qê~åëä~íÉ=pÉéíÉãÄÉê OMMT
Design guide
mêÉëíêÉëëÉÇ=ÅçåÅêÉíÉ=ÄêáÇÖÉë=Äìáäí=
ìëáåÖ=íÜÉ=Å~åíáäÉîÉê=ãÉíÜçÇ =
The Technical Department for Transport, Roads and Bridges Engineering and Road Safety (Service d'études
techniques des routes et autoroutes - Sétra) is a technical department within the Ministry of Transport and
Infrastructure. Its field of activities is the road, the transportation and the engineering structures.
• The Sétra regularly exchanges its experience and projects with its foreign counterparts, through bilateral co-
operations, presentations in conferences and congresses, by welcoming delegations, through missions and
expertises in other countries. It takes part in the European standardization commissions and many authorities
and international working groups. The Sétra is an organization for technical approval, as an EOTA member
(European Organisation for Technical Approvals).
Design guide
mêÉëíêÉëëÉÇ=ÅçåÅêÉíÉ=ÄêáÇÖÉë=Äìáäí=ìëáåÖ=
íÜÉ=Å~åíáäÉîÉê=ãÉíÜçÇ=
Authors
This document was created by a working group consisting of:
Pierre Barras, CETE (Centre d’études Techniques et de l’équipement - Technical Engineering Center for
Infrastructure) du Sud-Ouest / Bridges Civil Engineering Structures Division)
Daniel de Matteis, Sétra (Service d’études techniques des routes et autoroutes -Technical Center for
Highways and motorways) / Large Bridges Division)
Jean-Michel Lacombe, DREIF (Direction régionale de l’équipement Ile de France – Ile de France
Regional Public Works Directorate) / Bridges Group
The monographs, iconography, drawings and 3D images were produced by Stéphane Chevrot, Philippe Julien,
Eric Lozinguez and Louis Resterrucci from the Sétra Large Bridges Division.
Acknowledgements
The authors would like to thank everyone who, through their help, comments and observations, contributed to
the creation of this document, especially:
Mr. Aubin (Bouygues), Mr. Bataille (Semi), Mr. Boileau (DDE 31), Mr. Chaboud (DDE 974), Mr. Doan
(SNCF), Mr. Duclos (Thales), Mr. Gaudin (SPIE), Mr. Gausset (EEG), Mr. Heusse (ERSEM), Mr. Kirschner
(SECOA), Mr. Le Faucheur (Sétra), Mr. Mossot (Demathieu et Bard), Mr. Poineau (Sétra), Mr. Primault
(Vinci), Mr. Ryckaert (SETEC), Mr.Thibaux (Eiffage TP), Mr.Treffot (DDE 67) and Mr. Xercavins (PX-
DAM).
Table of contents
AUTHORS 1
ACKNOWLEDGEMENTS 4
TABLE OF CONTENTS 5
FOREWORD 7
1 - BACKGROUND INFORMATION 8
1.1 - PREAMBLE 8
1.2 - TECHNICAL PROCESS 10
1.3 - FIELDS OF APPLICATION 11
1.4 - DEVELOPMENT OF THE CONSTRUCTION TECHNIQUE IN FRANCE 14
1.5 - MAJOR CIVIL ENGINEERING STRUCTURES RECENTLY CONSTRUCTED OUTSIDE OF FRANCE 19
2 - GENERAL DESIGN 21
2.1 - FIELD OF APPLICATION 21
2.2 - STATIC LONGITUDINAL DESIGN 21
2.3 - CHOOSING A CROSS-SECTION 30
2.4 - PRE-DESIGN OF A SIMPLE CROSS-SECTION 34
2.5 - BREAKDOWN INTO SEGMENTS 39
2.6 - MAIN RATIOS 41
3 - DESIGN AND VERIFICATION OF LONGITUDINAL CABLING 43
3.1 - CABLING PRINCIPLES 43
3.2 - STRESS CALCULATIONS 52
3.3 - VERIFICATIONS TO BE CARRIED OUT WITH REGARD TO NORMAL STRESSES 54
4 - TRANSVERSE AND LOCALIZED BEHAVIOUR 58
4.1 - VERIFICATION PRINCIPLES 58
4.2 - TRANSVERSE FLEXION 59
4.3 - GENERAL TANGENTIAL STRESSES 70
4.4 - SPECIFIC ELEMENTS 79
4.5 - LOCALIZED FORCES AND REINFORCEMENTS 81
4.6 - RULES TO COMBINE PASSIVE REINFORCEMENTS 85
4.7 - RECOMMENDED CONFIGURATIONS FOR REINFORCEMENTS 88
5 - CANTILEVER STABILITY 93
5.1 - PRINCIPLE OF CANTILEVER STABILITY 93
5.2 - STABILITY SYSTEMS FOR CANTILEVERS 94
5.3 - ACTIONS TO CONSIDERED 103
5.4 - COMBINATIONS OF ACTIONS DURING CONSTRUCTION 107
5.5 - VERIFICATION AND DIMENSIONING OF THE ANCHORING ELEMENTS 111
5.6 - VERIFICATIONS OF OTHER STABILIZATION METHODS 119
6 - CONSTRUCTION TECHNOLOGY 124
6.1 - CONSTRUCTION USING CAST-IN-SITU SEGMENTS 124
6.2 - CONSTRUCTION BY PREFABRICATED SEGMENTS 138
7 - ON SITE MONITORING 149
7.1 - BACKGROUND INFORMATION 149
7.2 - INSPECTION OF GEOMETRY 149
7.3 - INSPECTION OF TEMPORARY STRUCTURES 165
A3 BIBLIOGRAPHY 291
A3-1 – OFFICIAL TEXTS 291
A3-2 – SÉTRA GUIDES, SÉTRA-LCPC, SÉTRA-SNCF 291
A3-3 – OTHER PUBLICATIONS 291
A3-4 - ARTICLES IN MISCELLANEOUS PUBLICATIONS 291
AFPC/AFGC PUBLICATIONS FOR FIB (FÉDÉRATION DE L’INDUSTRIE DU BÉTON-CONCRETE INDUSTRY
FEDERATION) CONGRESSES 291
REVUE TRAVAUX 291
SÉTRA BULLETIN OUVRAGES D’ART 291
BULLETIN DES LABORATOIRES DES PONTS ET CHAUSSÉES 291
ANNALES DE L’ITBTP 291
TECHNIQUES DE L’INGÉNIEUR 291
PCI JOURNAL 291
REVUE L’INDUSTRIA ITALIANA DEL CEMENTO (IIC) 291
Foreword
The cantilever method is the most widely used technique for the construction of large prestressed concrete
bridges in France and throughout the world.
Since the beginning of the 1990s, concrete bridges built by this method have faced stiff competition in the
medium-span category from composite bridges and, to a lesser extent, from concrete bridges erected by
incremental launching. On the other hand, they are increasingly used for bridging large spans, as illustrated by
the Tanus viaduct over the River Viaur, the Tulle viaduct on the A89 highway and the new bridge over the
Rhine to the south of Strasbourg.
Intended for construction managers, consulting engineers and methods and project engineers, this guide
provides a detailed review of these structures, their field of use and the technology used in their construction.
For this reason, this guide replaces Technical Bulletin No.7 and its supplementary information, published by
Sétra (Service d’études techniques des routes et autoroutes - Technical Centre for Highways and Motorways in
December 1972, which had become obsolete with regard to several important points such as calculation
methods, prestressing design, the structure of form travelers and the management of delayed deformation.
Chapters 1, 2, 3, 5 and 6 of this guide cover certain points which are very specific to the cantilever method: the
general design of the structures, the design and calculation of longitudinal cabling, the stability of cantilevers
and construction technology.
Chapters 4, 7, 8, 9 and 10 are more generalized, respectively covering transverse flexion, site inspections,
problems and their repair, precautions to be taken to facilitate maintenance, and finally, the contents of
contractor tender documents. Although written with bridges constructed by the cantilever method in mind, the
information in these chapters will also be useful for anyone involved in the design or construction of large civil
engineering structures.
This guide is the outcome of a major collective effort and is another illustration of the expertise of French
contractors, engineering firms and construction agencies in the field of civil engineering.
Emmanuel Bouchon
1 - Background information
This first chapter introduces the major principles concerning the construction of bridges by the cantilever
method and its field of use. It also describes the history of the development of this method and of the applicable
regulations from 1943 to the present day.
1.1 - Preamble
The cantilever construction method is a very ancient technique, in which a structure is built component by
component above ground level.
Since ancient times, this method has been used for the construction of arches in Europe (Fig. 1.1) and in South
America (including the construction of Mayan arches), and for the building of wooden bridges (Fig. 1.2).
In the 19th and early 20th centuries, this method was applied to the construction of arched metal bridges, such as
the Gabarit and Viaur viaducts, or lattice girder designs, such as the Forth Bridge, the Bénodet bridge or the old
Pirmil bridge at Nantes (Fig. 1.3).
Fig. 1.3 – The old Pirmil bridge in Nantes Fig. 1.4 – The Normandie bridge
More recently, it has been used for the construction of cable-stayed bridges, such as the Saint-Nazaire bridge
over the River Loire and the Normandie bridge over the Seine (Fig. 1.4).
As far as prestressed concrete is concerned, construction by the cantilever method mainly applies to bridges
whose decks can be combined with straight or horizontally curving beams and which are built out from their
piers, with cast-in-situ or prefabricated segments (Fig. 1.5 and 1.6). These types of bridges are the focus of this
guide.
Fig. 1.6 – Cantilever construction of prestressed concrete box-girder bridge decks with cast-in-situ segments on the left and
prefabricated segments on the right
Many of the techniques used in this method are also employed in the construction of portal bridges with box
girder decks, such as the Bonhomme bridge in the Morbihan region of Brittany, the Auray viaduct (Fig. 1.7) and
the bridge over the River Truyère at Garabit.
Fig. 1.7 – Construction of the Auray portal bridge Fig. 1.8 – The cable-stayed bridge at Chalon-sur-
Saône under construction
Finally, and although not strictly within the scope of this guide, it should be mentioned that the cantilever
method is often used for the construction of cable-stayed bridges, such as the Iroise bridge over the River Elorn,
near Brest and the Bourgogne bridge at Chalon-sur-Saône (Fig. 1.8) and also for concrete arched bridges such as
the Roche Bernard bridge over the River Vilaine (Fig. 1.9) and the bridge over the River Rance.
This construction method consists of erecting the majority of a bridge deck without falsework or scaffolding at
ground level, by working in consecutive sections known as segments, each of which is cantilevered out from the
preceding segment. After a segment is built, the prestressing tendons fixed to the extremities are tensioned,
firmly attaching them to the preceding segments and thus forming a self-supporting cantilever which serves as a
support for the subsequent operations.
• Symmetrically in general, either side of a pier in order to minimize the moments transmitted to this
support during erection; the resulting double overhang is called a balanced cantilever (Fig. 1.10)
Although it is possible to build an entire structure using the cantilever method, the majority of structures include
cast-on-falsework sections at the extremities of the end spans.
Cantilever construction is often used in association with other methods such as:
• Construction on falsework, when parts of the structure are close to the ground and feature modest spans
• Construction by incremental launching, when the structure features a series of spans less than 65m in
length, of constant depth, supporting a road whose geometry is compatible with this technique.
Spans of 80 to 150m are preferred for bridges with prestressed concrete box girder decks built by the cantilever
method. However, this technique can be used for spans up to 200m in common widths without major problems.
Above this size, the quantities of materials increase significantly, thus reducing the cost-effectiveness of the
method.
The world record span for concrete bridges built by the cantilever method currently stands at 301 m and is held
by the Stolma Bridge in Norway. This is closely followed by the Raftsundet Bridge in the Lofoten Islands, also
in Norway, with a central span of 298m. Opened to traffic at the end of 1998, both of these bridges have central
spans partially made from lightweight concrete. These bridges both surpassed the Brisbane Bridge in Australia,
built in 1986, whose span of 260m had beaten the previous record of 240 m held by the Hamana Bridge in
Japan, built in 1977.
For a long time, the Gennevilliers Bridge, built in 1976, held the French record for the longest span with its two
spans of 172m. Following closely behind with spans of 172m and 144m was the Ottmarsheim Bridge, built over
the Alsace canal in 1979 using concrete partly made from lightweight aggregates. With a single span of 190 m,
the Tanus viaduct over the River Viaur in the Aveyron (Fig. 1.13) captured the record in 1998 before being
relegated to second place in 2002 by the new bridge over the River Rhine, south of Strasbourg, whose central
span measures 205m.
Firstly, the bridge decks are mostly built without any contact with the ground, making it possible to build
structures over rivers subject to severe flooding or above very deep and rugged valleys.
This method can also be used to erect structures with very different geometries. Thus, in elevation, it is possible
to design decks of a constant or variable depth. For the latter, parabolic, cubic or linear variations are all
possible. The method is extremely forgiving with regard to the geometry of the road supported by the bridge
because, in contrast to incremental launching and pushing techniques, any horizontal and vertical alignments
can be built without difficulty.
Finally, construction using elements of 3 to 4 m in length is cost-effective in terms of the formwork tools
required for the bridge deck, even if the spans are few in number and of different lengths. In the case of
prefabricated segments, the small size of these components also helps to limit the weight of the elements to be
assembled, thus reducing the cost of the installation equipment.
Disadvantages
However, there are also certain drawbacks to the cantilever construction method.
For identical spans, bridges built using this method are much heavier than composite structures. They therefore
need larger supports and foundations than those required for composite structures. Of course, this makes the
cantilever method less attractive, especially when the foundation terrain is of mediocre quality or when the site
is in an earthquake zone.
Another major disadvantage to this method is the large number of tasks which have to be carried out in situ,
both for the casting of the deck and for the development of the access routes to the site. Although the number of
these tasks is reduced when the segments are prefabricated, of course, they are nevertheless greater in number
than for an incrementally launched concrete bridge. When the structure crosses traffic bearing routes, the
frequency of these tasks may compromise the safety of travelers and/or of workers on the site. These routes
must then be closed, which often poses major problems.
From an aesthetic point of view, bridges built by the cantilever method often have relatively thick decks, which
can pose problems on certain sites. As a result, by breaking down their construction into small elements and
multiple casting phases, there are more likely to be differences in color between two consecutive segments.
Spans
120
150
200
300
35
70
90
Type
Now, prestressed concrete box-girder bridges built using the cantilever method are designed for spans between
60 m and 300 m in length. This technique has to compete with a number of different solutions operating within
this very wide range of spans.
For spans of less than 80 m, bridges built using the cantilever method are most commonly of a constant depth.
They are in competition with girder bridges with a composite concrete and steel framework. If the geometry of
the supported road is compatible, they also have to compete with incrementally-launched bridges made from
prestressed concrete, which are economically viable for spans of between 35 and 70 m.
For spans of between 70m and 120m, bridges built by the cantilever method may be of constant or variable
depth. They are in competition with girder bridges with a composite concrete and steel framework. For practical
or aestetic reasons, composite concrete and steel box girder bridges or cable-stayed bridges are also often
designed to cover this range of spans.
For spans of between 100 m and 200 m, bridges built using the cantilever method are almost always of variable
depth and are in competition with composite or metal box girder bridges (beyond 140m) and cable-stayed
bridges. Within this range of spans, presetressed concrete box girder solutions with lightweight metal webs may
also prove to be economical.
1.4.1 - 1946-1952
Construction using the cantilever method was used for the first time in France by Albert Caquot for the building
of the Donzère and Bezons reinforced concrete bridges in 1953, using a form traveler suspended from a metal
girder (Fig.1.15).
In Germany, Finsterwalder also used this technique for the construction of the Neckarsens and Baldunstein
prestressed concrete bridges in 1950. It was then used for the construction of the Worms and Koblenz cantilever
bridges in 1952, featuring a large span of 114 metres (using the form traveler technique).
In the same year, Nicolas Esquillan used a very similar technique with a form traveler suspended from a metal
beam to build the La Voulte railroad bridge, consisting of several 60 m-wide portal spans.
It should be noted that at this time, there were no French design regulations concerning the cantilever
construction method or even for prestressed concrete.
1.4.2 - 1953-1964
This period was marked by the introduction of regulations, the development of design methods, the
improvement of the characteristics of prestressing reinforcements and the development of prestressing
procedures.
During this period, the bridge-building techniques using the cantilever method improved considerably. As a
result, we can refer to two distinct generations of bridges.
The bridge decks of first generation structures were embedded on piers and even on abutments and featured
hinges at mid-span.
Built in 1957 by GTM, the Chazey bridge over the River Ain was the first French bridge to be truly built by the
cantilever method and the first in a series of major structures including the Beaucaire bridge over the River
Rhône and the Savines bridge over the Serre-Ponçon reservoir dam in the Hautes-Alpes region. The Chazey and
Beaucaire bridges suffered from prestressing defects and have since been demolished. The former was replaced
by a new cantilever bridge in 1973 and the latter by a composite bridge in 1995.
As the first generation bridges suffered from an excessive deformation of their cantilever elements after several
years, due to an underestimation of the effects of concrete creep and shrinkage, a second generation of bridges
was designed and built with continuous spans and therefore without hinges at mid-span.
• The bridges at Goncelin, over the River Isère and Lacroix-Falgarde over the Ariège, designed by the
STUP (Société Technique pour l’Utilisation de la Précontrainte – Engineering Company for the Use of
Prestressing). These were the first continuously rendered structures (1962)
• The bridges of Choisy-le-Roi, near Paris, and Pierre-Bénite, near Lyons, built in 1965 by Campenon-
Bernard, which were the first structures to use prefabricated segments and glued conjugated joints.
1.4.3 - 1965-1975
This was a period of enormous developments and constantly changing regulations. It began with the publication
of the IP1 (Circular no. 44 of August 12 1965 relating to the provisional instruction for the use of prestressed
concrete), and it finished with the publication of the Circular of April 2 1975, which brought an end to the
second generation structures and paved the way for third generation bridges.
• The Oléron bridge (1966), approximately 3,000m in length and built using prefabricated segments
installed for the first time by a launching beam
• The Oissel bridge over the A13 highway: 700m long without an intermediate expansion joint (1970)
• The Calix viaduct in Caen, whose collapsed cantilever prompted the Sétra to define its rules for the
stability of cantilevers which are still in force today (1975)
• The Saint-Cloud bridge (1974), on the outskirts of Paris, whose very wide (20.4 m) and slender deck
(spans of 100m and a 1/30 slenderness ratio), had to be reinforced in 1990
• The Gennevilliers bridge over the River Seine near Paris, with a span of 172 m (1976)
• The bridge over the River Loire at Orléans (1976), whose box-girder deck featuring three webs with bar
prestressing, had to be repaired in 1978 and 1987.
1.4.4 - 1975-1982
Bridges built during this period can be described as third generation bridges. Designed in accordance with the
rules established by the Circular of April 2 1975, (including accounting for creep and thermal gradient), these
structures were much better designed and did not suffer from the difficulties encountered with previous
generations of bridges.
Worthy of note amongst the structures built of conventional concrete during this period are:
• The Mâcon bridge over the Saône, which was one of the first new-generation bridges (1977)
• The numerous interlaced viaducts of the Saint-Maurice interchange, between the A4 and A86 highways
near Paris, built with prefabricated segments (1980)
• The Mathilde bridge near Rouen, whose central span includes an independent 115m long metal span,
supported on a 30-m cantilevered girder made from prestressed concrete (1980).
Between 1975 and 1982, several bridges were also made from lightweight concrete, such as:
• The Tricastin bridge (1979), whose end spans and the beginnings of its central span are made from normal
concrete, which acts as a counterweight and compensates for a highly unfavourable arrangement between
the spans (25m – 142m – 25m) ;
• The Ottmarsheim bridge, which features a 172m lightweight concrete span (1980).
Two remarkable railroad structures were also built during this period:
• The crossing of the Seine at Nanterre via the railroad spur for the new town of Cergy-Pontoise (1977),
which is a prestressed concrete structure of 1,390 m whose two viaducts of 229 m (48m, 85m, 48m, 48m)
and 221.5m (48m, 85m, 48m, 40.5m) were built using the cantilever method
• The 400m long Viaduc de Commelles on the “conventional” Paris-Brussels and Paris-Lille lines, with a 4-
web box-girder deck carrying four railroad lines and featuring main span of 45m (1980).
On the regulatory level, this period was characterized by the generalization of regulations concerning limit state
calculations (BPEL 83 [Béton Précontraint par la méthode des Etats Limites – Limit State Prestressed Concrete
Code], followed by BPEL 91 and finally BPEL 91 revised in 1999). The introduction of Quality Assurance and
the development of french and european standardization also led to clear changes in the rules concerning the
building of structures.
On the technological level, major progress was made in the design of major civil engineering structures made
from prestressed concrete, due largely to the development of external prestressing.
The following structures are notable examples of traditional road bridges built during this period, although this
is not an exhaustive list:
• The bridge over the River Loir at La Flèche, which was the first bridge to be built by the cantilever
method and positioned by rotation (1983)
• The Pont à Mousson viaduct over the River Moselle, which was one of the first bridges to feature external
prestressing
• The Sermenaz viaduct, near Lyons, with completely external galvanized prestressing
• The Île de Ré bridge (1988) whose deck consists of 3,000 m of prefabricated segments made from B60
category high-performance concrete
• The Arrêt-Darré viaduct, whose cantilevers were angled at the end of construction to follow the
longitudinal profile (1988, [SER 90])
• The viaducts of Bourran, at Rodez, and La Rivière Saint-Denis, on Reunion Island, whose design features
double-shelled piers (1991, [BOU 91], [BOU 94.1], [CON 91], [BOU 92] and [BOU 94.2])
• The Cheviré bridge, in Nantes, whose central span of 242 m includes an independent span of 162 m in
length, consisting of a box-girder with an orthotropic deck plate (1991, [VIR 90 2], [VIR 91 2] and [VIR
94])
• The Arcins bridge, near Bordeaux, consisting of two parallel structures of 650 m in length made from
prefabricated segments assembled by combination prestressing (1993, [ABE 91] and [ABE 94], Fig.
1.16)
• The construction of a parallel lane on the Gennevilliers bridge over the River Seine [CHA 94]
• The Piou and Rioulong viaducts on the A75 highway, whose cantilever segments are supported by metal
struts (1995, [CRO 94] and [CIL 96], Fig. 1.17)
• The Viaduc de Rogerville on the A29, featuring two 680-m long decks made from prefabricated segments
with innovative keyed expansion systems on certain spans (1996, [RIC 96], [JAC 96] and [JAC 98])
• The Tanus viaduct over the River Viaur, spanning 190 m and featuring a pier of over 100 m in height
(1998, [BOU 94.3], [SER 98] and [GAC 98])
• The second Pont-Salomon viaduct, which represents one of the first applications of Eurocodes 1 and 2
(2000, [DAL 00] and [DEWOl]
• The viaducts of La Clidane (length: 132 m), La Barricade (length: 150 m) and Tulle (length: 180 m),
supporting the A89 highway [LAC 02]
• The new bridge over the Rhine to the south of Strasbourg, which boasts a record single span structure of
205 m above the navigable channel of the Rhine (2002, [DEM 00], [DEM 01.1], [DEM 01.2], [DEM
01.3], [DEM 02]).
Fig. 1.16 – The Arcins bridge in Bordeaux Fig. 1.17 – The Piou viaduct
Particularly notable portal road bridges built using the cantilever method since 1983 include:
• The bridge over the Loch d’Auray, with an opening of 109 m between the base of the portal legs (1989,
[VIR90.2], Fig. 1.18)
• The bridge over the River Truyère at Garabit, with an opening of 195 m between the base of the portal
legs (1993, [GIL 93] and [CAN 94]).
Noteworthy railroad structures built since 1983 include several viaducts on the TGV high-speed Rhône-Alpes
line (extension of the TGV Paris-South Eastern line to Valence) and of the TGV high-speed Méditerranée line,
including:
• The Costière viaduct, situated in the northern section of the eastern Lyons bypass: 1,725 m long in total,
900 m of which were built using successive cantilever segments with main spans of 88 m (1992).
• The Avignon viaduct over the River Rhône, whose two independent 1,500-m long decks were
prefabricated (Fig. 1.19, [BOUS 98.1])
• The Vernègues viaduct, with a semi-circular transverse cross section. Measuring 1,210 m, this was built
using a combination of the cantilever method and incremental launching techniques [BOUS 98.2]
• The 1,734-m long Ventabren viaduct, which relied upon incremental launching techniques, successive
cantilever segment construction and a rotated installation.
Fig. 1.18 – The portal bridge over the Loch d’Auray Fig. 1.19 –TGV high-speed railroad bridge over the Rhône at
Avignon
Finally, a number of highly innovative road structures were also built during this period, including:
• The Sylans and Glacières viaducts over the A40. With respective lengths of 1,266 m and 214 m, both of
these structures featured two parallel decks with triangulated concrete webs (1987, [BOU 90])
• The Corniche bridge at Dôle with corrugated webs, (1994, [COM 93], [LEB 94] and [REI 94])
• The three Boulonnais viaducts over the Al6 highway, whose decks are made of prefabricated segments
with four triangulated metallic webs [MEU 98]
• The bridge over the Vecchio in Corsica, with open webs made of prefabricated triangular panels (1999,
[PAU 98] and [PAU 00])
• The bridge over the Bras de la Plaine, on Reunion Island, whose single 260-m span is made from two pre-
stressed slabs linked by a triangular tubular metal structure (2002, [CHU 02], Fig. 1.20).
• Access viaducts to the new Severn Bridge in Great Britain [COM 94] and [COM 96]
• The new São João railroad bridge over the River Douro in Portugal
• The Medway Viaduct on the TGV high-speed rail line between the Channel Tunnel and London [POROl].
Although built using a slightly different method to that described in this guide, we should also make a special
reference to extraordinary Confederation Bridge between the North American continent and Prince Edward
Island in Canada, whose central section is made from forty 250-m long spans (Fig. 1.21, [BOI 96] and [COM
98]).
Fig. 1.20 – The bridge over the Bras de la Plaine Fig. 1.21 – Transportation of a prefabricated cantilever for the
Confederation Bridge
2 - General design
This chapter starts by covering the more general aspects of the design of bridges with box girder decks built by
the cantilever method: layout of the supports, deck height variation law and choice of a cross-section.
It goes on to describe the more specific aspects of the project: design of a simple cross-section, layout of the
segments and ratios of materials. The chapter only covers road bridges.
• It is suitable for a very wide range of spans (from 40 to 200 m, or even 300 m)
• The supported road can have any type of geometry, both horizontally and vertically
• Between 60 and 100 m, the bridge deck can be of constant or variable depth
• This method can be used regardless of the natural characteristics of the gap to be bridged (large depth,
steep slopes, very poor-quality soils, coastal site, etc.).
We shall cover each of these different points in detail during the course of this chapter. We shall also see how
piers are positioned in the gap to be bridged, how the transverse structure of the deck is chosen and designed
and how its formwork is accurately determined.
The simplest structures are made from main spans of identical length. This allows the construction of identical
cantilevers, which simplifies the design of the erection and concrete casting equipment used and improves
output.
The end spans are usually longer than a half-cantilever. The additional length, representing 10 to 20 percent of
the length of the main spans, is usually built on falsework as this is generally the most economical method. It
helps to balance out the moments in the different spans under operating loads and ensures positive support
reactions on the abutments.
Fig. 2.1 – Distribution of spans for a simple bridge built by the cantilever method
Fig. 2.2 – Bridges with a combination of large spans in the river section and shorter spans on land
Fig. 2.3 – Bridge consisting of variable length spans according to the depth of the gap
Therefore, the most common structures consist of a series of equal spans flanked by end spans which are 60 to
70 percent of the length of the main spans.
Gaps to be bridged often feature constraints that make it impossible to design a structure of the type we have
just described. It then becomes necessary to build structures incorporating several different types of cantilevers.
The example in Figure 2.2 below shows a structure consisting of one or more large spans, as required by the
need for a wide navigation channel, and a series of shorter – and thus more economical – spans crossing
unnavigable flood zones.
The example in Figure 2.3 shows another structure featuring a large span in the deepest part of the valley to be
crossed and shorter spans elsewhere.
In both of these cases, it should be emphasized that the transition from large to small spans is carried out via a
span whose length is the mean of the two standard spans. It should also be noted that the end spans are 60% of
the length of the adjacent standard spans.
