The foundation should be poured without interruption to within d.

If alignment needs improvement, add shims or wedges at


1/2 to 11/2 inches of the finished height. The top surface of the appropriate positions under base, so that retightening of
foundation should be well scored and grooved before the anchor nuts will shift shafts into closer alignment. Repeat
concrete sets; this provides a bonding surface for the grout. this procedure until a reasonable alignment is reached.
Foundation bolts should be set in concrete as shown in Figure NOTE: Reasonable alignment is defined as that which is
4. An optional 4-inch long tube around the bolts at the top of mutually agree upon by pump contractor and the accepting
the concrete will allow some flexibility in bolt alignment to facility (final operator). Final alignment procedures are cov-
match the holes in the base plate. Allow enough bolt length for ered under “Alignment Procedures.”
grout, shims, lower base plate flange, nuts and washers. The
e. Check to make sure the piping can be aligned to the pump
foundation should be allowed to cure for several days before
flanges without placing pipe strain on either flange.
the base plate is shimmed and grouted.
f. Grout in base plate completely (See “Grouting Procedure”)
FOUNDATION and allow grout to dry thoroughly before attaching piping to
PIPE
SLEEVE
BOLT pump. (24 hours is sufficient time with approved grouting
procedure.)
10. Grouting Procedure
Grout compensates for uneven foundation, distributes weight
of unit, and prevents shifting. Use an approved, non-shrinking
(OPTIONAL) grout, after setting and leveling unit (See Figure 5).
WASHER a. Build strong form around the foundation to contain grout.
b. Soak top of concrete foundation thoroughly, then remove
surface water.

BUILT-UP
c. Base plate should be completely filled with grout.
CONCRETE FOUNDATION
d. After the grout has thoroughly hardened, check the founda-
tion bolts and tighten if necessary.
FIGURE 4 – FOUNDATION
e. Check the alignment after the foundation bolts are
9. Base Plate Setting (Before Piping) tightened.
NOTE: This procedure assumes that a concrete foundation f. Approximately 14 days after the grout has been poured or
has been prepared with anchor or hold down bolts extending when the grout has thoroughly dried, apply an oil base paint
up ready to receive unit. It must be understood that pump and to the exposed edges of the grout to prevent air and mois-
motor have been mounted and rough aligned at the factory. If ture from coming in contact with the grout.
motor is to be field mounted, consult factory for recommenda-
11. See ANSI/OSHA Coupler Guard Removal/Installation
tions. Bell & Gossett cannot assume responsibility for final
(next page)
alignment.
NOTE: 12. Alignment Procedure
TO KEEP SHIMS IN
ALLOW 1" FOR SHIMS. PLACE ALLOW GROUT
NOTE: Permissible misalignment will vary with the make of
PLACE ON BOTH SIDES TO FLOW AROUND GROUT ONLY TO coupling. Consult coupling manufacturer’s data when in
OF ANCHOR BOLTS. HOLD DOWN LUGS. TOP OF BASE RAIL. doubt.
Allowances are to be made for thermal expansion during cold
PUMP alignment, so that the coupling will be aligned at operating
BASE RAIL temperature. In all cases, a coupling must be in alignment for
continuous operation. Even though the coupling may be lubri-
cated, misalignment causes excessive wear, vibration, and
GROUT bearing loads that result in premature bearing failure and
X. ultimate seizing of the pump. Misalignment can be angular,
APPRO
1" GAP parallel, or a combination of these, and in the horizontal and
vertical planes. Final alignment should be made by moving
CONCRETE and shimming the motor on the base plate, until the coupling
FOUNDATION hubs are within the recommended tolerances measured in
LEVELING OF PUMP BASE total run-out. All measurements should be taken with the
ON CONCRETE FOUNDATION.
pump and motor foot bolts tightened. The shaft of sleeve
FIGURE 5 – SETTING BASE PLATE AND GROUTING bearing motors should be in the center of its mechanical float.
a. Use blocks and shims under base for support at anchor NOTE: Proper alignment is essential for correct pump opera-
bolts and midway between bolts, to position base tion. This should be performed after base plate has been
approximately 1" above the concrete foundation, with studs properly set and grout has dried thoroughly according to
extending through holes in the base plate. instructions. Final alignment should be made by shimming
driver only. Alignment should be made at operating
b. By adding or removing shims under the base, level and
temperatures.
plumb the pump shaft and flanges. The base plate does not
have to be level.
WARNING: Unexpected Start-up Hazard
c. Draw anchor nuts tight against base, and observe pump Disconnect and lock out power before servicing.
and motor shafts or coupling hubs for alignment. (Tem- Failure to follow these instructions could result in serious
porarily remove coupling guard for checking alignment.) personal injury or death and property damage.