Location Map
Northbound Inside Shoulder (no work on Southbound) All traffic will be allowed to use shoulder lane in peak periods (no flexible delineators) AM and PM peak hours to alleviate traffic queues and improve merging Static and dynamic signing, lane markings, and overhead lane-use system included
Typical Section
Pavement Work
Mill and overlay, restripe Northbound I-495 within project limits Reconstruct outside shoulder to full depth pavement Widen right shoulder at Georgetown Pike Interchange to provide emergency pull off Pavement joint repairs for improved ride and longer pavement life
Structures
No major bridge work anticipated. Sound wall/retaining wall impacts under evaluation. Pier protection will be upgraded at overpasses within project limits Overhead dynamic and static sign structures along median barrier and outside barrier
Concept of Operations
Advance DMS signs, static signs, overhead lane control signs, and striping to delineate shoulder lane Light gray color for shoulder lane to provide contrast Additional camera coverage and traffic detectors along Northbound I-495
Other Items
During construction, no lane/shoulder closures during peak hours. Minor drainage work anticipated Median barrier modifications to upgrade to meet current standards No right-of-way or utility relocations anticipated
Schedule
Citizens Information Meeting - November 19, 2013 NEPA Document - January 2014 Notice to Proceed for Construction - May, 2014 Open for traffic - December, 2014