Other examples
Certain special techniques may be used to circumvent these strict rules concerning the distribution of spans and
the balancing of cantilevers. They include over-cantilevering, the use of counterweights and building out from a
counterweight span, etc. These techniques are described in Paragraph 2.2.4. Due to their cost, they are only used
in very specific cases imposing the layout of piers (highly urbanized sites or the presence of railroad lines and
canals) or when it is impossible or particularly costly to extend the bridge deck.
Nevertheless, for structures of a constant depth, it is possible to design unequal spans by shifting the joints (à
valider pour "clavages"). It is then possible to shift certain piers slightly, which would otherwise be badly
positioned (Fig. 2.4).
We shall now discuss the variation laws which determine the possible depth of the bridge deck, while
mentioning the most economical solution for each range of spans.
With regard to the criteria concerning suitability for the site, it is very difficult to establish rules to dictate the
most appropriate form for a given site. However, it should be noted that:
• If it is possible, a constant depth is well suited to geometrically complex structures: especially very curved
bridges; the same applies to structures located in complex areas (urban sites, interchanges, etc.)
• A variable depth is generally quite well suited to deep valleys and large watercourses
• It is often a good idea to highlight certain sections of the gap by using spans of variable depths at its most
outstanding sections.
When the main spans of a structure are less than 65/70 m long, bridge decks of a constant depth are generally
the most economical, because the savings made by simplifying the formwork tools for the deck (form travelers
or prefabrication units) and reinforcement for the deck are much greater than any possible savings in materials.
In this case, the depth of the deck is between 1/20 and 1/25 of the maximum span. However, a minimum of 2.20
m is required for satisfactory movement inside the box girder.
Fig. 2.4 – Slight shifting δ of the piers for a structure of constant depth
(The shifting of the joints δ is thus double the value of δ)
For spans of above 100 m in length, the quantities of concrete and prestressing materials used increase
significantly and the cost of a constant depth solution increases in comparison to a variable depth solution. For
structures with very tall piers, which are sensitive to the effects of wind both in service and during construction,
this phenomenon is even more noticeable as the surface area affected by the wind increases by approximately
25%.
In spite of the previous comments, the desire to create increasingly elegant and original structures has led to the
design of structures with decks of a constant depth for spans well in excess of 90/100 m in recent years. For
example, the unsuccessful concrete-based design for the Verrières viaduct featured a deck of a constant depth
despite having a maximum span of 144 m.
In excess of 65 m/70 m, very large forces affect the cantilevers, requiring a large deck depth at piers which
seems very excessive at the other sections of the span. It therefore becomes economically viable to build a deck
of variable depth.
For these structures, the variation in depth between the crown and the pier is generally parabolic in form. The
cantilever must be symmetrical in order to guarantee its stability during construction. The section of end span
which is cast on falsework or built by over-cantilevering is always of a constant depth (the same depth as the
crown).
In standard cases, the depth at the pier hp is between 1/16 and 1/18 of the length of the span in question. The
depth at the crown is generally between 1/30 and 1/35 of this same distance, with a minimum of 2.20 m for ease
of movement within the box girder.
hc hp
A statistical study carried out for the publication of this guide shows that the following formulas can be applied
to a deck on simple supports:
l l
On pier: = 14 +
hp 45
l l
At the crown: = 19 +
hc 7
This formula is applicable for any value of l included in the field of application for bridges built by the
cantilever method.
In recent years, certain structures have been built with a cubic-type variation in deck depth. This solution, which
slightly reduces the effects of selfweight, results in a somewhat more stretched appearance than a parabolic
variation. However, this may pose problems due to insufficient depth in the quarter-span area, because the
variation in depth may be unsuited to the distribution of bending moments and shear forces. As the curvature is
more pronounced near the piers, it is also important to ensure that the sideways thrust due to the compression of
the lower slab is correctly accounted for.
Certain structures have also been designed featuring a linear variation in depth over 20 to 25% of the length of
the main span, with the remainder of the spans being of a constant depth (Fig. 2.7). Although it is quite easy to
implement, this solution is only used for modest spans. It is sometimes adopted for architectural reasons or to
create a slightly greater clearance than that which is given by a parabolic intrados. It requires the presence of a
cross beam at the level of the change in gradient, in order to take up the vertical component of the compression
in the lower slab.
Designers often design structures with spans of very different lengths in response to the constraints imposed by
the gap to be crossed. In such cases, it is possible to give the deck a variable depth in the large spans and a
constant depth elsewhere (see the example in Figure 2.3). Clearly, for transition purposes, the depth of the large
spans at the crown must be equal to the depth of the deck in the areas of constant depth, which often leads to the
adoption of a deeper deck than is necessary.
We shall now describe the support conditions on piers possible for a bridge deck built using the cantilever
method (simple supports, fixed support, etc.), along with the field of application for each of these solutions.
The majority of bridges built by the cantilever method rest on simple bearings when in service, whereas during
construction, they are embedded on piers using the cantilever stabilizing devices described in detail in Chapters
5 and 6.
In most cases, elastomeric pot bearing devices are used for the permanent bearings. These are particularly
suitable for bridges built by the cantilever method as they are extremely robust, compatible with very large
vertical loads and compact. They are also available in several types – fixed models, models that slide one way
and those that slide in multiple directions – thus absorbing the movements of the bridge deck at the end
supports.
However, when the vertical forces are less than 7 MN per bearing, it is possible to use laminated rubber
bearings. These are also used in earthquake zones, as they improve the distribution of horizontal forces between
the supports.
When the piers are very tall, it is often preferable to embed the bridge deck on top of the pier (Fig. 2.9). This
solution was first used by Campenon Bernard in 1963 for the bridge over the Moulin à Poudre valley in Brest.
This technique offers the benefit of simplifying the bridge’s construction and service since no provisional
cantilever stabilizing devices or bearings are used.
However, the piers and central span form a frame which is sensitive to the linear deformations of the deck under
the effects of temperature, shrinkage and creep. If the piers are short and solid, their great rigidity causes
moments and shear forces which they are not usually capable of withstanding. Therefore, this is only a viable
solution for very tall structures on slender piers.
In certain cases, rather than being hollow, the piers consist of two separate shafts with a gap of several metres,
penetrating into the box girder (Fig. 2.10). The fixing in this situation is almost perfect as it uses the
compressive and tensile stresses present in each of the shafts while remaining flexible with regard to horizontal
movements, because each shaft only offers a low level of resistance to flexion. The Pont de Choisy-le-Roi over
the River Seine was built according to this principle.
In general, this can prove to be an excellent solution in earthquake areas as it gives the structure a high level of
longitudinal flexibility.
It was recently used for the construction of several structures such as the Tulle viaduct in which the upper part
of the main piers is made from double shafts, both consisting of a box girder, and in the Rodez and La Rivière
Saint-Denis viaducts in which the piers are made from two thin walls [BOU 91] and [BOU 92].
2.2.3.3 – Bridge decks that are partly embedded and partly supported on simple
bearings
Many structures have to bridge gaps with significant variations in depth. This requires piers of very different
heights.
When the gap is crossed by a series of identical standard spans, and thus with identical cantilevers, the deck
usually rests on simple bearings on all of the piers. This solution makes it possible to keep the structure very
repetitive and therefore easy to construct.
When the gap is bridged by a structure featuring spans of different lengths, it is often advisable to embed the
deck on top of the tallest piers and use simple bearings for the other piers. This technique was adopted for the
viaduct over the River Viaur at Tanus [SER 98] and for the Pays de Tulle viaduct [LAC 02] over the A89
highway.
2.2.3.4 – Bridge deck embedded on two rows of bearings on piers (for information)
In the interests of thoroughness, we would like to mention that a third solution was used in the past and
consisted of fitting two rows of laminated rubber bearings on top of each pier. This created a elastic fixed
support for the deck on the pier.
The bridge connecting the French island of Oléron to the mainland and the Blois bridge over the River Loire
were built according to this principle.
This solution is no longer in use today because, due to the bulkiness of the bearing devices, very wide pier heads
were required and these were considered to be visually unattractive.
2.2.4.1 – Over-cantilevering
The over-cantilevering technique consists of extending the length of one side of a cantilever by one or more
segments, with the other side being already joined to the adjacent cantilever or to a cast-on-falsework section
(Fig. 2.11). Therefore, this method can be used to extend one span in relation to the others.
Fig. 2.10 – Bridge deck embedded on two piers which are both made from two parallel walls
This technique seriously complicates the cantilever cable layout for the segments forming the extended
cantilever. Indeed, as the rear anchorages of these tendons cannot be placed on the edge of the segments, they
must be housed either inside anchor blocks within the box girder, thus complicating the formwork operations, or
in a cross beam on top of the pier, which significantly lengthens these tendons. This technique must therefore be
used sparingly: when using a form traveler to build the section of an end span which would usually be cast on
falsework in a very steep-sided valley, for example.
A gap to be bridged sometimes features a very long and distinct central area (a river or a ravine etc.) in which it
is impossible to erect any piers. In these situations, the designer may decide to design a normal structure with
piers either side of the central area and end spans equal to 60 % of the length of the central span. If this approach
produces end spans which are located very close to ground level, therefore being useless, it might be worth
opting for two short end spans which are cast on falsework, with a deep cross-section to act as a counterweight.
The central span would therefore be entirely constructed by over-cantilevering out from these two spans (Fig
2.12). The bridge over the River Est on Reunion Island is a good illustration of this method.
Another good example of this technique is provided by the Nantua viaduct. On this viaduct, it was impossible to
build the far end of one of the end spans on falsework. Over-cantilevering out from the adjacent pier was also
difficult given the length of this section, so the engineers decided to use the over-cantilevering technique from a
small additional span built on falsework and situated on the adjacent slope. As this span was designed to be
supported in the neighboring Chamoise tunnel, the engineers made this span as short as possible by giving it a
very massive and thus very heavy cross-section, which was able to compensate for the imbalances.
This technique requires the development of a specific cabling arrangement. For the large span, this closely
resembles traditional cantilever cabling, but in the counterweight spans it is very different, with numerous
cables anchored in the cross beams on abutments or in the interior anchor blocks.
It should be noted that large forces are transmitted to the counterweight. Therefore, it is essential to ensure that
the forces are properly transmitted from the bottom for the counterweight box to its vertical walls and up to the
cantilever tendons which are anchored there.
It is sometimes impossible to design sufficiently long end spans, i.e. at least 55% of the length of the adjacent
span. In this situation, the weight of the segment on the abutment and the end cross beam in which the external
tendons are anchored is not enough to counteract the support uplift under the effect of a rare load applied in the
central span. To prevent this phenomenon, which would eventually lead to the failure of the expansion joint, the
box girder can be filled with concrete poured during the second phase through hatches built into the upper slab.
It is also possible to increase the thickness of the cross-section of the cast-on-falsework section of this span (Fig.
2.13).
For very short spans, when the support reactions on the abutments are still negative, it is possible to reverse the
direction in which the bearings operate (Fig. 2.14) and to make the walls or posts of the abutments work in
traction, as is the case for the Ottmarsheim and Beaumont-sur-Oise viaducts. However, this is a highly complex
solution, which can lead to significant problems during the changing of bearings and it should only be adopted
when all of the very severe installation constraints have been taken into consideration.
2.2.4.4 - Hinges
Historically speaking, the first structures to be built using the cantilever method incorporated a crown hinge
(Fig. 2.15).
The advantage of this solution was to create an isostatic structure in its permanent phase. Therefore, there were
no barriers to stand in the way of deformations due to concrete shrinkage or creep or temperature variations, and
there were no parasitic stresses.
However, it was difficult to adjust the hinges due to the fact that it is difficult to estimate the deformations
affecting the cantilevers during construction. The differential height difference between the ends of two adjacent
cantilevers could be compensated for by applying a vertical force, but a sudden change in level remained and
this became more pronounced over time under the effect of delayed deformations due to creep. Furthermore, the
hinges have a limited life span and there is a risk of seizure or blockage.
This solution also requires the presence of a expansion joint which is expensive to maintain.
As they are sources of major pathologies on these first structures to be built using the cantilever method, hinges
are hardly ever used on modern bridges. They are only found on a few very long structures (e.g. the Cheviré
bridge in Nantes, or the Île de Ré bridge etc.) to allow for expansion and/or to reduce the risk of damage to the
structure in event of impacts from heavy ships. In all circumstances, they are no longer situated at the crowns of
the spans.
In this interests of thoroughness, we should also mention the devices used on the Rogerville viaduct on the A29
highway [UAC 98]. These devices, consisting of two metal beams parallel to the webs of the box girder, make it
possible to fit expansion joints in the deck while transmitting shear forces and bending moments.
In the 1980s, several large span structures were partially built from lightweight concrete as this reduced the
selfweight of the bridge deck box girder.
Faced with stiff competition from other solutions (composite box girders, prestressed concrete box girders with
lightweight metallic webs, etc.) this technique has virtually disappeared in France. On the other hand, as
mentioned in Chapter 1, the two largest bridges in the world built by the cantilever method feature lightweight
concrete sections in their central span.
The large overhangs created in the construction phase require the use of a cross section with a high resistance to
torsion. This is one of the reasons why designers opt for box girders. These cross-sections also feature a lower
slab which lowers the centre of gravity and allows for efficient cabling on the pier. This is of paramount
importance, as construction by the cantilever method produces very large negative moments.
There are several types of box girders. We shall now describe them and specify their fields of application.
For deck widths of less than 20 m, the most economical solution is almost always a box girder with two webs,
featuring two solid slabs.
Upper slabs are made from reinforced concrete for widths of up to 15 or 16 m. For longer widths, they are often
transversally prestressed using low-strength tendons. For example, there may be three or four waxed or
lubricated T 15 single strands per metre or four 4T15S tendons per 3.50 to 4.00 metre segment.
This type of box girder is compatible with all of the deck depth variation laws (constant, parabolic, etc.).
For deck widths of between 18 and 25 m or more, the most common solution consists of a box girder with two
webs, featuring a ribbed upper slab and a solid lower slab (Fig. 2.17).
One rib is used per standard segment, i.e. one every 3 to 4 m. In the narrowest structures, these ribs are made
from reinforced concrete and they are of constant depth between the webs. When the decks are very wide, the
ribs have a more elaborate geometry and are prestressed using medium-strength tendons (12T15 or 19T15).
The presence of ribs complicates the formwork for the deck and thus the construction of the segments. Before
choosing a design for the transverse ribbing, it is therefore advisable to verify the resulting weight gain in
comparison to a prestressed slab that is thicker but of constant depth. Furthermore, the external tendons must not
strike the ribs near the cross beam on the pier. Recesses in the ribs are therefore created close to the piers or
shorter ribs are used, thus allowing the tendons to pass freely.
As in the previous example, this form of box girder is compatible with all of the height variation laws.
For deck widths of between 18 and 25 m, it is also possible to design decks featuring a slab of constant
longitudinal thickness without ribs, although this is often prestressed (Fig. 2.18). The webs are usually vertical
and the steel or reinforced concrete struts are aligned under the cantilevers [GIL 96]. The struts may also be
replaced by two acutely angled lateral concrete walls (Fig. 2.19).
These structures are aesthetically very pleasing. However, they are somewhat more difficult to construct than a
box girder featuring an upper slab with ribs. Furthermore, they are restricted in application to structures of a
constant depth. Indeed, if the depth of the box girder varies, the axes of the struts or the lateral walls must be
distorted, which is extremely difficult and costly to carry out. Because of this, their use is restricted to structures
with a maximum span of 80 to 90 m.
Fig. 2.17 – Example of a wide box girder with slab featuring prestressed rib stiffeners
Fig. 2.19 – Example of a wide box girder with thin lateral walls
For large widths, it is also possible to design a bridge deck consisting of two box girders connected by their
internal cantilevers (Fig. 2.20).
In France, this solution is now rarely used on very wide structures. However, in other countries, it has recently
been used on several occasions, including for the access viaducts built from prefabricated segments for the new
bridge over the River Tage in Lisbon, and the viaducts for the second crossing of Severn estuary in England
[COM 96]. It also remains widely used in Asia. It should be mentioned that this type of structure is particularly
suitable for the construction of wide prefabricated bridge decks, as this involves the construction of two narrow
decks side by side which are then fixed together transversally.
Nevertheless, controlling the creep-induced deformations in each of the box girders made from concrete of
different ages remains a major problem during the construction of these structures. Furthermore, in the case of
structures with skew lines of support or those featuring shifted piers for each box girder, the installation of the
transverse prestressing is highly complex.
Like the simple monocellular box girders, double-cell box girders are compatible with all of the deck depth
variation laws (constant, parabolic, linear, etc.).
For widths of between 15 and 20 m, it is possible to design box girders with three webs (Fig. 2.21).
• They are difficult and costly to build because two formwork cores must be used
• For the same cost, more aesthetically pleasing structures with struts or transverse ribs are often preferred
• Certain structures of this type have been affected by major pathologies, due to the difficulty of
guaranteeing the even distribution of forces between the webs.
Fig. 2.20 – Example of a bridge deck consisting of two box girders joined together transversally
Fig. 2.21 – Older solution consisting of a box girder with three webs
These box girders are still constructed overseas and particularly in South-East Asia, where labour is cheaper.
Furthermore, western companies have exported their equipment to these countries.
A number of structures featuring highly original and innovative bridge decks were constructed in France during
the 1990s.
First, we shall mention the Sylans and Glacières viaducts, constructed for the A40 highway near Nantua at the
end of the 1980s. These viaducts feature two independent, different in height, prefabricated prestressed bridge
decks, in which the conventional full webs are replaced by an ultra-lightweight concrete truss, as for the
Bubiyan bridge in Kuwait.
Built in the 1990s to support the Al6 highway, the Boulonnais viaducts also feature bridge decks consisting of
prefabricated segments with truss webs, which on this occasion are made from metal tubes [MEU 98].
The Corniche viaduct in Dôle, in the Jura region of France, also features a bridge deck with ultra-lightweight
webs, but these are made from corrugated metal sheets [REI 94]. The fourth bridge with corrugated metal webs
to be built in France after the structures in Cognac, Charolles and the Parc Astérix, the Dôle viaduct was the first
French bridge of this type to be built using the cantilever method.
The Vecchio viaduct, built in Corsica at the end of the 1990s, also has a highly original bridge deck, consisting
of two parallel concrete slabs connected by triangular concrete elements acting as webs [PAU 00].
In the following section, after a brief preamble on the subject of cabling, we shall examine the design of the
different elements that make up a standard monocellular box girder. The figure below specifies the notations
used:
The cabling on standard modern structures consists of three types of tendons: cantilever tendons, internal
continuity tendons, and external continuity tendons.
Cantilever tendons take up the negative moments, both during construction and when the bridge is in service.
They are housed in the upper gussets. Their anchorages are often situated on the edge of the segments at the
nodes between the webs and the upper slab.
Internal continuity tendons are designed to take up the positive moments that occur during construction due to
site loads, the thermal gradient and delayed concrete deformations. In the end spans, they must also take up the
weight of the cast-on-falsework sections. They are situated in the lower gussets of the box girder close to the
webs and are anchored in anchor blocks.
External continuity tendons complement the internal prestressing, taking take up the operating loads and the
weight of superstructures. They are situated between the webs and slabs, outside the standard section. They are
anchored in massive cross beams on piers or abutments and are deflected via concrete beams called deviators.
In a simple box girder, the webs are often situated at a quarter of the width of the box girder (C ≈ B / 4). The
upper slab is solid and its thickness varies transversally in order to adapt to the transverse forces encountered.
The thickness of the upper slab at the end e1 depends on the retaining system used (see the Sétra technical guide
for security barriers). It is a minimum of:
At the anchorage of the cantilever, the thickness e2 depends on the superstructures and the functional cross
section. As an initial estimate for a reinforced concrete slab, we could use 1/7 to 1/8 of the width of the
cantilever for e2, measured from the start of the gusset. This value can be reduced for prestressed concrete.
Its thickness at mid-span e4 is equal to D/25 or D/30, or even D/35 for very wide transversally prestressed box
girders, with a minimum of 20 cm. At the fixed support point, the value e3 can be estimated at 0.10 meters
+D/25 (with D representing the centre distance between the webs expressed in meters). In general, we also
verify that: e3 > e2 – 0.10 m and e3 > 1.5 e4
In light of the preceding information, the mean thickness of the slab for a simple box girder amounts to between
22 and 26 cm, not including the gussets used for connecting to the webs of the box girder.
The transverse prestressing makes it possible to reduce the dimensions of e2, e3 and e4 by approximately 10% if
there is sufficient space to house the cantilever tendons. It is important to pay particular attention to ensuring
that the transverse tendons are properly covered and that they are correctly anchored at the ends of the slab, as
the effectiveness of these operations can also determine the thickness of the end of the slab.
Ribbed slabs, of course, are thinner. Their thickness varies between 22 cm for a normal centre distance of 3 m to
3.50 m between ribs, and 10 cm for a much smaller centre distance. It also depends upon the construction
method used for the segments (cast-in-situ or prefabricated).
Box girder webs are usually angled because this arrangement facilitates the removal of formwork and reduces
the width of the pier heads. Also, the external cladding of the webs is often of better quality when they are
angled. The angle typically adopted varies between 10 and 30%.
Longitudinally, the webs are normally of constant thickness for bridges of variable depth and of variable
thickness for decks of constant depth. When thickening is required near the piers, a sudden variation is built in
(by benching and from the inside, of course) in order to facilitate the construction.
Vertically, the webs are almost always the same thickness throughout their entire height. For spans in excess of
approximately 100 meters and in certain projects in which performance is maximized, the webs are sometimes
thickened in proximity to the upper deck as the shear forces are greatest in this area.
Usually, the cantilever tendons are anchored in the upper gusset or in a high-level anchor block. In this case, as
the web is not breached by the tendons, its thickness can be reduced to the strict minimum needed to resist shear
forces when the bridge is in service, while benefiting from the significant reduction in shear forces brought
about by the raising of the external tendons. However, during the construction phase, there is virtually no
reduction of the shear force, as the external tendons have not yet been tightened. The total thickness Ea of the
two webs can be estimated at Ea = L/275 + l.25 x B/L – 0.125: a relation in which L is the main span and B is
the width of the upper slab (with Ea, L and B expressed in meters).
It is sometimes desirable to pass the cantilever tendons down through the webs in order to increase the reduction
in shear forces brought about by the prestressing. This becomes compulsory for very wide structures with large
spans, in which the fixing of a single pair of tendons per segment is not sufficient.
In this case, the thickness of the webs must also conform to a certain number of conditions concerning the
proper concreting and anchoring of the tendons on the edge of the segments:
It can also be added that shear force strength requires the conservation of an effective web thickness of Ea equal
to 0.26 + L/500, with Ea and L in meters. This formula (somewhat less favorable than the previous formula for
short spans and relatively narrow box girders), gives good results for spans of between 70 and 170 m, and for
deck widths of less than 15 m. This thickness must be increased for wider decks.
The thickness of the lower slab is minimal at the crown and maximal at the pier. The thickness variation laws
according to the horizontal axis are either linear, parabolic or of the fourth degree. The latter variation law is
used to maintain the minimum thickness of the slab over a large length and to save weight. Stepped variations in
thickness, also known as “on demand” variations, are sometimes used. In the cast-on-falsework sections, the
thickness of the lower slabs remains constant and is equal to that of the crown.
Minimum thickness
In the central section of the spans, the lower slab must be as thin as possible (18 to 22 cm) in order to limit the
selfweight of the box girder. For wide structures, transverse bending predominates and thickness tends to be in
the region of 25 cm. In structures of an older design, this slab used to house continuity tendons which had to be
protected against corrosion by a layer of concrete equal to at least half of the diameter of the duct. As the power
of the tendons increased, this system finally resulted in cracking due to the distribution of the prestressing force
to the area around the anchorages. Today, continuity tendons are housed in the lower gussets of the box girders
and the cover thickness requirement specified above no longer applies to the slab. However, it is advisable to
adjust the minimal thickness of the slab Ec in order to ensure that the upper layer of its transverse
reinforcements do not come into contact with the ducts of prestressing in the gussets. It is also recommended
that this thickness should not be less than one third of the thickness of the webs, so that the box girder can be
considered to be impervious to transversal deformations.
Ec ≥ 2 ∅ + d + e avec Ec ≥ 18à 22 cm
Fig. 2.25 – Detail of the lower slab
Maximum thickness
The thickness of the lower slab on the pier Ep is determined by the limitation of compression in the bottom fiber
when the bridge is in service. This value, which is largely dependent on the span and widths of the slabs, varies
between 35 and 80 cm or even more. It is advisable to adopt a safety margin for the maximum stress level in
order to limit the redistributions due to creep.
For structures which vary in depth parabolically or cubically, the lower slab must also be transversally resistant
to sideways thrust due to the combined effects of the compression of this slab and its curvature.
The upper gussets must fulfil several functions which generally influence their dimensions:
• They house the cantilever tendons and ensure that their cover thickness
• They allow for the deflection of the cantilever tendons prior to their anchorages
• They thicken the nodes of the webs/upper slab, allowing them to absorb the forces due to the distribution
of the cantilever tendons which are now almost always anchored at these nodes.
In cast-in-situ structures, prefabricated concrete blocks incorporating the anchorages for cantilever tendons are
still sometimes used, as this system allows the tendons to be tightened a few hours after the segments have been
cast. These blocks must therefore be situated in the webs/slab nodes and they may also influence the dimensions
of the upper gussets.
In light of the preceding points, the gussets are empirically designed and accounted for in the rough calculations
and are only precisely established after the cantilever tendons and transverse reinforcements have been
accurately calculated.
In conclusion, it should be noted that the internal shape of the gussets is always rectilinear, presenting an angle
of between 30 and 45° to facilitate casting. On the other hand, their external form is often circular for purely
aesthetic reasons.
The lower gussets are normally boxed in by the lower part of the central core of the formwork for the segment.
They are angled at a slope of 40 to 45° in order to facilitate the flow of the concrete and prevent the formation of
accumulations of pebbles or concreting defects. When the lower slab is wide, the angle of the gussets can drop
as low as 15 or even 10° from the horizontal in order to improve the take-up of transverse bending forces. In
these situations, the gussets are not cast in formwork but simply smoothed over during the concreting process.
As we have previously mentioned, the internal continuity tendons are anchored in the protruding anchor blocks,
situated at the junction between the webs and the lower slab (Fig. 2.28). These anchor blocks are generally a
little shorter than the standard segments. They are constructed at the same time as the rest of the segment.
Bridges built using the cantilever method incorporate major cross beams directly above the piers and abutments.
Cross beams on piers play a particularly important role:
• By transmitting the shearing flows caused by shear force and torsion in the bridge deck from the webs and
slabs to the bearings and piers
• By transmitting the vertical component of normal stress in the lower slab (Resal effect) to the bearings
and piers (see 4.2.3.1 and 4.2.3.3)
• By taking up the local loads on the upper slab between the webs
• By providing anchorages for the external prestressing tendons distributing their forces
• By transmitting the vertical component of the external prestress tendons that are deviated inside the
segments on piers to the bearings and piers (see 4.2.3.4).
• By transmitting the shearing flows caused by the the shear force and torsion of the bridge deck from the
webs and slabs to the temporary bearings and piers
• By transmitting the vertical component of normal stress in the lower slab (Resal effect) to the temporary
bearings and piers
• By taking up the forces caused by the cantilever stabilizing systems and transmitting them to the
temporary bearings.
Concrete deviators situated in the different spans are used to deflect the external prestressing tendons (Fig.
2.29). These usually consist of a lower rectangular beam capped by two thin trapezoid walls.
We have already seen that the longitudinal geometry of the structure is dictated entirely by its mode of
construction. This also influences its breakdown into segments (Fig. 2.30).
In the following section, we shall see how the lengths of different types of segments are determined. In certain
specific situations, it should be noted that the breakdown into segments may also be conditioned or influenced
by the need to have a uniform distribution of:
• The bridge deck’s transverse ribs or struts, if applicable
• Cornice elements with architectural design features that must be evenly matched to the BN4 posts.
The edges of the segments are usually perpendicular to the structure’s extrados, and thus to the longitudinal
section, but vertical joints may also be used.
Standard segments are of a constant length which varies between 2.50 m and 4 or even 5 m according to the
structures.
