According to the given data, the Production cycle times are as follows:
Complete cutting : 4 days after cut issue
Complete Sewing : 9 days after complete cutting
Complete Finishing : 4 days after complete sewing
Reasons:
Absenteeism
Poor Work Methods
Low Operator performance
Poor operator utilization
Frequesnt style changes in each department which leads to re-balancing of line each time leading to loss of
output
Remedies:
Operator Training to increase operator perofrmance
Carry out method study to develop better procedures
Correct Line balancing to optmize operator utilization
Processing single style in a continuous flow to reduce change over times, it’ll further reduce the line balancing
time.
Rejections after each department lower the quantity of goods finally produced.
For example, for style 3C, 2740 pieces were cut, 2720 pieces were sewn and finally 2650 pieces were finished.
It is clear from the data that pieces are getting rejected.
Reasons:
Low Operator Skill
Poor methods
Remedies:
Operator Training to increase operator perofrmance
Carry out method study to develop better procedures