations could
may
known
as mensuration.
and comparisons of
bodies.
Definitions.
is
The
its
any
figure
the measure of
thickness or any
other dimension.
The
cubical contents of
any
figure is the
measure of
its
solidity,
or whole capacity, and has reference to the three dimensions, length, breadth, and thickness.
ESTIMATING
If the figure is considered as hollow, then the cubical contents
becomes
its
The
capacity or capability of containing matter. linear dimension of a figure is expressed by its length in a
direct line in
to
breadth or thickness.
is made by fixing be compared and the required dimension obtained; thus, for calculating the area of a figure the unit is usually a square, one side of which is the unit of length, and the area
Units.
The
may
becomes the square measure of the figure. This is expressed in common terms by square inch, square foot, square yard, or any other given unit and the measure of the surface is
which
is
called cubing
it.
Rules. Numerous rules have been adopted for obtaining these dimensions when given dimensions are known, and a tabulation of
of
some of the more important and useful of these follows, by means which it is hoped that the student may be able to solve most of the ordinary problems which will arise in common practice.
diameter
3.1416
Area
0.07958
half
the
diameter
of a circle
of a circle
circumference
X X
0.159155
Radius
Diameter
Diameter
0.56419
of a circle
of a circle
0.31831
1.12838
circumference X- 0.2251
diameter
base by
-J-
0.8862
Area of a triangle
the altitude
ESTIMATING
ellipse
Area of an
.7854
= = = = =
surface
solidity
X X
1.2407
3.8978
pyramid
Surface of a cube
J altitude
2 sum of parallel sides of similar solids are to each other as the cubes of
altitude
To
Rule
Multiply the
1
See Fig.
Area-abxbc
Fig.
2.
Area
1.
= <ae
be
To
To
Rule
by
See Fig.
2.
hypothenuse of a right-angled triangle when the base and perpendicular are known: Rule Add together the
find the
square of the known sides and extract the square root of the sum. See Fig. 3.
4.
To
find
one side of a right-angled triangle when the hyside are known: Rule From the square
square of the given side, and
ESTIMATING
Fig.
2.
Fig.
3.
Fig.
4.
Fig.
5.
10
ESTIMATING
the square root of the remainder will be the other side. See Fig. 4. To find the area of a trapezium: Rule Divide the figure 5.
into triangles by drawing a diagonal these triangles will be the area of the
6.
of the areas of
5.
See Fig.
To
allel sides
Add the two parand mutliply by one-half the perpendicular distance between
find the area of a trapezoid:
Rule
them.
See Fig.
6.
Fig.
7.
6.
Fig.
7.
To
find
one side by
this
half
the area of a regular polygon: Rule Multiply its perpendicular distance from the center, and
Table of Multiples to Compute Measurements of Regular Polygons, the Side of the Polygon Being Unity
NAME OF POLYGON
ESTIMATING
length of a side only is given the polygon by the number in
10.
:
II
Rule
Column
To
find
polygon that
circle,
when
known:
the
Rule
circle
by
name
11.
of the polygon in
the
To
find
the radius of a
circle
that can be inscribed in a given polygon, when the length of a side is given
:
Are<l=lb)-(cd)x.7854Fig.
8.
Rule
Lateral Area =2 ac
Fig.
9.
12.
To
an irregular polygon: Rule Divide the polygon into triangles and add the areas of all
the triangles.
13.
Fig. 7.
To
Rule
difference between the squares by .7854. 14. To find the area of an ellipse:
Flg
'
Rule
111
^pyramid
15.
Multiply the two axes together and the product multiplied by .7854 will be the area.
circumference of an ellipse:
To
find the
Rule
Square
12
ESTIMATING
AREAS OF CIRCLES
SIZE
ESTIMATING
SOLID CONTENTS
19.
13
To
find
the solid
contents
of
pyramid:
Rule
Find
and
multiply this
by J height.
Rule
Multiply
To
the area of the base by the height. 21. To find the solid contents of
the area of the base by J of the height. 22. To find the solid contents of the cube of the diameter
a cone:
a sphere:
Rule Rule
Multiply
Multiply
by
.5236.
SCALE OF WAGES
The
petition,
is
at
upon com-
demand, and labor organization. The cost of labor is steadily on the increase, while the hours
The
tions operates to a certain degree to lessen the effective power of labor, so that the amount of work done in a day is not what it repre-
sented a few years ago. The various schedules given in the following pages are based upon the current price of labor in Boston, Mass., in 1906, and while
this is likely to
there
is
be upset somewhat by a general advance in 1907, not likely to be a great difference for some time. Blank
left in
spaces are
can
fill
in local or varying prices of labor. of Eight Hours, in Various Trades, Boston, Mass.,
1906
$3 28
.
/" rf.
Brick Masons
4 80
.
?. .77
.
Hod
Carriers
2 40
.
77".
Plasterers
Plasterers' Helpers
5.00. 3 00
. .
...<?.T7.
.
.frr
.
Lathers
4.50.
#f?.
2 50
.
4.00 4.80
2.60
14
ESTIMATING
Roofers
ESTIMATING
15
In taking quantities in irregular ground, the plot should be divided into a number of definite squares and the contents of each square taken separately. See Fig. 11.
Cost of Excavating.
localities
The
The
and under
differing conditions,
details or in execution.
judgment.
will
Excavating is usually priced by the cubic yard and average about as follows:
12 cu. yds. per day at $2 .40 $0 20 out 12 cu. at .20 $2.40 Throwing yds. per day
Picking
Wheeling 50
ft.
away
10
$0.50
Excavations in clay or very hard soil may cost from $0.50 to $1.00 while rock excavations- will cost from $2.00 to $10.00, or more,
according to the nature and
position of the rock.
Re-fill-
Division of plot.
or loose gravel, which can be done by means of a horse scraper, will cost $0.30 per cu. yd. Pile Foundations. The cost of piling varies with the nature
of the soil
pile necessary.
as an average length, then piles 30 ft. long, to receive footings, will cost $3.50 to $4.00 per pile.
STONE
WORK
Stone walls are figured either by the perch or the cubic yard. off a stone foundation, it is customary to take the corners twice, that is, each different face of the wall is measured
In taking
from out
to out, thus
the extra labor of laying up the corners. The cost of a perch of rubble foundations laid in Rosendale
cement mortar,
to 3,
may
be taken as follows:
16
ESTIMATING
1
perch of stone
J barrel
cement
at $1
20
ESTIMATING
will cost, if the stones
17
each block:
Stock, 4 cu.
ft.
at .60
sq.
ft.
$2.40
.67
joints 2
ft.
at .25
at .25
Rock
face 6 sq.
1.50
.57
Cost of 6 superficial
or 76J- cents per square
If the
ft.
foot.
same were
surface would be 70 cents a square foot instead of 25 cents, making the cost per
Limestone
is
used to a
large extent, especially in conjunction with brick, for trimnrngs for various kinds of
buildings.
Limestone
will
cost
at
;
the
quarry about 30 cents a cubic foot this will apply to Indiana limestone only. Lake. Superior redstone will cost 35 cents; In estimating, cents. Fig 13 Limestone window Set about 20 per cent should be added for waste, 5 per cent quarry waste, and 15 per cent for cutting waste:
Ohio sandstone, 50
* Prices of
Common
Shapes of Limestone
foot foot
foot
$1 .50
1 50 2.50
.
x 12 in. per lineal x 14 in. without nosing, per lineal x 14 in. with nosing per lineal Door sills, 8 in. x 12 in. per lineal Window sills, 5 in. x 12 in. per lineal Window sills, 5 in. x 8 in. per lineal Window caps, 4 in. x 10 in. per lineal Window caps, 8 in. x 12 in. per lineal Wall coping, 5 in. x 20 in. per lineal Platforms and large slabs, 6 in. thick, per sq.
Water
table, 8 in.
.25 .00
.75
.70
1 1
foot
foot
ft.
.00
.50
2.00
is
* Window Sets.
A common
use of limestone
in the
form of
window
and
consisting of a flat arch in three pieces with keystone, a light sill, as shown in Fig. 12.
sets,
* These
prices are based on a freight charge The freight on L.ake Superior stone is The freight on Ohio stone
ft.
to Boston.
18
ESTIMATING
The
rise of these
caps
is
inches.
will
an average sized window, say 4-foot opening, cost for a 4-inch reveal $10, and for an eight-inch reveal SI 5.
sets for
These
Sandstone.
cent
The
cost of dressed
sandstone
is
about 10 per
more than
Setting.
that of limestone.
cost of setting cut stone
The
may
be taken at 15
Fig.
13.
20 cents for platforms, water table, steps, etc. Trimming ting at the building will cost about 10 cents per cubic foot.
and
fit-
foregoing prices are based upon quarry-men's wages at $2.50 per day, and stone cutters' wages at $4.00 per day. Much of the cutting and finishing of stone is done by machinery, so that the question uf
The
wages
prepara-
many
other branches.
is
Marble.
A more
obtained in a variety of colors, in different parts of the country. The price of marble differs in different localities but for general purposes
ESTIMATING
may be
taken as about double the figures which Bluestone
is
19
we have quoted
for
limestone.
Bluestone.
ings, etc.,
but
is used in the East mainly for flagging, copused to a considerable extent for building, in Central
and Western sections. The price of bluestone flagging 3 inches thick with trimmed joints and face planed arid dressed, will be 65 cents
a square foot; with natural face, 35 cents to 45 cents. Bluestone ashlar 8 inches thick with natural face and dressed joints, will cost
square foot, and 15 cents a square foot for setting. In some localities granite, lying in upturned strata with open weathered seams, is to be obtained. This
$1. 00 per
Seam-Faced Granite.
used for facing walls in ashlar work, being set on edge in the wall with the seam-face showing; thip will cost, in place, 4-inch to 8-inch See Fig. 13. thick, from 60 cents to 75 cents a superficial foot.
is
BRICKWORK
Brickwork is usually estimated by the thousand bricks, but is sometimes priced by the cubic foot at 40 cubic feet to a thousand. A mason in one day will lay ffom 800 to 1,000 common bricks, or 300
to
400 face
bricks.
of bricks in a wall may be found by multiplying the area by 7J for each 4 inches of the thickness of the wall. superficial Openings of the size of ordinary windows are generally deducted, but very small openings will cost more to make than the deduction.
The number
An
Mortar.
allowance for breakage should be made of 5 per cent. Bricks are laid in mortar made of lime or cement,
according to the strength required. Lime mortar should not be used in damp situations, or where great strength is required. The difference in cost of lime and cement mortar is so little that cement
mortar
is
The
in
some
cities require
brick
work
to
be laid
cement mortar for a certain part of the height. Cement mortar makes a darker joint, but where a white joint is required it can be obtained, without loss of strength, by using Portland cement and lime mortar.
Cost.
of mortar
The
cost of brickwork
by the thousand
in various kinds
may be
analyzed as follows:
20
ESTIMATING
In
1
3 lime mortar,
1,000 bricks 3 bu. lime at $.36 per bu. \ load of sand at $1 75 per load
.
10 hours,
mason
at $.60 per
hour
$19.96
In
1
$9.00
1
.
80
.88
6 00
.
3 00
.
$20.68
In
1
$ 9.00
Portland cement at $2. ip load sand at $1.75 \ 10 hours, mason at $.60 per hour
1}
bbl.
2.62
.88
6.00
3 00
.
$21.50
From
these tables
estimate in
bricks laid in
- 3 lime mortar
3 cement mortar
$20 00
.
21 00
.
22 00
.
So that, on a job of ordinary size, the difference between lime and cement mortar ought not to be considered, where cement mortar
will give
assurance of greater
stability.
Face Bricks.
Face bricks
be had either
of colors. On ordinary face plain or moulded, and in a variety brickwork a mason with tender will lay about 300 to 400 bricks in
a day.