For cast-in-situ segments, the most important selection criteria are the casting time and minimizing the number
of construction cycles and thus the number of segments. This optimization policy can sometimes lead to the
construction of segments of different lengths for the same half-cantilever. For example, in order to optimize the
construction cycles, the segments for the new bridge over the River Rhine to the south of Strasbourg vary in
length from 3.00 m close to the piers to 5.00 m in mid-span (at the design stage, the length was constant and
equal to 3.25 m).
The main aim when determining the length of prefabricated segments is to reduce their weight. Indeed, as we
shall see in Chapter 6, prefabricated segments must be moved using special equipment which obviously has a
limited capacity. However, it should be noted that the shorter the segments, the harder it is to conform to the
geometry of the cantilever.
At the preliminary design stage, it is common to calculate the length of the segments in such a way as to ensure
that there is the same number of standard segments as there are pairs of cantilever tendons determined by the
calculations. But this is only one option and it is often necessary to anchor two pairs of tendons per segment for
very wide structures featuring large spans. As we have already established, the length of segments calculated in
this way in the preliminary design may be modified during the construction surveys, in order to use form
travelers built for a previous site or to reduce the number of segments and optimize the construction cycles.
Regardless of the method adopted, it can be considered that smaller cross sections have longer segments. Thus,
segments of 2.5 to 3m are designed for very wide structures or bridges featuring large spans, and longer
segments of 3 to 4 m can be used for narrow or short-span structures.
For cast-in-situ structures, the segment on pier (SOP) generally measures at least 8 m, in order to ensure that it
is capable of supporting two form travelers during the construction of the first pair of segments. To support the
installation of the pair of form travelers on the segment on pier, it must be twice as long as the standard
segments plus an additional length of 50 centimeters to one meter.
The segment on pier represents a very large volume of concrete which can very rarely be constructed in a single
phase. Furthermore, its formwork must be designed to resist the significant thrusts exerted by the fresh concrete.
For cast-in-situ structures with a small number of piers, it may be beneficial to reduce the length of the SOP. In
this case, the second segment of the first pair is constructed after the first form traveler has been moved. The
cantilever is highly unbalanced before the installation of the second form traveler, but this is permissible given
the small moment arms at this stage of the construction.
For prefabricated structures, the dimensions of the segment on pier are often incompatible with the capacity of
the equipment used for transporting and installing the segments. The SOPs are therefore divided into two or
three sections to be assembled by prestressing.
The length of the closing segments varies considerably according to the technique used.
For cast-in-situ structures, the closing segments are slightly shorter in length than the standard segments because
one of the form travelers is generally used for their construction. However, the closing segments must not be so
short that it becomes difficult to dismantle the internal formwork from the form traveler. The closing segments
require specific formwork, usually made from wood, which can be broken down into components small enough
to be removed via a manhole. The length of the closing segments must also facilitate the overlapping of
longitudinal reinforcements and the tightening of the last segments cantilever tendons. Therefore, their
minimum length is approximately two meters.
For economic reasons, the closing of segments on prefabricated structures is carried out using the simplest
possible system. This closure is thus reduced to its simplest form, not exceeding 15 to 20 cm in length. A joint
of this length is made from non-reinforced concrete. Its shortness makes it impossible to tighten the cantilever
tendons usually attached to the last standard segments. Therefore, temporary lashing provides the only form of
prestressing before the jointing takes place.
• (L being the length of the principal span of the structure in meters and e in meters)
The ratio of non-prestressed reinforcement bars is generally somewhat higher for prefabricated structures,
because they often have a lower equivalent thickness than cast-in-situ structures and because reinforcements for
temporary lashing and hoisting equipment must be added.
(*) For non-prestressed reinforcement bars, the ratio is strongly dependent on the type and thickness of the
upper slab (thick slab, ribbed slab, etc.), on the conditions imposed for the cumulation of distribution, shear
and bending reinforcements and on the accepted value for the elastic limit of the reinforcement bars in the
calculations (400 ou 500 MPa).
• Continuity tendons: designed to take up the forces resulting from all of the additional structures added to
the structure after the construction of the cantilevers.
Until the mid-1980s, all of the pre-stressing on structures built using the cantilever method was situated inside
the concrete.
Today, mixed prestressing technology, i.e featuring tendons both inside and outside the concrete, is used on a
virtually automatic basis in France. For a structure with three spans, the following sequence of operations
applies to the stressing of these different tendons:
• Tensioning of the cantilever tendons inside the concrete for assembly of the standard segments (Fig. 3.1)
• Stressing of the continuity tendons outside the concrete, stretching across one or two spans, in order to
take up any additional loads (Fig. 3-4).
• For the assembly of consecutive segments and to take up negative moments due to the selfweight of the
cantilevers and site loads during the construction phase
• To help take up negative moments due to dead loads and imposed loads, along with the external
continuity tendons when the bridge is in service.
These tendons are situated at the area of the upper axis of the bridge deck in order to act efficiently against
negative moments. In virtually all cases, they are positioned inside the concrete in order to obtain the maximum
effect.
In older designs, these tendons were almost always deviated vertically at their extremities and their anchorages
were positioned inside the webs. The main advantage of this arrangement was to reduce the shear force due to
the angle of the tendons, which was particularly favourable in proximity to the piers.
• The bulkiness of the anchoring plates requires a large minimum web thickness (normally around 45 cm)
• In accordance with the french design regulations, the thickness of a web must be reduced by the thickness
of a half to one cable duct for the calculation of shearing stresses, depending on the design rules used
• Cantilever tendons undergo significant angular deflections, which results in signicativ losses due to
friction.
In conventional modern designs, shear force is reduced by placing the continuity tendons on the outside of the
concrete. Therefore, it is no longer necessary to drop the tendons down into the webs at their extremities, and
they can be anchored directly in the upper nodes. The drawbacks of the old cantilever tendons systems are thus
avoided.
For upper slabs of common widths (10 to 12 m), one tendon is anchored per web and per segment. For wider
upper slabs, it may be necessary to anchor two cables per web and per segment. Likewise, it is possible to create
a recess in the gusset gussetcorresponding to the size of the anchorages for the additional prestress tendons (cf. §
3.1.3.1). Because of this, the dimensions of the upper gusset gussets are directly related to the number and sizes
of the tendon anchor plates and to the position of the cantilever tendon ducts.
Standard alignment
Cantilever tendons undergo vertical and horizontal deflections in the upper node. Whenever possible, the
vertical deflections are dissociated from the horizontal deflections (Fig. 3.5).
The tendons must have a rectilinear alignment when they pass through the joints. In order to guarantee the
correct assembly of the duct elements, the alignment of the cables in the passage through the joints is usually
perpendicular to the formwork surface of the facing.
Comb layout
The "comb" cable layout aligns tendons automatically, which simplifies their installation (Fig. 3-6). Indeed,
such a layout:
• Always uses the same points of passage through the joints so that a single facing can be used
It is also apparent that the anchor plate is automatically angled on the axis of the web in one direction and then
in the other.
Further information on “comb” cable layouts can be found in the article entitled "Practical design of cantilever
tendons in bridges built by the balanced cantilever method” (FIP Symposium - London – September 1996).
Fig. 3.6 – Comb cantilever tendon layout: plan view and detail of gussets
On Figure above, we can observe the stress relating to the presence of stitching tendons on the support. The
stresses relating to the recesses used for the attachment of the form travelers (cast-in-situ segments) and hoisting
equipment (prefabricated segments) should also be mentioned.
It is also possible to position the anchor plates at the level of the gusset gussetand on the outside of the web
reinforcements, to prevent the systematic cutting of the vertical stirrups in proximity to the tendon anchors. In
this case, only the first tendons are anchored in line with the web: the following ones are anchored alternately on
either side. This arrangement also makes it possible to attach two cables per web if necessary.
Two or four cables can be specified per segment. If, for the aforementioned reasons, we decide not to anchor the
tendons in the webs and want to avoid increasing the size of the gusset gusset, the optimum number of tendons
specified for the end of each segment is two (one tendon per web). This arrangement makes it possible to
standardize the reinforcements for the segments.
During the construction of a cantilever, the most unfavourable situation generally occurs during the casting of
the final pair of segments. The cantilever tendons anchored in this final pair of segments are not tensioned in the
design phase and are therefore not required for the construction of the cantilever. Furthermore, experience
shows that, because of the presence of the external continuity cables which span the entire length of the
structure, there are more cantilever tendons than needed when the bridge is in service. As a result, decks can be
designed without the need to anchor cantilever tendons in the final pair of segments. This final pair then
functions provisionally as reinforced concrete. This arrangement is commonly used for bridges with
prefabricated segments in which the shortness of the closing segment (20 to 30 cm) makes it impossible to
tension these tendons.
During the assembly process, lashing bars must be used to hold prefabricated segments in place parallel to the
extrados until the cantilever tendon is tensioned. These bars hold the segment temporarily in place while
exerting a minimal pressure of approximately 0.2 MPa on the adhesive in the segment joint. The segments are
generally anchored in a staggered pattern on the vertical ribs built into the inner face of the webs, midway
between the segment joints (Fig. 3.7).
For very large structures (span > approximately 120 m), a proportion of the cantilever tendons may be situated
outside of the concrete in order to reduce the size of the upper gusset gussets and thus the dead loads
In order to reduce the shear stress in certain types of structures, it is possible to drop a proportion of the
cantilever cables down into the webs (generally those of the first segments), according to a design similar to the
layouts used in older structures (Fig. 3.8).
These provisions are used for structures of variable depth in which the aim is to reduce the depth on the pier,
and for structures of constant depth over 60 m in length.
As described in Chapter 2, in order to reduce the cast-on-falsework sections close to the abutments, or to build
spans of different lengths, it may be necessary to construct one or more segments known as “extended cantilever
segments” at a one end of the bridge only.
The cantilever is thus asymmetrical and the cantilever tendons anchored in these segments may be asymmetrical
in relation to the pier. However, they must be anchored at a sufficient distance from the section on the pier in
order to allow for the dispersion of the prestressing force within this section.
In general, continuity tendons are designed to take up all of the additional forces applied to the structure after
the construction of the cantilevers.
In older designs, these tendons were all located inside the concrete. They were aligned in the lower slab at mid-
span and were attached to the anchor blocks protruding over the slab, or raised in the webs and anchored inside
recesses built into the extrados of the bridge deck. The large number of tendons meant that they had to be
distributed throughout the entire width of the lower slab, which led to the development of major pathologies
(see Chapter 8).
Today, continuity prestressing is generally mixed, i.e. consisting of tendons situated both inside and outside the
concrete. This paragraph only concerns the use of mixed cables. For continuity tendons which are situated
completely inside the concrete, the reader is advised to refer to SétraSétra Technical Bulletin No.7 published in
1972.
Continuity tendons situated inside the concrete are strung across the central part of standard spans and inside the
extremities of the end spans (Fig. 3.9 and 3.10).
Designed to resist positive moments, these cables are situated inside the lower gusset gussets and are attached to
the anchor blocks situated at the intersection of the web and lower slab (Fig. 3.11).
They are often offset in relation to the top of the lower deck in order to standardize their alignment in the anchor
block.
At the minimum, internal continuity prestressing is designed to be capable of taking up the shrinkage after
grouting, thermal effects (thermal gradient and uniform temperature variation) and the reaction effects of the
structure during the construction phases between the casting of the concrete fro the closing segment and the
tensioning of the external continuity prestressing.
The attention of designers is drawn to the fact that, due to the effect of temperature variations, the provisional
cantilever joints are liable to create significant forces in the bridge deck and supports, especially if the latter are
rigid.
For the end spans, the internal continuity prestressing also has to take up the weight of the cast-on-falsework
section.
• Positive moments in the span due to dead loads (including shrinkage and the redistribution of forces due
to creep) and imposed loads, in tandem with the internal continuity cables
• Negative moments on the pier due to dead loads and operating loads, in tandem with the cantilever cables.
In elevation, they are therefore situated close to the lower slab in mid-span (?) and close to the upper slab on
supports. In order to account for construction tolerances, a distance of approximately 5cm must be allowed
between the outside of the tendon ducts and the concrete of the segment slabs. This minimum distance will be
also observed in relation to the top of the anchor blocks for the continuity tendons.
In a plan view, the external continuity cables are situated close to the webs. To take account of construction
tolerances, a distance of approximately 5cm must also be allowed between the outside of the tendon sheaths and
the concrete of the segment slabs and/or the anchor blocks. For curvilinear structures, it is necessary to recenter
the tendons using additional deviators.
The tendons are deflected via the cross beams on piers and intermediate cross beams (deviators) on the spans,
resultings in a polygonal alignment which is rectilinear per section. The deviators are generally situated between
a third and a quarter of the way along the span (Fig. 3.12).
According to the length of the structure and the number of spans, they may be strung form one end of the deck
to the other or overlapped across two or three consecutive spans, or even more. Considering the difficulties
involved in the threading and grouting of curved tendons, they must be limited in length to approximately 200
m. This value may be slightly exceeded, especially in order to stretch a tendon across two spans of over 100 m
in length. Longer curved tendons (e.g. 3 spans of 120 meters, i.e. 360 meters for 19T15 "super" tendons) have
already been successfully tensioned.
These tendons may also stretch from span to span. In this case, they may be anchored in the deviator cross
beams.
For example, for a symmetrical three-span structure, the following design allows for a precise adjustment of the
prestressing in each span using two types of tendons (Fig. 3.13).
Fig. 3.13 – Different types of tendons used for optimizing the external cabling on a three-span bridge
There must be a sufficient number of external tendons to prevent any structural deficiencies in the event of the
breaking or removal of a tendon. However, too many tendons could risk overloading the box girder and lead to
maintenance problems. In practice, there are often between three and five pairs of internal continuity tendons.
It is interesting to note that in a mixed cabling system, the external tendons play a major role in taking up the
negative moments on the supports. This leads to a significant reduction in the number of cantilever tendons
compared with older structures in which the cantilever tendons had to take up all of the negative moments.
If there are no problems of shear force, it is also possible to reduce the number of external tendons and to
compensate for them in the central zones by using additional continuity tendons, which are more economical, as
they are shorter.
Specific precautions must be taken at the design stage in order to overcome any deficiencies in the internal
prestressing inside the concrete during the construction phase (excessive friction, inability to thread tendons,
etc.). These provisions must be designed to compensate for a prestressing deficiency of between 5 and 10 % of
the probable prestressing force Pm for the category in question. For example, it is possible to:
• Avoid using the full capacity of the anchor plates, thus making it possible to attach additional strands
• Build in empty ducts which could be used to insert one or more pairs of additional cables if necessary.
Compulsory for cantilever tendons, these empty sheaths are also recommended for internal continuity
cables. The layout of these empty ducts must allow tensioning to be carried out at any time during
construction, either by making room in the gusset gusset for an anchor plate, or by positioning the duct in
such a way as to allow the tendon to be anchored in an additional anchor block. The last of these
provisions does not apply to prefabricated segments.
Unused empty ducts are injected at the end of the construction phase.
It must be possible to replace the external prestressing. More precisely, it must be possible to dismantle it
without causing any damage to the structure apart from the possible destruction of the cable and its duct (cf.
Circular of February 28 2001 “Conception de la précontrainte extérieure au béton" [Design of prestressing on
the outside of the concrete]).
The general provisions for external prestressing, the products and materials used and their implementation are
described in Chapter 7 of the supplement to the fascicule 65 A of the French CCTG (General Technical
Clauses).
Anchorages for additional prestressing and recesses in the deviators must be designed at outset in order to
facilitate any necessary repairs or strengthening of the structure. The additional prestressing force must be equal
to at least 20 % of the external continuity prestressing force determined during the construction of the bridge
deck. In practice, at least one sheath per web is provided, allowing for the progressive replacement of all of the
external continuity tendons.
In order to prevent the development of resonance in the external tendons and avoid the risk of whip action in the
event of an accident, the SétraSétra guide to external prestressing of February 1990 recommended the
installation of intermediate tendon retention devices when the external part of the cable layout exceeds fifteen
metres for a road structure and 10-12 meters for a railroad structure. Experience acquired in this field has shown
that free lengths of approximately 25 m are acceptable. Acting as intermediate supports and helping to hold the
ducts in place during their replacement, these devices must be rigid (Fig.3.14).
In the majority of bridges covered by this guide, cantilevers are stabilized by vertical prestressing cables housed
in the segments on piers. As these tendons may conflict geometrically with the longitudinal prestressing, it is
important to bear this in mind when determining the transversal positioning of the external and cantilever
tendons.
A geometrical conflict is also possible in transversally prestressed bridge decks between the transverse tendons
on the one hand, and the cantilever and external continuity tendons on the other (Fig. 3-15). In order to prevent
this type of conflict, it is important to accurately define the position of the transverse prestressing and then to
determine the location of the longitudinal tendons. In general, it is advisable to place the transverse tendons in
the first bed and the cantilever tendons in the second.
For the majority of the verifications, the stresses are calculated using an elastic model for the bridge deck.
The calculation must take account of the successive phases in the loading of the structure. Therefore, it is
necessary to carry out a precise analysis of the construction phases and of the subsequent loading phases
(consecutive concrete casting and stressing operations, in addition to the removal of formwork and the moving
of form travelers, support transfers, adjustments, etc.).
As the form travelers are built from rigid metal components, the selfweight can be represented by a single
nominal value calculated using the design drawings, as recommended by the BPEL 91, revised in 1999 and
notwithstanding the Directives Communes (Common Guidelines) of 1979.
However, it is also important to account for the elements which are added to the bridge deck such as anchor
blocks, diaphragms and deviators. Finally the selfweight of the bridge deck also depends on the weight of the
ducts, tendons and grout used for the injection of the external prestressing.
Except under special circumstances, the unit mass of concrete is fixed at 2.5 t/m3.
If high or low density aggregates are used, the unit mass of the concrete γt , and of the bridge deck (prestressed
and reinforced) is evaluated on the basis of the unit mass of the concrete alone γb, measured for a laboratory
sample of concrete without reinforcements using the following formula:
ρ
γt = γb +
7,85
(
× 7,85 - γb )
In which ρ is the total ratio of non-prestressed and prestressed reinforcement bars in t/m3 (a value of p = 0.2 t/m3
is generally adopted).
Standard concrete based on basaltic aggregates and high-performance concrete have higher densities (allow
around 50 kg/m3 more for HPC).
For the verifications of longitudinal flexion, the prestressing can be represented by a single probable value Pm.
For large structures, specific precautions are taken (empty ducts, measurement of transmission factors, etc.) to
ensure that the probable prestressing value Pm is properly obtained. In this case, values of k = 0.02 and
k’ = 0.95 should be used for the Service Limit State calculations, in accordance with Article 4.10.1 of the BPEL
91, revised in 1999.
During the construction of the cantilevers, random site loads must be considered when calculating the
longitudinal flexion of the bridge deck (Fig. 3-16). These loads are:
• A concentrated load QPRA2 of 100 kN applied at the end of the cantilever, representing the weight of the
cable rollers, compressors and other equipment likely to be used on the structure.
Concrete shrinkage and creep in hyperstatic structures built according to flexible static plans gradually modifies
the stresses and constraints that were initially calculated.
It is difficult to give a quantitative evaluation of this redistribution. For this, a computerized calculation is
required, which takes account of the construction phases and the laws of behavior of the different materials
(including the scientific creep test for concrete).
A calculation of this type will be performed at the design stage, in which certain construction phases may be
grouped together.
Two compulsory calculations must be performed in the framework of the construction surveys:
• Firstly, an initial calculation of longitudinal flexion (A), is carried out according to the company’s
provisional construction schedule, with coefficients of friction according to the type of prestressing used
• Secondly, after the complete construction of the bridge deck, and in order to determine the actual stress
state of the structure in operation, a post-construction calculation (B) is performed according to the actual
construction schedule, using the mean coefficient of friction measurements, and the actual mass of the
segments for prefabricated structures.
Should significant changes be made to the work schedule, it is also necessary to perform a third calculation to
take account of the rearranged work schedule. Any change of sequence of operations will be validated by a
calculation.
Finally, while awaiting the implementation of the Eurocodes, whose materials laws are considered to be more
realistic, another calculation can also be performed in order to determine the reverse deflections during
construction, using a creep law that is more realistic than that of the BPEL (quicker). Nevertheless, it is
recommended to perform a creep test in order to make sure that the concrete creep law does not differ from the
theoretical model of behaviour that was adopted.
Several software programs have been designed by private or public engineering firms for bridge calculations
including for structures built using the cantilever method.
Sétra has developed two programs designed for these types of calculations amongst others:
• STl software ;
• The PCP (Ponts Construits par Phases [Bridges Built in Phases]) system.
These programs are used for calculating three-dimensional or flat structures made from bar components and are
intended for the design of civil engineering structures. They can account for prestressing reinforcements,
construction phases and imposed road loads. The calculations are performed according to the Strength of
Materials theory applied to elastic beams, in which each segment is normally represented by a beam element.
The calculation must closely follow all of the construction phases in order to consider the load application dates
and the aging of the materials (shrinkage, creep and relaxation) between these different phases.
Paragraph 3-3 describes the verifications to be carried out with regard to normal stresses due to normal force.
These calculations must be performed at the Service Limit State and at the Ultimate Limit State, when the
structure is under construction and in service.
Verifications to be carried out with regard to shearing stresses are covered in Chapter 4.
Considering the absence of longitudinal reinforcement bars passing through the joints, decks made from
prefabricated segments are generally verified longitudinally according to class I of the BPEL 91, revised in
1999. Article 3.1.43 of the BPEL 91, revised in 1999 also describes the possibility of verifications being made
in class II subject to the joints remaining fully compressed under Pm. In this case, in accordance with Article
6.1.32, the stressed zone must also be less than 5 cm in height.
The choice of verification category must be clearly stated in the STC (Special Technical Clauses).
In addition to the verifications specific to the static balance which are covered in Chapter 5 of this guide, SLS
(Service Limit State) verifications must be performed at all phases of the construction of the cantilever in order
to verify the prestressing of the bridge deck.
The loads to be used include the known site loads (form travelers etc.) and the random site loads defined in
paragraph 3-2.4.F
For structures verified in class II, the comment in Article 6.1.23 of the BPEL 91, revised in 1999 can be applied
and a tensile stress limit equal to ftj instead of 0.7ftj can therefore be considered in the coating section.
The internal continuity prestressing inside the concrete is designed to take up shrinkage, creep and thermal
effects (thermal gradient and uniform temperature variation) during the construction phase between the casting
of the concrete for the closing segment and the tensioning of the external continuity prestressing.
The positive thermal gradient can be considered to be equal to 8° C. A negative thermal gradient of 5° C must
also be taken into account.
In the case of structures with prefabricated segments, it is also important to consider the launch beam and the
low-bed semi-trailer. For structures verified in class II and considering the very short site design phase, the
comment in Article 6.1.23 of the BPEL 91, revised in 1999, can be applied, and a tensile stress limit equal to ftj
instead of 0.7ftj can be considered in the coating section.
• Upon commissioning
• After all of the delayed losses and redistributions have occurred (e.g. after 50,000 days, this period may be
considered to be “infinite”, even if all of the losses and redistributions have not occurred according to the
laws of the BPEL)
It is difficult to apply ULS coefficients to a structure built in phases. For the verification of longitudinal flexion
in service, the following simplified method is proposed:
Given that:
• c represents the empty states envelope (state upon commissioning, state after all losses) without
weighting (this envelope was been used for SLS verifications)
• d represents the state according to a new calculation performed by applying all of the dead loads at the
same time (without prestressing)
[c] + [ 1.5 e]
With this method, the forces due to the prestress tendons have not been increased. Indeed, if we take:
P: to be the prestressing
G: to be the dead loads except for the prestressing [concrete (envelope before and after creep), equipment and
asphalt]
Q: to be imposed loads
With this calculation method, which is considered to be unfavorable, the Ultimate Limit State is not generally a
key factor with regard to longitudinal flexion.
The dimensioning of a prestressed concrete structure built by the cantilever method is performed at the Service
Limit State. Structures dimensioned in this way are then verified at the Ultimate Limit State.
The dimensioning can be carried out according to the steps outlined below:
The cantilever cabling is dimensioned in the construction phase. It must take up the selfweight of the concrete in
the cantilever and the site loads defined in paragraph 3-2 above.
If it is possible to choose the length of the standard segments, i.e. if the length of the form traveler is not
imposed, it may be beneficial to choose a segment length and prestressing units that are compatible with the
attachment of two tendons per segment. In this situation, it is necessary to test most common prestressing units
and to choose the one that gives a conventional segment length, i.e of between three and four meters.
In most cases, the dimensioning of cantilever tendons takes account of the normal stresses in the upper axis of
the section situated directly above the temporary blocks, at the moment of the casting of the final pair of
segments, i.e. before the tensioning of any cantilever tendons that might be anchored in this segment.
In the case of the final pair of segments without cantilever tendons, the casting of the closing segment may be
the critical phase.
2nd stage: determining the continuity tendons situated inside the concrete
The continuity cabling inside the concrete is dimensioned in the construction phase. It must take up the effect of
the thermal gradient in the construction phase before the stressing of the continuity tendons situated outside the
concrete in addition to the effect of the selfweight of the end spans. The internal continuity cabling must also
take up some of the redistributed delayed forces.
In general, the same prestressing units are chosen for the internal continuity tendons and the cantilever tendons.
3rd stage: determining the continuity tendons situated outside the concrete
These tendons are designed to take up the operating forces which are not absorbed by the two preceding families
of tendons.
Initally, it is important to concentrate on shear stresses and to discover which segments have permissible levels
of shear stress without the reduction made by the external tendons. In this way, the location of the external
prestressing deviator can be determined. This must be situated between a third and quarter of the way along the
span (a third of the way along the span for variable thickness and a quarter for constant thickness). It should be
noted that this method can only give an approximate alignment because the permissible shear stress depends on
the normal stress, which is itself dependent on the prestressing that is used.
After obtaining an initial alignment, the focus can then be switched to the normal stresses in order to determine
the intensity of the prestressing. As the number of external tendons is always the greatest on piers, an initial
estimate of the dimensions of the tendons can determined by concentrating on the lower axis of the crown
section and by considering that the redistributions of forces due to concrete creep create a tensile stress of
approximately 2 MPa.
The final alignment can be obtained by making certain adjustments to these initial estimates such as:
• Altering the length of the different tendons (the tendons may cross one, two or three spans)
If there are no shear force problems, it is also possible to reduce the number of external cables and to
compensate for them by using additional internal continuity tendons in the central zones, which are more
economical because they are much shorter.
– Stresses (flexion and shear) arising from the transverse behavior of the bridge deck
– Tangential effects originating from the general longitudinal flexion covered in this chapter, because it is
essential to combine them with localized effects when performing the detailed verifications and
determining the reinforcements
– The distribution of localized forces
– The forces in specific elements (segments on piers and deviators).
Although the majority of the points covered are not specific to bridges built by the cantilever method, we
have decided to include them because they are not dealt with in any other guide. Furthermore, it is
important to design the cross-sections of structures properly in the first place, rather than to rely on
complex calculations to remedy any problems. Finally, this chapter describes how to accurately account
for the forces in specific elements such as segments on piers, deviator segments, anchor blocks, etc.
• Transverse flexion
• Tangential effects
It is then possible to determine the reinforcements for the cross-section in accordance with the different
accumulated actions taking into account their concomitance.
In a structure of constant depth, the calculations for transverse flexion are performed in a standard section. In a
structure of variable depth, they are generally performed in a section close to a pier and in the crown section.
This makes it possible to account for the differences in behavior between two sections of contrasting height,
with the taller section close to the pier being more flexible than the crown section.
For structures of constant depth characterized by a thickening of the lower slab close to piers, this variation is
sufficiently localized that it is not normally necessary to perform a specific calculation in addition to the
calculation for the standard section.
• -The upper slab: at the base of the cantilever, at the gusset located on theinner side of the box-girder, and
in the centre of the slab
• -The webs: at the level of the centre of gravity and at the upper and lower extremities
When the structure is in service, the usual actions must be considered: selfweight of the structure, weight of the
superstructures, weight of road traffic loads, any transverse prestressing, loads on the lower slab, etc.
In the construction phase, additional actions must be introduced in order to account for the forces developed in
certain situations encountered on site. These forces include:
• The forces developed by some of the tie bars for the form travelers
• The weight of a launch beam on the section of bridge deck that has already been constructed
• The weight of a segment stored on the segment to be calculated: a situation encountered on certain
prefabrication areas with insufficient storage space.
