I nsul ated Panel s
Sept. 2009
I N S U L AT E D WA L L S Y S T E MS
Installation Guide
KS600/900/1000 Optimo Wall Fassade System
Horizontally Laid
Note: Ensure steelwork is suitably lined, levelled and within tolerance.
Min. bearing face for vertical joint steelwork is subject to joint option, this
guide shows joint option Inline Black and Silver with 120mm bearing face.
Refer to Kingspan Design and Construction Guide.
Min. bearing face for intermediate support is 60mm.
Where long runs of integrated ribbon windows are installed in conjunction
with horizontal laid architectural wall panels, the vertical panel joints
should terminate above and continue below the window units. Contact
Kingspan envirocare technical services for shoe and defector details.
Gun-grade sealant type non-setting butyl sealant
neutral silicone sealant.
d
c
h
i
g
j
k
f
b
e a
m
l
Fit panel bearers, located
maximum 150mm from panel
ends and at maximum 1500mm
centres. Ensure that bearers are
accurately lined and levelled
Ensure vertical secondary steel
face at horizontal and vertical
interface is continuous to
provide a support for the VJ1
EPDM bubble gasket air seal.
Cover ashings required where
gap is greater than 20mm
Fit galvanised drip support angle
using low prole fasteners. An air
seal consisting of an unbroken
6mm bead of gun-grade sealant
is required between support angle
and oor
Line, level and x drip ashing
using low prole fasteners. Joints
in the drip ashing to incorporate
butt straps sealed with two runs
of gun-grade sealant
Column face
Vertical rail
Drip ashing
Galvanised drip
support angle
Air seal - 6mm bead
of gun-grade sealant
Vertical rail Vertical rail VJ1 bubble
gasket
Evenly spaced and
correctly located
Site applied PIR insulation
or gun applied re rated
foam insulation
Panel bearer at ends of
panel & max. 1500mm
centres between
Horizontal intermediate support
Vertical rail Vertical rail VJ1 bubble
gasket
Evenly spaced and
correctly located
<20m
m
Install main fasteners through
the male joint at panel end
into each vertical rail location
Note: Some installations may require
additional fasteners depending on wind
loadings/specication. Check project
specic details.
P1
P1
P1
C1
P2
P2
C2
C1
P1
P2
Install 2 No. main fasteners
at intermediate support
position (minimum)
VJ1 EPDM bubble gasket
Locate rst module element
(P1) on panel
bearers ensuring panel is evenly
spaced and correctly positioned
between vertical joint centres
Lower the next module element (P2) into position ensuring that the
factory applied weather seal is compressed and that the AWP
ller remains in position. Ensure that the panel is evenly
spaced and correctly positioned between vertical joint
centres. Install main fasteners at each panel end and
intermediate vertical steel member as previous
Apply an unbroken 6mm bead of gun-grade
sealant to provide an air seal between back of
module and drip support angle. This air seal should
meet the previously installed bubble gasket
Column face
Vertical rail
KS1000 Optimoinsulated
fassade module horizontally laid
Air seal - 6mm bead of
gun-grade sealant
A VJ1 EPDM bubble gasket is required at each
vertical panel joint detail to provide an air seal.
Apply gasket to the vertical steel member, ensure
that it overlaps the vertical leg of the drip ashing
Note: Some installations may require
additional fasteners depending on wind
loadings/specication. Check project
specic details.
Bed an AWP ller in
neutral silicone sealant at module element
ends, and
run a gun-grade air seal
across male joint
Air seal VJ1
EPDM bubble
gasket 60 x 10mm
Air seal gun-grade
sealant to male joint
Run a gun-grade
air seal across
male joint
AWP ller beaded
on neutral silicone
sealant
at every horizontal
panel joint
AWP joint ller and
neutral silicone
sealant
AWP joint ller and
neutral silicone
sealant
Factory applied
weather seal
Gap subject to
vertical joint option
Note: Wall modules can be installed in either a
tiered or coarsed sequence.
Visually check internal liner joint to ensure
panels are joined fully.
