WORK TURNED OUT BY LABOUR PER DAY (residential)

Quantity per person


Sl No. Particulars of Item Unit
per day
1 Earth Work & Excavation
1.1 For soft & ordinary soil Cum 3.0
1.2 For hard soil Cum 2.0
1.3 Backfilling Cum 4.0
2 Plain Cement Concrete
2.1 For Foundation
2.1.1 1:4:8 Cum 2.0
2.1.2 1:3:6 Cum 1.5
2.1.3 1:2:4 Cum 1.5
2.2 For Flooring
2.2.1 1:4:8 Cum 2.0
2.2.2 1:3:6 Cum 2.0
2.2.3 1:2:4 Cum 2.0
3 Reinforcement Cement Concrete in
3.1 Footings Cum 1.5
3.2 Column Cum 1.0
3.3 Slabs Cum 2.0
3.4 Beams Cum 1.0
3.5 Staircase Cum 1.0
4 Steel Reinforcement Work
4.1 Footings Kg 190.0
4.2 Column Kg 200.0
4.3 Slabs Kg 175.0
4.4 Beams Kg 173.0
4.5 Staircase Kg 173.0
4.6 Lintels Kg 100.0
4.7 Stirrups, spacers & links Kg 150.0

Page 1 of 5
WORK TURNED OUT BY LABOUR PER DAY (residential)

Quantity per person


Sl No. Particulars of Item Unit
per day
5 Shuttering Works
5.1 Footings Sqm 7.7
5.2 Column Sqm 4.0
5.3 Slabs Sqm 4.3
5.4 Beams Sqm 3.3
5.5 Staircase Sqm 3.3
6 Masonry Works
6.1 Size Stone Masonry
6.1.1 In foundation Cum 1.5
6.1.2 In superstructure Cum 2.0
6.2 Burnt Brick Masonry
6.2.1 9" Brick Wall Cum 1.8
6.2.2 4.5" Brick wall Sqm 2.0
6.3 Solid Block masonry
6.3.1 8" Solid Block Sqm 8.0
6.3.2 6" Solid Block Sqm 8.0
3.3.3 4" Solid Block Sqm 8.5
6.4 Hallow Block Masonry
6.4.1 8" Hallow Block Sqm 9.0
6.4.2 6" Hallow Block Sqm 9.0
7 Joinery Works
7.1 Wood works for
7.1.1 Doors Cum 1.3
7.1.2 Windows Cum 1.0
7.2 Aluminum Works for
7.2.1 Doors Sqm 0.8
7.2.2 Windows Sqm 0.5
8 Plastering Works

Page 2 of 5
WORK TURNED OUT BY LABOUR PER DAY (residential)

Quantity per person


Sl No. Particulars of Item Unit
per day
8.1 Internal Sqm 10.0
8.2 External Sqm 8.0

Page 3 of 5
WORK TURNED OUT BY LABOUR PER DAY (residential)

Quantity per person


Sl No. Particulars of Item Unit
per day
9 Flooring Works
9.1 Mosaic Flooring Sqm 7.0
9.2 Ceramic Flooring Sqm 7.0
9.3 Vitrified Flooring Sqm 10.0
9.4 Granite Flooring Sqm 5.0
9.5 Marble Flooring Sqm 5.0
9.6 Glazed tile dadoing Sqm 8.0
9.7 Tandoor Flooring Sqm 7.0
9.8 Kota Flooring Sqm 7.0
9.9 Cudappa Flooring Sqm 7.0
9.10 Eurocon Flooring Sqm 6.0
9.11 Clay tile Flooring Sqm 10.0
9.12 Interlock Paver Block Sqm 10.0
9.13 PVC flooring Sqm
9.14 Wooden Flooring Sqm
10 Painting Works
10.1 Internal
10.1.1 OBD Sqm 12.0
10.1.2 Emulsion Sqm 12.0
10.1.3 Texture Sqm 10.0
10.1.3 Enamel Sqm 8.0
10.2 External
10.2.1 Snowcem Sqm 20.0
10.2.2 Exterior Emulsion Sqm 7.0
10.2.3 Texture Sqm 5.0
11 Water proofing works Sqm 5.0
12 Structural steel works Kg 80.0
13 Structural Glazing Works Sqm 3.0

Page 4 of 5
WORK TURNED OUT BY LABOUR PER DAY (residential)

Quantity per person


Sl No. Particulars of Item Unit
per day