It should be remembered that monocellular bridge decks represent the vast majority of structures built by the
cantilever method. The methods described hereafter, and especially the "simplified" methods, apply to this type
of structure. In the case of more complex structures, only sophisticated modeling techniques provide a
satisfactory response to the problem posed.
Transverse forces can be calculated in different ways according to the type of deck in question:
• Using a 2D model
• Using a 3D model
For the upper slab, it is possible to use nomographs to calculate the forces, either by directly incorporating the
statutory French loads (using Thénoz’ nomographs with loads from Fascicule 61 title II of the French CCTG, or
more general methods (Pücher or Homberg), to which the loads from any regulations can be applied (e.g.
Eurocode 1) or even loads that are not specified by a particular regulation. The Thénoz and Pücher nomographs
are only used for slabs of a constant thickness while the Homberg nomograph accounts for thickness variations.
For conventional structures (monocellular box girders), the forces are calculated using nomographs for double-
embedded slabs for loads situated between the webs, and nomographs for embedded slabs for loads situated on
the cantilevers. Next, the moments obtained at the embedded section are added at the upper nodes in a 2-D
model representing a section of deck of a unitary length (Fig. 4.2).
Therefore, this calculation is completely valid for distributed loads such as selfweight or the fittings. For
concentrated loads (road traffic loads), it is only an approximate calculation because on the one hand, the force
is unevenly distributed along the fixed support and on the other, it does not represent the distribution of forces
from the upper slab towards the webs and the lower slab. Calculations using finite elements have shown that this
type of calculation is reasonably accurate for the upper slab when the webs are sufficiently rigid. This remains
valid for the upper part of the webs, as there is not yet a significant distribution of forces in this area. However,
this calculation is nowhere near as representative for the lower part of the box girder.
[Sétra’s Bulletin Technique (Technical Bulletin) n° 1 and its Ouvrages d’art (Civil Engineering Structures)
Bulletin n° 13 of November 1992 contain further details about this method.]
According to these calculations, the transverse moments acting in the box girder are:
• For the introduction of the moments at the nodes of the frame, it is necessary to add the moment due to the
shear force calculated at the theoretical edge of the slab, by multiplying it by the distance between this
theoretical end fixing and the upper node situated on the centerline of the web (Fig. 4.3). This shear force
is not given by the nomographs, but it is easy to calculate
• For stability, this model must include two supports. In order to avoid parasitic forces resulting from a
blockage of the nodes in the model, it is necessary to free one of the supports transversally. These
supports must be situated at the bottom of the webs (in the case of inclined webs), because the vertical
reactions would then develop a horizontal component (of the normal force in the webs) which does not
exist
• If we simply apply the fixed support reactions of the double-embedded slab at the upper nodes and place
the frame supports in the lower nodes, a compression appears in the bars representing the webs, which
does not exist in reality. In the interests of accuracy, it is essential to apply the opposite of the load applied
(vertical force and torsion moment) to all of the bars of the model in the form of shear flows on each bar.
This presupposes that the unitary flows due to a vertical load or a torsional moment have first been
determined using a calculation program for the characteristics of hollow sections (Fig. 4.4). Of course,
this type of calculation requires a balancing of the loads for each load situation. Then it is verified that the
support reactions are zero
• However, in the majority of the cases (monocellular bridge deck with a moderate width and a moderate
height), calculations can be simplified not applying this equivalent flow and neglecting the normal effort
in the web. This approximation is justified by the weak difference with the reinforcement calculated with
the previous method.
Fig. 4.3 – Relative positions of the forces calculated at the fixed support of the slab (for
the nomographs) and of the upper node of the modeled frame to which the efforts are
applied
As the principle is obviously valid, this method can be extended to structures other than monocellular box
girders. However, the fact of directly applying the fixed-end moments (with the nomographs giving a single
value) presupposes that the structure and the forces are symmetrical.
Fig. 4.4 – Shear flows due to a vertical force in a monocellular box girder
For more complex structures (multi-cellular box girders), a common approach is to determine equivalent
vertical loads giving the same moments in the middle of the slab and at the fixed support (uniformly distributed
loads and knife-edge loads), which will then be moved transversally into different positions in order to obtain
the maximum effects in the transverse structure.
As the frame effect in a structure of variable depth depends on the rigidity of the webs (according to their height
and thickness), and to a lesser extent on the thickness of the lower slab, these calculations are almost always
performed for the section on the pier on the one hand, and for section at the crown on the other, as mentioned in
the preamble.
[For further information about these methods, refer to Analyse structurale des tabliers de ponts (Structural
Analysis of Bridge Decks) by J.A. Calgaro, - Presse des Ponts et Chaussées 88].
For conventional standard sections, the 2D model is usually adequate, in spite of its lack of precision in the
lower areas of the webs and in the lower slab. Despite its complexity, a 3D model is not significantly more
accurate.
On the other hand, for elements with non-standard sections, a 2D calculation is often too simplistic and
unrealistic in terms of the actual distribution of forces. For example, this includes:
Therefore, it is necessary to adopt another type of modeling (3D with bars or finite shell elements) which shows
up local structural variations (ribs, thicker sections of webs, crossbeams on supports or deviator beams, etc.) or
non-homogeneous behavior. Significant distorsions may be shown in the cross-section of multi-cellular bridge
decks under the effects of both symmetrical and asymmetrical loads. The analysis of this three-dimensional
phenomenon also requires 3D modeling (Fig. 4.5).
In order to study the behaviour of a complex standard section, it is necessary to model a portion of
bridge deck that is long for the forces not to be disturbed by the conditions at the extremities. It is
advisable to divide the deck into sufficiently short sections, equal to approximately ¼ to ½ of the
height, in order to obtain the correct local forces
For a segment on pier, it is possible to take account of the longitudinal symmetry in order to halve the
size of the model. In this case, it is necessary to be very careful to modelize conditions at the limits
(the six degree of freedom of the nodes are not all embedded) to guarantee the representativity of the
model. Furthermore, because on the one hand, we are using the bridge deck’s actual supports, and on
the other hand, we are only interested in the forces in proximity to the crossbeam, we can also limit the
length of the modeled portion to a few sections (Fig. 4.6), as the external actions originate primarily
from the flows on the end section.
• In the other directions, the breakdown must remain consistent with that used in the longitudinal direction,
which rapidly increases the size of the model.
• Each rod has its own specific characteristics (area, bending inertia) and the torsion inertia is considered to
be equal to half of the bending inertia of the corresponding rectangular cross section (shell element - slabs,
webs, but does not apply for stiffener, rib, …) in order to account for the distribution of forces in both
directions of the beam grid.
• The strengthening pieces (segment on pier, deviator beams) modify the rods neutral axis. To determine
the rod center of gravity and inertia, it is important to take account for the effective width of slab.
• The external forces are applied to the segment in the form of flows in the end sections of the model.It is
therefore necessary that end sections should modelize the section of a standard segment.
• The loads applied to the section itself are balanced out by directly opposite flows (cf. § 4.2.2.1).
In this type of modeling, the forces given by the model are directly usable.
This method is more cumbersome than the 2D calculation method, but it gives a better representation of the
direction of the forces, especially in proximity to the bearings or perpendicular to the deviators. On the other
hand, due to the fact that it is impossible to generate elements automatically, 3D modeling is generally reserved
for segments on supports or deviators.
As mentioned previously, a shell-type finite element calculation can be performed when the structure is not a
traditional box girder, or for any other reason (better curracy for example).
These programs are extremely powerful and are capable of solving complex problems, but the engineer must
have an excellent command of finite elements and a detailed analysis of both the structure itself and its
modeling must be performed. Under no circumstances can they compensate for a poor initial design.
For detailed information about modeling and calculation methods, please refer to the "Emploi des éléments finis
en génie civil" (Use of Finite Elements in Civil Engineering) documents published by the AFGC (Association
française de génie civil - French Civil Engineering Association)].
• The conditions at the limits are very important, and the forces at the extremities of the model are
completely disturbed. Consequently, it is necessary to model a sufficiently long portion in order to obtain
a reasonably large undisturbed “usable” area. In general, it can be considered that the zone to be ignored
corresponds to approximately 2 to 3 times the height of the section. For example, if an entire span is being
modeled, it is extended by a segment of three times the height on each side (Fig. 4.7).
• In order to apply the general forces correctly, it is also necessary to extend the shell model with bars
representing the deck itself, featuring the same cross-section characteristics.
• Of course, the segment of shells and bars are connected by an arrangement of rigid bars laid out in a
“spider” configuration.
• The shape of the elements must not be too distended, in terms of their two-dimensional characteristics and
their thickness. Thus, a maximum ratio of approximately 2 is recommended between the plan-view
dimensions and the thickness, giving a shape similar to a rectangle, for which the ratio should also not
exceed 2 (otherwise, use triangular elements). Consequently, the slabs and webs can be broken down into
elements measuring approximately 0.50 m to 0.60 m in the plan view, with the crossbeams or deviators
also having maximum thicknesses of 0.50 to 0.60 m
• It should be remembered that the results for finite elements are given at the centre of gravity of the
element. The structure should therefore be broken down in such a way that the centres of gravity of the
elements are situated in line with the correct cross sections: at the gussets for example. Otherwise,
interpolations will have to be performed: a long manual operation that is a source of errors or inaccuracies
• The prestressing must be entered in the form of external forces. None of these forces should be omitted
(anchoring forces and thrusts close to the deviations), because the system forms an independently
balanced structure
• The dead loads are entered over the entire structure, including on the bars outside the shell segment
• Traffic loads: in order to perform an accurate calculation, after defining the calculation sections (in the
transverse direction), it is possible to determine the lines of influence (or rather the surfaces of influence)
of the efforts in question in these sections, which makes it possible to choose the positions of the loads in
order to obtain the maximum effect required.
Furthermore, the designer’s attention is drawn to the fact that this method can be very cumbersome due to the
need to move the imposed loads “manually” on the upper slab for certain finite elements programs which do not
have an automatic load placement function.
In general, the forces given by the model are directy exploitable; however, the reinforced concrete elements, or
“T” sections require a reconstitution of the forces on the section based upon the constraints for each element.
One of the main advantages of this method is that it gives an effective representation of the behaviour of the
structure, both in the standard parts and in specific areas such as the segments on piers or deviators, and it also
takes account of the interaction between the general effects and the local effects (general dispersion). This type
of model must not be used to determine highly localized dispersion forces such as those in the first
regularization prism or the radial tendon forces in the deviators, which we can continue to calculate manually.
Remarks
The shell finite elements are not adapted to model properly the massive parts of a segment on pier (cross-beam
or anchorage block for example) ; it is then necessary to add offset rods or 3D finite elements, but which present
other difficulties, such as determine the efforts and deduce the corresponding reinforcement (see also § 4.4.1).
This method must be used in very specific cases and require a high level in modelling with 3D finite elements.
In bridge decks of variable depth, the longitudinal compression in the lower slab creates a lateral thrust (due to
the curvature of the slab) which creates a transverse flexion of this slab.
This slab is embedded in the webs of the box girder, preferably using a gusset.
This is a cylindrical shell subjected to longitudinal compression stresses which can be considered to be uniform
transversally to the structure.
This stress field causes a lateral thrust towards the top of the slab which is balanced out by the embedding of the
slab in the webs and causes a transverse bending moment, which stresses the upper axis on the centerline of the
slab and the lower axis in line with the fixed end in the web.
This moment varies throughout the length of the structure due to the longitudinal variations in the thickness of
the slab and the extent of the stresses in the section. In a cross-section, the distribution of the fixed end moments
in the webs and in the span also varies according to the relative stiffnesses of the slab and webs (with the upper
slab generally being constant).
The lateral thrust in a given section of the structure of a unitary length is expressed per (transverse) meter of
slab, by:
e
q = σ b moy
Rmoy
with σb moy = mean stress in the lower slab for the segment in question
e = thickness of the lower slab in this segment
Rmoy = mean radius of the mean axis of the lower slab for the segment in question.
Note
In the case of a high curved lower slab (for example with a cubic depth variation), instability of this lower slab
may occur under compression in the most curved zone. [See article from P. Faessel – Journée de l'AFPC April
1974 and M. Virlogeux – Annales de l'IBTP February 1981].
The presence of prestress tendons in the lower slab causes a phenomenon of the same type but in the opposite
direction. These tendons are tensioned in the second phase after the completion of the cantilevers, when the end
or intermediate spans between consecutive cantilevers are closed. Two different situations are identified:
• Construction irregularities.
The presence of tendons in the curved slabs generates similar forces to those described above, but in the
opposite direction. However, these tendons are close to the centre of the span, an area of low slab compression:
the action of these tendons is therefore preponderant. Furthermore, the presence of ducts reduces the strength of
the section and thus increases the likelihood of the structure breaking along lines parallel to the ducts.
P
By calling f the linear force of the radial thrust of the tendon, this force is equal to f = with:
R
Furthermore, irregularities in the alignment of the ducts during construction, particularly in line with the
segment joints, produce concentrated forces which can result in problems or even spalling in the lower slab.
Indeed, if the radius of curvature becomes very small (producing an angular point), the force increases
significantly amd can lead to the breaking of the slab.
It is thus highly inadvisable to place tendons in the lower slab of bridge decks of variable depth. Even for
structures of constant depth, this arrangement is not recommended, because the segments are short and the large
number of joints increases the risk of irregularities. In addition, the differential shrinkage can cause cracks near
the tendon layouts which can lead to the corrosion of the tendon.
Note
The lateral thrust also exists when continuity tendons are placed in the gussets. However this phenomenon is
less severe because the thickness of the concrete enables better distribution of the forces.
In bridge decks of variable depth with linear gussets, localized lateral thrusts originate in the lower slab at the
point of intersection of two rectilinear portions of lower slab subjected to longitudinal compression stresses.
The same applies directly above the supports when the slope of the slab suddenly changes.
The resultant is directed according to the bisector of the mean lines of the slab, giving a concentrated effort
which results in strong localized stresses in the lower slab.
This is why it is essential to place a stiffener or crossbeam in this area in order to transfer the force towards the
webs and to take up the transverse flexion of the slab.
On a support, a crossbeam is also needed to take up the torsion forces due to the asymmetrical loading of the
bridge deck.
External prestressing tendons are deviated in deviator crossbeams with a small radius of curvature. They thus
develop large localized forces which must be taken up by these deviators. The principle is the same as above,
with the radial thrust being directed according to the bisector of the tendons layouts.
In the case of a bridge deck with a high curvature in the horizontal plane, the horizontal component of this thrust
is not negligeable.
In addition to conventional flexion forces due to the thermal gradient, in certain cases it is advisable to consider
the localized effects caused by a gradient operating between the two faces of the upper slab.
This gradient results in transverse flexion which is added to the other stresses. In the webs, the corresponding
section of reinforcement is added to that which is determined by the general shear force.
The figure 4.12 represents the thermal gradient in a common concrete box-girder according to Eurocode 1 –
Section 1.5. It shows that a thermal gradient exists in the upper slab.
For information only, we propose to consider a gradient of 10°C in the upper slab under the form of a linear
gradient. The combination to use is the same as the one for general flexion : G + Wr + 0.5 Δθ.
Note
This gradient has some effect only in the case of multicellular box girders. It is not necessary to take it into
account in the case of monocellular box girder.
Lower slab
The lower slab requires generally few lateral reinforcements unless it is very wide. As concreting is made at the
contact of the previous segment, the shrinkage can cause a longitudinal cracking. This phenomenon will be
amplified with a high strength concrete, a wide lower slab or a cement with a high hydratation heat. Therefore,
we advise to place a minimum reinforcement ratio equal to 10-4 fc of the lower slab section (with fc expressed in
MPa). For example, it gives 0.4% for a C40/50 concrete.
In the absence of transverse prestressing, the verification of the parts and the calculation of the reinforcements
are carried out according to the instructions in the BAEL (Béton armé à l’état limite - Limit State Reinforced
Concrete Code) 1991, revised in 1999. Cracking is generally considered to be detrimental.
When the transverse section is prestressed (upper slab), the verification of the parts and the determination of the
prestressing bars and reinforcements are carried out according Class III in the BPEL (Limit State Prestressed
Concrete Code) 1991, revised in 1999. But it is generally advised to increase the lateral prestressing because this
latter is only determined by the condition of zero traction in concrete under dead loads while the imposed loads
have a much bigger effect. The required amount of reinforcement would be high because the traffic loads would
cause frequent and repetitive cracking. To limit the amount of reinforcements (it is necessary to enable a good
concreting) and to limit the fatigue risk in these reinforcements or their corrosion, the class III rules have to be
completed as followed :
For the sake of good design and to prevent excessive cracking, the upper slab must remain transversally
compressed under a proportion of the imposed loads: for example, under the effects of the fatigue truck Bf (a
single truck placed in the centerline of the slower lane), specified in the "Ponts métalliques et mixtes - résistance
à la fatigue" (Metal and Composite Bridges – Resistance to Fatigue) guide published by Sétra/CTICM (Centre
technique industriel de la construction métallique - Industrial Technical Centre for Steel Construction)/ SNCF
(Société nationale de chemins de fer - French Railways). Such a choice has to be written in the Special
Technical Clauses (STC). The contract can also impose the amount of transversal prestressing.
The verification of the bridge deck under tangential stresses consists of checking:
• Firstly, that the shear stresses are permissible at all points, in order to reduce the probability of cracking.
Cracks caused by shear forces do not close up on their own like flexion cracks when the stress is reversed.
Furthermore, failure due to shear forces is a brittle rather than a ductile phenomenon. This is why
calculation methods always have a greater safety margin for shearing
• Secondly, that the non-prestressed reinforcement bars designed to take up the forces due to the
concomitance of flexion and shear forces are properly positioned and dimensioned with regard to the
statutory requirements (verification at the Service Limit State and the Ultimate Limit State). It should be
remembered that verification at the service limit state is designed to control cracking and at the ultimate
limit state the aim is to ensure safety by preventing brittle fractures.
Shear force calculations are carried out on sections of the beam perpendicular to the mean axis (Fig 4.13 where
G1 and G2 are respectively the center of gravity of the vertical cross-sections and of the cross-section
perpendicular to the mean axis.
To simplify, calculations of shear force are sometimes carried out on vertical sections, or more precisely, on
sections perpendicular to the upper axis. This calculation is usually less favourable, although not always so, as
the distribution of areas and stresses may reverse the phenomenon (cf. § 4.3.3).
• Thermal gradient
1) Segment on pier
The segment on pier is a large structure which is subjected to highly variable stresses during the construction of
the bridge deck and when the structure is in service. Therefore, rather than just concentrating on the definitive
situation, it is important to verify all of the major phases, from construction through to commissioning.
• Imbalances during the construction of the cantilever, with the segment on pier being embedded
(asymmetrical casting , detachment of form traveler)
• The tensioning of the external prestressing in the segment on pier (maximum distribution forces)
2) Standard segments
• The end of the construction of the cantilever (maximum prestressing in the section)
Tendons anchored at less than one regularization length from the section being studied create some distribution
effects which add to the general effects (in particular shear force) provided by the design program. .Certain
design programs include them just after their anchorage, other include them only at the other side of the
segment.
Furthermore, the angle of the tendons in relation to the mean axis generally reduces the shear force according to
the diagram 4.17. Therefore, it is important to be consistent when using the design program to account for the
reduction of shear force due to the tendons in order to avoid counting the same force twice.
Fig. 4.17 – Diagram of the reduction of shear force due to the tendons
For structures of variable height, the mean axis presents an angular point directly above the support.
Consequently, the support reaction is not equal to the sum of the shear forces to the right and left of this support,
but the vertical component of the normal force in the section must be added to it.
The development of highways and urban structures has led to the construction of extremely wide structures.
Although the majority of structures are now mono-cellular box girders, multicellular structures are also
sometimes used. These structures are more difficult to build and their complex transverse behavior, when not
fully understood, may lead to problems in the webs (non-uniform distribution of shear forces, especially for box
girders with three webs, as the central web takes up the most force). In particular, this type of section is sensitive
to the distorsion (deformation of the cross-section) that appears under loads. 3D modeling is required to account
for the transverse and longitudinal stiffnesses of the section.
Another solution that has been virtually abandoned in France is to construct structures with two box girders
joined together by the upper slab. The main disadvantage of this method is the differential shrinkage which
appears between concrete of different ages: between the concrete used for the box girders on the one hand and
that used for the transverse grouting on the other. The creep leads to a transfer of loads :
• Vertically the parts built in the second phase leans against the first box girder
• The normal force of the part built in the second phase tends to go to the part built in the first phase.
However, this transfer of loads has only a moderate effect on the stresses.
Finally, the effective width of the upper slabs on very wide monocellular box girder structures (with or without
struts and/or ribs) is reduced in relation to their total width (shear lag phenomenon). It is important to consider
this when evaluating flexion stresses. For an initial approximation, this phenomenon can be accounted for
according to the precepts of Article 5.4 of the BPEL, by limiting the effective width to 1/10th of the length of the
span in question, on either side of the web (for a box girder with two webs, this makes it possible to reach a total
effective width of b = total thickness of webs + 0.4 l. However, the presence of ribs improve the distribution of
forces in the upper slab, in preventing the buckling of this slab ; it is therefore not necessary to reduce the
effective width in such a structure.
It is recommended to concentrate the cantilever prestress tendons perpendicular to the webs so that they can
directly take up the loads applied by the webs (by shearing). Furthermore, it is advisable to place a tendon at the
end of each cantilever and position it so that it compresses the ends of the upper slab (see § 4.5.3 for further
details).
Finally, the distribution of forces concentrated in this type of section is not compatible with the normal
simplified rules and requires a specific study.
In structures of variable depth, we usually see an adjustment of the shear force due to the fact that the mean fibre
is inclined in relation to the slab: the compression in the slabs presents a component in the direction of the shear
force.
A part of the shear force is balanced by the normal force in the slab.
with:
According to the BPEL, the areas in question for the calculation of Nls and Nus are the slabs and gussets,
excluding the webs.
As can be seen in the formula above, the upper slab exerts a Resal "counter-effect" in opposition to the effect in
the lower slab. This is usually weak in proximity to the supports, as the compression of the upper slab is limited,
whereas because the variation in height is the greatest in this area, there is a greater Resal effect due the lower
slab. [For further details on theoretical methods, see the article by M.Virlogeux in the Annales de l’I.T.B.T.P,
no. 391, February 1981].
With modern calculation methods, calculations are systematically performed on section perpendicular to the
neutral axis. For the pre-design calculations, it is possible to perform calculations on vertical sections provided
that:
• Shear forces are directed in the usual direction according to the cantilever, in contrast to what can happen
in highly asymmetrical spans in which a reversal of the shear force can be observed.
ΔV = - Nls sin α with α being the angle of the lower slab from the horizontal
As mentioned previously, the vertical section calculation is less favorable. This is especially true close to the
supports due to the steeper angle of the mean line, and less so in proximity to the crowns. The difference may be
as much as 1 MPa in certain configurations.
For a traditional structure with two webs, the shear reaction caused by shearing force can be expressed by the
following formula:
S( y )
τ m = Vred with
bn ( y ) I
S(y) Static moment at the y ordinate (i.e. of the part situated above the transverse slice in relation to the line
passing through the centre of gravity).
When the webs are angled, the width b is the straight width of the web in question and not its skewed width
directly above the slice.
This formula supposes that there is no concentrated forces in the vicinity of the studied section. Additional steel
reinforcement brought by the tendon anchorages are determined with the distribution calculations.
As for the value of the nominal width, in the event of there being a tendon in proximity to the joint (“internal”
tendon), it should be remembered that the whole diameter of the duct shall be deduced from the width when it is
not injected, or injected with a flexible product, and a half-diameter shall be deduced when it is injected with a
cement grout (cf. BAEL Article 7.4.1).
T
τT = with
2Ωe
T moment of torsion;
Ω Area of tube defined by the middle surface of the box girder walls
This torsion is caused by asymmetrical loads (dead loads and especially imposed loads) and by any curvature of
the bridge deck in the horizontal plane.
• This calculation obviously supposes that the section is undeformable, which is generally the case, as the
structures feature deviators which act as stiffeners and have webs with approximately the same thickness
as the slabs (with quite similar stiffnesses). This undeformability hypothesis can be considered if the
length between stiffeners does not exceed 5 to 6 times the box girder width. Beyond, the box girder
distorsion increases the difference of longitudinal flexion between the webs and can be expressed with an
offset coefficient applied to the loads.In the case of a curved bridge which section is supposed
undeformable as indicated above, the torsion induced by the curvature has to be taken account for at
different stages:
• At the construction of the cantilever, for self-weight, the center of gravity of the arch portion is on the
inner side of the curvature. As a result, the torsion effect tends to load the support on the inner side
• The fittings weight applies on the continuous structure, and generates a torsion opposed to that of the self-
weight
• The external prestressing having a polygonal layout, generates a torsion which increases the load on the
support on the inner side.
The sections are verified according to Article 7.2 of the BPEL 1991, revised in 1999. The stresses σx, σt and τ
calculated at any point of a section, must therefore satisfy the following inequalities at the service limit state:
For σx > 0
⎡
τ 2 − σ x σ t ≤ 0,4 ftj ⎢ftj +
2
(σ x + σ t )⎤⎥ (no failure due to cracking)
⎣ 3 ⎦
τ 2 −σ x σ t ≤ 2
ftj
(0,6 fcj − σ x − σ t )⎡⎢ftj + 32 (σ x + σ t )⎤⎥ (no failure due to shearing and compression)
fcj ⎣ ⎦
⎡ 2
τ 2 ≤ 0,4 ftj ⎢ftj + σ x ⎥
⎤
and τ2 ≤ 2
ftj
(0,6 fcj − σ x )⎡⎢ftj + 32 σ x ⎤⎥ with the first formula nearly always
⎣ 3 ⎦ fcj ⎣ ⎦
predominating.
When the calculations are performed with the probable value of prestressing Pm, the limit stress τ must be
multiplied by a coefficient k’. Special precautions must be taken with regard to structures built by the cantilever
method due to their technical complexity. Consequently, a figure of 0.95 is usually adopted for this k’
coefficient (BPEL, Article 4.10.1).
The reinforcements are determined at the ultimate limit state (BPEL, Article 7.3.2):
At fe ⎛ ftj ⎞
≥ ⎜τ red .u − ⎟⎟ tgβ u for reinforcements perpendicular to the mean axis.
bn st γ s ⎜⎝ 3 ⎠
Eurocode 2 (EN 1992 1.1 - Article 6.2) does not require verification at the service limit state. The procedure for
calculating the non-prestressed reinforcements is similar to that laid down in the BPEL, with the contribution of
the concrete accounted for in a similar way but with several additional refinements. As this document is still
under development, we shall refer back to it when it is finally published.
This technique has sometimes been used to improve the shear resistance of webs. The only reason for its
inclusion here is to remind readers of the drawbacks which led to its fall from grace:
• Considering the very short length of the prestressing tendons, their tension can differ considerably from
the expected value due to the setting of anchorage wedges. Only certain types of active reinforcements
can guarantee the correct tension (compression fittings, prestressing bars)
• The distribution of forces only occurs above a certain length - hence there is a lack of compression
between the anchorages at the bottom of the web. Therefore, the shear force at the web/lower slab
junction must be verified without taking account of this compression
• To guarantee the correct distribution of forces, it is necessary to bring the active stirrups very close
together. These stirrups have to be inserted into the passive reinforcement of the web, thus complicating
the concreting process
• Due to their design, these reinforcements emerge in the upper slab and are thus extremely sensitive to
corrosion. It is thus necessary to use “offshore” types of protection techniques, which makes this a
particularly costly solution (requiring sealed caps and ducts, for example)
• Finally, some of the vertical prestressing force is dissipated in localized areas of rigidity such as deviators
or crossbeams (zones in which the greatest shear reaction is usually encountered reached).
In order to prevent the fracturing of the vertical planes situated at the origin of the gussets (points S1, S2, I1, see
Fig 4.1 at § 4.1) due to excessive shearforce, it is important to tie in the shear strain using transverse
reinforcement bars. These bars are dimensioned in accordance with the instructions in Article 7.3,23 of the
BPEL 91, revised in 1999. It is also important to verify the shear stresses at the service limit state as mentioned
above (cf. § 4.3-6).
Fig. 4.21 – Tie bars to combat shear strain in the slab/web area
For the lower slab, a minimum level of transverse reinforcement is necessary to reduce cracking due to thermal
shrinkage in the central area of the slab. A value of 0.5% seems to be sufficient under the most penalizing
conditions (large width, HPC, etc. – see also § 4.2.4).