ESTIMATING
Faced bricks cost from $25.00
to $50.00 per thousand;
21
a good
average brick can be secured for $32.00. a thousand, laid, about as follows:
This
will
make
$32.00
.45
.
i load fine sand at $1 .75 3 days, mason at $4.80 1J days, tender at $2.40
88
14 40
.
3.60
$51.33
From
this
we
which $33.33 goes for stock and $18.00 for labor. Enameled bricks are to be had in various colors, white and buff being the most common. These bricks cost from $50.00 to $60.00
for $51.33 of
per
M.
Concrete.
Concrete
is
The
cost of concrete
if
used to a great extent now for footings, is not a great deal different
suitable sand and gravel, as is at a less price than a granite footing. Concrete with a reinforcement of steel
for piers, floors,
and
walls.
The
1-3
and
cost of a cubic yard of concrete, using the proportion of 6, may be summarized as follows
:
bbl.
Portland cement
$2.10
.75
3 bbl. sand
2.00
1
.
Mason, 2 hours
20
1.20
"$7^25
Cellar concrete 3 inches thick will cost $.60 to $.75 per square yard in place. Concrete of Rosendale cement can be put in at less
being for foundation walls about $6.00 per cubic yard; for piers $6.50 per cubic yard.
cost,
22
ESTIMATING
MISCELLANEOUS DATA
CHIMNEYS
Chimneys may be quickly estimated by the
lineal foot of height,
as follows:
1
flue
8
8
12
in. in.
in.
in.
in.
1 1
"
x 12
"
x!2
x
8 x 12
in.
in. in.
2 flues 8 2
"
in.
in.
per foot $0.90 with flue lining $1.10 " " " 1.25 per foot 1.00 " " " foot 1.20 1.50 per " " " foot 1.40 1.80 per " " " 2.20 per foot 1.75
FLUE LINING
Net
4J 4J in.x
in. in.
price per foot, outside dimensions. 8J inches $.10 8J in. x 17J inches $.32
x!3
x 8J
"
13
13
in.x 13 in.x 18
"
.30
"
"
"
8J 8J in.x 13
.42 .70
18
in.x 18
"
MASONS' SUPPLIES
Portland Cement
Rosendale Cement
Extra Lime for Skimming
No.
Plaster,
250
Ib.
bbls.
$ 2.10 per bbl. " " 1.20 " " 1.15 " " 1.05 " " 1.20 " " 1.60
.01] per
Ib.
in bbls. in 100 or
200
"
"
u
Ib.
keg
.01}
.Q3J
"
Mortar Hods
Brick Hods
10-in.
50 each
" "
"
1.25
.50
.
Mortar Hoes
2 Shovels, square point, plain back
Good No.
75
6'.
00
"
2.00
"
ESTIMATING
Metal Corner Bead
Iron "
23
Rim and
"
"
"
in.
in.
diameter "
"
in.
CELLAR COLUMNS
cellar support^, in place of brick piers, pipe columns cona steam pipe filled with cement, under a patent, are coming of sisting
For
many
localities.
These columns
cost less,
and take up
less
The
24
ESTIMATING
CARPENTRY
The Carpenter-Work of a building includes, in general, the if a wooden building, the floor timbers, studs of
and
walls, rafters, the covering in of the frame, with
its
skeleton or frame,
partitions
and clapboards, siding or shingles, the flooring, furring, and beads. This practically covers the constructive woodgrounds, work or carpentry proper, while to the term joinery belongs the outside and inside finish, windows and doors, sheathing and dado,
exterior finish
stairs
and
fixtures.
sections the general term carpentry covers all woodand working covering, while in others the distinction between the carpenter and the joiner is more distinctly drawn.
In
many
distinction,
For the purposes of this work it will not be necessary to hold this and so for convenience, the term carpentry will be used
branches of woodworking. Two distinct elements enter into the carpenter-work of any structure; the Material and the Labor, and the cost of both is subject The trend in both is in the directo fluctuation to a great extent.
to cover all
and materials
is
never quiescent,
any printed prices must be considered as comparative only, and must be carefully compared with local and known data before being
accepted as accurate or final. The material with which the carpenter works, consists in the main of three principal divisions, the Frame, the Covering, and the
Finish, and each of these has further subdivisions as will be noted.
Board Measure. All lumber which has not been wrought or moulded, is sold by "board measure" that is, the stock in each piece
is
is
reduced to a unit of a square foot of board one inch thick. This called board measure and is expressed by the abbreviation B. M,
Prices of lumber are usually rated by the thousand feet, so that the expression "Twenty-five dollars a thousand" means twenty-five To reduce dollars for a thousand square feet of stock one inch thick.
stock of greater thickness than one inch, to measure, several rules may be used.
its
equivalent in board
convenient method
is
to divide the
ESTIMATING
TABLE OF BOARD MEASURE
SIZE IN INCHES
25
26
ESTIMATING
Example.
x9
in.,
20
ft.
long?
2X9
-
20
30
ft.
B.
M.
12
When
may sometimes be simplified by varying the process and multiplying the length in feet, and the thickness and width in inches together, and dividing the whole product by 12.
Example.
16
ft.
How many
16
joist
2J in.-x 9
in.,
long?
2J
12
9
-
30
ft.
B.
M.
LUMBER
Dimension spruce lumber up present per M., board measure.
10-inch
stock, per lengths,
to 9 inches of
M.
*30.00
2.00
For long
add per M.
Hemlock boarding
Spruce boarding
45.00
4.00 3.50
50.00
Spruce clapboards
Siding cypress
30.00 55.00
Drop or
Laths
novelty siding
5.00
in.
35.00 40.00
in.
in.
50.00
Georgia pine,
common
rift
$70.00 45.00
ESTIMATING
Maple flooring Quartered oak
North Carolina
$ 55.00
flooring
pine,
rift
27
125.00 to
stock
150.00
40.00 33.00
$ 45.00
1
80.00
75.00 90.00
120.00
Oak, quartered
Birch
65.00
Whitewood Ash
s52.00
55.00
Elm
INSIDE DOOR
2ft.
40.00
FRAMES
.
in.
x6
ft.
8 8
$1.00
1.10 1.15
.75
2ft. 10 in. x 6
ft.
3ft.
in.
x7
ft.
In taking
off the
for the purposes of estimating, the most accurate method is to take a schedule of every piece of timber from the framing plans, but as it often happens that the estimates are asked for from the general drawings,
before
framings
are
made,
it
become the custom in many the walls and floors by the square of
has
sills,
100 superficial feet, making separate allowance for plates, and other large timbers.
If
it
girders,
desired to take off the frame separately in the absence of framing plans the following data may be of use. The sills of an ordinary house will usually be from 6 in. x 6 in.
is
to
girders from 6 in. x 8 in. to 8 in. x 10 in., and in. x 8 in. to 3 in. x 12 in. joists generally 16 in. on centers. of Wall studding outside frame and bearing partitions will
in.
x 10
in.,
floor
from 2
usually be 2
in.
x 4
in.
- 16
in.
on
centers.
Studding of
clos-
IN
ESTIMATING
and
x 6
light walls will usually
in.,
ets
be 2
in.
in.
x 3
in.,
and
in.
4 6
in.
sometimes two 2
x 12
in.
x 4
in.
in. to
in.
and 18
in. to
24
in.
on
centers.
sills
and
be
measured by the linear feet in the outside wall. The position of the main bearing partitions will usually give the number and location of
the girders.
fireplaces
and
8
stair
in.
Studs are doubled at openings and at corners, and openings will call for timbers of a large size, say
width.
from 6
in. to
Assuming that the joists are 16 in. on centers, the number of a floor will be given by taking f of the length of the building joists on The number of studs in the outside in feet, and adding one joist. frame at 16 in. on centers may be found by taking of the number of
f-
for each
adding one stud for each door and window. To this must be added
number
in the inside
Three quarters of give the number of studs This allows for doubling
of studs at openings
and corners.
For the number of rafters take the length of the building divided distance of the rafters apart and add 1, this gives the number the by of pairs of rafters if a plain gable roof, while the number of rafters in a hip roof can be found by dividing the whole distance around the
building by the distance apart.
Spruce lumber is generally used for framing, but Georgia pine must sometimes be used for large girders. The cost of spruce lumber is from $26.00 to $28.00 per M.,
Cost of Frame.
for sizes
in.
M.; 14 in. sizes $40.00; 16 in. sizes Hard pine from the South by shipload will cost about $5 00
per
M,
of
The
M.
sill
;
labor of framing
sills,
30
ft.
long, containing
ft.
Stock, 90
B.
M.
M. $2 34
.
Labor
of framing at
$10 00 per M.
.
.90
$3.24
ESTIMATING
29
Dividing this by 30, the length in feet, we get lO-^ cents, or about 11 cents a running foot. In this same way the posts, girts, and other special timbers may be figured.
Having disposed of the large timbers separately we can An analysis of this the floors by the square of 100 feet. up a follows: us result as gives Cost of a Square of Flooring:
Floors.
now
take
Joists 2 in.
x9
in.,
16
in.
on
centers, 112J
ft.
B.
M.
at $26.00
sq.
ft.
$2.92
1
.
50
10
Bridging
50
2 40
.
.80
.
75
.15
in.,
16
in.
on centers
40
10
Nails
Labor
1.00
ft.
of Spruce at $40 00
4 00
.
1.30
1.50
.
15
25
$ 1 7 82
.
way we may
in.
on
centers,
M.
at $26.00
$ 1.30
Waste J stock
Nails
at
$24 00
.
30
ESTIMATING
$3 61
.
50
.25
2. 18
$6 54
.
Roofing with 2 in. x 6 in. rafters spaced 20 in. on centers 2 in. x 6 in. rafters 20 in. on centers at $26.00
will cost
$1 .56
.39
Waste}
Labor
Nails
2.00
.
10
Boarding
2.40
.60
Waste Labor
Nails
1.00
.15
$8 20
.
M.
at $26. $1
30
Waste
Nails
J stock
'
.65
.15
1
.
50
.40
$4.00
Windows
Window frame
Sashes 3
Blinds
ft.
$1.20
ft.
x5
1.75 1.00
.15 .38
Blind fastenings Weight, 30 Ibs. at 1J cents per Ib. Sash cord, 20 ft. at 1 cent per ft. Sash fast
Inside casings, 20 ft. at 3 cents per Stop beads, 16 ft. at If cents per ft. Labor, 8 hours at 41 cents per hour
ft.
.20
.25
.
70
.28
3 28
.
$9.19
ESTIMATING
Inside doors of average size will cost, complete: Door 2 ft. 8 in. x 6 ft. 8 in. x 1 } in. pine, to paint
31
$2 40
.
"
Frame
Casings
1.00
1
.
33
15
Threshold
Nails
.05
Hardware
Labor, 8 hours at 41 cents
1.25
3.28
$9 46
.
in place
Rift hard pine upper floors will cost, per square of 100 square feet $6.50 Rift hard pine flooring, 100 ft. B. M. at $65.00
of stock
2.16
2.00
.15
3 cents per
Ib.
Paper
Total cost of floor per square
.25
$11 .06
Approximate cost per square ft. Finishing with shellac and wax
Total per square foot finished
11 cents
3 cents
14 cents
ft.
25 cents
4 cents
29 cents
A common
Door 3 Frame
in.
x 7
ft.
in.
x 1}
in.
$ 5.75
4.50
2.50
ft.
Plate glass
Casings, 20
at 4 cents
.80
Hinges
.68
4.50 4.00
$22.73
32
ESTIMATING
pair of sliding doors, fitted
complete, will
average
about
as
,
follows:
2 doors 3
ft.
in.
x 7. ft.
in.
x 1|
in.
each
$6.00
1
.
44
98
40 40
grounds, at 1 cent
.40 .80
2 cents
Astragal
1.00
.20
Chafing strip
Lock
Hangers and track
Sheathing pocket, 84 ft. at 40 cents Labor, 40 hours at 41 cents
4.50
4 50
.
