BP-07

SITE PAVING, UNIT PAVERS AND SITE UTILITIES

SCOPE OF WORK

DESIGNATED 100% CBE SUBCONTRACTING SET-ASIDE REQUIREMENT

DEFINITION OF PROJECT AREA:

The Scope of Work includes the site utilities work and site paving features at the
Georgetown Neighborhood Library which is located at 3260 R Street, NW, Washington,
DC.

SITE PAVING, UNIT PAVERS AND SITE UTILITIES PACKAGE


Contractor shall be responsible for labor, material and equipment for all site paving and
site utilities at the site of the Georgetown Neighborhood Library as indicated in bid
documents (100% Final Construction Drawings and Specifications dated July 9, 2009).
Available on CD. Work includes but is not limited to the following specification sections
Division 1 – General Requirements
Division 2 – Site Construction
02080 Piped Utilities
02239 Site Clearing (As applicable to your work)
02260 Excavation Support and Protection
02300 Earthwork (As applicable to your work)
02510 Water Distribution
02530 Sanitary Sewerage
02630 Storm Drainage
02751 Cement Concrete Pavement
02764 Pavement Joint Sealants
02780 Unit Pavers
02761 Porous Unit Paving
Division 7 – Thermal and Moisture Protection
07920 Joint Sealants (As applicable to your work)

1. Furnish and install erosion and sediment control measures as detailed and
required by the District of Columbia and shown on the documents.
2. Relocate existing chain link fence, connect to the existing pavers and
relocate the existing benches at the adjacent Book Hill Park.
3. Excavation , backfill and compaction as required to perform the work of
this contract.
4. Rough grade for all paving and upon completion of all site utilities work
grade to be left +/- 0.2’ (foot).
5. Furnish and install new domestic water and fire pipe from water main in
street to new library Water Room location. Tap existing water main
location in and provide valves and other required fittings. Domestic and
Fire water lines are to be extended to with-in 5’-0” of the building. Include
Underpinning/support of existing structures or utilities in order to
complete the Work.
6. Flushing and chlorination of water lines as required.
7. Furnish and install new sanitary sewer line from main to within 5’-0” of
building.
8. Furnish and install new storm sewer line from main to within 5’-0” of
building. Work to include all structures and storm vaults.
9. Restore existing street paving (both temporary and permanent), sidewalks,
curb and gutter all to final acceptance, with provisions for flagmen, traffic
control, temporary paving, steel plates or any other necessary provisions
for the completion of the work. The traffic control plan must be approved
prior to performing of the work. Implementation of the traffic control plan
based on approved (M&J) traffic control plan.
10. Furnish and install all indicated manholes, meters, valves, boxes, hydrants,
cleanouts, vaults, grate inlets, trench drains, etc as specified.
11. Removal and disposal of existing sidewalks and paving as indicated or
required.
12. Demolish and removal of existing catch basins and/or manholes not to
remain or interfering with new storm system design.
13. Remove and/or cap existing water, sewer, storm and gas lines that are
being abandoned.
14. Demolish existing partial concrete paving and walks, brick walks, and
curbs not intended to remain and interfering with new paving design.
15. Build lower terrace grass stairs with oversized brick riser edge and
reinforced concrete footings.
16. Furnish and install concrete and granite curbs as indicated.
17. Furnish and install concrete walks, roads and miscellaneous paving
systems per civil and landscaping details, including all required expansion
and control joints.
18. Furnish and install reinforcing steel and mesh as shown and required.
19. Furnish and install brick and flagstone paving including stone and
concrete subbase or other foundation as required. Repair existing brick
and stone paving to restore to like original condition.
20. Furnish and install precast wheel stops at parking.
21. Furnish and install sidewalk handicapped ramps as indicated.
22. Furnish and install bluestone paving including subbase.
23. Furnish and install limestone treads, risers and pavers, to match existing.
24. Furnish and install permeable/porous concrete unit paving system
including subbase and underdrains.
25. Provide pavement joint sealants as specified.
26. Provide all indicated parking stall, directional or other painting on
pavement.
27. Install pipe bollards furnished by others. Installation includes concrete
base and fill.
28. This Contractor is to clean the street as required to remove any dirt or dust
tracked onto the street from his operations.
29. Install embedded items in the work provided by others.
30. Hoisting as required for this work
31. This Contractor is to coordinate the tapping of the water and sewer lines
with the proper authorities, including performing this work after hours or
on weekends.
32. Provide any Independent Testing & Inspection Services required for this
Work, including but not limited to materials testing and inspections;
33. During the period of this work, contractor agrees that all employees must
be experienced in performing the work.
34. Contractor shall remove and transport debris resulting from erection
operations and materials off site Recyclable materials shall be separated
and stored or stockpiled without intermixing with other surplus materials
before transporting to recycling facilities in accordance with a recycling
program consistent with the Project LEED Certification Program.
35. Contractor to obtain and pay for any permits or fees as required for this
work, including public space permits.
36. This Contractor to include multiple mobilizations for performing this
work.
37. Contractor shall comply with all identified performance and specification
requirements to achieve LEED points toward the Silver certification goal
as indicated in the bid documents.
38. Contractor shall take all necessary precautions to avoid damage to all
existing and completed construction in place.
39. It is Contractor’s responsibility to read the Hazardous Materials Survey
Report for Georgetown Neighborhood Library, including the July 8th ,
2008 addendum.
40. Contractor shall submit bids detailing their proposed means, methods and
schedule for this scope of work.
41. Provide labor for incidental project clean-up
42. Provide miscellaneous temporary protection of existing conditions during
construction as specifically specified herein and OSHA safety
barricades, rails and floor coverings, for this Work.
43. Engineering, site survey and layout for this Work including field
measuring as required ..
44. Provide construction progress documentation & photographs, including
existing building pre-construction condition documentation.
45. Contractor shall leave the workplace in a clean and presentable condition
ready for subsequent trades and prepared for finishes as specified.
46. Submittals will be required for approval prior to execution of the work.
47. As-built drawings.

Exclusions

1. Foundation drain tile


2. Fine grading
3. Painting of pipe bollards