4.4.1.1 Generalities
It should be remembered that the initial static design of these parts of structures often does not allow for the
application of Strength of Materials principles for the wire frame beams at all points. It is thus important to
verify that the morphology of the segment on pier is capable of withstanding the transmissions of internal forces
(e.g. the subsequent anchoring of the external continuity prestressing, crossbeam for definitive or temporary
bearings).
• The transmission of support reactions from the bearings (both temporary and permanent) towards the
webs
• The take-up of the lateral thrust of the lower slab by this same crossbeam for a variable height
• The distribution of the prestressing forces due to the tendons positioned in the segment on pier (SOP).
4.4.1.2 – 3D model
As previously mentioned in § 4.2.2.2, a 3D model is generally used to model the segment on pier due to the
presence of reinforcing elements (crossbeam, thicker sections of web, etc.) which completely modify its
behavior in comparison to a standard section. This model is used to verify the first three points presented above.
It is also possible to use a strut-and-tie model [cf. J. Schlaich - PCI Journal – May / June 1987] to verify this
transmission of forces. The principle of this method is the following:
• Construction of a model composed of struts and ties which replace the actual stresses fields by straight
elements and which concentrate the stress deviation in the nodes
The difficulty of this method is the construction of the model. The rods of the model have to be oriented
according to the direction of the internal forces given by the Elasticity Theory. The usual method is the load
path method. The model is linked to the rest of the structure where the stress are supposed to be regularly
distributed and linearized (B zone as Bernoulli, cf Schlaich). The model is balanced with the force brought by
this zone B. The stress diagram of this B zone is divided in such a way as to balance the concentrated forces by
the corresponding zone with regularly distributed stress. The load paths have to link the two sides of the studied
zone without crossing each other.
But it is sometimes difficult to determine the load path. It can require the use of a finite element model. This can
be quite cumbersome.
The reader’s attention is drawn to the fact that although this method is very effective for use with any irregular
parts of this type, it requires the engineer to have a very good understanding of structural behaviour. A poor
choice of struts and ties could lead to an incorrect arrangement of reinforcement bars and the use of excessively
or insufficiently large sections. The latter choice would be a much more serious problem.
Figure 4.22 below shows the behavior of the support crossbeam under the effect of the torsion of the box girder.
As an example, the figure 4.22 represents the working of the crossbeam under the effect of the torsion
transmitted by the box girder, for a common type of crossbeam ("V" shape). Other types of crossbeam can be
considered : "A" shape, or strengthened frame.
In the case of structures with high curvature, the bridge deck is subjected to torsion moments caused by the
curvature, which results in significant shear reactions in the webs close to the piers. Obviously, the crossbeams
on piers have to take up these additional forces (see also § 4.3.5).
The fourth point (distribution) is verified according to the usual principles (Appendix 4 of the BPEL). However,
as the section is not constant (anchor blocks and thicker sections of web), it is necessary to make a choice
between the sections in which the distribution of stresses is carried out. Considering the relatively large depth of
the bridge deck in this area (especially in the case of structures of a variable depth), this distribution length
generally includes the “standard” cross section of the bridge deck. It is on this section that we shall consider the
stresses to be evenly distributed. On the other hand, when evaluating the shear stresses at the level of the
transverse slices, it is reasonable to consider the actual section, i.e. including the additional thicknesses of the
anchor blocks. This has hardly any effect on the reinforcement which depends primarily on force rather than
stresses.
Remark
To study the distribution of forces due to tendon anchorages in segments on piers, (or in segments on
abutments), the upper slab has been sometimes considered as a beam supported by the web and the
reinforcement calculated as a flexion reinforcement. This method was not satisfying since this "beam" is not a
beam as a matter of fact because of the existence of the rest of the slab behind the element artificially isolated
with length lr. The rebars will be placed at the opposite side of the anchorages where as the cracking phenomena
always occur near the anchorages. This can lead to an incorrect arrangement of rebars and to severe problems in
the structure. Anyway, it is advised to place some reinforcing bars in the opposite sides of the anchorage blocks
to make it non brittle.
Segments on abutments have to transfer much smaller forces to the supports than segments on piers. On the
other hand, the distribution forces are much greater due to the fact that all of the external tendons are anchored
in the same section. For this reason it is advised to place a transversal prestressing to reduce the passive
reinforcement and make concreting easier. This prestressing enables also a cracking control.
The design principles are the same as for the segments on piers. As the height is constant, the phenomenon of
lateral thrust due to the compression exerted by the lower slab does not exist.
The balance of the end strut will have to be studied very carefully. In general, it is sufficient to anchor two
longitudinal tendons in the inferior angle above the support.
When concreting these segments, generally with a inner wood formwork, it is important not to wait too much
before stripping not to obstruct the shrinkage.
Furthermore, it is necessary to stiffen the end of the upper slab under the pavement joint in order to take up the
localized flexion forces at this edge under the effects of the moving loads.
In general, the distribution of prestressing is verified in accordance with the instructions in Appendix 4 of the
BPEL 91, revised in 1999. However, as this article features several ambiguities or omissions, the following
specific additions should be made – while awaiting modifications to this appendix.
As it currently stands, Eurocode 2 does not have a chapter about the distribution of concentrated loads.
For the regularization length, it must not be assumed that the bridge deck is simply “rotated” through 90°. This
would give an excessive length, resulting firstly in very low shear forces and the use of insufficient
reinforcements, and secondly, in these reinforcements being positioned too far from the point at which the
forces are applied. It must be remembered that the cracks which are observed in examples of the distribution of
concentrated efforts always appear near the anchorage. It is recommended to use half of the width of the bridge
deck in the case of a box girder.
Reinforcement bars for the anchor blocks are determined in accordance with the instructions in Appendix 4 § 2
of the BPEL 91, revised in 1999.
It should be remembered that it is highly inadvisable to situate anchor blocks or tendons inside the concrete in
curved (cf. § 4.2.3-2) or even straight lower slabs, and that it is preferable to place them in line with the gussets
at the junction with the web.
The transverse reinforcements in these anchor blocks must tie the blocks into the rest of the section.
• Reinforcement bars at the top of the anchor block in order to tie the block into the neighboring box girder
wall (A1 reinforcements)
• Reinforcement bars taking up the radial thrust when the tendon deviates (A3 reinforcements)
• Tie bars for the rest of the anchor block (A2 reinforcements).
The aim of the calculations is to verify the safety at rupture for cracked concrete. However, in order to facilitate
these calculations, the problem is compared with a non-cracked state, considering the anchoring force at the
2
service limit state and limiting the stress in the reinforcements to σs = fe
3
F
For the A1 reinforcements, the cross section is equal to : A1 = 0,2 with F being the force at the anchorage.
σs
This represents nearly all of the “surface” and “spalling” reinforcements described in the BPEL
For the A3 reinforcements, we simply use F sin α according to the deviation plane of the tendon; this value is
normally around 0.2F.
Finally, for the A2 reinforcements, a maximum value of 0.2F is also used due to the fact that the prestressing
force is directed towards the concrete and it thus exerts a component that is perpendicular to the “horizontal”
calculation axis.
The areas of reinforcements in question must be the sum of the cross sections in both planes (horizontal and
vertical). For example, two sections of reinforcements must be considered for A1 and the same applies to A2 and
A3.
The reinforcement elastic stress shall be taken with its real value, because it is a ultimate limit state verification.
For example, with fe=500 MPa for classical reinforcement Fe E 500 (no limitation to 400 MPa). Because the
excess of reinforcement leads to concreting difficulties, we have to be careful not to overdimension this zone.
Furthermore, it is important to respect the concrete cover – not too small, not too high – to guarantee the
concrete durability.
(For further details, see "bulletin Ouvrages d'Art" from Sétra n°11 from January 92 and comments and
observations in n°12 from July 92 and n°14 from March 93.)]
Traction reinforcements may be necessary to take up the traction due to the obstructed shortening of the
concrete, behind the anchor blocks. These reinforcements are determined in accordance with the instructions
given in Appendix 4 § 2.3 of the BPEL 91, revised in 1999, by limiting their length near to tendon.
The major characteristic of the external tendons is their great individual power which, added to the fact that the
force is obviously applied outside the concrete, results in the need to ensure that such large forces are securely
anchored. Mistakes in this area have sometimes led to complete failures which could have been avoided with a
minimum of forethought at the design stage.
In the first place, it is a matter of common sense to position the anchorages for external tendons in the
crossbeams as close as possible to the webs and slabs in order to transmit the forces as directly as possible
towards the walls of the box girder. Transmission via compressed concrete struts is always the most efficient
method.
Furthermore, it is essential to make the anchoring elements thick enough (in the longitudinal direction of the
bridge deck) to ensure that they are capable of transmitting most of the force. A lack of thickness results in
punching shear in the element in relation to the box girder tube which cannot be taken up by the reinforcements
alone.
Finally, it is sometimes more appropriate to foresee a phasing which limits the dissymetry of tensioning forces,
rather than thickening the anchorage blocks to resist an inappropriate intermediary phase.
In prefabricated structures, the segments have multiple shear keys designed to transmit the shear force. The
shear reaction is considered to be taken up over the shear keys cross-section according to the following formula:
The shear keys alone have to take up the shear force before polymerization of the adhesive.
A conventional shear keys such as the one shown hereafter (cf. Fig. 4.25) can take up:
Vad = τ b . 0,10 . b with b representing the width of the shear key (0.10 is the height of the keyshear (Vn+1)
In certain situations in which there is a rapid rate of assembly, several segments may be lashed before the first
joint has had time to polymerize (up to four segments on the Ile de Ré bridge, for example). The number of
shear keys required is calculated accordingly: it is considered that the shear force of n segments is taken up by
the shear keys alone in the first section at the end of polymerization. Because some of the shear keys could
break during stripping, it is necessary to foresee additional keys.
Once the adhesive has polymerized, the shear force is taken up throughout the entire height of the web, as for
cast-in-situ structures.
It is essential that the shear keys leads to a web side, for the glue to evacuate when compressing the joint : for
evident aesthetical reasons, we make the keys lead to the inner side of the box girder. Furthermore, shear keys
have to be placed in the upper and lower slab to prevent the shifting of the slabs. Finally, in the case of variable
height decks with vertical joints, these keys take up the the vertical component of the compression in the lower
slab which slopes gradually towards the supports.
It is advised to compress the joint section with 0.2 MPa in order to spread the glue in all the section.
It has already been mentioned in paragraph 4.3.2.4, that extremely wide structures, which are becoming
increasingly common, have specific behaviors and a reduced effective slab width. In the case of prefabricated
segments, they suffer from a problem that increases with width, although this phenomenon is shared by all
prefabricated structures: a transverse “banana-shaped” deformation occurs in the horizontal plane due to the
thermal gradient between the segment in the process of hardening and the segment that has already been cast.
This causes the joints to open up when the segments are brought together and thus leads to a non-uniform
distribution of the stresses (in the transverse direction), which can result in cracking at the ends of the joints.
[For further information, refer to the article in the PCI journal - July-August 1995]. In certain extreme projects,
an accumulated deformation of 24 mm can occur over a span of approximately 30 meters in length.
• Transverse flexion
• General shear force (including torsion). The tangential stresses accompanying the general or localized
flexion stresses result in shear stresses which are added to the shear stresses due to distribution described
hereafter
• Localized forces (reactions from the support system, application of the cantilever or continuity
prestressing, forces due to the site loads or form travelers). The distribution of these forces in the structure
gives rise to stresses which are added to the shear stresses described above.
• An additional reinforcement positioned in proximity to the concentrated efforts in order to take up the
distribution of these forces.
It should be noted that the distribution forces are only high for the external tendons, firstly due to their high
individual power, and secondly because several of them are placed in the same section (usually on a support).
Cantilever tendons, like continuity tendons, are less powerful and it is rare to find more than one pair of them in
the same section, which results in moderate distribution.
• The combination of shear force and torsion reinforcements is carried out according to Articles 7.6.54 of
the BPEL 91, revised in 1999 and A.5.4.4 of the BAEL 91, revised in 1999
• The combination of dispersion and shear reinforcements is carried out according to Article 4 of Appendix
4 of the BPEL 1991, revised in 1999:
⎧ A1
⎪
Acis = max ⎨ ⎧1,5 A2 with A1 distribution reinforcements
⎪min ⎨ A + A
⎩ ⎩ 1 2
• In the slabs, there is no combination of tie bar reinforcements with the transverse flexion reinforcements
according to Article A.5.3.2 of the BAEL 91, revised in 1999. However when shear stress are close to
limits or in the case of very important distribution stresses, we will apply the combination rules quoted
below for webs (zone of anchorage at the end of deck for example).
In the webs, we shall place reinforcements with a total section of Ae on the external side and Ai on the internal
side must be implemented in such a way that, using the following notation for the sections used to calculate the
flexion reinforcements:
Principle
Indeed, the combination of reinforcements must firstly take account of the non concomitance between the
flexion forces. In a single horizontal section of web, a loading case giving flexion reinforcements on the external
side of Afl ext will not give reinforcements on the internal side Afl int ≈ 0 (except in the case of incorrect
dimensioning requiring the use of compression reinforcements). As a consequence, the reinforcements on the
opposite side may take up the shear force, as this does not require a specific position in the section. Thus, it is
not necessary for the areas of flexion and shear to be added up. [for further information on this theory, see the
Article from D. Le Faucheur on this topic in the "bulletin Ouvrages d'Art" from Sétra n°41 October 2002].
Remarks
The coefficient k represents the part of additional reinforcement necessary to take up the shear force. It is equal
τu
to : k =
2 f sin β cos β
3 bu u u
τu being the shear stress at Ultimate Limit State (ULS) and bu the angle of the strut associated with the shear
force and limited to 30° (in case of casting in two phases, the value of bu is 45°). The ultimate compressive
0,85 fc
strength of the concrete is equal to fbu = .
θ γc
The theory quoted above use concomitant load cases. The complete study would be a useless complication. To
simplify we can consider separately the characteristic combination for shear stress and the one for transversal
flexion. It is then justified to take θ=0,85 (for short term loads). In this hypothesis, the coefficient k is equal to :
τu
k=
0,444fc sin βu cos βu
It has to be noted that this is a ultimate limite state calculation. As a consequence, the reinforcements for flexion
has to be calculated at ULS and not at Service Limit State (SLS) as it is the case for detrimental cracking.
Otherwise it would be too severe and not coherent with the theory developped in this article.
This calculation principle is determining only for very thin webs. Indeed, the transversal flexion use a great part
of its capacity and consequently it is necessary to complete the reinforcements to take up concurrently the shear
force.
Similarly, it is necessary to consider consistent loading cases for the accumulation of reinforcements:
• If we consider the construction stages, maximum flexion is obtained when the bridge is in service,
whereas distribution is lower due to the existence of a certain symmetry in the anchoring forces on
supports, or due to losses of tension in the cables.
• Geometrically, for a cantilever tendon anchored in the height of the web, the transversal flexion is
maximal at the top of the web where as the combination of general shear force and distribution force is
under the anchorage (because shear stresses have the same sign under the anchorage and opposite sign
above the anchorage).
• Transverse reinforcement of the webs with shearing and distribution force frames
Upper slab
As mentioned above, the tie bar reinforcements must not be added to those determined by transverse flexion. In
both cases, relatively large cross sections are obtained.
Webs
It is usually possible to limit the loading cases with regard to transverse flexion. A symmetrical loading case
produces maximum flexion in the webs, whereas offset trucks produce maximum torsion and give a lower level
of shear force.
Lower slab
In the lower slab, transverse flexion forces are reduced due to the distribution of the imposed loads from the
upper slab through the webs. In the case of very wide structures, attention should be focused on the relatively
large tie bars between this slab and the web. This is the reason for the very long gussets which are usually used
in this type of structure.
Upper slab
In general, it is preferable to position the transverse reinforcements (main bars with larger diameters) in the
external layer and the longitudinal bars (secondary bars) in the internal layer.
When the slab is transversally prestressed by tendons, it is advisable to position them underneath the two
previous layers, especially as this allows them to drop down inside the slab in accordance with bending moment,
without being obstructed by longitudinal reinforcements.
In order to improve the casting quality of the slab and the webs, no more than two transverse reinforcements and
one stirrup (i.e. three reinforcements in a plan view) should be placed side by side.
Given that it is common to find prestressing ducts in the upper slab, it is necessary to position duct supports
sufficiently closely together in order to prevent the tendon from wobblingand make sure that there is no risk of
the slab spalling once the tendons are stressed. The recommended spacing is approximately 0.50 m to 0.75 m.
Furthermore, to avoid reinforcements deformation which could give an unsufficient reinforcement for the
durability of the structure, it is necessary to place either some chair spacers between the two reinforcement
layers, or some rectangular stirrups as it is the case in the lower slab (Fig 4.27 and Fig 4.29).
Lower slab
In proximity to the piers, the lower slab is submitted to very high compression. It is not recommended to use
compressed reinforcements to take up this force if the slab is of insufficient thickness. Indeed, a spalling force
appears at the ends of compressed bars, which weakens the overlapping areas and requires reinforcing with tie
bars. Information concerning the precautions to be taken with compressed parts can be found in § A.8 of the
BAEL 91, revised in 1999).
• Thicken the slab, being aware that the weight gain is small as the variation in thickness is generally
parabolic and that this thickness is only apparent near the supports
In all cases, the slab tends to delaminate due to compression, hence the need for tie bars. Consequently, it is
strongly recommended to place reinforcement rectangular stirrups rather than concrete chairs within the slabs in
order to support the upper layers. In addition, the rectangular stirrups add greater rigidity to the reinforcement
and thus help to improve the cover of the reinforcement bars.
Lower gusset
An example of the reinforcement of the lower gusset is provided below. The tendon ducts must be supported by
a special structure, which must be absolutely welded to the main reinforcement. Stiffness is necessary to prevent
the ducts from shifting during the concreting under buoyancy, which could lead to very strong radial thrust
when tensioning with disastrous consequences.
Webs
As for the slabs, the transverse reinforcements are positioned in the external layer. Considering the depth of the
decks of bridges built by the cantilever method, it is very rare for the web reinforcements to be contructed in full
rectangular stirrup. They generally consist of two overlapping parts.
It is essential to avoid overlaps along the walls, i.e. in the standard section of the web. There are two possible
ways to resolve this problem:
• By using two L-shaped parts, which overlap in the full thickness of the upper and lower gussets
• Or by using large U-shaped part with a small U-shaped part as a top reinforcement, with the overlaps only
occurring in the upper gusset (Fig. 4.31).
The transverse reinforcements are joined by transverse rebars embedded inside the web, generally in the form of
stirrups ending on one side in a hook and on the other in a simple angled return. For the sake of durability, it is
better to place the hook on the external side of the bridge deck. The angled return should not be placed parallel
to the wall; instead, it should be angled towards the inside of the bridge deck (Fig. 4.32). At least four stirrups
should be used per square meter or two rectangular stirrups if this solution is used.
Longitudinal reinforcement
In the case of segments cast in situ, the longitudinal reinforcement cannot (save exception) respect the rules of
alternated overlapping according to the Article 6.1.23 from BAEL, because of a problem of lack of space given
the dimensions of the segment.
The segments on piers are massive parts for which it is advisable to carry out a specific analysis in order to
evaluate the stresses due to thermal shrinkage during differential cooling in the body of the concrete after
hydration of the cement. The temperatures rise in direct proportion to the volume and thickness of the cast
concrete and its hydration heat. This analysis may lead to the development of an optimized sequence of
operations for the segment on pier, taking account of the type of cement and any provisions that might be
implemented in order to promote the regular and homogeneous cooling of the concrete. Whatever the
circumstances, it is necessary to use crack control reinforcements capable of controlling any peripheral cracking
in this structure. In addition, this rise in temperature does not only produce forces; it can also lead to internal
chemical reactions within the concrete itself, known as sulfate reaction. These can cause severe problems in the
structure of the bridge itself.
The risk of such reaction appears only for very large thickness, around one meter for example.
5 - Cantilever stability
This chapter is entirely devoted to the problem of the stability of cantilevers in the construction phases. It
successively covers the causes of instability, different stabilization solutions and finally, the verifications to be
carried out.
It is essential to prevent the cantilever from tipping on the pier crosshead. To evaluate this risk, two types of
situations leading to imbalances must be considered:
• A temporary situation which occurs during construction when the cantilever is unbalanced due to the
weight of a segment that is built or installed before its symmetrical counterpart is in place, asymmetrical
site loads or a rising wind acting on one of the half-cantilever
In both cases, the combinations of actions to be used relate to the static equilibrium limit state.
Two families of combinations should be analysed: basic combinations corresponding to the first situation and
accidental combinations corresponding to the second. In the first case, it is verified that the cantilever does not
detach from its temporary supports; in the second case, a slight detachment is tolerated with a limited
overstressing of the stressed reinforcements that are used to secure the cantilever to its pier.
It is also important to verify the strength of all of the mechanical components which contribute to the stability of
the cantilever and of the whole pier and its foundations. This second verification relates to the strength ultimate
limit state. For simplicity’s sake, the partial safety factors for the combinations used for this verification are
identical to those used in the calculation of stability.
This chapter only provides general recommendations applicable to standard situations. Thus, the loads to be
used and the combinations of actions to be analysed must be adapted according to the sequence of construction
operations and the equipment used on site. Furthermore, for structures featuring large spans, built high up on
exposed sites, an additional ten-year wind value must also be carried out. It should also be noted that the rules
included in this chapter do not include construction errors or the failure to comply with construction procedures
relating to the casting or assembly of segments or to the movement of form travelers or assembly equipment.
Before the construction of the first cantilever, the contractor must supply the site with accurate, dimensioned
plans, showing all of the systems to be implemented along with their quality and tolerances. A specific
procedure must describe all of the construction phases, specify the order of phases that must be observed and
provide warnings about any dangerous events with a reasonable probability of occurrence. This procedure
brings together the different design calculations and construction methods. Drafted by the site’s Organization
and Methods Department, it must be approved by the engineering office and the site manager and must be read
by everyone involved in the construction of the bridge deck, especially the site foremen and sub-foremen.
The operations laid down in this report cannot be modified without the prior permission of the author and of the
engineering office which performed the stability verifications.
To a large extent, the choice of the process used to stabilize the cantilevers depends on the general design of the
structure (see Chapter 2). The span arrangement, the final support system and the design of the piers are
obviously major considerations when choosing this system.
Six main solutions can be used to stabilize cantilevers on their piers. We shall now examine them in detail.
Stitching via prestress tendons is the most widely used method for stabilising cantilevers during the construction
(Fig. 5.2). In principle, this is the most economical method for spans of less than 120 meters in length and
whose relatively massive piers offer a large crosshead surface. The method consists of tensioning vertical
reinforcements in order to secure the segment on pier to its supports.
During construction, the segment on pier rests on a set of temporary blocks on either side of the bridge bearing.
The use of the definitive bearings during the construction of the cantilevers is not recommended because there is
a significant risk of damage and, in any case, it is essential to adjust the bearings at the end of construction.
The stitching reinforcements are positioned at the side of the temporary blocks. Their upper anchorages are
generally placed in temporary prefabricated anchor blocks, positioned on the upper slab, sometimes on a metal
cross beam (Fig. 5.3). They then drop down through the segment on pier passing close to the webs, next to or
inside the support crossbeam.
Fig. 5.3 – Section through the SOP with its stitching tendons
In the lower end, the tendons are either tied off inside the pier shaft or anchored in the usual way. In the latter
case, the anchorages may be situated on the side of the foundations or in anchor blocks housed on the inside of
the piers if they are hollow.
The stitching prestressing is generally centred on the centreline of the pier. In certain specific cases, it may be
beneficial to reduce the number of tendons by offsetting them longitudinally. This applies:
• When a given direction of assembly or order of casting for the segments must be followed
• When the half-cantilevers are asymmetrical or made from different types of concrete.
In these specific cases, it is always important to check what would happen in the event of an error in the
construction process.
For prefabricated structures, a longitudinal offsetting from the base of the incremental launching beam produces
a similar effect (due to the support reaction caused by its weight and its anchoring tendons). In the case of
curved cantilevers, it is also possible to offset the tendons transversally in order to balance out the torsion
moment due to the curvature of the bridge deck.
Prestressing tendons are sometimes replaced by prestressing bars. However, this solution is not recommended,
because, in the event of an incorrect alignment between the recesses built into the segment on pier and the pier
crosshead, the bar may be subjected to parasitic flexion which could cause it to fail.
This method consists of increasing the center distance between the temporary support blocks by placing them on
temporary metal or concrete pilings (Fig. 5.4). This is only feasible when the bridge deck is situated at a
reasonable height above the ground (less than 15 meters or so).
• When the pier head dimensions are reduced, often for architectural reasons
• When the pier shafts do not have enough resistance to flexion to stabilize the cantilever on their own.
This is a viable solution for aquatic sites, provided that the pilings are supported on the foundation bulkhead for
the pier.
The cantilever is usually stabilized by two pilings positioned symmetrically in relation to the pier. However, a
cantilever may sometimes be stabilized by a single piling, especially when:
• A difference in weight due to the geometry or to the use of lightweight concrete affects both of the half-
cantilevers
• The structure is a portal bridge, as the portal legs cannot take up the vertical loads until the cantilevers are
connected.
Vertical prestressing on pilings usually completes this system (Fig. 5.5). If a single piling is used, this
prestressing is essential in order to prevent the side opposite the piling from tipping over.
This prestressing may also be replaced by a counterweight placed on the same side as the piling (Fig. 5.6, [JAE
00]).
For information, a variant also exists for prefabricated structures. This involves attaching the launch beam to
one of the half-cantilevers via compression bracing in order to stabilize it.
Stitching tendons may be positioned outside the pier in order to increase their efficiency. In this case, they are
anchored in the first cantilever segments and pass outside the pier shaft (Fig. 5.7). In the lower section, they are
anchored on massive counterweights on land, or fixed to the pier foundations (especially on aquatic sites where
the lower anchorages can be housed on the bulkhead). The tendons must be injected for adhesion to the
foundations. They must be protected against corrosion and damage caused by impacts to their upper sections.
• When the dimensions of the pier head units are reduced and do not allow for a sufficient center distance
between the stitching tendons (Fig. 5.8, [JAE 00]) ;
Fig. 5.8 – Stability via tendons outside a pier with a small crossheadl
A genuine system of temporary staying can also be used to resist wind-related dynamic stresses for tall
structures with large span lengths or more modest structures in windswept sites: Fig. 5.9 [BOU 94.3] and [GAC
98]). In this situation, the stays are anchored to a segment situated at a third or a quarter of the length of the half-
cantilever in the upper section and to a counterweight block on the ground equipped with vertical ties or pilings
working in traction. An efficient and economical anchorage can also be provided by attaching the stays to the
foundations of neighbouring piers.
These stays are very effective at absorbing the rocking motion around a horizontal axis perpendicular to the
centerline of the bridge deck. They supplement the fixed support or vertical stitching produced by the tendons
on piers. The stays usually consist of external prestressing tendons at moderate tension (30% of the tendon’s
maximum tension).
Certain angled stays may also be used to limit the torsion of the pier under asymmetrical horizontal forces due
to the action of wind on each half-cantilever (or under dynamic wind effects).
In addition, we should mention that it is sometimes better to stay the pier rather than the cantilever, especially
for very tall structures that have a short total span (although this is quite a rare occurrence).
If the structure has spans of very unequal lengths or very short end spans, it is possible to use the closure of the
small spans to stabilize the adjacent half-cantilevers (Fig. 5.10). At the start of the construction of the half-
cantilever, the structure must be stabilized using traditional methods. When the cantilever reaches the middle of
the shorter span, the central connection segment is assembled. The longer span is then built by over-
cantilevering, using the weight of the rear span to counteract the imbalance.
Fig. 5.10 – Closure of a rear span with counterweight and extended cantilever
When the cantilever is permanently embedded on its pier, the stability calculation is given by the strength
calculations for the pier shaft and foundations (Fig. 5.11).
For structures subjected to very strong winds, additional stays are often necessary, requiring extra verifications
under dynamic wind effects (see 5.2.1.3).
This solution is also required in the case of double pier shafts (Fig. 5.12).
In the most common situations, the pier heads must be designed to receive the following components (Fig.
5.13):
• Stitching tendons
• Jacking points for cantilevers under construction or nearing completion, or for changing bearings
• Seismic stops for protection in the event of earthquakes or impacts from boats.