3 36
.
16.40
$39 14
.
and
These are some of the principal parts of a house analyzed will serve to show how the cost of any portion may be obtained by dividing it into parts and pricing each portion by itself.
Following are some miscellaneous details of carpenter work carpenters working in pairs can put up in a day about
:
Two
300 300
B.
B.
B. B. B.
600 800
600 500
ft.
B.
M. M. M. M. M. M.
of studding.
of rafters.
of floor joist. of wall or roof boarding. of matched boarding. of diagonal
matched boarding.
MISCELLANEOUS ITEMS
CELLAR WINDOW
Frame
Sash
$1.50 1.20
.
Hardware Labor
15
.50
$3.35
CELLAR DOORS
Stock door, 2
ft.
in.
x 6
ft.
in.
x 1J
in.
Frame
Finish, 36
ft.
$2.25 1.00
1.62
4^
in.
anish
ESTIMATING
Threshold
33
Hardware Labor
$0.15 85
.
3.00
~8W~
Paper on walls under clapboards or shingles per square: Paper
Laying
$0.20 05
.
$0.25
Inside Finish.
in place:
wood
or cypress,
$0. 12 .40
.
cost
in.
in.
ft.
ft. wainscot of narrow sheathing, per running Plain wall sheathing, per square foot
05
.3^ in.
cap
for wainscot
.06
.06
in. in.
ft.
4
3
1
.07
.35
8 00
.
Finishing
been moulded
one cent for every square inch of section a trade discount, which at present is 30 per cent
will cost 5 cents
per foot
less
30 per cent,
per
foot.
in.
Casings, 5
$0.03i
.05J
in. in.
Base, Sin.
Plinth blocks, 5
x8 x5
in.
in.
Corner blocks 5
Stock pattern
Newels, 5
in. in.
x If x 1J
in.
in.
in.
05
.05
stair rail
2^
x 2J
in.,
per foot
17
Balusters, If each
.09
Newels, 6
Plate
5 00
.
6 00
.
rail and picture moulding per foot Picture moulding per foot
.09
-01J to .03
3 drawers
3 50
.
case, 5 drawers
13 00
.
OF THE
UNWERSlT
34
ESTIMATING
Inside
2ft. 8
in
in.
2
'^
ft.
x 6
ft.
10
in.
in.
in.
in.
2.50 2.80
3ft.
x7ft.
x 1J
Window Frames
2J
ft.
^
$1 10
.
x 4J
ft.
ft.
3ft. x 5
1.20
STAIRS
trade of stair-building, while a part of the general work of joinery, is usually taken up as a separate trade and is done by
The
men who do
to
nothing
else.
have the
stairs figured
better,
if
possible,
stair-builder,
who
will have the special tools, moulds, and stock necessary for this branch of carpenter work. There are usually in every house, two sets of stairs, one in the
front part of the house and one in the back part. Sometimes the as the stairs are so arranged to land together in second story, but
divide
somewhere
in
their
part, the
height upon a common landing, one elaborate, running from the front hall, and the other from the back hall or kitchen.
is
This
is
and
See
often
When two
in,
and
is
this
we
shall
UP
consider.
Front
Stairs.
The
nary width and elaboration, say from 3 ft. to 4 ft. wide with turned balusters and
Fig.
14.
Combination Staircase.
at
$3.50
to
moulded rails and posts, in white wood or North Carolina pine, may be approximated This is on the basis $4.50 per step, complete.
$1.50 per step for labor, the remainder for the stock. Panelling in connection with the stairs should be figured at $.40 to $.50 per
sq.
ft.
stock,
oak 75 per
ESTIMATING
35
Winding steps will cost about double the 'price of straight steps for material, but the labor will be increased only about 50 per cent.
This price
with li
in.
will allow of
hard pine treads and plain moulded turned balusters, two to a tread.
definite data
rail
No more
is
can be given as to front stairs, as there finish, and such a wide range
in .selection
and balusters. and panelled newel may be had moulded In general a good
for $5.00 to $8.00, landing posts $3.00 to $4.00, rail 15 to 18 cents per lineal foot, balusters 9 to 12 cents each. Balusters
add 30 cents. See Fig. 15. These prices are for open brackets are used on the outside
12 to 15 cents per step.
string
stringer,
stairs,
it
if
will
add
Back Stairs. Common box stairs, for general use in the back and attic portions of a house, will cost about $1.60 per step, this includes 85 cents
for
Winders
will
be used more frequently here than in front stairs ard will cost about double the price of a straight step.
plank with no risers will cost about 65 cents per step, giving 20 cents for labor and 45 cents for stock.
Open
cellar stairs of
Pattern.
Summary.
From
the foregoing
it
will
be found that a
flight
wood will cost, at the average run of 16 steps, the same in ash $96.00; in oak $112.00. This
a fair price for good plain work and will give a satisfactory result. The back stairs at 15 steps would cost $24.00 and the cellar
Under conditions where much of the handrailing $7.80. could be done away with, the prices could be reduced considerably.
stairs
DAY'S
WORK
fittings
36
ESTIMATING
1
fitting blinds,
fitting doors, 5
per day
of floors, per square of walls of plain roofs of hip and va~ ley roofs
$1 50
.
1 1
50 50
20
75
2 00
.
Heavy framing
Boarding walls Boarding walls with matched boards Boarding walls diagonally
1
.
1
1
00
00
00
75
Boarding
roofs
floor
floor diagonally
Laying rough
Laying rough
1
.
.00
Bridging floors
Furring brick walls 12 Furring brick walls 16
in.
50
on centers on centers
6
in.
1
1
.50
in.
.00
.
floor,
stock
50
Laying spruce upper floor, 4 in. stock Laying hardwood floors, 2 \ in. stock
Shingling walls and roofs Clapboarding walls
2 00
.
2.50
2. 18
2.18
.
25
Work by
Making window frames Making door frames Door frame with transom Setting window frames, each Setting window frames in brickwork, each
Hanging blinds, per pair Fitting and hanging sashes per pair Hanging transoms Casing windows
00
50
1
.
30
50 50
.32
.
40
.80
ESTIMATING
Large size windows and cellar windows
Casing door opening, one side Casing door opening, both sides
Fitting, hanging, Fitting, hanging,
37
$1 .50
.
Attic
75
32
65
65
00
13.00
1
.
Work
in
common
50
Exterior Finish.
in the
The
main, of the water table at the bottom, the belt midway, and
Water
Belt
table,
3 members at 3 cents
$0.09
.03
.08
ft.
.
Corner boards
Cornice, 3 to 6 cents each member, or per
50
Gable
.60
An
foot,
ordinary piazza will cost, complete, making for an 8 ft. piazza a cost of
$0.56
.28
1
.
11
1
ft.
studding at 2} cents
bunch shingles
00
13
Nails
Labor
4.00
$5.94
in.
x8
each
Labor
Erecting
$3.50
38
ESTIMATING
simple balustrade of straight square balusters 1J
fooj:
in.
will cost
per running
Top
rail
rail
in.
ft.
x4
x 4
in. in.
SO. 12
Bottom
Labor
.08
.
12
.32 SO. 64
Sheathing
Waste
Furring Nails
Labor
$8.50
Piazza Finish:
Stock pattern, 5
in. in.
turned columns
8 8
ft.
ft.
long long
$ 2.00
turned columns
2.75
3 50
.
in.
Colonial columns 9
ft.
ft. ft.
ft.
long long
long
Stock pattern, 10 in. Colonial columns 9 9 8 in. Doric Column from detail
10
10
in.
5.50
6 50
.
9 9
in. in.
long
long
8.50
15.00
1
1
in.
Column from
in. in.
detail
ft.
ft.
ft.
x5
x6
in.
in.
x4 x4
.00
.
50
.10
If x 3f in. per
ft.
ft.
.06
Piazza
rail
2} x 3J
in.
per
.07
1
.
00 to
2 00
.
pipe at 15 cents
$3.40
ESTIMATING
39
HARDWARE
The
is
best
way
hardware
is -to
and price
from the
dealer.
The
constantly changing.
of ordinary value.
$2.50
(bronze metal)
to
$4.00
8.00
1.50
2 00
.
7.00 to 10.00
6.00 to
1.00
to
6.00 to 10.00
1
.
50 to
2.00 to
3 50 up
.
3.00
Double acting floor hinge per pair Double acting spring hinge "
Window
Sash
fast
2 00 up 1.10 up
.
each
fixture
set
.25 to
.35
Transom
.30 to
.50
.
Cupboard door
60
1.25 to
1
3.00
2 50
.
.85
2.50 to 3.75
3 50 to 5 50
.
.
NAILS
Nails are priced from a base price per hundred weight adopted the manufacturers, which includes certain sizes of the more by common kinds. From this base the different kinds of nails are
priced by means of extras, as agreed upon. The present base includes common, fence, and sheathing nails in sizes from 20 penny
to
60 penny.
Following is a schedule of all kinds of cut and wire nails in general use and the extra price of each kind per cwt. above the
base,
which
is
$2.50 per cwt., for cut nails and $2.45 per cwt.
40
ESTIMATING
ESTIMATING
41
42
Earthen drains 4
ESTIMATING
in.
20
75
Arch brick
laid in wall
sq.
M.
ICO 00
.
5.00
.50
.
25
beams per
Ib.
Ib.
.03
.02
1
Copper skylights per sq. ft., heavy Plastering 2 coats on wire lath Wooden balustrade per ft.
Outside blinds for a house
will
.75 to 2 .50
.
65
50
average per pair Inside doors, 5 cross panels, pine to paint, average Store sash If in. per lineal foot
.85
3 25
.
.30
1
.
Storm sash for house will average Outside door frame with transom
Inside door frames will average
55
3 50
.
1.10
1
.
Same with transoms Factory window complete 4 ft. Framing heavy lumber per M. Planing lumber per M. Laying plank floors per M. Common bricks per M.
85
in.
ft.
in.
3 00
.
12
00
2 00
.
9 00
.
9 00
.
20 00
.
7 25
.
6.54
11.80
6 00
.
ROOFING
Description. Many kinds of material are used for covering roofs, depending upon the nature of the work, the pitch of the roof,
the desired appearance, and the availability of material. Shingles. The roof covering of an ordinary wooden house
is
shaved or sawed, but sawed generally of shingles. THese are either come in bundles of 250, or shingles are generally used. Sawed shingles four bundles to the thousand. These quantities are based on a width
ESTIMATING
of 4
less
in. to
and consequently,
they are wider they will be numerically narrower, there will be more in number.
if
Common
shingles are 16
in. to
18 inches in length.
Measuring. In measuring for shingles the quantities are usually taken by the square; equal to 100 sq. ft., and the number of shingles
or exposure which is given to the required will depend upon the lap is the roofs On length usually 4J inches, and on exposed shingles.
walls 5 or 6
inches
is
out of special designs a greater or less exposure may be given. The covering capacity of 1000 shingles at various Quantities.
exposures
is
as follows:
111 sq.
ft.
weather
167 194
sq. sq.
ft.
ft. ft.
= = = =
222 sq.
Sawed cedar
from $4.00
shingles of best quality marked "Extra" and clear shingles, that is,
having the exposed lower third of clear stock, will cost $3.50 to $4.00 per thousand, and it will require 5 pounds of 4 penny nails. These will cost 3 cents a pound if plain, or 5 cents, galvanized.
A carpenter
hours
will
in
one day of 8
much
cut up. This will cost at $3.20 per day from $2.14 to $3.00. In estimating shingling an
allowance will be necessary for waste; this should be about 5 per cent on plain roofs and 8 to 10
per cent on roofs with valleys, or dormers.
Slating.
Fig.
16.
many hips,
made
in
Slates are
Slating.
different sizes
from 6 x 12 up
to
16x24 and
work.
