The Saint Cloud Hospital in Minnesota needed to expand but had limited space. They used five ground improvement techniques - jet grouting, chemical grouting, tieback anchors, soil nails, and vibro replacement - to prepare the site. Jet grouting and soil nails were used to construct retaining walls up to 34 feet deep to support excavation for new foundations near existing buildings. Chemical grouting stabilized soils under utilities and a transformer. Vibro replacement improved loose soils at the front of the new addition. The complex project was completed with no issues and received an engineering award.
The Saint Cloud Hospital in Minnesota needed to expand but had limited space. They used five ground improvement techniques - jet grouting, chemical grouting, tieback anchors, soil nails, and vibro replacement - to prepare the site. Jet grouting and soil nails were used to construct retaining walls up to 34 feet deep to support excavation for new foundations near existing buildings. Chemical grouting stabilized soils under utilities and a transformer. Vibro replacement improved loose soils at the front of the new addition. The complex project was completed with no issues and received an engineering award.
The Saint Cloud Hospital in Minnesota needed to expand but had limited space. They used five ground improvement techniques - jet grouting, chemical grouting, tieback anchors, soil nails, and vibro replacement - to prepare the site. Jet grouting and soil nails were used to construct retaining walls up to 34 feet deep to support excavation for new foundations near existing buildings. Chemical grouting stabilized soils under utilities and a transformer. Vibro replacement improved loose soils at the front of the new addition. The complex project was completed with no issues and received an engineering award.
Tieback Anchors, &Vibro Replacement ounded in 1886, the Saint Cloud Hospital now serves more than a half- million people in central Minnesota. Expansion of the facility was needed in order to continue to provide a high level of patient care while meeting the increasing demand for service. Since the hospital complex is built on a bluff overlooking the Mississippi River, space for expansion was extremely limited. Hospital offi- cials therefore had to work with the natural slope of the land to locate a multi-story addition that would match the height of the existing building. Site soils consisted of medium dense to very dense, glacially-deposited sand and gravels with cobbles and boulders, overlaying a five to seven-ft stratum of sandy, silty clay. Five different ground improvement techniquesjet grouting, chemical grouting, tieback anchors, soil nails and Vibro Replacementwere used to prepare the site for the new construction. Jet Grouting The new addition was to be built in an area adjacent to both the original, 7-story structure and two wings of a 4-story addition built in 1963. Footings would be located 24 to 32 ft below the existing buildings. Furthermore, since the new addition would be adjacent to one wing of the 4-story addi- tion, new footings in this area would be located 24 ft directly below the edge of the existing footings. Underpinning to ensure the integrity of the existing structures during foundation excavation for the new addition required three retaining walls. Typically, driven steel piles with lagging, or sheet piling are used for this type of project. However, hospital officials were concerned about potential ground loss from under the footings and about the effect of F excessive noise and vibrations from piling operations on the hospital facility, patients and staff. The Owner's architect and structural engineer, Horty & Elving of Minneapolis, therefore specified that the underpinning and retaining walls were to be constructed using non-vibratory ground modifi- cation techniques. The construction manager, Kraus Anderson of Minneapolis, accepted a design-build proposal from Hayward Baker using jet grouting and soil nailing. As well as being much less disruptive than conventional exca- vation support, jet grouting is a very flexible system that can be accomplished with a high degree of safety. This was a key consideration for portions of the work, given the presence of cobbles and boulders and the limited work area. Wenzel Engineering I nc. of Bloomington, MN was contracted to design the retention system. Owner Saint Cloud Hospital Saint Cloud, MN Engineer Horty & Elving Associates Minneapolis, MN Underpinning Design Wenzel Engineering Inc. Bloomington, MN Expansion of the hospital was accomplished with minimal disruption by using multiple Ground Modification techniques. Saint Cloud Hospital Expansion Saint Cloud, Minnesota Project Summary 2010 Hayward Baker Inc. (www.HaywardBaker.com) 1 of 4 Jet Grouting Design Considerations The retaining walls were required to provide underpinning support for the loads from the existing footings as well as the loads from the retained soils, up to 34 ft beneath those footings. The design also had to provide for the footings of the new addition that were to be constructed 24 ft directly below and adjacent to the existing footings. Since the retain- ing walls were required to remain in service for approxi- mately ten months, adequate surface drainage was an impor- tant additional consideration. Two types of wall were incorporated into the retention system to meet these criteria: A vertical, jet-grouted wall wrapped around the corner of the existing, 4-story structure adjacent to the excavation and reinforced laterally with soil nails to underpin the structure where risk of settlement was the greatest concern. Inclined soil nail walls where more space was available between the existing building and the new structure. Soil Nailing and Jet Grout Wall Construction For the jet-grouted, wrap-around walls, vertical, 3.5 ft diameter, interconnected Soilcrete columns were con- structed upwards from a depth of 25 ft to support the existing footings and the retained soils. At footing loca- tions, a second row of angled columns was constructed to provide additional support for