The size of the permanent bearings varies enormously according to the structures: from 0.50 x 0.50 m for
structures with short overall spans to 1.10 x 1.10 m or more for structures with large spans.
Suppliers’ catalogues are useful for evaluating the surface area required for elastomeric pot bearings. These give
the plan view dimensions according to the maximum reaction under rare combinations at the service limit state.
In the absence of such catalogues, it is possible to estimate the diameter of the pot bearing by considering that
the elastomer stress reach 30 MPa under these same combinations. The dimensions of the plate can be estimated
by considering that the stress on the concrete of the pier is limited to 0.6 fcj.
For modestly-sized structures in which the bridge deck rests on laminated rubber bearings, this surface area is
calculated using a pressure of 13 to 15 MPa at the SLS under the same conditions as mentioned above.
In both cases, the minimum projecting ledge on the surface of the pier is 15 centimeters.
The surface area of the temporary blocks is determined by calculating the stability of the cantilever (see
paragraph 5.5.2). Solid blocks may also be replaced with sand boxes which can be removed without having to
raise the bridge deck.
The jacks must be capable of raising the entire cantilever before the placement of the closing segment in order
to insert the permanent bearings and change the bearings when the structure is in service.
However, for the changing of the bearings, it is possible to reuse the area of the crosshead that had previously
been reserved for the temporary blocks. Therefore, the raising of the deck must only be considered in the
construction phase. For information, 500-tonne jacks have a diameter of 40 centimeters. They must be placed on
metal blocks (e.g. measuring 0.50 x 0.50 m) in order to limit the stress on the concrete to approximately 20
MPa. The limit stress values obviously depend on the compressive strength of the concrete in the pier head
units. These are given in paragraph 5.5.2. It should also be noted that the clearance required between the
underside of the bridge deck and the bearing base is approximately fifty centimeters for jacks with a capacity of
500 tonnes.
From the outset, the design of the segments on piers and pier head units must incorporate the constraints
associated with the cantilever stability systems. Indeed, stability systems which cross the segment on pier
vertically (prestressing tendons or bars) interfere with the cantilever tendons situated in the upper gussets, the
deviator tubes used to house the continuous external tendons and the dispersion reinforcements in the
anchorages for the external tendons on the pier (Fig. 5.16).
It is also necessary to cross the highly reinforced areas of the lower slab, in light of the problems concerning the
transmission of temporary and permanent support reactions towards the webs of the box girder.
In all cases, the stitching system shall be designed to transmit the forces towards the support blocks as directly
as possible. In the upper part, the tendons must be anchored in thick areas.
The stitching tendons pass into the crossbeam on the pier if it is very thick or close to it and in proximity to the
webs if it is thinner (Fig. 5.17). A system consisting of anchor blocks, a distribution beam and vertical uprights
must also be envisaged for the transmission of the jacking force when the cantilever has been completed.
• The loads defined hereafter are not described in any statutory document; however, they represent the rules
of good practice in the field and have been successfully used since 1975. Thus, it is essential to formalize
these loads in the contract
• The proposed design methods depart from the rules for the creation of combinations in the Directives
Communes sur le Calcul des Constructions (Common Guidelines for the Design of Constructions) of
1979 (DC 79). This must be specified in the Special Technical Clauses.
The evaluation of dead loads, for this particular phase in the construction of the cantilever and for all of the
construction and service phases for the structure, must be performed with the greatest of accuracy, while taking
account of the precise geometry of the bridge decks and particularly of the crossbeams, deviators, anchor blocks
and the other morphological characteristics of the structure.
The weight G of the cantilever is calculated using a unit weight γ of 24.5 KN/m3 according to the formwork
plans (strictly speaking, the BPEL 91 fixes the concrete’s unit mass at 2.5 t/m3).
If high or low density aggregates are used, the measurement of the unit mass γt of the concrete used for the
bridge deck (prestressed or reinforced) is based on the unit mass of ordinary concrete γb, using a laboratory
sample of concrete without reinforcements using the following formula:
ρ
γt = γb +
7,85
(
× 7,85 - γb )
A figure of ρ = 0.18 at 0.22 t/m3 is normally used for bridges built by conventional cantilever segments. It
should be noted that HPC is denser than traditional concrete. For this type of concrete, approximately 50 Kg/m3
should therefore be added to the aforementioned values.
The weight of a half-cantilever situated on the unbalanced side is increased by 2% (Gmax), whereas the weight of
its corresponding half is decreased by 2% (Gmin).
For the rough calculations, simplified formulae can be used to calculate the weight of a cantilever. For example,
if the depth of the bridge deck varies parabolically and the thickness of the lower slab varies in linear fashion,
the approximate weight of the half-cantilever and the position of its centre of gravity can be determined using
the following formulae (Krawsky’s formulae), with B1 designating the section on the pier and B0designating
the crown section:
(B1 + 2 B0 ) γ lf
P=
3
(B1 + 5 B0 ) lf
d=
4 × (B1 + 2 B0 )
(NB: the selfweight of the half-cantilever calculated using this formula does not include the weight of the
crossbeam on pier or the weight of the anchor blocks, deviators and ancillary parts situated on the span).
This simplified method allows for a manual approach, which can be used for the preliminary calculations for the
structure. It is included here for illustrative purposes but it is not intended to replace precise calculations which
remain indispensable.
For curved bridges, it is obviously important to consider the offsetting of the weight of the cantilever, which
creates a transverse moment in the pier.
The BPEL makes a distinction between site loads whose size and position are known, and random loads, for
which a fixed allowance must be made.
Known loads are loads whose weight and position can be specified in each phase of construction, e.g. launch
beams, cranes used assembling segments, form travelers, etc. (Fig. 5.19). If there are significant uncertainties
concerning weights or positions, maximum and minimum characteristic values are determined and applied in
the most unfavorable way.
For cast-in-situ structures, this mainly concerns the weight of the form traveler, expressed as QPRC1, whose
standard value varies between 0.30 and 0.90 MN according to the length of the segments and the width of the
bridge deck. At the rough calculation stage, the weight of the form traveler is sometimes considered to be equal
to half the weight of the heaviest segment. In reality, this weight is highly dependent on the system used to
stiffen the form traveler under the weight of the fresh concrete. With complex systems featuring prestressing
bars, the weight of the structural steel can be significantly reduced.
For prefabricated structures, known site loads mainly concern the reactions at the base of the launch beam
during the installation of the segments.
In the calculations, these loads must be increased by + 6% on the side of the heavier half-cantilever or decreased
by 4 % on the opposite side (QPRC1 max or QPRC1 min) according to the same principle as for the selfweight of the
cantilevers.
Random site loads (Fig. 5.20) correspond to the materials stored on the bridge deck (e.g. cable rolls), small
equipment (e.g. compressors), staff and various climatic effects not considered elsewhere (rising pressure of
wind under a half-cantilever).
• An evenly distributed load (QPRA1) of 200 N/m²over a half-cantilever in standard situations (total span <
120 m). This load, which includes vertical wind force provided that the site is not exposed, is applied to
the completed segments and the form traveler
• A concentrated load (QPRA2) of (50 + 5 b) kN applied to the end of the cantilever, at the far end of the last
completed segment (b designates the width of the upper slab of the box girder expressed in meters); this
load represents the weight of cable rolls, compressors, small equipment, etc.
These loads are arranged in such a way as to produce the most penalizing effect.
For structures with an overall span of over 120 meters, the intensities of the loads QPRA1 and QPRA2 must be
calculated according to the equipment that is actually used on the site.
The load QPRA1 in the previous paragraph only includes the vertical wind force for structures with a total span of
less than 120 meters.
For other structures, including those with more modest spans but which are exposed to frequent strong winds,
for example in steep-sided valleys or in unstable areas where strong gusts of wind are common, it is important
to consider an additional load.
The additional wind effect (Qw) is equivalent to a uniform load with an intensity of 100 to 200 N/m², depending
on the characteristics of the site. It is essential to perform a specific study to analyze the nature of the site and
the local climatic conditions before this load can be reduced for very large spans (over of 200 meters).
This distributed load applies in a vertical direction from the bottom to the top on the horizontal frontal area of a
half-cantilever. Longitudinally, this force applies from the end of the form traveler to the row of temporary
blocks situated on the same side (or, more simply, to the centerline of the pier). Transversally, the width of
application is the width of the upper slab of the box girder.
Furthermore, in exceptional cases, (tall structures with a large overall span and relatively flexible piers), a
dynamic study is essential in order to evaluate the behaviour of the cantilever on its pier and determine how to
stabilize the cantilever before the closing segment has been completed (staying, compression bracing, etc.). This
is covered in paragraph 5.4.3 of this chapter.
Horizontal wind force only needs to be considered in particular cases: for tall structures in sites which are
exposed to strong and irregular winds caused by the morphology of the site. Such places often include coastal or
mountain valleys or sites exposed to winds that are renowned for their intensity.
In this case, we consider that one of the half-cantilevers is subjected to a uniform load of QWt. This load must be
evaluated on an individual basis for each project. In general the load is derived from the CECM (Convention
Européenne de la Construction Métallique – European Convention for Structural Steelwork) regulations. The
intensity of this load depends particularly on the height of the bridge deck and the ruggedness of the site.
• For the calculation of the piers and the foundations, the whole of the cantilever and its pier should be
loaded
• For very tall structures, the dynamic analysis prescribed in the previous paragraph must account for this
horizontal wind force.
The collapse of all or a part of an empty form traveler or a prefabricated segment during the assembly process
(FA) is allowed for by a dynamic increase coefficient of 2 in order to take account of the energy accumulated by
the deformation of a half-cantilever affected by the fall. This amounts to reversing the direction of the weight
the form traveler QPRC1MAX or of the last prefabricated segment on one of the half-cantilevers (Fig. 5.21).
For a cast-in-situ structure, it is possible for any mobile load to collapse during one or more of the form
traveler’s phases of movement. In the majority of cases, the calculations performed allow for the fact that the
entire form traveler might fall. However, a lower value could be adopted if a specific analysis of the safety of
the form traveler were to be carried out by the designers of this equipment at the start of the construction
surveys (see Fascicule 65A of the French CCTG).
For prefabricated structures, it is possible for any part that is not lashed by prestressing to collapse during one or
more phases of the assembly sequence.
• The ultimate limit state of static equilibrium, aiming to ensure the stability of the cantilevers on their pier
• The ultimate limit state of strength: for the different elements whose role is to provide stability and for the
elements which are stressed during these phases, especially the pier head units, the piers and their
foundations.
For each limit state, considering the nature of the actions, a distinction can be made between a temporary
construction situation, relating to a verification under a fundamental combination, and an accidental situation,
relating to a verification under an accidental combination.
During the construction surveys, these verifications must be systematically performed for the casting or
assembly of every pair of segments.
As we have already mentioned, the rules described hereafter are not as strict as those in the 1979 Directives
Communes sur le Calcul des Constructions (Common Guidelines for the Design of Constructions), according to
which it would be necessary to apply a load factor of 1.1 to the the selfweight of one side and 0.9 to the
selfweight of the other side. Therefore, it must be officially agreed in the Special Technical Clauses that these
rules differ from the recommendations of the DC79, as they are not regulations in the legal sense of the term.
For the verification of static equilibrium at ultimate limit states, the cantilever must not move from its temporary
supports. If the cantilever is embedded on the pier, no static equilibrium verification is required, although the
strength of the pier must be verified.
For the verification at ultimate limit states of strength, the different elements (blocks, tendons, pilings,
temporary stays, etc.) and the supports and foundations are verified using partial coefficients of safety for the
materials corresponding to the fundamental combination.
For cast-in-situ structures, the key phase at the pre-design level can be considered to be casting of the final pair
of segments. It is assumed that both form travelers have been moved forward and that the casting of one of the
two segments has been completed, whilst the casting of the other segment has not yet been performed, or the
form traveler has been emptied due to a defect in the concrete.
Likewise, at the preliminary design phase for prefabricated structures, the cantilever is studied during the
assembly of the final pair of segments. It is assumed that one of the two segments has been lashed to the end of
the cantilever and has been released by the assembly equipment. The other segment has not yet been assembled.
It is essential to analyse this imbalance on a systematic basis, even if the sequence of assembly or construction
operations calls for simultaneous operations. This is because:
• For a cast-in-situ structure, an incident during casting may lead to fresh concrete being emptied from one
of the form travelers, even if casting is carried out simultaneously.
Combination A1: 1.1 (G max + G min) + 1.25 (QPRC1 max + QPRC1 min + QPRA1 + QPRA2 [+ QW])
Combination A2: 0.9 ((G max + G min) + 1.25 (QPRC1 max + QPRC1 min + QPRA1 + QPRA2 [+ Qw])
In these formulae, Qw refers to the additional wind action to be considered for structures with a total span length
of more than 120 meters, or which are exposed to strong and frequent winds (see 5.3.2.3)
Combination A1: 1.1 (G max + G min) + 1.25 (QPRC1 max + QPRC1 min + QPRA1 + QPRA2 [+ Qw])
Combination A2: 0.9 (G max + G min) + 1.25 (QPRC1 max + QPRC1 min + QPRA1 + QPRA2 [+ Qw])
The left-hand form traveler is empty The right-hand form traveler contains a segment
(n - 1 segments on left) (n segments on the right)
These combinaisons are used for verifications at ultimate limit states of strength under accidental combinations
involving elements designed to provide the temporary fixed supports, and the supports and foundations
supporting the cantilevers.
In an accidental situation, the structure must be capable of resisting the collapse of a form traveler (or of a
segment in the case of a prefabricated structure).
In this case, the cantilever may be lifted off its temporary support blocks, but security is maintained by bringing
the full capacities of the materials into play, e.g. in the case of temporary prestressing, the tendons could be
overstressed.
The left-hand form traveler is empty The left-hand form traveler contains a segment
(nv - 1 segments on the left) (nv - 1 segments on the right)
Fig. 5.24 – Accidental situation to be considered for cast-in-situ structures
Combination B1: 1.1 (G max + G min) + FA -+ (QPRC1 max + QPRC1 min + QPRA1 + QPRA2)
Combination B2: 0.9 (G max + G min) + FA + (QPRC1 max + QPRC1 min + QPRA1 + QPRA2)
Very tall structures are usually very sensitive to the action of the wind. Specific rules must be applied to them,
not only to avoid penalizing them with an excessively high equivalent static pressure, but also to verify the
behaviour of the cantilever under dynamic wind effects.
For large cantilevers, e.g. when the sum of the span length and of the height of the pier exceeds 180 meters, it is
essential to perform a turbulent wind analysis at the ultimate limit state.
This specific dynamic analysis, which is carried out using one or more specialist wind effect programs (e.g. the
French PCP program), is designed to assess the amplitude of the oscillations caused by wind turbulence on a
flexible structure.
• A static description of the wind and its fluctuations (reference wind speed, ruggedness of the site, altitude,
wind turbulence, etc.)
• A dynamic modal analysis of the structure, giving the deformities and durations of the fundamental modes
of vibration in addition to the corresponding generalized masses
• The aerodynamic characteristics (drag, lift and moment coefficients) of the bridge deck and piers. (Some
of these coefficients can by determined for simple shapes by applying the rules of Eurocode 1 – Actions
du vent et de la neige sur les structures [Actions of wind and snow on structures]. Wind tunnel testing
must be carried out for the others).
The accumulated static and dynamic effects are used to determine and verify the stresses in the concrete and the
reinforcements for the pier shaft.
In the construction phase, the dynamic calculations are performed at the ultimate limit state only and by take
account of the ten-year wind effect. In service, they are performed with a fifty-year wind at the ultimate limit
state and also at the service limit state.
As the current regulations are quite limited with regard to this type of verification, the Special Technical Clauses
must comprehensively describe the actions, the combinations of actions and the safety coefficients to be
adopted.
The reader may also refer to the document entitled "Comportement au vent des ponts" (Behaviour of Bridges in
Wind) published by the AFGC, in addition to the articles entitled "Pont de Tanus: Les études des effets du vent"
(The Pont de Tanus: Wind Effect Analyses) [BOU 94.3] and "Le viaduc de Bourran à Rodez " (The Bourran
Viaduct at Rodez [BOU 91] for additional details.
It is important to specify that the dynamic analysis of wind effects must be carried out at the design stage
because it may raise questions about the design of the structure and also because the collection of data required
for this calculation often takes quite a long time, which could cause problems with regard to the deadlines
allowed for the construction surveys.
For these calculations, the segment on pier is considered to be undeformable. The position of each block or
temporary support includes an installation error of 5 centimeters (in the sense of a reduction in the space
between these temporary supports).
M and N are the stresses resulting from type A and B combinations. M and N are calculated for each of the four
combinations A1, A2, B1 and B2. e is the distance between the centerlines of the two rows of temporary support
blocks and d is the distance between one tendon and the opposite row of blocks (Fig. 5.27).
In the event that M/N < e/2, there is no risk of the cantilever tipping over; in theory, this means that stitching
tendons are not necessary; however, a minimum of two pairs of tendons are used for safety reasons (e.g. one
pair of 12T15 tendons per row of blocks). We use:
N M N M
Ra = − + Fi2 and Rb = + + Fi2
2 e 2 e
With Fi2 = 2 × (1 − p ) × σp0 × s
The values of e and d are derived from the dimensions of the segment and the pier head unit. It is difficult to
give advice with regard to the minimum values of e and d because they are highly dependent on the length of
the cantilever and the width of the box girder. Values of 3.00 to 3.50 m are common for e and d. This requires
pier head units of between 4.50 and 5.00 m wide.
In the event that M/N > e/2, stitching tendons must be used to restore the balance of the cantilever. To calculate
the number of tendons to be used, a distinction is made between type A and type B combinations.
The cantilever must not lift up. The prestressing must therefore compensate for the rising reaction force of block
A under the action of M and N (Fig. 5.28).
N M
Ra = − + Fi ≥ 0
2 e
N M
Rb = + + Fi
2 e
with Fi = n × (1 − p ) × σp0 × s
Under the action of the resultant N and the moment M of the loads applied to the cantilever, the segment on pier
remains in equilibrium due to the increase of the tendons tension ΔTg in a row of temporary supports and the
compression Rb, of the blocks in the other row supports (Fig. 5.29).
The equilibrium of the forces applied to the segment on pier when it rotates at an angle of dα around a row of
blocks and when the tendons lengthen or shorten, can be expressed in the following way:
Fg = Fi + ΔTg ≤ Ful c
Fd = Fi + ΔTd d
ΔTg d
= e
ΔTd (e − d)
+ M + Fd × (d − e ) = 0
Ne
− Fg × d − f
2
R b − Fg − Fd − N = 0 g
Fg and Fd refer to the tensions in each line of tendons; Fi is their initial force, Fu1 is their limit tension at the
ULS, with ΔTg and ΔTd being the variations in tension of each line of tendons (positive for a lengthening of the
tendons). It should be noted that ΔTd is either negative or positive but less than ΔTg, according to the position of
the blocks in relation to the tendons.
We obtain Fg and Fd according to Fu1 and Fi in the equations c, d and e and they are carried over into f. We
also know that:
fpeg
Ful = n × s × and Fi = n × (1 − p ) × σp0 × s
γp
⎛ N× e ⎞ d
n × s = ⎜M − ⎟×
⎝ 2 ⎠ K
The variation in tension in the line of tendons situated on the side of the rising force is equal to:
fpeg
Δσ = − (1 − p ) × σ p0
γp
Δσ
and the lengthening of the cables is equal to: ε=
Es
Δσ
For tendons with a free length of L, the stretching ΔL can be evaluated at L × . Therefore, the rotation of the
Es
segment on pier is:
L Δσ
tan(α ) = ×
d Es
For very tall or highly flexible piers, it is necessary to add the rotation of the pier head unit under the effect of
the unbalance moment M and the variations in tension of the stitching tendons.
If the designer considers the rotation of the cantilever to be too great, the response is to limit the increase of the
tendons tension by establishing a reduction coefficient for the value of the ultimate force of the tendons Ful.
In standard situations in which losses are 20%, this stretching can reach approximately 3%, which corresponds
to 6 centimeters for non-injected 20 meters cables. The calculation of rotation gives an angle of 1 degree for a
tendon situated 3.50 meters from the opposite row of blocks: a value which is considered to be acceptable.
The designer’s attention is drawn to the fact that, as the cantilever stabilization tendons are temporary, they are
not usually injected with cement grout. Consequently, if they are anchored at the foot of a very tall pier, their
extensibility and therefore their elasticity are significant, which may cause dynamic effects that could aggravate
the phenomenon during the rotation of the cantilever.
We use the maximum number of tendons per row. The number given by the preceding calculations is rounded
up to the next biggest even number, taking account of the need to place the bundles of tendons close to each
web. Knowing the prestressing force applied by each group of tendons, we can now dimension the blocks in
rows A and B.
The surface area of the blocks is such that they are compressed to fbu under the maximum reaction Rb,. As the
concrete of the blocks and the pier crosshead is hooped, its characteristic strength under compression can be
increased. Article A.8.4.23 of the BAEL 91 fixes this stress at:
⎛ f ⎞
fcf = fcj × ⎜1 + 2 × ρ t × e ⎟
⎜ fcj ⎟⎠
⎝
with p representing the percentage of steel in the single hooped core, with an upper limit of 0.04.
On the other hand, for blocks positioned on high and massive bearing blocks, the compressive stress in the
concrete used for the bearing block is limited in order to avoid splitting the pier (Article A.8.4 and Appendix E.8
of the BAEL 91). The maximum value not to be exceeded is fclim, = K fbu with:
0,85 × fcf
fbu Ultimate strength of the concrete at ULS fbu =
θ × γb
⎡ 4⎛a b ⎞ ⎤ ⎛ 4 a 0 ⎞ ⎛ 4 b0 ⎞
K = 1 + ⎢3 − ⎜ 0 + 0 ⎟ ⎥ ⎜ 1 − ⎟ ⎜1− ⎟ ≤ 3,3
⎣ 3⎝ a b ⎠⎦ ⎝ 3 a ⎠ ⎝ 3 b ⎠
In order to obtain the critical value of 3.3 in the last formula, the support surface must have a large overhang in
relation to the blocks. Such overhangs are rarely compatible with the dimensions of the pier head unit.
Fig. 5.31 – Plan view dimensions of a block and its bearing block
The table below gives the orders of magnitude of the critical values given by this calculation according to the
strength of the concrete and the type of verification to be carried out:
Supposing that there are two blocks of dimensions a × b per support row, we have:
Rb
S = 2×a×b =
f c max
a and b are determined by examining the plan view of the pier head unit, allowing for the dimensions of the
permanent bearings and of all of the fittings on the pier heads.
Hooping identical to that used on the permanent bearings is calculated and added to the lower face of the
segment on pier and underneath the temporary blocks (cf. Article A.8.4, Appendix E.8 of the BAEL 91).
Appendix A of the standard NF EN 1337.3 (classification T 47.820-2) may also be referred to, which considers
uniformly loaded B0 surfaces.
Firstly, we verify that the cantilever does lift up with the number of tendons determined previously. For this, Ra
and Rb are calculated as if the cantilever was not lifting up:
N M
Ra = − + Fi
2 e
N M
Rb = + + Fi
2 e
If Ra is positive, there is no lifting up and the surface area of the blocks S is calculated by the formula:
Rb
S = 2×a×b =
fc max
If Ra is negative, we solve the equations c to g, but this time Fg = Fi + ΔTg, < Fu1 (this time Fi is known).
This gives:
e ⎛ K ⎞
Rb = × ⎜⎜ Fi × K 4 + N × 3 + M ⎟⎟
K1 ⎝ 2e ⎠
with:
K 1 = d 2 + (d − e )
2
K 2 = d3 + e × (2d − e ) × (d − e )
K 3 = 2 × K1 − e2
K 4 = (2d − e ) ×
K2
e × d2
We determine the surface area of the blocks S using the same formula described previous paragraph.
The dimensions of the blocks determined in this way must be increased by 5 to 10 centimeters for the coating of
the hoops.
The static equilibrium combinations calculated previously for the equilibrium of the cantilever and the
verification of the anchoring elements are directly used to verify the pier and its foundation at the strength
ultimate limit state, without modifying the coefficients of these combinations.
The vertical reinforcement bars of the pier shaft must be verified at the ultimate limit states for bending and
compression under the action of N and M. Type A combinations are considered to be fundamental
combinations, whilst those of type B are accidental combinations (γb =l,15, γs =l,00).
The designer’s attention is drawn to the fact that this verification is only carried out at the ULS. It is thus
important to limit the cracking of piers in temporary construction situations, i.e. with the equivalent of type A
combinations at SLS. To account for this phenomenon, we can either perform an additional calculation at SLS
by transposing type A combinations, or limit the working stress ratio of the reinforcement bars to the ULS under
this same type of combinations, e.g. to 400 MPa.
However, the piers must also be verified at the SLS and ULS for all other situations in the construction and
service phases.
In the case of a single piling, the verification rules are similar to those described previously.
Therefore, we start by studying the imbalance on the side of the piling (the side where the first of a pair of
segments is cast or assembled). Type A and B combinations are studied by verifying the same criteria as for a
cantilever secured exclusively by vertical stitching tendons situated in the pier. The blocks must not lift up under
type A combinations. Under type B combinations, the tension increase in the stitching tendons and the angle of
rotation of the cantilever are limited to a value to be determined in the Special Technical Clauses (to
approximately one degree).
The stability of the piling must then be verified. For short and massive pilings, a deviated bending and
compression calculation suffices, while taking account of an additional eccentricity of the blocks in both
directions or of a fault in the angle of the piling shaft. Further details about the values to be used in the
calculations can be found in the BAEL 91 or BPEL 91. For very slender pilings, it is essential to perform a
calculation to the second geometrical and mechanical order in order to prevent the buckling of this support. It is
vital to connect the piling to at least the pier head and to connect very tall pilings to the shaft at one or more
intermediate levels.
Next, we shall study the case of an imbalance on the opposite side to the piling during the assembly or casting
of the second of the pair of segments. Here, the type A combination is only studied, because the form traveler or
the prefabricated segment on the piling side has been made safe and is no longer likely to fall. The fact that there
is no detachment from the support on the piling means that the stitching tendons placed in line with the piling
can now be dimensioned.
The same type of calculation is used in the case of two pilings placed symmetrically in relation to the pier.
However, detachment from one of the pilings is authorized under type A and B combinations. The cantilever
then rests on one or two rows of blocks (type A or B combination) and on the piling situated on the side of the
imbalance.
For prefabricated structures, the collapse of the form traveler is replaced by the collapse of the segment being
moved in the aforementioned verifications.
The cable stays must be arranged in the most symmetrical arrangement possible in order to minimize the
disturbance to the geometry of the cantilever during construction.
For this calculation, it is necessary to make the following simplifying assumptions (Fig. 5.32):
• As a simplification, the stitching cables are situated in line with the temporary blocks; e is the center
distance between the two rows of cables; the cross section of one row of cables is s; the length of the
cables is 1 and their modulus is E; the force exerted by a row of cables is Fi
• The pier, of height h and constant inertia I, is considered to be embedded on its foundation
• Each row of cable stays has a cross section of s’; the cable stays are all identical, of modulus E^ and
length 1’ ; the initial force of a row of cable stays is noted as Fi’ (or Fg’ and Fd’ taking account of the
variations in tension due to the tilting of the cantilever)
• The cantilever is considered to be undeformable in terms of longitudinal flexion (this hypothesis remains
valid if the cable stays are not attached too far from the pier).
Furthermore, it must be remembered that the stabilizing cable stays contribute additional flexion forces that
must be taken up by the cantilever tendons.
Fig. 5.32 – Forces applied to the cantilever without detachment from the support
In the absence of cable stays and supposing that the cantilever does not lift off, the support reactions on the rows
of blocks A and B are as follows:
N M
RA = − + Fi
2 e
N M
RB = + + Fi
2 e
In general, if the reaction RA is positive, the cantilever does not need to be stayed. As this situation is of little
relevance to this paragraph, we shall instead assume that cable stays are required.
In order to calculate the cross-section of the cable stays, we differentiate between situations with type A and
type B combinations. As with cantilevers stitched by two rows of cables, there are two stages to the calculation:
• Firstly, the cross sections of the cable stays are dimensioned by limiting their increasing of the tension and
the rotation of the cantilever under all combinations (types A and B) and by making sure that the blocks in
row A are not decompressed under type A combinations
• Once the cross section of the cable stays has been determined, the support blocks are dimensioned by
verifying the compression on row B for type A and B combinations.