They
are laid
:
with
than ex-
posure, that
is
44
ESTIMATING
gives the gauge to which slates should be laid, Fig. 16; this lap is usually 3 inches, so that the exposed length of any slate may be
it,
found by subtracting this lap from the length of the slate and dividing by 2. This exposure multiplied by the width of the slate gives the
exposed area of the slate, and the number of slates in a given area may be found by dividing the area in square inches by the exposed area of the slate.
Example.
a roof
(14
in.
if
8-in.
in.)
-3
2
5J
in.
in.
x 5J in.
44
sq.
in.
327.
44
sq.
In measuring a slate roof it is usual to allow an extra width of from 6 inches to a foot, according to localities, on hips, valleys, eaves,
and wall
of roof.
work
involved.
made
for towers
and
all
varied forms
Quantities.
roofing
is
The number
533
6 x 12
7 x 14
10 x 20
11
165 138
377 277
214
x 22
8 x 16 9 x 18
12 x 24
114 83
14 x 28
:
10
1
in.
x.16 in.
$ 7 50
.
Labor
Nails
day, slater
3 50
.
.15
.
.50
.15
SiTTso
Tin
roof per sq. ft, average Gutters per ft., galv. iron Galv. iron conductors per ft., put up
roof, plain per
$0.11
.90
.18 to .25
50 00 roof, with battens per square 6 00 Gravel roofing, 5-ply per square Zinc flashing, 1J cents per inch of width, per foot.
.
.
Copper Copper
square
40 00
.
ESTIMATING
Tiles.
45
Where a
special feature
is
to
be made of the
roof, tiles
are often used but these are found in t>ach a variety of shapes, sizes, and prices, that a roof of this sort should always be given to a roofer
to estimate.
Metal Roofs.
Copper or
tin is generally
metal covering is desired. Copper roofs, if steep enough to show as a feature of the building, are usually laid with ribs over battens. This
Copper roofing will cost from $35.00 to $40.00 per square. Flashings around skylights and balustrades, 30 to 50 cents
a lineal
foot.
For a cheaper metal roof, tin is generally used this may be used on steep or flat roofs. Tin for roofing should be painted on the under side and carefully soldered on the top.
;
roofing will cost from $10.00 to $12.00 a square. Composition Roofs. For flat roofs, a composition of tar
Tin
and
is
often used;
the cost of this depends upon the number of layers of paper and "moppings" of tar required, but a 5-ply roof will give good service
and
will cost about $6 00 a square. Gutters and Conductors. Gutters and conductors are both
.
made of wood or metal, metal being preferred in metal gutters copper and galvanized iron are used.
Copper gutters
Goosenecks
will cost
all cases.
For
about
.
Copper conductors
. .
$1 25 a 50 to .75 a
.
lineal foot.
foot
5 00 to
00 each
1
1
00 each
00 each
Galvanized iron gutters will cost about 90 cents a lineal foot, and conductors, 18 to 25 cents a foot according to size.
PLASTERING
Plastering is measured by the square yard and in 2-coat or 3-coat work. In taking off plastering it
is
is
usually done
customary
to
deduct only one-half of the area of openings to allow for the extra
work
46
In some
ESTIMATING
localities
not generally followed. Narrow strips, such as chimney breasts, if less than a foot wide, are generally called a foot. Round corners, beads, and arrises must
lineal foot.
Raking
at
work
should be charged at two prices and domes, groins, and intersecting Cornices are taken by the square foot of girth soffits, at three prices.
with enrichments charged separately by the lineal foot. Lathing. Lathing is generally included in the plasterer's price although put up by a different set of men. Lathing is estimated by
the square yard or by the thousand laths, the price being $2.75 to S3.25 a thousand.
Labor.
Two
do from 40
to
50 square yards of three-coat plastering, or 60 to 70 square yards of two-coat work, in a day of 8 hours, and 1,200 to 1,500 laths makes a 100 cq. yds. of lath and plaster will cost day's work for one lather.
about as follows, for two-coat work:
1,500 laths at $4. 75 per Ibs. 3d. nails at $3.20 per cwt.
laths
.
10
$ 7.12 32
.
Labor on
6
1
4 50
.
4 80
.
.24
1.80
15 00
.
4 50
.
Cartage
1.00
$39.28
Cost of a square yard of two-coat work, $39.28
to
-r-
100
39
40 cents.
This
is
done
in the
a price which is on the increase and, while plastering is country towns as low as 35 cents per yard it will not be
ESTIMATING
For three-coat work we may take the following schedule: Laths and putting on, as above $1 1 94
.
47
6.24
.32
Slbs.hairat .04
1J
loads sand at $1 80
.
2 70
.
1.70
20 00
.
6 00
.
1.00
$49.90
cents. sq. yd. of three-coat work, $49.90 In some portions of the country a set of rules has been of plasterer's work which are in the adopted governing the valuing
Cost of a
-^-
100 = 50
Rules.
main
"
as follows:
First.
Measure on
all
walls
and
or any openings of plastered, without deducting any grounds extent than seven superficial yards.
Second.
Returns of chimney-breasts, pilasters, and all strips of as twelve inches plastering less than twelve inches in width, measure the down to is finished and where the base, surbase, wide; plastering
or wainscoating, add six inches to height of walls. Third. In closets, add one-half to the measurement.
ceilings
Raking
ceilings,
and
soffits
domes or groined
Fourth.
feet of interior
the ground than the first twelve feet, add five per cent; for outside work, add one per cent for each foot that the work is done above the
first
twelve feet."
Stucco-work
less
is generally governed by the following rules; viz., than one foot girt are rated as one foot, over one
superficial.
When work
For each
one-fifth. run same cornice, add one foot to length of cornice, and, for each external angle, add two feet. All small sections of cornice less than twelve inches long
add
For raking
price;
cornices,
add one-half;
circu-
work double
domes and
48
ESTIMATING
all
For enrichments of
higher the work
is
The
add
first
to
it
above ground, the higher the charge must be; at the rate of five per cent for every twelve feet above the
twelve feet."
PAINTING
Painting taken solid to
is
make up
estimated by the yard, doors and windows being for the extra labor of cutting in the sashes and
mouldings.
Railings, fences, grilles,
and similar surfaces are taken solid. one day will cover 100 yds. of outside work one
Ten
make a
On
day's work. first coat, one pound of paint will cover about 4
sq. yds.
and
One pound
Shingle stains require a gallon for every 500 shingles if dipped two-thirds in, and for a brush coat after laying," a gallon will cover
about 200
1 1
feet of surface, or
1500 shingles.
gallon of priming color will cover 50 yards will cover 50 yards gallon of zinc white of will cover 44 yards white gallon paint gallon of black paint gallon of stone color gallon of yellow paint gallon of green paint
will cover
1
1 1 1 1 1
will cover
will cover
will cover
gallon of emerald green will gallon of bronze green will cover 75 yards
The
weight on various
SECOND COAT
Red
lead
112 221
100 Ibs. of
252
White lead
*The figures represent square feet covered by gistency, applied evenly with a brush.
324
paint of the usual con
ESTIMATING
FIRST COAT
49
SECOND COAT
Oxide of zinc
378
453
756
453
Red oxide
540 872
540
412
ON METAL
Red lead
White lead
Oxide of zinc
477
648
1134
Red oxide
870
1417
1296
ON PLASTER
Red lead
White lead (on Oxide of zinc
sized wall)
324
362
594
(unsized wall)
55
99
The
INSIDE
coat per sq. yd. 2 coats per sq. yd. 3 coats per sq. yd.
1
WORK
$0.12
.20
.
25
1 1
1
coat shellac per sq. yd. coat size and 2 coats paint
.10
.20
.30
INSIDE FINISH
1
filler,
coat varnish
$0 20
.
filler,
filler,
.25
coat
"
.30
.25
1 coat
1 1
coat
coat
paste "
filler, 1
filler,
.30
.35
"
filler,
50
ESTIMATING
Tinting walls in distemper will cost 15 cents per sq. yd. for small amounts and 10 cents per sq. yd. for 50 yds. or more. Finishing hard wood floors with filler, shellac, and 2 coats of varnish or wax finish
will cost
30 cents per
sq. yd.
OUTSIDE PAINTING
new work per sq. yard new work per sq. yard 3 coats new work per sq. yard
1
coat
$0.10
.18
.
2 coats
25
SANDING
2 coats paint, 3 coats paint,
coat sand per sq. yd. coat sand per sq. yd. 3 coats paint, 2 coats sand per sq. yd.
1
1
$0 28
.
35
.50
Painting on brick will cost 12 cents per yard for the first coat, but subsequent coats will cost no more than on wood. Tin roofs can be painted one coat for 5 cents a yard.
a brush coat in addition costs 50 cents.
pair for
1000 shingles dipped two- thirds of their length will cost $3.00 and Blinds are rated at $1.50 per
an average
size.
HEATING
The
heating of a building
is
generally
made
the subject of a
methods for house heating are, the Hot Air Furnace, the Hot Water Boiler, or the Steam Boiler. Sometimes a combination system of hot air and steam, or hot air and hot water is
used.
who
follow this particular branch of construction. the heating will range according to the system 12% of the cost of the building, as follows:
6%
to
6 to
ESTIMATING
These
self.
51
figures are
is
reliable
way
to obtain
it-
by taking
The hot air heating of an ordinary house can Quantities. be approximated closely by the builder on the basis of cubic contents to be heated; and the area of piping and capacity of the furnace
can be approximated by means of the following general- rules To determine the size of pipe for any room, find the cubic contents of the room in cubic feet and divide this by 25 for rooms on
:
the
first floor,
and by 35
for
third floors.
the cold air box at least j of the combined area of pipes, none of which should be smaller than 7 inches in diameter.
Make
Example.
of seven
may
be as follows:
FIRST FLOOR
Parlor
12 x 15 x 9
sq. in.
ft.
ft.
divided by 25
divided by 25
81 sq.
= =
10
65 58
or 9
ft.
Hall
g'x 20 x 9
ft.
Add 40%
pipe
making
ft.
in.
in.
Dining
Room
14 x 15 x 9
ft.
divided by 25
76
SECOND FLOOR
Chamber Chamber Chamber
Bath
13 x 15 x 8J
11
x 12 x 8
14 x 16 x 8J
= = =
1658 cu.
ft.
-=-
35 35
1122 cu.
ft.
-r-
1904 cu.
ft. ft.
-j-
35 35
Room
8 x 10 x 8i =
:
680 cu.
-5-
= = = =
48
sq. in. or
in.
in.
pipe
pipe
32
55
sq. in.
or 7
20
in. in.
each
156 sq.
in.
64
'
sq. in.
in.
in.
pipes 50 pipes 38
sq. in.
sq.
in.
in.
396
the size of the furnace and
From
this scale
we can determine
52
ESTIMATING
furnace to carry say 400 to 500 sq. feet of pipe area would from $100 to SI 25. The labor on pipes, registers,
to $24.
The cost of piping will depend on the distances to run but the material can be estimated as follows:
Round
from A. A. charcoal
plates, as follows:
SIZE OP PIPE
ESTIMATING
Zinc per
Ib.
53
$0.10
Ib.
.
Wrought
iron per
04
09 09
Ib.
sq.
ft.
.08
Register box netting per sq. ft. Asbestos paper at 1J Ibs. per sq. ydo
.05 .05
Figure cold air supply f combined area of piping. Register grilles take up J of area of register.
Locate registers nearest convenient point to furnace, inside Locate furnace so that all pipes will be as part of room preferred.
nearly equal in length as possible.
Estimate pipes by lineal foot, but elbows and dampers rately, also registers with boxes and borders.
sepaair
partitions.
Radiators are
number
Radiation.
The amount
so
depends upon
many
of radiation necessary for each room varying conditions that all rules are in a
way approximate.
Certain formulae
in ordinary cases,
may
The same is true of making the estimates of hot water or steam and the contractor should in all cases have the job figured by an
expert.
may
be determined
ESTIMATING
from the cubic contents of the rooms to be heated by the following tables which give the proportions of one square foot of radiating
surface to the cubic contents of the various
rooms
in cubic feet.