Check panel cover width module as works
progress to ensure "creep" does not occur,
particularly important when windows are
incorporated into the elevation.
This is a generic Optimo installation guide,
however details may difer from project to project.
Project specifc construction details must be used.
Please refer to the Kingspan Design and
Construction Guide for further information.
= = = =
= = = =
Install air seals and AWP ller at
module ends as previous. Refer
to items j
Locate the preformed corner module element (C1)
on panel bearers ensuring panel is evenly
spaced and correctly positioned between
the vertical joint centres and install main
fasteners through the male joint
Air seal VJ1
EPDM bubble
gasket 60 10mm
AWP joint ller and
neutral silicone sealant
Air seal gun-grade
sealant to male joint
neutral silicone
sealant
Gap subject to
vertical joint option
AWP joint ller and
Neutral Silicone sealant
p
o
n
s
r
t
q
The gap between the module ends is to be lled with PIR
insulation board or gun applied re rated canister insulation
to a depth to suit the top hat section. If PIR board is used,
ensure that continuity of insulation is achieved by lling any
gaps with re rated canister applied insulation
Note: There are several types of vertical joint options. This guide assumes that an
Inline Black or Inline Silver top hat detail is being used.
Prior to installation of the top hat
apply a neutral silicone sealant to horizontal
panel joint at modul ends in line with
AWP ller
Lower the preformed corner module element (C2) into position ensuring
that the factory applied weather seal is compressed and that
the AWP ller remains in position. Ensure that the panel is
evenly spaced and correctly positioned between the vertical
joint centres and install main fasteners into each vertical steel
member as previous. Refer to h and i
Place the top hat in to the vertical joint, aligned to the
bottom of the module. Fix through the insulation inll to the
vertical steel member at max. 500mm centres, ensuring
top hat is pulled tightly against panel to ensure effective
weather seal. Care must be taken not to overdrive
Incorporate a butt strap into the
top hat joint, sealing with two
runs of gun-grade sealant
Apply 9 x 4mm PVC sealant to internal
legs of SP8 (joint option C) extruded
aluminium top hat section
Air seal - VJ1
EPDM bubble
gasket 60 x 10mm
KS1000 Optimo
insulated wall panel
horizontally laid
SP4 push in black
EPDM r-tree gasket
tted before canister
insulation has set
Site applied PIR insulation
or gun applied re rated
foam insulation
Any joints in supporting
steelwork to be plated over
with 0.4mm steel liner ashing
Nom. 30mm
15mm
Min. steel bearing face 120mm
Alternate Joint Detail
Joint Option Onyx
Note: Integrated windows not to be
used with Optimojoint Onyx.
Push t joint
Inline gasket
(SP10) into
position
Air seal VJ1
EPDM bubble
gasket 60 10mm
Site applied PIR
insulation or gun applied
re rated foam insulation
AWP joint ller
and neutral silicone
sealant
Air seal gun-grade
sealant to male joint
Push-in gasket SP10 9mm 4mm PVC
sealant (site applied)
SP8 extruded
19mm
25mm
35mm 28mm
Min. steel bearing face 120mm
35mm
51mm
aluminium top hat
section (25mm deep)
Components
KS1000 OptimoWall Module Element
Primary/Main
Fastener
Neutral
Silicone
Sealant
PIR
Insulation
Low Prole
Fastener
Drip Flashing
Panel Bearer
AWP Filler
9x4mm 6mm
Butt Strap
VJ1 EPDM
Bubble Gasket
Fire-rated
Canister
Insulation
This installation guide should be read in
conjunction with the project specic
design drawings and method statements.
Although this installation guide is deemed
to be correct at the time of publication,
Kingspan reserve the right to amend the
information at any time in the future.
Installation Guides are available for the full
range of Kingspan Insulated Roof, Wall and
Faade Systems.
Please call Kingspan on:
Ire: +353 (0) 42 96 98500
UK: +44 (0) 1352 716100
Galvanised Drip
Support Angle
Butyl Rubber
Tape Sealants
Gun-Grade
Sealant
Top Hat
SP8
Push-in
gasket SP10