You are on page 1of 1

To Date..

The Engineer

Dear Sir

Defects Liability Certificate

We now consider that all works of amendment, reconstruction, remedying defects, shrinkages
and other faults required to be carried out under Clauses 49 and 50 of the Conditions have
now completed.

May we therefore request the issue of the Defects Liability Certificate pursuant to Clause 62.1
of the Conditions.

Yours faithfully

Contractor Ltd