STEAM
ONE SQUARE FOOT OF RADIATION WILL HEAT
ESTIMATING
or cesspool,
if
55
if
end of
the soil pipe, and take off carefully every pipe with its fittings, which should be itemized carefully as this data will be useful in getting
at the
amount
be estimated by the lineal foot, allowing in each joint f of a pound of lead for every inch in diameter
Soil Pipes.
of the pipe. List prices of pipe and fittings can be obtained from the dealers, which are subject to discount; these vary from time to time, but the
mon
present discounts will be found to bring the prices of the materials about as follows
:
more com-
DRAINAGE
4-in. extra
3-in. extra
2-in. extra
heavy heavy
soil
soil soil
ft.
30
22
15J
ft.
ft.
For
fittings
4-in.
2.00
cleanout
4-in. lead
bend
50 1-50
.
.50
.20 .22
Solder per
Ib.
WATER SUPPLY
40
gal.
1-in.
1-in.
$15.00
.60
.09
|-in.
i-in.
1-in.
.06
.05
1
.50
f-in. stop
i-in.
Sill
.90
.
80
cock
1.00
For
fittings,
WATER
1
cu. ft
ft.
1 cu.
56
ESTIMATING
1 cu. ft.,
1 1
62.321
Ibs.
1004
1692
oz.
Ibs.
Ibs.
cu. yd.
in.
1-foot cylinder
8J 49.1
.028
Ibs.
1-inch cylinder
Ibs.
in.
depth
in feet
x 433.
Contents in cu.
x 2375
barrels.
Head
of water
pressure in Ibs,
per sq.
in.
x 2.31.
in.
Number
Diam.
inches 2 x .04.
Supply for one person is 15 gallons a day. Actual use 6 gallons to 12 gallons. Water 34 feet high has a pressure of 15 Ibs. per sq.
in.
equal to atmosphere.
CAPACITY OF CISTERNS
In Gallons, for
Each Foot
in
Depth
DIAMETER
IN
FEET
Herbert
I1L
Roofs Covered with Shingles Stained Green. All Outsldt Woodwork Staim-d Dark Brown. No Paint on Outside except on Sash.
L,ath.
RAN
Built in
f904.
House, Constructed the Same as if for All Year-Round Use, and Provided with Heating Plant.
HOUSE AT WASHINGTON, ILL. Herbert Edmund Hewitt, Architect, Peoria, 111. Cost, about $4,500. House was Built for a Summer
bitf
ESTIMATING
Enamelled iron lavatory complete
5-ft. G-in.
57
$25.00
.
to
$40.00
enamelled iron bath complete $60 00 to $100.00 Bath tub only $25.00 to $35.00
One
part
parts
$15.00
$30.00 $45.00
to to to
$18.00
$35.00
Two
Three parts
List prices of fittings
to large discounts,
$60.00
may
be obtained from
all
dealers, subject
constantly changing.
Having made a complete list of pipe, fittings, and fixtures, the labor of construction of an ordinary job of plumbing will run from 20 to 40 per cent of the cost of materials.
Labor.
GAS FITTING
As
to cost.
in
plumbing so
in
gas
fitting,
cost in fixtures,
makes
it
piping only, of an ordinary house will cost from $1.75 outlet, and the whole outfit should cost from 3 to 5 per cent of the cost of the house.
to $2.00
The
an
50 03
.
.
04
05
J-in.
main
.08
ELECTRIC
WORK
The
for electric lighting and bells, but fixtures are generally left to be provided for by a later agreement, as there is such a great latitude
in selection
and
cost.
:
wiring one of two systems is usually employed the conduit system, where the wires are all run in pipes or conduits, and the knob and tube system, where the wires are run in the clear
electric light
For
space between timbers, secured to porcelain knobs, or passing through short tubes of the same material.
58
ESTIMATING
In general, the rough wiring of a house may be reckoned at $4.00 and $2.00 per outlet for knob and tube
for every time the wires are
fixtures.
work.
This
is
These vary
make and
finish.
.00.
good rotary switch can be had at from 90 cents to $1 Push button switches from $1.00 to $1.10.
to
40 cents.
manufacturer, and should bear the label of inspection acceptable to the local Insurance board.
The
cost of wire will vary with the gauge and the insulation but work should cost, for No. 14 wire, 2 cents a foot.
It is well to
house, the
remember that, in electric wiring, the larger the more per outlet the wiring will cost. This seems contrary
but
is
to expectation
to
length of wire.
Bells.
to the plan
ten,
bell.
and choice of the owner. For an ordinary house the number would range from six to and the cost should be from $18.00 to $25.00 or about $3.00 per
Alterations on this Plaster House Completed in the Spring of 1906 at a Cost of $8,000. Taking into Consideration the Changes Made In the House and the Work Pnt in on Repairing and Raising the Roof, etc., an Entirely New House of this Size Could be Built for Nearly this Sum-Certainly within $9,000.
ESTIMATING
PART
The
taking-off of quantities
II
and making-up of an actual estimate, This is done, as is the end toward which our efforts are now directed. has been said, in a number of ways, no two persons arriving at the same conclusion or following exactly the same methods. To give the
student a practical idea of how estimates are made, we shall now demonFor this purpose, strate the method of procedure in an actual instance.
wooden Colonial residence of which the and the method of making these, are fully and working drawings, plans described in the course on "Architectural Drawing," and of which the details are also described to a certain extent in the chapters on "Building
we
Superintendence;" and shall proceed at once to take and make up an estimate of cost.
is
order in which they occur in the specification or in the operation and ending with the
Painting.
Two methods of
may may
He
take off simply his own particular branch of the work, relying on each sub-contractor to give him a price for the detailed portions of the work; or, if he is a general contractor, he may, with the requisite
knowledge of general building operations, take off all the quantities, pricing them according to his knowledge, and may submit his prophis own figures. The latter method requires and is followed great experience, generally by large contractors, who have in their employ men whose business is mainly to take off quantities and make up estimates.
osition
on the basis of
The
following estimate has been carefully made up on the basis .as to prices of materials and labor. In
actual practice, details of more or less importance will vary in different localities and among different contractors; but the example
fully.
&
fcl
a?
62
ESTIMATING
ESTIMATE
OF
FOR GEORGE
A.
JONES, ESQ.
$15.00
10.00
$25.00
EXCAVATION
Excavation is priced by the cubic yard; and in this to which the excavated material must be carted distance the regard, In the present case, the material will be an important consideration.
is
NOTE.
no unusual conditions
will
have to be considered.
As before mentioned,
foot larger all
it is
sill
usually well to dig a cellar at least a line, so that plenty of room may be
afforded to the
mason
This should
be done
As
lies entirely
separately,
remembering
wall,
that
it
will
extend
below the
making about 8
feet of height.
QUANTITIES
Cu. FT.
....
336
.... 272
; .'.
.
83-
...
140
....
.
544
328
LLLVAT1QNl/ee/tr~
Pig. 3
64
ESTIMATING
Brought forward
1 1
,784 cu.
ft.
MISCELLANEOUS QUANTITIES
Piers
2ft.
in.
X X X
X
ft.
in.
X
X
ft.
in.
12
168
Trench
185
ft.
in.
1 ft.
in.
1 ft.
in
308
129
Area
14ft.
in.
2ft. Sin.
X X
X X
3ft.
Gin
Gin
Drains
123
ft.
in.
ft.
in.
1ft.
645
242
Cesspools 5 ft. 6
in.
ft.
in.
8
8
ft. ft.
in in
lOft.Oin. XlOft.Oin.
800
120
Dry Wells
6
2ft.
in.
2ft.
in.
oft.
in.
Total,
TCT96
$262 50
.
cu.
ft.
ft.,
STONEWORK
LS IN
4
\
yt-
-.'t
1
pi
-r
ESTIMATING
Brought forward
23ft.
in.
480 cu.
.316
ft.
12
ft.
ft.
28
6ft.
10ft. Oin.
8ft.6in. 9ft.0in.
25
6
Oin.
in.
23
Oin.
X X X X X X X X X X X X X X X X
-r-
8ft. Sin.
6ft.Tin. 8ft.3in.
6ft. Tin.
ft.
in.
6ft. Tin.
X X X X X X X X X X
......
......
132
1ft.
1ft.
8 in
6 in
385
59
Ift.Oin. ......
66
93
123
Ift.Sin
Ift.Sin Ift.Sin
1 ft.
2T4
66
8 in
Ift.Sin. ......
252
14
PIERS
2ft. 6 in. 5ft. 6 in.
2 2
ft.
ft.
in.
in.
ft.
in.
ft.
in.
12ft. Oin.
3ft. 6in.
12
ft.
Oin.
ft.
in.
X X X X X
X
Ift.Oin
1 ft. 1 ft.
Oin..
in
14
4
84
..
2ft.
Oin
Oin.
ft.
84
T3
AREA
14ft. Oin.
3ft. 6 in.
1ft.
6 in
Total,
2,519 cu. ft
2,519 cu.
ft
25
UNDERPINNING
ESTIMATING
Brought forward $
101
perches of mortar walls, at $4.25 14J perches of underpinning, at $6 50
.
.
67
36 00
429 25
.
94 25
.
$559.50
6ft.7in.
l,264sq.ft.
1 40
$ 56.00
CESSPOOLS
LEACHING CESSPOOL
23
ft.
in.
ft.
in.
1 ft.
in.
282 cu.
ft.
-h
25=
1 1J
perches.
11J-
perches at $3.50.
,
$39.65
2.50
42. 15
Cover
TIGHT CESSPOOL
11
ft.
in.
8ft.
in.
92
sq.
ft.
15 bricks
1,380 bricks.
$27.60
Ironcover
3.00
30.60
ft.
in.
11
ft.
in.
-r-
25
=
27.50
perches
11 perches at $2.50
DRAINS
171
ft.
at $.20
14bendsat$.30
$34.20 4.20
38.40
$754.15
BRICKWORK
Find the number of bricks in a foot of height in each or pier, reckoning five courses to the foot of height. chimney
NOTE.
CELLAR
35
107J 55
X X X
8 8
TT
f OG, - GEO&GE.-A-JDM&J0UILrtE-
60IL.DWJ
Fig.
5.
cx
k i
ESTIMATING
Brought forward
71
1,580 bricks
VERANDA PIERS
58J
10
585
6 in
in in
CHIMNEYS
107J 105 35
35
127^ 35
57i
127J
X X X X X X X X
ft.
700
1,155
lift. lift.
4ft.
385
157
701
Gin
6 in
ft.
19ft.
4ft.
Oin
665
Oin Oin
230
1,402 7,560 bricks
$ 151 20
.
11
ft.
Summary
7,560 bricks at $20.00 per M., laid ...... 3 fireplaces at $30.00 each
.
.
90.00
9.10
10.80
FLUE LININGS
36ft.,
26ft, 13 9
68ft.,8J
in.
13
in.,
at
$.35
in.
round, at $.30
13, at
$.30
20.40
$ 281 50
.
CONCRETING
SQ. FT.
23
3 15
ft. ft.
ft.
in. in.
in.
4ft. Oin.
X X X X
38
9
in
874
28J 390
6 in
in
26
7ft.
Oin
28
1,320 sq.
ft.
$88.20
PLASTERING
NOTE. Take off square feet of plastered surfaces, and deduct one-half of the openings, after reducing to sq. yds.
CELLAR
23
9
ft. ft.
SQ. FT.
Oin.
in.
X X
38
3
ft. ft.
Oin.:
in
874
J
28
Carried forward
902
sq.
ft.
bourne - Artefact
9*
ba/ton.
TJWoa
botlding
/!
FiRJT-FLOOR,01
Ocedegf hi
.
234007
. 1 1
-"ooA.-
8.