The calculation described hereafter does not follow this scheme but the underlying principles are clearly shown.
The cantilever must not lift off. The staying must therefore compensate for the rising reaction force of block A
under the action of M and N
N M
RA = − + Fi + Fi ' ≥ 0
2 e
N M
RB = + + Fi + Fi '
2 e
In general, the cable stays are made to work at 30% of their maximum capacity. In fact, the tension increases are
larger than those of the tendons. Furthermore, this low initial tension means that they can be used as temporary
cable stays on other cantilevers on the structure. Finally, when stressed in this way, they only undergo very
small delayed losses.
As the cantilever does not lift off from its support blocks, the stitching tendons are not subjected to any tension
increase. On the other hand, due to the flexibility of the pier under rotation, the cable stays are subjected to
variations in tension and the cantilever rotates to a certain extent.
It is thus necessary to verify that there is no movement from the blocks and that there is an acceptable amount of
variation in the tension of the cable stays and in rotation of the cantilever.
Given that:
h
k is the flexibility of the pier under rotation: k = ( θ = k Mp )
E Ip
Ip : its inertia
l'
K’ is the flexibility of the cable stays: K ' =
E s s'
ΔTg’ and ΔTd’ are the variations in tension of the cable stays under the effect of the rotation of the cantilever.
Their tensions are equivalent to:
Δl g ' Δl d '
θ ≈ tg θ = 2 = −2 (Δl'g et Δl'd are the variations in length of the cable stays)
e' e'
Given that:
ΔTg ' ΔTd '
θ ≈ tg θ = 2 K' = − 2 K'
e' e'
e' k e' k
θ = k Mp and therefore: ΔTg ' = Mp and ΔTd ' = − Mp
2 K' 2 K'
2 K' k
θ≈ M
2 K ' + k e' 2
N M ⎛⎜ k e' 2 ⎞
⎟
R A = Fi + Fi ' + − 1−
2 e ⎜⎝ 2 K ' + k e' 2 ⎟
⎠
R B = Fi + Fi ' + N − R A
However, this calculation is only valid if a block A remains compressed. Thus, it is necessary to verify that:
⎛ k e' 2 ⎞ ⎛
M ⎜1− ⎟ ≤ ⎜ Fi + Fi ' + N ⎞⎟ e
⎜ 2 K' + k e' 2 ⎟ ⎝ 2⎠
⎝ ⎠
The calculation is similar, but the detachment of the cantilever from block A is permitted while limiting the
rotation of the cantilever.
Fig. 5.33 – Forces applied to the cantilever in the event of its detachment from the support on side A
The additional terms ΔTg1’ and ΔTdl’ due to the rocking of the bridge deck on block B are added to the
expression of the tensions in the cable stays (Fig. 5.33):
On the other hand, the tendons in row A are overstressed. Their tension can be expressed as:
Fg = Fi + ΔTg
l
If we note K as the stiffness of the tendons ( K = )
Es s
as the cantilever is undeformable, the variations in the lengths of the tendons and cable stays are proportional:
K (e + e' ) K (e − e' )
ΔTg1 ' = ΔTg et ΔTd1 ' = ΔTg
2 e K' 2 e K'
Finally, we must add the effect of the overstressing of the tendons in row A under moment M. Therefore, we
have:
e' e' e
Mp = M − Fg ' + Fd ' + ΔTg
2 2 2
or by replacement in the expression of ΔTg’ :
ΔTg ' = Mp
k e'
2 K'
=M
k e'
2 K'
(
+ Fd ' − Fg '
k e' 2
4 K'
)− ΔTg
k e e'
4 K'
( ) ⎛
Fg ' 4 K ' + k e' 2 = 4 K ' Fi + 2 k e' M + k e' 2 Fd ' − ΔTg ⎜ k e e' − 2 K
e + e' ⎞
⎟ c
⎝ e ⎠
The rotation of the cantilever is the sum of the flexion rotations of the shaft and of the rocking around the
support B:
(
θ ≈ 2 Fg ' − Fd ' ) Ke'' + ΔTg Ke
6 - Construction technology
This chapter covers the technology required for the construction of prestressed concrete bridges using the
cantilever method. The first part deals with cast-in-situ structures and pays particular attention to the design of
temporary structures (form work for segments on piers, form travelers etc.) and cantilever stabilization systems.
The second part is dedicated to structures made from prefabricated segments. Therefore, this includes a
detailed description of the prefabrication plant and the equipment used for the transportation and assembly of
segments (launch beam, crane, low-bed semi-trailer, etc.).
Every year, numerous bridges are built using this method in France and abroad. Some of the largest structures
built in recent years include the bridge over the River Rhine to the south of Strasbourg, the Viaur viaduct at
Tanus for the RN88 main road, the second Genevilliers viaduct over the River Seine for the A15 highway and
the viaduct over the River Loire at Cheviré. Notable examples outside of France include the Norwegian bridges
of Stolma and Rafsundet, the Brisbane Bridge in Australia and the Hamana bridge in Japan, all of which are
notable for their great span.
Segments on piers are always built using special formwork which is specially designed for this part of the
bridge deck and assembled on a work platform attached to the tops of the piers (Fig 6.1).
The external formwork consists of fixed metal shuttering. The internal formwork is either built from traditional
wooden shuttering or carried out using an articulated metal tool. On certain structures with only one or two
piers, the length and thus the cost of the external shuttering for the SOP are reduced by using the external
formwork of the form travelers to encase the lateral sections of these segments.
The working platform, fixed to metal inserts embedded on the top of the pier head unit, is externally rectangular
in shape (Fig. 6.2). It has cut-outs in the middle for direct access to the underside of the segment on pier and the
top of the stability blocks and bearings.
Segments on piers are usually built in two phases: the first phase includes the lower slab, the gussets gusset and
the base of the webs; the second phase features the rest of the transverse section and the crossbeam on pier. The
completion time for a segment on pier is 6 to 10 weeks for a traditional structure but may stretch to 15 weeks for
structures which are very wide and/or with a very lon span .
Standard segments are built using highly complex formwork equipment called form travelers (Fig. 6.3).
Depending on the situation, this equipment is either built specifically for the site or existing equipment is
adapted to suit the site.
Like many other formwork tools, form travelers include three major elements, each of which performs a
particular function:
• A metal structure: used for attaching the form traveler and the future segment to the most recently
constructed segment
• Metal shuttering panels: used for giving the concrete the required shape
• Gangways and work platforms: for access and to allow employees to work in all areas of the segment
being built.
Although a large variety of form travelers are available, they are usually broken down into three families
according to the position of their supporting beams or their main beams in the metal framework. These
categories are:
• Form travelers with supporting beams situated above the upper slab
• Form travelers with supporting beams situated along the webs of the box girder
• Form travelers with supporting beams situated below the lower slab.
In France, the second type of form travelers, with supporting beams situated along the webs, is by far the most
commonly used, especially because the absence of any beams at the base of the segment to be constructed
makes it possible to insert a reinforcing cage that has been entirely prefabricated at ground level (Fig 6.4).
Frequently used after World War II, the first type of form travelers is no longer widely used in France.
However, they are regularly used in other countries (Fig. 6.5).
The third type of form travelers is only used in very specific cases.
The second and third types of form travelers are often called “below-slab” models, as opposed to the first type
of “above-slab” form travelers.
In the rest of this chapter, we have decided to concentrate exclusively on the second type of form travelers, i.e.
those with supporting beams situated along the webs. This family of form travelers can be split into two sub-
groups: those with an upper beam of the same width as the box girder, which are ideal for segments of a
standard height and width, and form travelers with a smaller cross beam and launch or transfer beams, which are
commonly used for very tall or wide segments.
In recent years, these form travelers have been used in the construction of numerous bridge decks and notably
those of the second Pont Salomon viaduct [DEW 01], the Digoin viaduct [DIEU 00], the Tanus bridge [SER
98], etc.
Described schematically, their metal framework consists of three large sub-structures (Fig. 6.6):
Fig. 6.6 – Principle of the framework for a form traveler with lateral beams
• A large U-shaped structure situated under the bridge deck, supporting the formwork for the underside of
the cantilevers and the external faces of the webs, along with the formwork for the lower slab; this
structure consists of two large longitudinal lattice girders, called supporting beams, and one vertical
“front” beam, which is also a lattice girder. This girder is situated at the end of the form traveler on the
segment n + 1 side, with segment n being the segment to be cast. In certain cases, horizontal bracing is
added to these two elements and situated under the lower slab
• An upper crossbeam, sometimes referred to as a transverse transfer beam, positioned on the upper slab of
segment n-1, at its free end (Figure 6.6 shows the specific example of a C-shaped upper beam)
• Sliding beams, supporting the formwork for the internal surfaces of segment n and situated under the
central part of the upper slab.
The design of the different elements described above takes account of two very different situations: the
movement of the equipment on the one hand, and the reinforcement, cabling and concreting on the other.
In the static phase, the connections between the three sub-structures are as follows:
• The upper beam rests upon the upper slab of segment n-1
• The U-shaped structure is fixed to the upper beam via rods across the upper slab that has already been
constructed; these rods are highly prestressed in order to reduce the deflection of the U-shape under the
weight of the concrete
• The sliding beams are supported on the front beam on the side of segment n+1 and attached to the upper
slab via transverse hangers on the side of segment n-1.
In the movement phase (Fig. 6.7), the support conditions for these elements evolve in the following way:
• The U-shaped structure is suspended on the upper beam, either via rods situated on either side of the box
girder, and thus without crossing the upper slab which has already been constructed, or via brackets
extending out from the upper beam under the cantilevers (in which case, this is called a C-shaped upper
beam). Other methods are also used. As the centre of gravity of the U shape is situated well in front of the
suspension plane, it has a tendency to tip on the crown side, but this movement is stopped by wheels fixed
to the rear of the supporting beams and blocked by the cantilevers that have already been constructed (Fig.
6.8)
Fig. 6.7 – Static schema of the form traveler during translatory movement
The movement of the upper beam and the U-shaped structure is carried out using long-stroke horizontal jacks
situated on the upper slab and pushing against the upper beam (Fig. 6.9). Depending on the situation, the sliding
beams are moved by tackle (Fig. 6.10) or by a second set of long-stroke jacks (Fig. 6.11).
Fig. 6.9 – Upper beam with long-stroke jack (at bottom of photo)
Using the form travelers described above, the major stages in the construction of a standard segment are as
follows:
Standard segments of conventional dimensions and shapes are almost always cast in a single phase, with a
construction cycle of between 48 and 72 hours per pair.
For a large segment, the suspension of the lower part of the form traveler from the ends of the upper beam
requires very large and thus very costly upper beams. For the construction of very wide bridge decks, it is thus
increasingly common to use form travelers that are designed to move on a “transfer frame”, which is positioned
transversally, very close to the webs.
• An upper beam without cantilevers, supported at right angles to the webs (Fig. 6.12)
• Longitudinal upper transfer beams, only used in the movement phase (Fig. 6.13)
• A main metal framework, which is virtually identical that used for the aforementioned type of form
travelers, with two large support beams and one front beam, usually in the form of lattice girders
• Sliding beams situated under the central section of the upper slab, as for the first type of form travelers
• Lower transfer beams, or sliding beams, situated along the two support beams.
Fig. 6.12 – Upper beam without cantilever Fig. 6.13 – Upper transfer beam
In the static phase (Fig. 6.14), the support and operating conditions for the form traveler are virtually identical to
those for the first type of form travelers. The main difference concerns the presence of lower transfer beams,
which in this phase are fixed to the two support beams.
The differences are greater in the movement phase (Fig. 6.15). Indeed, in this phase, it is necessary to:
• Place the two upper transfer beams on the segment that has just been constructed
• Release the lower transfer beams and suspend them from the two upper transfer beams in order to form a
frame capable of accommodating the main framework of the form traveler
• Release the main framework (both support beams and the front beam), lower it onto the frame consisting
of the four transfer beams and slide it into its new position, normally via long-stroke jacks
• Fix the main framework to the concrete and the upper beam
• Re-attach the lower transfer beams to the support beams, separate them from the upper transfer beams and
remove the latter.
The form travelers used for the Pays de Tulle viaduct on the A89 highway are good examples of this type of
form traveler [LAC 02].
As mentioned at the beginning of paragraph 6.1.2.1. of this guide, there are many different types of form
travelers and the preceding presentation is far from exhaustive. Special form travelers are commonly built for
the construction of bridge decks with struts, lateral shell elements or even hybrid structures (e.g. the bridge over
the Bras de la Plaine, the Vecchio bridge, the Corniche bridge in Dole, etc.) [CHU02], [PAU 00].
Considering the very high manufacturing costs for a pair of form travelers, efforts are often made on new
projects to reuse equipment that was designed for a previous site.
Unfortunately, as the decks of large bridges have no standardized elements, significant modifications often have
to be made to the form travelers in order to reuse them for the construction of a new bridge deck. Considering
the risks involved, the engineering design and implementation of these modifications must be handled with the
same care as for the original design and manufacturing phases.
The weight of form travelers that are custom-made for a specific project is normally quite close to half of the
weight of the heaviest standard segment. However, this ratio is sometimes exceeded, especially when a form
traveler that was originally designed for a wider bridge deck is reused on a narrower project.
The vast majority of deviator segments on composite prestressed concrete bridges are constructed in two phases:
the standard section is built using the form traveler used for the standard segments; the lower beam and the
deviator beams are built using wooden formwork with the concrete introduced through apertures left in the
upper slabs directly above the beams (Fig. 6.16). With this method, the reinforcement bars awaiting insertion
into the beams must be bent and then unbent - requiring the use of ADX steel - in order to allow the inner core
of the form traveler to slide freely. However, it is increasingly common to use mechanical couplers at the
junction between the webs and the deviator beams, making these operations unnecessary. It is now also possible
to use special high bond strength reinforcing steels which are capable of withstanding a bending-unbending
cycle without any loss of strength.
There are several structures in which the deviator beams were built in a single phase. In some of these
structures, a special metal core was built specifically for these segments.
In terms of their construction, segments built by over-cantilevering are similar to standard segments. Therefore,
they are built using form travelers designed for these segments.
Closing segments are normally constructed in a single phase, using one of the form travelers used for the
construction of the standard segments. If it is possible to remove the central core once the final segment is in
place, the internal parts of the closing segments are encased using the original core, as is the case for the
standard segments. If this is not the case, which is by far the most common situation, it is necessary to design
and use a special inner core, which can be broken down into small, easily transportable sections.
It should be noted that the most common practice is to use standard form travelers for the construction of the
closing segments. However, this does not happen systematically, and on certain projects, contractors prefer to
build special equipment for these segments, which allows them to remove their form travelers as quickly as
possible.
During the construction of the closing segment , the formwork equipment is positioned on simple supports at
both ends of the cantilevers because it would not be strong enough to withstand the thermal effects that might
develop in the continuously-rendered span. If the formwork equipment is specially built, these support
conditions pose no problems, but if one of the standard form travelers is reused, special precautions must be
taken because the majority of these tools are designed to operate in an overhanging position.
On certain sites, it is important for the aforementioned formwork equipment to be equipped with a system
designed to prevent certain parasitic movements of the cantilevers - especially their rotation around the axis of
the piers due to the effect of wind. Normally, this system consists of longitudinal beams fixed to the overhangs
of the last standard segment in each cantilever.
The time of the casting of a closing segment must be chosen with care. It is important to prevent the
development of significant thermal effects between the setting of the concrete – the moment at which the span
becomes continuous – and the stressing of the first continuity tendons. Therefore, casting in the late evening is
recommended during very sunny periods.
Two to three days are required to complete a closing segment, depending on the project.
In the majority of cases, the longitudinal profile of the natural terrain around the abutments makes it necessary
to construct the end sections on horizontal centering resting on the abutment crosshead and on one or more
temporary metal pilings (Fig. 6.17). The formwork for the bridge deck is then erected on this centering and the
casting is carried out in sections of 3 to 4 m.
However, it is possible to construct the end sections of the bridge deck on centuring towers, if the natural terrain
lends itself to this solution. This is the most economical technique.
End zones may also be built directly using the same form travelers used to construct the standard segments. In
order to limit the imbalance of the cantilever, a temporary piling is placed under the last standard segment on the
abutment side and then caulked after the cantilever tendons associated with this segment have been stressed.
This piling also helps to reduce flexion at the end of the bridge deck (Fig. 6.18) [DEM 02].
Fig. 6.18 – Construction using form traveler and temporary piling on the end section of an end span
The following section contains technical information concerning the stabilization of cantilevers. This
supplements Chapter 5 of this guide.
Stitching prestressing is normally carried out by tendons. In the lower section, according to the piers, these
tendons may be anchored on the underside of the crosshead, by forming a loop in the shaft or on the foundation
bulkheads. In the upper section, they must be anchored to anchor plates housed in the upper slab of the SOP. If
this solution is impossible due to the density of reinforcements in these parts, the anchorages are housed in
prefabricated concrete blocks positioned on top of the SOP and removed after the stress has been released from
the stitching tendons. A resin or mortar is inserted between these blocks and the SOP in order to guarantee the
correct transmission of forces between these elements.
Some contractors also use bars to provide the temporary prestressing. However, this solution is not to be
recommended because any error in the positioning of the prestressing ducts could result in parasitic flexions in
the bars or could even make it impossible to insert the bars.
If the pier head unit is big enough to accommodate the bearings, blocks, stitching tendons and jacks
simultaneously, the most economical stabilization system consists of temporary prestressing and hooped
concrete blocks placed directly on the pier head (Fig. 6.19).
During construction, the cantilevers rest on the concrete blocks and the bearings are in place but not in contact
with the SOP.
After the closing segment is in place, the structure can be placed on the permanent bearings. This consists of:
Once these operations have been carried out, the blocks are no longer in contact with the SOP and may be
removed by a crane or other equipment (Fig. 6.21). In this way, the support reaction of the bridge deck is
gradually transferred from the stabilizing blocks onto the permanent bearings.
If the pier head units are too small to accommodate jacks and blocks side by side, the cantilevers are constructed
on concrete blocks placed on sand boxes consisting of a removable metal shell filled with graded sand (Fig.
6.20). Once the closing segment is in place, the gap between the underside of the SOP and the top of the
bearings is caulked as before; finally, the sand is blown out of the boxes (Fig. 6.21). Thus, vertical forces are
progressively and without jack transferred from stabilizing blocs to permanent bearings.
A large variety of sand boxes are available. On the simplest projects, they are rectangular and four boxes are
used per pier. On more complex projects, the sand boxes are proper cylindrical pot bearings and up to a dozen
may be used per pier. Whatever their type, these boxes must be dimensioned and designed to be undeformable.
If not, this could lead to an uneven distribution of the support reactions between the sand boxes, thus resulting in
structural and/or geometric disorders.
It should also be noted that the geometry of the cantilevers has to be perfect with this system, because as a sand
box can only be emptied, it cannot be used to raise the bridge in case of problem.
6.1.7.4 - Jacks
Although this technique is rarely used, it is also possible to construct a cantilever entirely on jacks. This
technique has the benefit of using the same system to perform both jacking and blocking functions, so that
smaller pier heads can be used. For this to be possible, the jacks are immobilized during the construction of the
cantilevers. They must therefore be equipped with lock nuts.
When the structure is positioned quite low above the natural ground and if the pier head unit is too small to
accommodate blocks, e.g. because it is an “exact” match for an older design, it is possible to stabilize the
cantilevers using temporary pilings placed either side of the piers (Fig. 6.22). At the bottom, these pilings,
which are usually metal tubes filled with concrete, are attached on top of the foundation bulkhead; at the top,
they are attached underneath the lower slab of the segments on piers or of the first standard segments.
For the second Saint-André de Cubzac viaduct, and still because of excessively small pier head units, composite
systems with blocks and cable stays were used tostabilize the cantilevers [JAE00].
In the interests of thoroughness, we should also mention the second Gennevilliers viaduct over the River Seine for
the A15 highway, which was equipped with self-leveling pot bearings injected with silicone rubber [CHA 94].
In order to allow for the rapid stressing of cantilever tendons, contractors sometimes prefabricate the concrete
which surrounds the anchor plates for these tendons.
As the cantilever tendons on older structures were often anchored quite low down, as their alignment was
designed to reduce shear force, these elements were situated in the webs of the box girder and were rectangular
in shape.
Today, rectangular blocks are still used when several tendons need to be anchored in close proximity to each
other. However, for single tendons, more and more contractors are using prefabricated cylindrical blocks whose
only reinforcements are helical hoops with jointed coils which also form the external formwork of the
prefabricated block (Fig. 6.23 and 6.24).
It is imperative for the weight of the form travelers to be considered in the calculations for longitudinal flexion,
as this increases the forces on the structure, particularly during the construction of the cantilevers.
The form travelers may also influence the positioning of the cantilever tendons and continuity tendons, as their
operation relies on prestressing bars which cross the slabs close to the webs where the internal prestressing
tendons are situated. During the design stage for pretressed concrete bridges built by the cantilever method
using reused form travelers, it is not possible to choose the position of these bars. This must be accounted for in
the design of the cantilever tendons.
It is also important to consider the forces caused by the form travelers when analyzing tranverse flexion. These
forces usually lead to the localized strengthening of the reinforcements in the upper slab and in the top part of
the webs (Fig. 6.25).
Réaction de l'appui support de la
poutre supérieure
Fig. 6.25 – Example of localized forces exerted by the form traveler on the box girder in the construction phase
In conclusion, it is essential for the organization and methods department and the engineering firm to work very
closely together during the construction surveys for a structure built by the cantilever method.
However, specific difficulties may raise or lower this threshold. Thus, a very short contractual completion time
or difficult climatic conditions may increase the appeal of prefabrication. On the other hand, a lack of space
close to the site or difficult access conditions may mean that there is no alternative to the in-situ construction of
reasonably long structures.
French bridges built recently using this technique include the Ile de Ré bridge, the Saint-André viaduct for the
A43 highway in Maurienne, the Rogerville viaduct on the A29 [JAC 98], the second A20 viaduct over the River
Dordogne at Saint-André de Cubzac [JAE 00], and finally, the Avignon viaducts for the TGV Méditerranée
high-speed rail line.
The prefabrication plant is set up on a site of approximately 2 hectares in area. This is usually located next to the
site, but it may also be situated several kilometers away. It can be broken down into two major areas: the first is
used for the construction of the segments and the second is reserved for their storage (Fig. 6.26).
Prefabrication units have been preferred for the construction of segments for the past ten years or so. Thanks to
significant improvements in geometrical accuracy, this method has definitively taken over from the costlier long
bench method with an ogee mold (Fig. 6.27) which also requires more space.
A prefabrication unit is a construction area the length of two to three standard segments, in which the assembly
of formwork and the casting of segments take place (Fig. 6.29 and 6.30). The lateral formwork consists of two
metal sides; longitudinally, this function is carried out by a metal plate on the crown side and a by segment n-1
on the pier side, which results in a perfect joint between the different elements (Fig. 6.28). A well designed unit
produces one standard segment per day or one segment on pier every two days. In order to maintain such high
rates of production, the units are equipped with concrete distribution booms supplied by pipework or conveyors
connected to a concrete plant on site. They also take delivery of complete reinforcing cages, which are
manufactured on jigs by specialist workshops and are equipped with all inserts (ducts, anchor plates, anchor
rails).
Fig. 6.30 – Detail of a prefabrication unit (from left to right: the matched mold
segment, external formwork, internal formwork)
Depending on the number of segments to be constructed, there may be between three and several dozen units in
total. Some of these units specialize in segments on piers and abutments while the others are reserved for
standard segments.
Segments on piers are always split into two in order to avoid the need for oversize transportation and hoisting
equipment. The half-segments on piers are manufactured side by side in specialized units; after separation, they
are transported to the units specializing in standard segments for use as matched molds for the first standard
segments of each cantilever. According to the project, the deviator segments are either built in specialized units
or in the standard segment units, with the beams being constructed in the second phase outside of the unit in
order to avoid having to modify the construction cycle for the standard segments. Specialized units are reserved
for the construction of hinged segments, if these are included in the design of the bridge deck.
Considering the errors that they have to compensate forr, the closing segments are cast-in-situ rather than
prefabricated. They are also reduced to several tens of centimeters in length.
The segments are stored on the prefabrication site for a period of one to three months. The concrete is thus
extremely strong when the segments are assembled; therefore, the prefabricated anchor blocks described
previously (see 6.1.8) can be dispensed with. In general, the segments are stored on just one level. If necessary,
and after verification of the segments, they may also be stored on two or even three levels. The segments are
first transported by large traveling gantry, initially from the prefabrication units to their storage area and then
onto a mode of transport (barge, low-bed semi-trailer, etc.).
Tyre-mounted low-bed semi-trailers are the most widely used form of transport for segments (Fig. 6.31).
Depending on the sites and the chosen assembly mode, the semi-trailer is either driven onto the portion of
bridge deck that has already been constructed or onto a track marked out on the ground in line with the structure
to be built. Loaded is usually carried out by a gantry crane at the prefabrication site and unloading is performed
by the assembly equipment (see 6.2.3 above).
The segments can also be transported by barge if the structure crosses a navigable waterway or one that can be
made navigable, e.g. by dredging [JAE 00].
Background information
Launch beams are the most widely used method for assembling prefabricated beams in successive cantilever
segments. This self-propelled handling device is supported by the bridge deck and piers and therefore is free
from almost all of the constraints relating to the crossing (Fig. 6.32). The initial cost of a launch beam is very
high, but as it is usually designed to be used on several consecutive sites, it can be paid off over a long period.
In recent years, numerous bridges have been built using this method. In France, the most notable examples
include the Sylvans and Glacières viaducts on the A40 highway [BOU 90], the Ile de Ré Bridge, the Boulonnais
and the Rogerville viaducts on the A29 highway [JAC 98] and the Saint-André bridge on the Maurienne
highway (A43). Examples in other countries include the access viaducts for the second Severn crossing in
England [COM 96], the access viaducts to the Prince Edward Island viaduct in Canada [COM 98] and numerous
urban bridges in Thailand and Hong Kong.
Standard launch beams can be broken down into around ten elements, all of which are made of metal (Fig. 6.33
and 6.34):
• Two triangular-section lattice girders of between 3 and 5 m tall and 100 to 250 m in length according to
the beams, made from sections assembled using prestressing bars
• Two bridge cranes traveling on the lattice girders and used to manoeuvre the segments.
The lattice towers and legs can be moved longitudinally along the lattice girders using to a system of capstans.
The lattice towers can also slide inside their supporting cross beams. This transverse movement is required for
the construction of curved sections, for example. The bridge cranes are equipped with spreaders which are used
to position the segments as closely as possible to their final position, both longitudinally and transversally and
for any type of geometry.
A standard launch beam weighs between 300 and 600 tonnes. The completion time for its construction is
approximately one year and it costs between 1.5 and 3 million euros.
During the assembly of the segments on piers on support Pn, the launch beam rests on its two lattice towers and
the front leg. Once both half-SOPs have been assembled, adjusted and stitched, the rear leg is removed and the
front lattice tower slides in place on top of the SOP on pile Pn. The beam can then be moved forward so that the
rear lattice tower is positioned at the end of the cantilever centred on Pn-1. The front leg is then placed at the
end of the lattice tower on the Pn+1 side, so that it does not obstruct the assembly of the standard segments. This
operation can now begin (Fig. 6.35).
Fig. 6.35 – Different stages in the sequence of operations for a launch beam
During the construction of a cantilever, the two symmetrical segments S and S' are normally assembled one
after the other. On some sites, a “symmetrical” assembly method has been used. This method, which consists of
synchronizing the release of the two S and S' segments by both carriages, reduces the stresses imposed on the
supports by eliminating non-accidental imbalances.
When the bridge deck consists of two parallel bridge decks, it is very common for the adjacent cantilevers of the
two decks Fa and Fb to be constructed simultaneously. To this end, the two lattice towers are placed on the
transverse rails straddling the central gap, which allows the launch beam to cross over from one bridge deck to
the other and thus to assemble cantilever Fa immediately after cantilever Fb. This method is also used when the
bridge deck consists of two box girders joined in the middle and when each box girder is built and assembled
on-site before the longitudinal grouting of these box girders is carried out. In general, this technique improves
the speed of the assembly and prestressing of the segments. In the case of box girders joined side by side, this
also significantly reduces the differential creep between the two box girders.
