Inspection CheckList

Air Distribution System

AIR CONDITIONING
PROJECT

FLOOR

LOCATION

ACCORDING TO DRAWING/s No.

INSTALLED BY

VISUAL INSPECTION

Check for air outlet installation (black painted wooden frame, no gap between grille and screed)

AIR FLOW TEST


1) Check air flow through each outlet
(Fill table and compare to nominal values + or - 10% difference are accepted)
2) Check temperature on the last outlet
(Compare to air handling unit outlet temperature 1C difference is accepted)
3) Check noise level on outlet
(Fill table and compare to specified values)
4) Check noise level under main distribution duct
(Fill table and compare to specified values)
5) Check for lack of vibration of duct
6) Check for equal soft distribution of the air in rooms (no draught, no dead corner)

OBSERVATIONS

.
.
.

CHECKED BY

.
PHONE: ..

DATE