ESTIMATING
Brought forward
15
ft.
73
902 403
sq.
ft.
in.
30ft.0in.
X X
26
ft.
in
8ft.0in
240
1,545 sq.ft.
FIRST STORY
25ft.0in.
11
ft.
ft.
in.
25
Gin.
in.
490 ft.
X X X X
40ft.0in
3
ft.
1,000
in
33
16
ft. ft.
Gin...
in
420
4,410
5,863 sq.
ft.
16
ft.
in.
520ft. Oin.
X X X
40ft.
in
1,000
19ft Oin
8ft. 6 in
313
4,420
5,733 sq.
ft.
sq.
ft.
OUTS
32 doors, average 40 sq. 34 windows, average 15
1,790 sq.ft.
13,141 sq.
ft.
ft
1,280
sq. ft
510
1,790 sq.
ft.
+
sq.
2
ft.
==
=
=
895
sq.ft.
ft.
less
895
12,246 sq.
.
sq. yds., at
$ 40
$ 544 40
.
CARPENTER WORK
FRAME
Ft. B.
M.
136 74
"
250
188
"
"
4 4
X X X X X
in. sill
564
272
Gin.
"
10
494 500
376
2,206
2,206ft. B.
M.
at $38.00 per
M
UNDER FLOOR
"
$ 83.82
Oin.
40ft. Oin.
1,000
Carried forward
~$
83.82
o'ra34i7es
of
I I I I
Fig.
9.
ft
Au
OF-
0*2
of
34- >5
Fig. 10.
OF THE
UNIVERSITY
OF
76
ESTIMATING
Brought forward
llft.Oin.
$ 83 82
.
26
ft.
in.
X X
3
16
ft.
in
33
ft.
6 in
429
1,462 sq.ft.
1,462 sq.ft.
$ 136.70
in.
16
ft.
in.
421
sq.
ft.,
at $10.50
per square
44 21
.
Oak
25
ft.
in.
llft.Oin.
X X
40
3
ft.
in. in.
ft.
33
1,033 sq.
ft.
1,033 sq.
ft.
$ 206 .60
PORCH FLOOR
6ft.
in.
in.
ft.
X X
llft.Oin. 5
ft.
66 45
sq.ft.
"
in.
PIAZZA FLOOR
26
ft.
in.
in.
X X
9
7
ft. ft.
in. in.
----
234
144
"
y
ft.
"489 sq.
ft.
60.39
in.
X X
25
17
ft. ft.
in in
340
$ 241.20 $ 135.34
THIRD STORY
l,340sq.
ft.
in.
X X
16
ft.
in.
16ft. 6 in.
X X
2 sides
990 sq.
ft.
2 sides.. 1,122
" "
$ 352.07 $
FLASHING
.TiN ROOF, FRAME AND BOARDING
21ft.0in.
40.00
7ft.6in
-PLAN-Or-THlRD-FLOOR-cS-'ROOFo
l a T. i.i
4-\5 iii
7 S
i
Fig. 11.
78
ESTIMATING
Brought forward Gin
6 in 6 in
$1 ,300 33
.
19ft. Oin.
llft.Oin.
14ft. Oin.
X X X
6ft.
5
9
ft.
ft.
60
ft.
474sq.
172
6
3
ft.
99.16
Oin.
ft.
ft.
in.
in.
X X X
20ftOin
10
ft.
ft.
Oin.
in.
X X
3,440 sq.ft. " " 130 " " 2 sides 54 _ 3,624 sq.ft.
2 sides
3,624 sq.
ft.
$ 300 79
.
INSIDE STUDDING
180
196
ft.
in.
in.
ft.
28ft. Oin.
X X X
8 ft. 6
8ft.
in
1,666"
224
"
"
Oin
"
3,510 sq.
ft.,
$ 140.40
CLAPBOARDING
44
6
2
ft.
in.
ft.
ft.
in.
in.
39 ft. Oin.
X X X X
19
ft.
in.
8
9
19
ft.
ft. ft.
O'in.
in.
Oin.
X X X X
2 sides
1,
672
96
sq.
ft.
2 sides 2 sides
36
1,482
2 sides.
" "
3,286 sq.
ft.
ft.
25.38
$ 235 85
.
MISCELLANEOUS
DORMERS
6,at$50each
$ 300.00
MAIN CORNICE
180
ft.,
at $1.25 per ft
225.00
BALUSTRADE ON ROOF
96 ft, at $0.50 per ft 18 posts, at $1.50 each
Carried forward
$48.00 27.00
75.00
$2,676.53
ESTIMATING
PIAZZA FINISH
Cornice
79
102
ft.,
204.00
Columns
9 in place, at $10.00 each
90.00
20.00
Corner Pilasters
$38.00
12.00
Small Posts
8J,
at$1.00each
50.00 25.00
OutsideSteps
Lattice
55
ft.
in.
1 ft.
in.
82J
sq.
ft.,
at $.15
ft
12.37
11.10
25 .00
BULKHEAD STEPS
CORNER BOARDS
252
ft.
in.
Sin.
168
persq.
ft.
50.40
WATER TABLE
117J linear ft, at $.20 per
ft
23.50
$11 20 each
.
$ 44 80
.
$5 25 each
.
21 .00
in. in.
X X
at $13.
33 each
$106.64
80.08
$ 11.44
at $11 .44
each
2 windows, 2 2 windows, 2
6
6
in.
in.
X X X
4ft 6
5 3
ft.
ft.
in
in.,
6
9
in. ,
24 00
.
22 00
.
in., at
$18 24 each
.
36 48
.
window, 3
ft.
4 in.
ft.
in.
16 57
.
-PLATE,
CH
4*8
PiATI
(2)
s:
S
H-P.
-LEDGERBOARD-
5*
H.P.
LEPCiFR-
I
I
-PlATE
TWO
2A-4-"
-FLOOR. o 12 3
of
Ii III
I
-t
I
&
I
e 7 e.
I
Ij^-^r-t
Fig. 12.
ESTIMATING
81
1
1
window, 3 window, 2
4
6
in. in.
2 windows, 3
/.
.
4 in.
6
X X X
X
ft. ft.
ft.
6
5
5
5
6 in. (birch
in.
14.45
(whitewood), at
$13.33each
ft.
26.66
45.76 56.33
4 windows, 2
.-.:
in.
$11 .44each
side
and top
ft.
lights
,
in.
in.
REAR DOOR
2
ft.
10
in.
ft.
6 in
13.46
CELLAR SASHES
12, at $3.25 each.
39.00
INSIDE FINISH
Coal bins in basement, 240 sq. ft. Studding 240 sq. ft. at $3 00 per square $ 7 20
.
"
"
"
11.40
3 25
.
21 85
.
in.
1 ft.
in.,
25
ft.
ft
15 50
.
BASEMENT PARTITIONS
46
ft.
in.
ft.
in.,
368
sq.
ft.,
32 20
.
26.61
ft
10. 12
10.00
FIRST STORY
in. X 7 ft. 6 in. (whitewood and birch finish) doors (whitewood and birch finish) pair sliding 40 ft. birch base at $.20 per ft 1
door, 2
ft.
20 67
.
53 52
.
8.00
22 67
.
door, 3
ft. ft.
in. in.
door, 2
10
X X
7 7
ft.
in.
in.
ft.
20 67
.
WOOD CORNICE
56 56
ft.,
ft.
IN DINING
ROOM
in.
X
IN
in. (birch), at
$.48 per
ft
ft
$26 88 3.36
.
30.24
WOOD CORNICE
82 ft., 6
in.
LIBRARY
6
in.
ft
$39.36
$4,035.19
82
ESTIMATING
Brought forward $39.36 $4,035.19 4.92 44 28
.
at $.06 per ft
OAK BASE
72ft. at$.20perft
1
14.40
7
ft.
door, 3
ft.
in.
6 in (whitewood)
12.59
56 33
.
VESTIBULE DOOR,
side lights
WHITEWOOD BASE,
Sdoors (N. C.
101
ft.,
at $.10 per
10 10
.
pine),
at$9.48each
47.40
100 00
.
50.00
26.00
MANTELS
Allowance
$125.00
Labor of setting
6.50
$131 .50
SECOND STORY
16 doors stock, at $9.48 each
1
$151.68
10.00
archinhall
20.00
'.
17.50
linen closet
25.00 20.00
linen closet
THIRD STORY
2 doors, finished one side, at $7.04 each 1 closet door
.
.$
14.08
7 04
.
Tank
Finished
Base, 14
floor,
ft.,
.'..'.
10.00
100
sq.
ft
ft
7.25
1
at $.10 per
.40
CONDUCTORS
120 ft., at $.13 per ft, put up.
.
$15.60 6.00
$ 21 .60
35 00
.
50 00
.
[NSURANCE
Total cost of Carpenter Work
10.00
$4,928.34
-ALU /"XAltt
RAFTER5
Z*(,'-2(>O.
TO BE 2X7"-2O'-O-C
PORttER RAfTERS
OF- ROOF1 1 1
r?TT/^f-*.
84
ESTIMATING
STAIRS
FRONT STAIRS
128ft. spruce,
120ft. whitewood,
85
ft.
30 ft.
at$30per at$70per quartered oak, at $150 per M. mahogany rail and turn
3.84 8.40
.......
12.75
24 00
.
25.00
15.75
66
.75
1
.
25 scotias at $.03
Nails, glue, etc
each
00
Labor
56.00
$148.15
BACK STAIRS
First Flight
$ 1.65
M
:
. .
6.30
48
.75
Labor
Second. Flight
16.00
25.18
$ 1.62
6.60
.51
75
75
Ipost
4ft. rail,at$.12iperft
50
.75
Labor
17.00
28.48
CELLAR STAIRS
40 ft. spruce, at $30 per 75ft. N. C. pine, at $60 per
Post
Rail
$ 1.20
4.50
50
1.20
Labor
5.00
12.40
$214.21
Framing
Total cost of Stairs
.
.
2 00
.
$216 21
.
ESTIMATING
85
HARDWARE
NOTE. This estimate is based upon a fair quality of hardware, the butts being of bronze-plated steel, the knobs of struck-up bronze metal, with rose and escutcheon combined; the sash fasts of solid
bronze metal, also
lifts
and catches.
BASEMENT
BULKHEAD, OUTSIDE
2 pairs extra heavy galv. $.85 each
hinges,
8-inch at
$1 .70
$ 10 each
.
20
Labor
1.00
BULKHEAD, INSIDE
1 1
pair heavy
T hinges, 8-inch
15
thumb-latch
10
Labor
50
THREE DOORS
3 pairs butts, 3
S^-inch, at
$ 15 each
.
45
3 sets locks at
$.45 each
1
1
.35
Labor
.50
HINGED WINDOWS
12 pairs butts, l^-inch, at
$ 06 each
.
72
12hooksand eyes,at
12 buttons, at
$.02each
$.02 each
.24 .24
Labor
1.50
$ 9.65
FIRST FLOOR
ENTRANCE DOOR
H pairs butts, 4i
1 set locks,
4J-inch, at
$.38 each
$ .57
9 50
.
bronze metal
Labor
2.00
3 J-inch, at
$ 30 each
.
2.10
7.00 5.25
$1 .OOeach
Labor
$9 65
.
ETC
mj
3IX:TION THRO'-KITCHEN -PANTRYs OCALE-
OF-
PANTRIES if
5CALJ,
3
I t I
- DETAIL
1?OT.
I
9
i
6
I
Fig. 14.
ESTIMATING
Brought forward $26 .42
.
87
$9 65
SIDE ENTRANCE
1J 1
DOOR
X
:
4 J-inch, at
:
$ 38 each
.
57
2.25
1
Labor
.00
ft.
in.
in,
Double
3.50 2.50
2.00
Labor
$.45 each
2.70
.
Si-inch, at
$ 15 each
.
90
Labor
4.00
BACK DOORS
1 set
4j-mch, at
$ 20 each
.