the vertical loads. Although the Soilcrete wall could now safely support the vertical loads, lateral restraint capacity was required to ensure support of the horizontal loads. Four levels of soil nails were therefore installed through the Soilcrete columns and into the retained soil at five-ft horizontal intervals. A total of 50 Soilcrete columns and 51 soil nails were installed for this wall. For the remaining two walls, the position of the build- ing allowed the construction of inclined, reinforced soil nailed walls to a depth of 34 ft at the 7-story building and 16 ft at the 5-story building. Each wall was constructed Cross section showing jet grouting and soil nail design. Four levels of soil nails provided additional lateral restraint for the Soilcrete wall. 2010 Hayward Baker Inc. (www.HaywardBaker.com) 2 of 4 However, the west one third of the structure was actu- ally founded at grade on spread footings, 5.5 ft higher and directly adjacent to the planned connector alignment. Soil borings and site investigation by Braun Intertec of Saint Cloud verified that the elevated portion was supported on a profile of mixed fill soils containing a 2.5-ft layer of clean sand over a 3-ft
layer of very soft (N=1), saturated,
silty sand and silty clay. Also, a 15-inch diameter storm sewer line and a 4-inch diameter, high-pressure water line passed directly through the area to be underpinned. Given the soil profile and the need for a vertical cut under the major footings that supported the seven-story structure, additional ground improvement was required before the soil nail wall could be constructed. To solve this problem, chemical grouting was used to stabilize the clean granular soils. The soft, cohesive materials were then con- tained by driving steel channels edge to edge along the side of the spread footing. The high-pressure water line was temporarily disconnected so that the final channel sheets could be driven to complete the retainment. A combination of steel wales and soil anchors provided the required lateral restraint. Chemical grouting prior to soil nailing stabilized the soils to ensure the integrity of a 15-inch diameter storm sewer line and a 4-inch diameter high pressure water line. from the top down in four-ft lifts. At each level, soil was excavated at a slight incline, followed by the installation of design-length soil nails at five-ft, horizontal spacing. Reinforcing mesh was placed over the exposed face, which was then stabilized with a five-inch thick shotcrete fascia. Drainage pipes were installed at the toe of each wall to channel surface water away from the construction area. During jet grouting, wet Soilcrete samples were retrieved and tested for unconfined compressive strength. Core-drilled samples were also taken at the interstice of completed columns and tested. Results verified that the design strength of 1500 psi at 28 days was being achieved. The age of the existing structure prompted concern on the part of the Owner over the potential for movement during the work. Therefore, throughout the jet grouting and soil nailing, third order optical survey measurements were taken twice daily. No movement whatsoever was recorded during the eight-month period that the excavation stood open. Chemical Grouting, Tieback Anchors and Steel Sheeting The new addition was designed to be connected to the 7-story building by a two-level tunnel founded at the base- ment footing elevation. It was expected that the footings for the 7-story structure were all at the same elevation. 2010 Hayward Baker Inc. (www.HaywardBaker.com) 3 of 4 Saint Cloud, continued Once this step was completed, the excavation contin- ued, in four- to five-ft lifts, for a total vertical cut of 34 ft, exposing the storm sewer line. The building was carefully monitored for settlement during the course of work, with no movement recorded. Chemical grouting was also used to underpin and retain the sandy soils under the hospital's main transformer base, undercut by six ft for the building footing construction. Vibro Replacement The front of the new addition extended out beyond the soil zone densified by glacial deposits and over an area loosened and re-deposited by the action of the Mississippi River. Vibro Replacement was used to construct stone columns through the loose, variable sandy, silty, granular soils to a depth of 25 to 30 ft below the working platform, providing sufficient improvement in bearing capacity to support the structure on spread footings. Engineering Excellence Award The complex nature of the ground improvement and the dif- ficult working conditions presented a considerable chal- lenge, both in design of the underpinning and excavation Left: The exposed face of the inclined soil nail wall was covered with reinforcing mesh and stabilized with shotcrete. Below, left: Vibro Replacement under way to improve loose soils. support and in the execution of the work. In recognition of the retaining wall design, Wenzel Engineering was pre- sented with a Grand Award in the 1999 Consulting Engineers Council of Minnesota Engineering Excellence Awards Competition. Odenton, Maryland 410-551-1980 Santa Paula, California 805-933-1331 San Francisco, California 925-825-5056 San Diego, California 858-514-2170 Broomfield, Colorado 303-469-1136 Tampa, Florida 813-884-3441 Deerfield Beach, Florida 954-428-8555 Alpharetta, Georgia 770-442-1801 Des Moines, Iowa 515-276-5464 Buffalo Grove, Illinois 847-634-8580 Burlington, Massachusetts 781-229-7359 Fair Lawn, New York 201-797-1985 Weedsport, New York 315-834-6603 Colfax, North Carolina 336-668-0884 Knoxville, Tennessee 865-966-0294 Ft. Worth, Texas 817-625-4241 Houston, Texas 281-668-1870 Seattle, Washington 206-223-1732 Vancouver, B.C. 604-294-4845 Mexico City, Mexico (52-55) 5290-4600 HaywardBaker.com Hayward Baker Inc. 2004 Haywar d Bake r Loc at i o ns Project Summary 2010 Hayward Baker Inc. (www.HaywardBaker.com) 4 of 4
Transactions of the American Society of Civil Engineers, Vol. LXVIII, Sept. 1910
The New York Tunnel Extension of the Pennsylvania Railroad.
The North River Tunnels. Paper No. 1155