Professional Documents
Culture Documents
Charles,
I didn't get a chance to fill you in on the meeting with Erik, Carl, Betty and Debbie on Friday. It appears that our target to
build 50 and 51 may be greatly impacted by federal requirements - up to an additional year delay. We found this out
Thursday and I wanted Erik to know asap. Carl and I explained to him that a year is not a short delay, and that the new,
displaced engine and truck company will cost us $2.6 million a year and provide little service to the target area.
Addtionally, the 2nd TRT plan really doesn't work under these circumstances. We compared $2.6M to the grant for 51's
and decided that we are not coming out ahead waiting a whole year. Complaints will come from FF's, Union, residents,
council, etc. We don't feel 50's is the same situation since we are already providing service from a good temp location.
Let me know if you want to talk more on this. This info is close hold at this time.
RH
CITY OF SAN ANTONIO Office of the City Manager
P. 0. BOX 839966
SAN ANTONIO TEXAS 78283-3966
February 5, 2010
In October 2009„ the City of San Antonio received a notice of a grant award for a total of $7.3 million in
American Recovery and Reinvestment Act funds to build 2 new fire stations to serve the citizens of San
Antonio. These 2 fire stations will serve people in 2 underserved areas of the City and reduce
response times from 8 minutes to 4.55 minutes.
We are very happy to receive such a grant award, however, the grant originally was expected to cause a
6 month delay in the completion of the facilities. At first, the City had intended to have these 2 stations
operational in October 2010 when two new fire companies are ready to occupy them and provide service.
As a result of some added green building design and construction requirements of the Federal
Emergency Management Agency (FEMA) we committed to our community that these fire stations would
be operational by April 2011. Two new companies are planned to be temporarily housed in the nearest
fire facility that has space. Housing the new companies at existing facilities is a transitional solution but
does not afford our community with the level of service that they would receive if the new stations were
built in the locations that we have selected (see attached service area maps).
Unfortunately, we have run into a few more hurdles in this process. We had expected to start preparing
the necessary environmental permits for these 2 projects months ago. However, FEMA had advised us
that we should not move forward with environmental clearance until we received notice that such
clearance was necessary. On January 25, 2010, a conference call with FEMA was held and we were told
that as a condition of the ARRA grant, an Environmental Assessment is required for each fire station. An
Environmental Assessment will take 60 days and review/approval by FEMA would take could take up to 3
additional months to complete. In addition, FEMA has not provided a timeline for review of our project
budget but we are told that FEMA has 6 months to get back with us. This will delay our project by a total
of almost a year which is not acceptable to our citizens.
We are asking your assistance in getting FEMA to move more quickly on the budget and environmental
reviews so that we may keep our commitments to our neighborhoods and begin providing a higher level
of fire protection. The City has already invested $2.6 million dollars in annual costs to bring on two full fire
companies to serve this area and we are unable to realize the service improvement commensurate with
that cost. The safety of our community is too important to wait another year, therfore, we are also
considering requesting the grant for a replacement fire station if FEMA is unable to respond to our needs
for these new fire stations in a manner that is more timely than they are currently indicating.
Sincerely,
Erik Walsh
Assistant City Manager
Fire Department Stimulus Grant Award
Original Project Completion Timelines
FEMA required the City to participate in an environmental and historic preservation review
(Initial information submitted in October of 2009):
o Increase the scope of the projects to include LEED Silver certification
o Add full fire sprinkler system to each project
o Add a diesel exhaust system to each project
Cost to accept the grant: The City redesigned the building plans to meet these requirements.
The cost to the City to accept the grant and fulfill these requirements is $1.6 million.
• October 2009 - available environmental information for Station #50 and #51 was
submitted as requested. City was informed that review would take up to 180 days.
City was notified last week that a full Environmental Assessment (EA) would be required. CIMS
Environmental states that a minimum of 75 days would be required to complete the EA with the
assistance of a consultant. The federal government then has 180 days to review.
• The City is currently awaiting a call back from the Grant Budget Office to determine the
timeline of a budget review that will also be required.