30
2.25
1.00
Labor
ICE-CHEST DOOR
1
pair butts, 3
3-inch
. . . .
!........,
:
40
.60
1
.
1 1
IH lever,
50
Labor
50
CHINA CLOSET
2 pairs glass doors 2 pairs butts, 2 J X 2 J-inch, at 2 elbow catches, at 2 cupboard catches, at doors pair* cupboard
$ 26 each
.
52
12
$ 06 each
.
$ 15 each
.
30
20
1
,
2 pairs
1 1
butts, 2 J
2^-inch, at
$ 10 each
.
elbow catch
.06
.15
cupboard catch
20 drawer-pulls, at
$.06each
,..,..
1.20
Labor
2.50
PANTRY
4 cupboard doors 4 pairs butts, 2 J
2^-inch, at
$ 10
.
each_
.40
$9 65
.
ESTIMATING
Brought forward $57.84 60 $ 15 each
.
$9.65
4 cupboard catches, at
1
bbl.
swing
.75
10 drawer-pulls, at
$.06each
...
t
.60
Labor
2.00
WINDOWS
15 sash
fasts, at
lifts,
$.30 each
'.$.06 each
4.50
1.80
7 .50
30 sash
at
Labor
CASEMENT WINDOWS,
4 pairs butts, 3
3-inch, at
$ 50 each
.
2 00
.
$1.00 each
$.45 each
2.00
.90
Labor
1.00
$81.49
SECOND FLOOR
SIXTEEN DOORS
16 pairs butts, 3J 16sets locks, at
3Wnch,
at ..... .$.30
each $ 4.80
$.90each
14.40 10.40
Labor
WINDOWS
14 sash
1
fasts, at
,
$.30each $.06each
:
4.20
35 1.68
.20
sash fast
lifts,
28 sash
at
2sashlifts,at
$.10each
Labor
Six
7.00
IN
DRAWERS
Labor
LINEN CLOSET
$.06each
.72
.25
12 drawer-pulls, at
$44.00
BATHROOM
1
pair butts, 3J
3i-mch
(nickel-plate)
1
40
.25 .75
1 set locks*
(nickel-plate)
Labor
$ 2.40
ATTIC
Two DOORS
2 pairs butts, 3i 2 sets locks, at
3J-mch,at
.$.12 each.
.$.24
$.45 each
90
...1.00
Labor
$137.54
j/EOTIO/1
THRO'
Fig. 15.
AND
POT
on
ESTIMATING
Brought forward $2 14
.
91
$137 54
.
20 70
1
Labor
.00
WINDOWS
8 sash
fasts, at
lifts,
. .
$.30 each.
.
.
.
.2.40
16 sash
at
$.06 each
..
96
.4.00
.3.00
1
Labor
6doz. H.
.05
Labor
Total cost of Hardware put on
.2.50
$ 17.95
$155 .49
HEATING
FURNACE
1
(28-in. firepot)
22
8-in.
at
$.091b.
REGISTERS
1
14
4 9
at
X X
box and
netting,
4.72
6.28
box and
box and
box and
netting,
$1.57 each
netting,
4 8
at
X X
$1.19 each
10-in. registers, stone,
4.76 4.60
3 24
.
4 8
at
,
netting,
$1.15 each
PIPING, including dampers, collars, and elbows 12 ft. 14-in. tin pipe, at $ 27 per ft. " "
. .
64ft.9-in.
at
$.16" "..
"
10.24
278ft.7-in.
"
"
at
$.10
"..
27.80
.50
(6 Ibs. asbestos
30
Ibs., at
$.05 Ib
2.60
$ 195.69
Office expense
profit
48.92
Carried forward
$244.61
$244 61
.
-AT-fclCGEDAlX-'/'VO
K7H- GEORGE.-
AjJOMEJ- -
JQj-
AKCMITICT-
Fig. 17.
ESTIMATING
Brought forward
.
93
$244 6 1
$4 80
.
LABOR
Measuring and laying out
risers,
man 1 day
Erecting risers, man 2 days, helper 1 day .... Laying out and erecting cellar pipes and fur-
12 00
.
19 20
.
4.80
10.00
Cartingand expenses
Total cost of Heating Apparatus
50.80
$ 295 .41
PLUMBING
WASTE AND
SOIL PIPES
2 4-in. lead bends, at$1.10each 2 4-in. sleeves, at $.65 each " at $.28each 5 2-in. 2 3
1
$2.20 1 30
.
.40
2-in. sleeves, at
$.45 each
90
li-in.
Pemberton trap
wiping, at $.25 Ib
6.80
7 50
.
30
Ibs. solder,
.84
4.70
3 .00
.
6-in. cesspool
4
1
.60
1
.
35
Soil pipe
47.87
15
ft. ft.
No. 55
3 .24
50
40ft. li-in.
"
pipe "
1
5 96
.
1.79
$ 2.70
1
$ 108 41
.
MISCELLANEOUS FITTINGS
3 4-in. b -assC.
1 5-in.
brass C.
O O
.50
.
12 50
12.00
1.25
ball-cock
2sillcocks
2.00 6.50
cocks
3.24
Carried forward
$41.69
$108.41
94
ESTIMATING
Brought forward $ 41.69
1
$ 108.41
boiler valve
and chain
.70
Ibs. tinned copper, at $.32 Ib 6 3-part hangers, brass 2 J-in. hose bibs
25
8 00
.
6 30
.
50
2. 10
55 .00
':...,....
lib. putty
05
.50
Ibs.
grafting wax
22.80
..
.
.
Oakum
FIXTURES
1
".'..
1.60
$ 140.24
36 x 24 x
back
$11 .40
24 x
..
14.00
3 .60
14. 10
-.
bathtub, complete
41.00 32.50
60 00
.
1
1
lavatory /complete
water-closet, complete 40-gallon boiler " " "
1 1
... ,
16.75
.85
stand
12
Ibs. fine
solder
3 12
.
2 70
.
.15
1.95
$202.12
22ft.Hnch
$4.41
.62
1
.
67
$23.49 16.24
39.73
7.95
9 75
.
3 .54
4 72
.
Lead,
oil,
etc
.65
$ 450.77
ESTIMATING
Brought forward $ 73.04
95
$ 450.77
.25
5 00
.
240 00
.
318 29
.
$ 769.06
Profit,
'.
76 .90
$ 845 .96
ELECTRIC WIRING
75
ft.
No. 4
S.
B. R.C. wire
$ 4.80
150
ft.
No.
S. B.
R. C. wire
4.26
2 00
.
40
30
1 1
.50
.
50
3.50
16 00
.
2,500
500
circular
loom
tubes
800
1,600
5iknobs
5-in. porcelain
100 100
18
Fire stops
12-in. porcelain tubes
10.00
1
Ceiling boxes
.80
30
11
11
Bracket boxes
Switch boxes
3 .00
2.20
12.10
55 00
.
15.00
15.00
5 00
.
Teaming and
Sundries
freight
5 .00
3.00
$ 225.46
Office expense, 10 per cent
22 55
.
$ 248.01
Profit,
20 per cent
49.60
$297.61
ESTIMATING
NOTE.
This estimate
is
figured
on
meter and to cover the meter, on an eight-circuit panel-board, which allows one spare circuit. The panel-board is to be made of slate, with
slate gutters
and
The labor is
small places, but
with good wood door and trim. estimated on wages being $3.60 per day for a journeylinings,
for helper.
is
This price
is
below what
paid in
some
cities.
made
may
such a wide range in design and cost, as well as in personal preference, that any data given can be at best only approximate.
The
following estimate
is
FIRST STORY
LIVING
1
ROOM
4-light electrolier
$17.50 13 00
.
HALL
2 2-light ceiling pieces, at $2.50 each
5 00
.
VESTIBULE
1
3-light cluster
5.00
*
PORCH
1
1-light ceiling-piece
.75
PARLOR
1
4-light electrolier
1
17.50
"
wall brackets
6.50
10.00
DINING ROOM
1
4-light electrolier"
1
"
wall brackets
5.00
2.25
2.70
Carried forward $86.20
ESTIMATING
Brought forward $ 86 20
.
PANTRY
1
1-light ceiling-piece
.75
ENTRY
11
PIAZZA
"
"
"
1.35
11
HALL
"
:"
"
1.75
SECOND STORY
2 1-light ceiling-pieces, at $1.50 each
$3 .00
ALCOVE
2 1-light ceiling pieces, at $2.50 each"
5.00
BEDROOMS
13 1-light brackets, at $2.50 each
32.50
.35
BATHROOM
1
1-light ceiling-piece
REAR HALL
1
1-light bracket
.35
THIRD STORY
HALL
1
$1 .35
ATTIC
1
3-ft.
drop-cord
.85
BASEMENT
LAUNDRY
1
$1 15
.
CELLAR
4
3-ft.
3.40
$ 140.00
LABOR
Installing
above fixtures with all necessary trimmings ... $ 12 00 Total cost of Electric Lighting Fixtures in place $152.00
.
PAINTING
OUTSIDE PAINTING
17 pairs blinds, three coats painting, at $1.50 pair .... $ 25 50 1,068 yds. three coats painting, windows and wood.
work, at $.20 yd
213.60
Carried forward $239.10
98
ESTIMATING
Brought forward $239.10
54 yds.
two coats
$.15 yd
metallic
paint,
upper side
tin
roofs, at
8.10
floors,
6.20
166 yds. filling, staining, and shellacing, and two coats hard oil finish, at $.20 yd
$33.20
61 .25
245 yds. filling and two coats spar varnish, first coat rubbed, at $.25 yd 403 yds. one coat shellac, three of paint, two coats
zinc
294 yds. treat with potash, one oil filler, clean, four coats sheUac, last coat rubbed with pumice and oil, oak and birch, at $.35 yd. , 109 yds. filling, four coats shellac, last coat rubbed
. .
102.90
32 70
.
oil,
floors at
$ 30 yd
.
114 yds. size and three coats paint, varnish, walls, at $.20 yd
last
coat with
,....,...
gloss, bath-
22.80
1.25
5 yds. three coats paint and one enamel ;......... tub, at $.25 yd
100 yds. three coats paint,
last
with zinc,
flat,
white-
wood, at $.25 yd 10 yds. one coat shellac on pipes, at $ 10 yd 299 yds. size and tint in water-colors, ceilings,
.
25.00
1
.
00
at
44.85
$ 900.75
GENERAL SUMMARY
Batter-Boards and Water Supply Excavation
$
25 00
.
262.50
754. 15
281 .50
88.20
544.40
4,928.34
Carried forward $6,884.09
Carpenter Work
-'
TTHtt-ON-FIRJT-
DODR-
-WINDOW-.
DGDR-
18.
100
ESTIMATING
Brought foncard $6,884.09 216.21
1
Stairs
Hardware
Heating
55 49
.
295.41
845.96
297. Gl
152.00
Painting
Total,
900.75
"$97747752
SCHEDULES
ANALYSIS OF CARPENTER
Following
is
WORK
These show how
portions of carpenter
the prices are obtained, and will be very useful for comparison, as the changes in cost of parts can be noted and kept up to date.
First Floor, price per square of 100 sq.
ft., including the floor beams, but no furring for plaster
bridging,
Joists,
and under
10-in.,
floors,
16 inches on centers
S3 .25
Labor
Nails
1.50
10
Bridging
50
hemlock, at $24.00
2 30
.
Under
Labor
Nails
floor,
Waste, one-third
80
75
1-")
$ 9.35
ft.
Stock
0.00
.
.
Waste, one-third
2.00
2.25
.25
Labor
Nails
$10.50
Quartered Stock
Oak
$10.00
Waste Labor
Nails
.
3.30 6.50
.25
$20.05
ESTIMATING
Porch or Veranda Floor, per square of 100 Joists, 2 X 8-in., 16 inches on centers
sq.
ft.
