You are on page 1of 3

Six tips for designing a cost-effective data

center
By Christopher Johnston, PE, National Critical Facilities Chief Engineer, Syska
Hennessy Group Inc.
08.22.2008
There's no way to avoid it: The total cost of ownership (TCO) for data centers gives
every owner a case of sticker shock. Not only is the capital expense (CAPEX) -- or the
cost to design, build, test and commission -- increasing, but the inevitable operating
expense (OPEX) increases on the horizon are daunting. Knowledgeable users have
forecasted that the OPEX will exceed the CAPEX.

Syska believes the following are the basic principles of reducing TCO and constitute best
practices:

1. Spread redundancy across multiple, lower-tier data centers


Consider whether upgrading the IT network can reduce the facility availability required.
For example, can three less costly Tier 2 facilities serve your needs better than two more
costly Tier 4 facilities? (Tier rankings are based on The Uptime Institute's tier
whitepaper).

The cost centers in higher availability design are:

 Redundant systems with redundant components in each system


 The increased operating cost that results from reduced efficiency due to a
redundant system and components.

Two Tier 4 facilities with a four-megawatt computer load may cost $100 million each for
a total first cost of $200 million, while three Tier 2 facilities of four-megawatt computer
load may each cost $46 million for a total first cost of $138 million. The difference in
first cost may be $62 million. The tradeoffs have to do with network costs versus facility
costs. Network costs will be higher for three facilities than for two.

2. Base data center site selection on utility costs


Consider the present and estimated future costs of utilities in site selection. Sustainability
must be considered in every project.

The best sources of information on utility rates for data centers include:

 Knowledgeable national specialists such as CB Richard Ellis, Jones Lang LaSalle,


Julian Studley and others
 The utility companies' published rate schedules and in-house experts
 Watching where others are going. In my recent experience, a low electric power
rate is $0.038-$0.04/KWH; average is $0.08-$0.12/KWH; and high is
$0.25/KWH.

3. Consider OPEX as well as CAPEX


Focus on long-term operating costs (OPEX) in addition to initial costs (CAPEX). For
example, consider a site that has, at present, low electric utility costs and medium water
utility costs. Air-cooled water chillers will provide the lowest initial cost, but rapidly
escalating electric utility costs may prove that water-cooled water chillers are the better
choice. Energy and financial modeling based on estimates of future utility costs will
reveal the best decision.

Most knowledgeable owners use a TCO model that considers both CAPEX, OPEX, cost
of funds, desired return on investment (ROI) and other factors.

4. Focus on scalability and modularity


If the initial UPS need is 50 watts/square foot and the ultimate need is 150 watts, design
for 75 watts initially that can be later upgraded to 150 watts. If the initial raised floor
need is 20,000 square feet and the ultimate is 40,000 square feet, design for 30,000
square feet initially with an additional 10,000 square feet shelled in for future fit out.
When faced with a choice between quality and quantity, opt for quality that can be
upgraded in the future to provide added quantity.

I try to avoid hard and fast rules since each client's needs are different and worthy of
independent thought. Some upgrades are simple to accomplish and suggest ratios for
consideration. For example, on Day 1 we install two UPS systems on capacity N to
supply N computer load in a system + system arrangement. On Day 2 when the owner
needs 2N computer load, we can add another pair of systems or we can add a third system
of capacity N to the two original systems and reconfigure the arrangement as 3N/2.

5. Keep data center design simple


Keep the design as simple as possible. Simplicity eliminates unnecessary components,
and cost increases reliability and maintainability.

Here are some examples:

 Minimize the number of layers in the electrical distribution system to reduce cost
and make selective coordination of the electrical system easier.
 Eliminate secondary chilled water pumps by making the primary chilled water
pumps variable speed.
 If all of the computer equipment is dual-cord and there are no motor loads
supplied by the UPS, then static transfer switches downstream of the UPS systems
are unnecessary.

6. Avoid one-of-a-kind or serial number 1 products


Use standard components and ratings wherever possible. Serial number 1 always has a
high initial and replacement costs. As an example, 4000-ampere switchgear bus is more
cost effective than 5000-ampere bus.

I recently heard from a client that has 12-year-old UPS equipment that is no longer
manufactured has some custom, one-of-a-kind control boards. As UPS equipment ages,
the availability of spare parts and trained technicians decreases.

Additionally, automate normal and emergency facility operations as much as possible.


Lastly, utilize technology instead of people wherever practical.

Follow these practices and you will be on your way to designing a cost-effective data
center.

You might also like