101
$2.60
1.00
:
at
$55
5 .50
1.80
......
,
1.25
.20
...
$12.35
Second Floor, per square of 100 sq ft. Joists, 2 X 10-in., 16 inches on centers
$3 25
Labor
Bridging
1.50
50
1
.
50 80
75
15
2.30
Waste, one-third
Labor
Nails
Upper-floor stock
4 00
.
Waste Labor
Nails
,
1.30
1
.
75
20
$18.00
sq.
ft.
8-in.,
16 inches on centers
,,,
$ 2 .60
Labor Under
1.50
floor.
'.
4.00
1
'.
Furring
Bridging
Shingled Roof, per square of 100 sq. ft Rafters, 2 X 7-in, 20 inches on centers
.50
50
$10.10
$ 2.17
2.25
2 50
.
80
1
Labor
Nails
Shingles
.25
...;.;..
20
4.00
3.25
25
Labor
Nails
$16.67
102
ESTIMATING
sq.
ft.
.
7-in.,
20 inches on centers
$ 2. 17
1
.
50
50
4 75
.
12.00
ft.
$20.92
sq.
$ 4 .00
Boarding
2.30
"...
Waste Labor
Nails
.80.
1
'........
.00
20
ft.
$ 8.30
.30
.65
Labor
Nails
1.50
.15
'
40
$ 4 .00
$4.00
3.25
Labor
Paper
Nails
50
.20
$7.95
Main
Gutter, perft
.12
Upper
Fillet
fascia
03
.01
Lower
fascia
04
08 02 06
Planceer
Bed-mould
Frieze
04
25 50
.10
Labor
Rough
furring
.25
Upper fascia
$ .03
Carried forward $ .03
JECTION-THKQ -W1NDDW-HZAD
Fig. 19.
104
ESTIMATING
Brought forward $ .03
Gutter
10
fascia
Lower
Fillet
03
01
;
.*
Planceer
08 02
.25
Bed-mould
Brackets
Frieze
15
Architrave mould
Soffit
03 05
10
Inside frieze
Labor
1.00
.15
$ 2.00
each$ 6.00
2.50
1
.
00
45
$11 .20
1.25
6
in.
ft.,
each$ 3.50
$ 3.50
Frame
Sashes, 17J sq.ft., at $.20 per sq.
ft
Blinds
1.00
;
Blind fasts
Inside finish
.15
1.19
10
64 3.25 $13.33
as above
day
Window,
ft., ft.,
ft.,
Architrave,
21
at
Back-band, 21
Beads,
17
at at
$ .73 63
.34
"
$1.70
.51
SOpercentoff
Weights and Cord for Window, as above ft.,21bs.per ft., 35 lbs.,at $.01J Weights,
.~
$ 1.19
per Ib
$
ft.,
.44
Cord, 20
_^20
64
ESTIMATING
Cost of Window, 2
ft.
105
in.
x 4
ft.
in.,
each$ 3.50
Frame
Window,
Blinds
11 J sq.ft., at $.20 per sq.
ft
2.25
.75
.15
Blind fastenings
10
.28
Cord
Inside Casing, 18 ft., at $.03J per Back-band, 18 ft, at $.03 per ft.
ft.
.........
...
,
.15
.......
.63
54
28
Stop-beads, 14ft., at
$.02 per ft
:
Labor
French Windows, 4
ft.
3.25
6
$11.88
6 in
X
6
ft.
in.,
.,
each$ 5.00
at $
.
Frame
Sash, 4
ft.
in.
ft.
in.,
34
sq.
ft.,
20 per
sq. ft
6.80
50
10
,
96
Labor
4.88
in.
$18.24
ft.
in.
(oak
finish),
each.$3.50
3.60
1.00
15 10
Window, 18sq.
Blind
fasts
ft.,
at
ft
Weights...
Finish (oak)
.
.
70
2.64
4.88
$16.57
Labor, IJdays
Rear Door, 2
ft.
10
in.
X
.
ft.
in.
Frame
Door, 21
Finish
sq.
ft.,
$4.00
at $ 25 per sq.
ft
...
5 25
.
.....:.....
:
.91
Labor
Nails
.
3.25
.05
$13.46
106
ESTIMATING
ft.
Front Door, 3
in.
ft.
in.,
Frame
Sill,
ft.,
at
$.25 per ft
at
$1.75
1.61
ft.,
$.10i 2.10
.81
.
Mullioncasing,20ft,at$.021 Vperft
Labor, J price of stock
Door, 3
3
in.
42
.
3 32
$10.01
ft.,
ft.
in.
21 sq. ft.,at$.25persq. ft Side-light panels, 6 ft., at $ 25 per ft 3 sash rims, at $.50 each
.
$5.25
,
.
50
1.50
ft.
.
ft.,
at
27.00
$35.25
Stop-beads
Architrave, 24 ft., at $ 04J per ft Labor, 3days
.
.
$ .28
1
.
08
9.75
$11.11
$56 37
.
Door, 2
ft.
in.
ft.
in.
(N. C. pine)
Stockdoor
$3.00
1
Frame
Threshold
Nails
.25
15
05
1.78
Finish,39Jft,at$.04iperft
Labor
Pair of Sliding Doors, 6
ft.
3.25
$9.48
ft.
$24 00 2.34
.
24ft.,
whitewood
:
1
1
.05
.82
.85
.50
ESTIMATING
Brought forward $30.56
107
.23
',.
.33
.15
1
.
50
ft.>
4 50
.
16.25
$53.52
Esti=
FIRST FLOOR
ROOMS
108
ESTIMATING
Location Sheet
INDEX
Page
Approximate estimates
Area, definition of
3 6 12
35 58
19 24 19
Bluestone
mortar for
Calculating the frame
19 19 27 24 24
2 23 32 32 22
Cellar
window
Chimneys
Composition roofs Concrete Conductors
Cost of excavating Cost of frame Cost of setting cut stone
,
45
21
45 15 28 18 49 49 48
6
list
of extras for
40
16 18 35 6 55
Cut stone
cost of setting Day's work for carpenter
Definitions
work
23 57
Estimate
approximate
110
INDEX
Page
Estimate
making-up
Estimating
of actual
59
of residence at Ridgedale,
Mo.
62-100
5 4 15 14 37
Face bricks
Finishing stock. Fixtures
Floors
,
Flue lining.
20 33 56 29 22
/.
. .
Frame
calculating the cost of.
'
27 28
31
34
Gas fitting
Granite Gutters Hardware..
52 52 57
16
.'
Heating
first floor
45 39 50
51
.
51 51
53
31
33 30 46
17
7
Lumber, miscellaneous
prices of
Nails
Outside walls
Painting
cost of
inside
108 26 18 22 8 45 39 29
outside
work work
48 49 49 50
INDEX
Painting
cost of
111
Page
50 2 37
15
'52
'.
47 45 54 57
5
1
2
31
53 52
31
30,
42
7
_.
18 13
Schedules
100-107
19 18
,
Seam-faced granite.
Setting cut stone, cost of
Shingles
cost of
,
..,.....*....;..
.*
measuring for
quantities Shingling outside walls.
Slating...
42 43 43 43 30 43 44 32 55
13 12 34 23 53 15
Solid contents
Solids, areas of
,
.
Stairs
58
25 12 56
7,
!
cisterns, capacity of
of multiples Tiles
10
Transportation
45 52 3
112
INDEX
Page
Units
Vitrified pipe, net price of standard. Wages, scale of
7 23
13
55 55
17
30
41
OF THE
UNIVERSITY
OF
ANNOUNCEMENT OF COMING
BOOKLS
,
PRACTICAL A
CARPENTRY. By G. Townsend. 150 pp., 224 illus. A working manual for Carpenters and Woodworkers in general. Not a theoretical treatise, but a practical working guide. Price, $1.00 GAS ENGINES AND PRODUCERS. By Marks and Wver.
150 pp., 90 illus.
SCIENTIFIC
STRENGTH OF MATERIALS. By E. R. Maurer. 140 pp 58 illus. For Architects, Builders, Steel and Concrete Workers. Enables one to
avoid mistakes.
Price
$1.00
Thorn and Collins. easy steps
For Engineers, rapidly developing field. Machinists, Automobilists. Price $1.00 MASONRY CONSTRUCTION. By Phillips and Byrne. 140 pp., 44 illus. Latest and best American methods. Price $ 1 .00
150 pp., 81 illus. Carries along by to complete mastery Multiplex less telegraph explained. Price
and Wire-
$1.00
MECHANICAL DRAWING.
WATER SUPPLY.
illus.
An
160 pp., By 140 iilus. Complete course in projections, shade lines, intersections and developments, exercises and plates. lettering, with
E. Kenison.
Price
POWER
STATIONS
AND
ested in matters affecting public health. Price $1.00 HIGHWAY CONSTRUCTION. By Phillips and Byrne. Modern methods for Road 140 pp. ,80 illus. Builders and all interested in better ways of communication. Price $ 1 .00 REINFORCED CONCRETE. By Webb and Gibson.
150 pp., 140 illus. A manual of practical methods for Architects, Builders, Contractors, Civil and Sanitary Engineers. Information for the Based first time made known to the world.
tests,
G. C. Shaad.
Workers.
$1.00
PATTERN MAKING. By James Ritchey. 150 pp., 250 illus. For Wood and Metal Workers and Molders. Methods of building up and finishing, fully described.
Price
$1.00
.
SURVEYING. By Alfred E. Phillips. 200 pp 133 illus. For Civil Engineers and Students. All
details of field
work explained.
By
E. A.
Price
$1.50
STEEL CONSTRUCTION.
Price etc. $1.00 MANAGEMENT OF DYNAMO-ELECTRIC MACHINERY. Crocker. 130 65 For illus. all who pp By F. B.
,
TUCKER. 300 pp., phase of the use of Based on actual exetc. For Architects,
Price
have to do with
Price
$1.50
E. Nichols
illus.
$ 1.00
BUILDING SUPERINTENDENCE. By
200
pp., 250
STEAM ENGINES.
By Leland and Snow, tfo PP., 63 illus. practical guide. Field covered in can a way anyone grasp. Price $ 1 .00
Costly mistakes occur through lack of attention at proper time, hurtful to Owner and discreditable to Archi-
ELECTRIC RAILWAYS.
103
illus.
By
J. R.
Cravath.
150 pp.,
tect and Builder. Gives thorough knowledge of methods and materials. Price $ 1.50 ARCHITECTURAL DRAWING AND LETTERING. By
Electric Locomotive, etc. Price. $1.00 ESTIMATING. By Edward Nichols. 140 pp., 35 illus. For all workers in Building trades. Tells how to estimate intelligently. Price... $1 .00 CONTRACTS AND SPECIFICATIONS. By James C.
Plant.
Bourne, von Hoist and Brown. 200 Pp., 55 drawings. Complete course in making working drawings and artistic lettering for architectural purposes. Price
$1.50
F.
130
PP
fully illustrated.
Forms
of
bonds,
Price
W. Turner. 200 pp., 200 illus. Meets every requirement of the shopman, from the simplest tools to the most complex turning and milling machines.
Price
Architects, Contractors,
and Owners
$ 1.00 $ 1.00
$1.50
Price
STAIR BUILDING AND STEEL SQUARE. By Hodgson and Williams. 130 pp.. 180 illus. Only up-toLeland and 150 pp. ,105 illus. Two books in one. of valves, gears, etc., fully explained.
TOOL MAKING. By E. R. Markham. 200 pp., 325 illus. How to make, how to use tools. Profusely
illustrated.
$1.50
Every
illustration
MACHINE DESIGN.
represents a
practice.
Types
Price
new
$1.00
Price
$ 1 .50
These volumes are handsomely bound in red art Vellum de Luxe, size 6% x 9^ inches. Sent prepaid to any part of the world, on receipt of price. Remit by Draft, Postal Order, Express Order, or Registered Letter.
OVERDUE.
196470