Without going into too much detail, it is worth mentioning certain launch beams that have been specially
designed or used by French companies in France or abroad.
A cable-stayed launch beam was used on the construction of the Ile de Ré Bridge. This solution helped to keep
the lattice girders to a reasonable height despite the length of the spans to be crossed (110 m). This also played
an important role in helping to reduce wind effects (Fig. 6.36).
Fig. 6.36 – The cable-stayed launch beam used on the Ile de Ré viaduct
The launch beam used for the construction of the H3 highway viaduct on the island of Oahu in the Hawaiian
archipelago in the United States, featured two independent upper beams, each of which was positioned on a
separate bridge deck. These beams were connected by a bridge crane.
This arrangement made it possible to assemble the segments on two parallel bridge decks of different levels and
separated by a very wide central gap.
If the piers are not too tall and it is possible to use heavy equipment at the foot of the bridge deck, prefabricated
segments can be assembled using cranes, which significantly reduces the initial investment costs.
If the structure crosses an expanse of water, the assembly is carried out using a 200T to 500T lattice boom crane
mounted on a barge (Fig. 6.37). If the structure crosses land, the assembly is carried out using a tracked crane
with a lattice boom of the same capacity (Fig. 6.38). Given the order of assembly of the segments, the crane
constantly moves from one end of the cantilever to the other.
Fig. 6.37 –Assembly using a river crane Fig. 6.38 – Assembly using a land-based crane
Whatever type of crane is used, a spreader is positioned between the hook of the crane and the segments. If the
transverse slope and longitudinal profile are minimal, the segment can be guided by joining frames and the
spreader can therefore be very simple. If the transverse slope or longitudinal profile is very pronounced, it is
better to offer up the segments in a position close to their final position, which requires much more complex
spreaders with transverse and/or longitudinal adjustments.
Several structures have been built using this technique in recent years. The most notable examples are the
Arcins viaduct over the River Garonne in Bordeaux [ABE 94], the second viaduct for the A10 highway over the
River Dordogne at Saint-André de Cubzac [JAE 00] and the "central" and “Expo" viaducts of the bridge over
the River Tage in Lisbon.
In addition to the launch beam and the crane, other methods exist for the assembly of prefabricated segments.
When each segment can be positioned on the ground in line with its final position, it is possible to “winch”
segments or parts of segments up to the bridge deck using lightweight metal girders. This method has been used
on at least four sites in France: on the Falaises viaduct on the A20 highway, on the Ottmarsheim bridge, where it
was used to raise whole segments and on the Sermenaz and Arrêt-Darré viaducts ([SER 90], Fig. 6.39), where it
was used to raise sections of segments.
Fig. 6.39 – Winch assembly principle (on the site of the Arrêt-Darré viaduct)
As the structure for the West Kowloon Expressway project, in Hong Kong, occupied a totally virgin site, the
segments were assembled using a gantry crane operating on both sides of the bridge deck (Fig. 6.40). The same
system was used for the Khurays Road viaducts in Riyad and, closer to home, on the A10 highway bridge over
the River Loire at Tours.
In order to release the assembly equipment as quickly as possible, the segments being assembled can be lashed
in place before the cantilever prestressing is brought into operation. This lashing generally consists of Ø36 mm
bars anchored in blocks at the top and bottom of the webs, in the web uprights or in the slabs (Fig 6.41). It is
dismantled after the stressing of the permanent tendons and the hardening of the epoxy adhesive. A normal
stress of approximately 0.2 MPa must be exerted by these bars, which guarantees the correct distribution of the
adhesive and helps it to set, while preventing any decompression at the end of the segments.
Fig. 6.41 – Anchor block for a lashing bar Fig. 6.42 – Construction of a closing segment with strip formwork
The mid-span closures between cantilevers are constructed in the traditional manner, by casting an in-situ joint
of approximately 20 centimeters in length. For such short joints, contractors often use strip formwork (Fig.
6.42).
As for in-situ casting, the extremities of end spans on the abutment side are usually built on falsework. In the
case of prefabricated segments, the corresponding segments are positioned and assembled on falsework. In order
to allow the movement necessary for perfect joints at the crowns, blocks or jacks are placed between the bottom
of the segments and the top of the falsework.
Before assembly, an epoxy adhesive is spread on the pier-side face of the segment being assembled. This
adhesive is spread by hand just before assembly to a thickness of approximately 1 mm.
As mentioned in the part of this chapter devoted to cast-in-situ segments, the choice of a stabilization system for
cantilevers is highly dependent on the size of the pier head units. Under these conditions, the stabilization
techniques for bridges made from prefabricated systems are the same as those described in section 6.1.6 above.
However, as it is difficult to correct the geometry of the cantilevers once the segments are joined, the cantilevers
are often built on supports featuring jacks equipped with lock nuts. If conventional blocks are used, caulking
must be applied between the top of the blocks and the bottom of the segments on piers in order to correct any
construction defects or errors in the assembly of these parts.
To be exhaustive, it is worth mentioning that cantilevers are sometimes stabilized by the launch beam itself.
This technique was used for the construction of the Baldwin viaduct in the USA [FUZ 94], and for the B3 South
viaduct to the north-east of Paris.
The instantaneous construction rate on a site using prefabricated segments varies significantly. At the start of the
project, no more than 3 m per day are completed. However, under normal operating conditions the speed of
construction reaches 12 m or 4 segments per day. The average speed is therefore 6 m per day.
Assembly using a crane or gantry crane creates very few longitudinal forces on the bridge deck, as the loads
applied to the cantilevers are limited to the weight of any work platforms that might be used. If the segments are
assembled using a launch beam or winch, greater forces develop in the bridge deck due to the weight of this
equipment and the segments being handled and must therefore be allowed for in the design.
For localized flexion, it is important to verify that the reinforcing of the segments is capable of taking up any
transverse moments that develop during the storage and handling of the segments, regardless of the assembly
method used. If the assembly uses a launch beam and/or requires the use of a low-bed semi-trailer, it is also
necessary to consider the localized forces created by this equipment when dimensioning the non-prestressed
reinforcements of the segments.
As for construction using cast-in-situ segments, it is important to perform a thorough analysis of the positioning
of the handling hangers and the internal cables in order to prevent any interference between these elements.
In conclusion, as for the construction of bridge decks using cast-in-situ segments, the design and construction of
bridge decks made from prefabricated segments using the cantilever method requires a very close collaboration
between the engineers of the engineering and design department and those of the organization and methods
department.
7 - On site Monitoring
This chapter covers the monitoring operations and particular precautions that need to be implemented during
the project. It places particular emphasis on topics relating to the construction of bridges by the cantilever
method. In the process, it extends its scope to the monitoring that must be performed and the particular
precautions that must be taken during the construction of all types of large engineering structures.
Monitoring prior to construction is primarily designed to evaluate the methods which are likely to be used by
the contractor and which will go some way towards defining some of the specifications of the contract.
Some of these monitoring operations will not be covered in this chapter, including the certification of
companies, the monitoring of plans and design calculations, the inspection of the SOPAQ (Schéma
organisationnel du plan d’assurance qualité - Quality Assurance Plan Organizational Scheme), and the Quality
Assurance Plan itself.
However, other monitoring operations performed prior to construction will be developed in the following sub-
chapters, including the inspection and approval of materials, the monitoring of the materials used and process
controls.
Inspections carried out during construction are designed to verify the correct application of the technical
specifications and compliance with the rules of good practice. Different aspects of these inspections will be
described in the following sub-chapters.
Post-construction inspections are designed to ascertain whether the initial objectives have been achieved. If both
of the previous types of inspections have been carried out, post-construction inspections will be a formality.
Therefore, they will receive only minimal coverage in this chapter.
Technical Document 4 entitled “Instruction technique sur la surveillance et l’entretien des ouvrages d’art :
topométrie" (Technical instructions for the monitoring and maintenance of civil engineering structures:
topographic surveying) is currently being prepared by Sétra. In Appendix 3, it provides a number of definitions
which help to specify the vocabulary to be used for clarifying the exchanges in this field.
The concepts of measuring points, reference points, frames of reference and networks are thus defined and are
clearly explained in the following section.
Measuring point
A measuring point is a point to which coordinates are attributed in order to monitor relative or absolute
movements.
• A visible point on the structure: rivet head, hole, paint mark, punch mark
• A point given by a part that has been fixed or welded to the structure: target, leveling stud
• A specific point in relation to a part that has been fixed or welded to the structure and designed to
accommodate accessories positioned by forced centring.
Reference point
A reference point is the association of a system of orthonormal axes and a point representing the origin of the
system of axes and whose movements are to be measured.
• The Ox axis following the tangent to the longitudinal axis of the bridge deck.
• The Oy axis following the normal to the longitudinal axis of the bridge deck,
Frame of reference
A frame of reference is a system of orthonormal axes (Ox, Oy, Oz) associated with a point of origin O, which is
used to identify the position from any point in space.
This conventional system, which is the working reference point established by the surveyor at the start of the
topographical operations, is used to calculate the position of the measuring points.
Network
A network is an arrangement of points determined by a set of planimetric and/or altimetric measurements. These
points are usually marked out on the site.
Two types of networks may be used in the topographical monitoring of civil engineering structures: absolute
reference networks or relative measurement networks.
Topometric operations consist of determining the positions of certain points whose movements will be
monitored, in relation to a previously defined network.
Obtaining the correct bridge deck geometry involves considering any data that might have a bearing on the
geometry of the piers and using reverse deflections to negate any drift that these data are likely to produce.
• The settlement of foundations under the action of the selfweight of the pier and the cantilever
• The effect of shrinkage and creep due to the weight of the cantilever.
The bridge deck is normally supported by bridge bearings which operate between concrete support blocks. An
inaccurate estimation of the vertical settlement of the pier may be compensated for by adjusting the thickness of
these elements. However, this is a difficult operation requiring careful preparation.
In the case of relatively small structures, it might be possible to consider the settlement of the foundations only.
This approach guarantees a successful closure of the span. While the aforementioned effects may be small for
small bridges, they increase in proportion to the height of the piers and the length of the spans. Piers of a
hundred or so meters tall, span lengths of approximately 180 m and a bridge deck of 20 m wide may result in
downward loads of approximately 20,000 tonnes and a vertical shortening of around 4 centimeters including
creep.
In the case of a rectilinear bridge deck, the construction tolerances inherent to any structure may lead to shifting
in the horizontal plane between cantilevers.
However, it is important to remember that a thermal gradient may act upon a pier shaft and cause a horizontal
shift of the pier head unit capable of affecting the measurements of movement during the construction of the
cantilevers.
In the case of curved bridge decks, it is necessary to examine the effect of the torsional moment applied to the
segment on pier by the cantilever under construction. This effect increases in proportion to the height and/or
flexibility of the pier.
Indeed, when a curved cantilever is built, the torsional moment applied to the segment on pier causes flexion in
the pier shaft which can alter the position of the pier head unit. Therefore, rather than building a perfectly
straight pier, it is necessary to anticipate this movement by building in a pre-deformation in the opposite
direction. The construction of the cantilever will have the following effects:
• The pre-deformation will be accentuated for the first segments, because the weight of these segments
remains offset in relation to the plane containing the pile axis and tangent to the curve of the horizontal
alignment of the bridge deck
• The construction of the following segments will gradually straighten out the pier until it becomes vertical,
provided that the estimate was correct.
The accuracy of the result is dependent on the awareness of the rheology of the concrete used. The concrete
must have consistent characteristics and the conditions of application must be the same throughout all stages in
the construction of the pier shaft.
Creep tests should therefore be performed on the chosen formula of concrete in order to obtain an accurate
estimate of the deformations in the structure.
Several types of measuring points can be positioned on the structure in order to help the surveyor monitor the
geometry. Each point has a specific function
Rivets
A rivet is a measuring device with a rounded head. It is used to monitor the leveling of a horizontal plane. This
inexpensive tool must be made from a hard-wearing, undeformable material designed to resist the effects of
weather and impacts on the site. A sufficient number of rivets must be used in order to monitor the elastic curve
accurately.
Medallions
A medallion is a piece of rustproof metal which is fixed to the structure. It features a rounded upper support
surface. The horizontal plane tangent to the top of the sphere supports the sight.
Medallions are used to monitor the levelling of a vertical plane and cost approximately the same as the rivets.
As for the rivets, exploitable data are only obtained if a sufficient number of medallions is used. This is
particularly important if a bi-directional phenomenon is being monitored.
Targets
Self-adhesive targets are discs marked with concentric circles which are attached to bonded metal elements or
directly onto the concrete itself, depending on the type of model used. They are used for monitoring verticality
in particular.
Targets can be used to measure both angles of orientation of a viewing axis from a known reference marker. If
repeated from three markers, this operation provides a good estimate of the position of the target point.
A retroflective target gives a third component in space: namely the distance from the observation point to the
measuring point. In certain cases, this component can increase the accuracy of the calculations, provided that
this distance is no more than approximately 100 meters. Therefore, it is important to make sure that the type of
theodolite used is compatible with the constant of the target in question, as this may vary from one model to
another.
The limitations of targets concern the mediocre accuracy of the measurements and the fact that their bonding
fails after a few years. Furthermore, on uneven sites, it can be difficult to position three markers with clear
visibility between each one.
Prisms
Prisms are a little more expensive and are positioned on a bonded base in the form of a corner plate that allows
the angle of the prism to be adjusted. A prism gives a direct measurement by defining the sighting angle and the
distance to the measuring point from a single known reference marker to which it is permanently directed.
The prism must be sited and angled in such a way as to reduce the damaging effects of dust, bad weather and
birds.
As with targets, it is important to check that the modele of theodolite used is compatible with the constant of the
prism in question, as this may vary from model to model.
A cantilever consists of several segments, which are manufactured, assembled and stressed at different ages,
using a material whose characteristics and composition may vary over time. It is important to predict the exact
extent of the deformation of the cantilever element in order to determine an adequate reverse deflection which
will be implemented in the prefabrication unit if the segments are prefabricated or in the form travelers if the
segments are cast in-situ.
When the structure is isostatic, the deformation of the cantilever is due to:
The effects of concrete creep and the delayed prestressing losses are added to the instantaneous deformation.
After the closure of the different cantilevers, when the structure becomes continuous and hyperstatic, the bridge
deck continues to deform due to the following effects:
• The removal of the temporary piers and the temporary cantilever stabilizing systems
Fig. 7.1 – Concreting curve for a single cantilever Fig. 7.2 – Concreting curve for a standard bridge built by the
cantilever method
Following this, the deformations due to concrete creep and delayed prestressing losses continue to develop.
It is therefore necessary to build in a reverse deflection in order to compensate for these different types of
deformations (Fig. 7.2).
The calculation of this reverse deflection must account for the probable values of the different applied loads:
• The density of the concrete must be realistic for the calculation of selfweight
• The coefficients of friction for the cantilever tendons in a straight line and on curves will only increase
very slightly
• The weight of the form traveler and the site equipment situated at the end of the cantilever will be
evaluated as accurately as possible.
The modulus of elasticity for concrete varies according to the age of the load and the duration of this load.
Therefore, it is always difficult to predict and control the deformations resulting from the construction of a
cantilever with accuracy. This difficult problem obviously supposes that the actual position of the segment on
pier in space is accurately known and is as close as possible to the theoretical position.
For a more detailed consideration of geometric monitoring, it is important to distinguish between cast-in-situ
segments and prefabricated segments. Indeed, a different frame of reference applies to each of these methods of
construction.
For segments which are cast in-situ using a form traveler, the frame of reference is absolute and relates to the
pier, which is also globally referenced. The construction of a new segment makes it necessary to adjust the form
traveler considering its position in space in relation to the overall geometry of the cantilever.
For segments which are cast in a prefabrication unit, the frame of reference relates exclusively to the preceding
segment. When a new segment is constructed, it is necessary to adjust the prefabrication unit in relation to the
end of the segment that is postioned as a matched mold.
Monitoring of levelling
The monitoring of the levelling of segments under construction is based on a document drawn up by the
engineering firm called the "construction pyramid". This indicates the theoretical dimensions to be obtained for
each stage in the progression of the cantilever and for each segment joint. These dimensions incorporate all of
the forces that apply to the cantilever under construction.
This pyramid is used to determine the dimensions for the adjustment of four key points on each segment joint:
both cantilevered ends and both ends of the lower slab, i.e. points P1to P4 shown on Figure 7.3.
P5 P6
P1 P4
P2 P3
Two additional points will be chosen on site in areas which seem to be the least affected by secondary
deformation, i.e. close to the webs, namely points P5 and P6 in Figure 7.3, which will be the first measurement
reference to be determined on site. The other points will be verified in accordance with this reference.
The only effect not to be considered in the engineering firm’s calculation is the deformation of the form
travelers. This phenomenon must include the form traveler’s suspension bars. The construction of the first
segment will incorporate a deformation assumption which will then be adjusted in accordance with the
measurements taken after casting. This deformation assumption may include the deflection of the form
traveler’s main girders if they were load tested during the acceptance inspection.
The adjustment of the form traveler is carried out by localization using localized reference points in relation to
the segment on pier, which is repositioned globally.
When the form traveler has been moved forward in order to build segment Vn, and before the final tightening of
its lashing onto segment Vn-1, the alignment of the formwork equipment and horizontal adjustment of the form
traveler are verified by theodolite.
The form traveler is now considered to be properly adjusted in relation to segment Vn-1 and the following
operations are carried out:
• Inspection and adjustment of the leveling and horizontal alignment of points P5 and P6
• Inspection of the levelling of the cantilevers and adjustment of points P1 and P4 if required
• Adjustment and monitoring of the leveling of points P2 and P3 defining the height of segment V
• Inspection of the spacing of points P2 and P3, i.e.of the width of the bottom slab.
Once the form traveler has been adjusted, all of the reinforcements for the segments can be installed.
Two corner irons are bolted onto the mask. These are marked with a punch and are integral with the concrete of
the upper slab close to points P5 and P6. The upper face of these corner irons is horizontal and is situated 20
mm underneath the extrados for protection. This upper face is kept clear of the concrete during casting.
Finally, an additional levelling inspection is carried out at the level of the mask.
• At the front, by altimetric adjustment in relation to the external formwork at the level of the supporting
beams (points P7 and P8).
Once the casting of the segment Vn has been carried out, it is necessary to carry out a general inspection of the
levelling of the cantilever. This operation begins as early as possible the following morning. This is the best
time of day to avoid the manifestation of parasitic forces due to temperature. A cantilever that is subjected to a
temperature gradient behaves like a highly sensitive bimetallic strip. The operation must be completed as
quickly as possible.
The corner iron is unbolted so that the mask can be removed. The corner iron becomes the measuring point for
monitoring the deformations of the cantilever.
The levelling measurement is carried out from segment Vn, which has just been concreted to the SOP, and is
repeated at each joint of the segment. The values measured are recorded on the monitoring documents and are
compared with the values given by the construction pyramid.
By analyzing the deviations that are observed (which is always a difficult operation), corrections can be made to
the adjustment of the form traveler for the construction of segment Vn+1.
The levelling measurements are completed before the form traveler is moved forward and before the
prestressing is tightened. Particular attention must be paid if heavy equipment such as a mobile crane is present
on the cantilever that has already been constructed, in order to ensure that the measurements are taken under
identical load conditions. Additional measurements can be performed in other phases if necessary.
It is important to pay great attention to the consistency of the measurements taken on site and the information
given by the construction pyramid. Any correction of the measurements must be performed after examining the
assumptions and the data used to create the construction pyramid. If differences go uncorrected on the first
cantilever, the risk of error becomes greater the closer we get to the closing segment with the cantilever already
constructed
The simultaneous monitoring of the geometry of the support is essential to ensure that the surveyor is always
capable of relating the pyramid to the absolute dimensions of the objective to be achieved.
Finally, it should be mentioned that for the construction of cast-in-situ segments using form travelers, the
sequence of operations always starts on the same side of the cantilever in general. There is no point in
accounting for this dissymmetry in the calculations if the form travelers are always adjusted on the basis of the
measurements made in the morning. On site, however, this sequence of operations could be modified by
reversing the order of casting if the levelling measurements reveal a systematic discrepancy between the two
sides of the cantilever.
During the setting up and commissioning of the prefabrication units in the prefabrication workshop or plant, a
number of precautions must be taken to facilitate the work of the surveyor and increase its reliability.
• That the longitudinal axes of the units follow the same alignment, which is called the prefabrication axis
• That the points which are used to measure the alignment and to mark out the prefabrication axis are
adequately spaced and perfectly visible from the units
• That the theodolite support frame is not exposed to hot sunshine, which reduces the size of the alignment
corrections
• That the support for the theodolite and the level are correctly in line with the prefabrication axis and that
these appliances are placed slightly above the upper level of the concrete of the segments
• That the reference point used for measuring the levelling is separate from the mask. This point could
consist of a measuring point on the structural steelwork of the unit or a graduated rule permanently
attached to a concrete post.
This is a complex topographical problem, as it involves constructing the independent segments on the ground in
such a way that they can be assembled in space in accordance with the established geometric data (Fig 7.4).
A prefabrication unit is described in Paragraph 6.2.1 and Figure 6.28 of this guide. Three parts of this unit can
be considered from the perspective of adjustments and monitoring:
• An initial mobile part: the core or internal formwork of the segment, which leans against the mask on the
one hand and the matched mold on the other; it requires no adjustment
• A fixed part, the mold or the unit itself, consiting of the mold base, the sides, wings and the mask; in
theory, this is fixed and its assembly requires great precision
• A second mobile part: the matched mold, consisting of the previous cast segment, placed on jacks used to
adjust the angle and position according to the geometric data.
The choice of adjustment points is thus of paramount importance. Their positions are identified by corner plates
bearing a punch mark or, better still, with a hemispherical indentation into which a ball bearing can roll. The
recommended configuration for these corner plates is shown in Figure 7.5:
• The adjustment points for levelling are situated in the areas least affected by deformations
• The adjustment points for alignment follow the segment’s true axis.
The measuring points may also consist of small plates capable of housing a mini-prism.
It is essential to position the points in such a way as to avoid any possibility of them being moved at elevation
when the casting is completed and to set them back slightly from the joint in order to protect them.
An additional precaution is taken for structures with a curved longitudinal profile or a variable transverse slope:
the distance from the measuring points to the joint and the axis of the segment shall be identical from one
segment to another.
The construction of a standard segment Vn requires three topographical inspections to be carried out on
segment Vn-1:
• Mapping of the levelling points and the prefabrication axis on Vn-1 in the prefabrication unit
• The surveyor must take the measurements before the removal of any of the formwork, as any impacts
could compromise the accuracy of the measurements taken
• It is advisable to check both alignment measuring points systematically before and after each operation, as
slight deformations may affect the base of the theodolite (due to strong sunshine or instability).
The segment on pier is particularly difficult to adjust. Accuracy is of the utmost importance because the
accuracy of the geometry of the cantilever to be built depends upon this adjustment.
In order to obtain a precise adjustment in space, it is possible to use angled blocks, wedges, bolts, etc. to make
fine adjustments to the position of the segment.
During the manufacture of the segment in the prefabrication unit, it is also important to provide secondary
alignment measuring points which mark out the entire width of the transverse axis of the segment (Fig. 7.6).
Fig. 7.6 – Alignment markers on the segment on pier Fig. 7.7 – Adjustment of the segment on pier at ground level
These measuring points are used to make adjustments at ground level through the observation of both axes of
the segment (Fig. 7.7).
Base curves, namely the alignment curve and the two levelling curves i.e the longitudinal profiles given by the
position of the rivets, are used to monitor and control changes in geometry.
The effects of the weight and bevahior of the concrete, prestressing and superstructures are anticipated and
compensated for via reverse deflections calculated by the engineering office. Although it is essential to
incorporate these reverse deflections, their calculation is only approximate and uncertainties remain with regard
to the accuracy of the geometry.
In order to track the changes in the actual geometry of the cantilever, simultaneous digital and visual inspections
are carried out in the form of graphs, base curves and the monitoring of lengths. These inspections obviously
incorporate the adjustment dimensions that result from the measurement of the existing segments and are
applied to the next segments to be manufactured.
The monitoring may reveal a systematic lateral drift if the stressing of the cantilever tendons always starts from
the same web. To counteract this, the order in which the cantilever tendons are stressed can be alternated.
It is possible that a mistake in the prefabrication might be overlooked on the prefabrication site, thus leading to a
fault in the geometry of the cantilever during the assembly process.
In the event of a major fault, the solution might be to disconnect one or more segments and carefully place
wedges in the joints with the segments securely lashed together. The remaining spaces between the joints must
be caulked before the segments are prestressed, taking care not to create obstructions in the sheaths that pass
through the modified joints.
This illustrates the importance of ensuring the accuracy of the geometry for prefabricated segments.
Comparison of deformations
For the construction of both cast-in-situ and prefabricated segments, it is necessary to analyze each phase in the
construction of the cantilever and to determine the deformation curve for each cantilever element, phase-by-
phase.
The line 1-2-3-4-5 represents the envelope of the different deformations, or the trajectory followed in space by
the end of the cantilever at each phase of construction.
By modifying the angular positions of the segments in small angles of α1, α2, etc., the cantilever may be
constructed in such a way that once completed, it has a satisfactory longitudinal profile, as shown in Figure 7.9
for the example in question. In each section, the modified profile will effectively compensate for the future
deformation.
It is interesting to compare the relative importance of the deformations and reverse deflections affecting
prefabricated and cast-in-situ segments. Figure 7.10 below shows these relative values for a structure designed
according to these two methods.
The design assumptions given in this figure show that in the majority of cases, the difference between the
methods will be greater if a cycle of less than one week is used for the in-situ casting of the segment and if the
prefabricated segments are stored for more than two weeks.
Whatever the circumstances, the deformations affecting a cast-in-situ cantilever will normally be two to three
times greater than for an equivalent prefabricated cantilever.
Once completed, the geometry of the cantilever must be inspected; this inspection must be carried out as early
as possible in the morning. This involves plotting curves corresponding to all of the measuring points in order to
obtain a geometrical representation of the area obtained.
The advantage for a cast-in situ cantilever is that corrections are made after each casting. Corrections are
therefore less likely to be needed when the cantilever is completed.
If the entire cantilever is incorrectly aligned, it is possible to improve its geometry to a certain extent by using
hydraulic jacks to alter the position of the segment on pier after the stitching tendons have been slackened off, if
the cantilever is simply supported on the pier. This may require the modification of the adjustment pyramid for
the adjacent cantilever if it has not yet been constructed. If the errors are significant, the general longitudinal
profile will have to be rectified.
If the cantilever is embedded on its pier, the misalignment can only be compensated for over the length of the
closing segment. The lashing of the last cantilever segment to the opposite cantilever, or the loading of the
higher cantilever may partly rectify this misalignment. However, such a manoeuvre is ill-advised, as it has the
disadvantage of modifying the stress state that was designed for the structure.
If the curves corresponding to all of the measuring points reveal localized irregularities, the following actions
may be considered once the whole structure is completed and continuous:
• It may be possible to plane off the humps, provided that a sufficient thickness of concrete remains over
the reinforcements
• If hollows exist, they must first be outlined by a trench of at least 10 mm; they can then be filled with
resin. After the application of the waterproofing, a first layer of asphalt will be applied and then planed in
order to modify the profile, supposing that the profile has been accurately determined in advance and
allows for thermal effects, for example. A second layer will then be applied. The disadvantage of such a
process is that it limits the thickness of any new layers of asphalt that will be added to the pavement at a
later date
• An extra layer of asphalt may be sufficient to level out the irregularities, but this technique also limits the
thickness of any new layers of asphalt that will be added to the pavement at a later date.
For 15 to 25 years after the bridge is commissioned, creep continues to affect the structure. After this time, the
evolution of delayed deformation is normally no longer significant. Therefore, in the first part of the life span of
the structure, deformations continue to affect the bridge deck. For the majority of structures, this is illustrated by
a lowering of the reference axis, the extent of which varies according to the sections in question.
If the theoretical longitudinal profile were to be obtained at the start of the bridge’s service life, this would lead
to a gradual decrease in user comfort over the years, corresponding to the development of creep within the
structure.
On the other hand, a policy of aiming to achieve the theoretical profile in the long term would result in a
structure that might be uncomfortable at the start of its service life, but this would improve with age.
Therefore, a compromise can be sought: the target profile is considered to be midway between the profile when
the bridge is commissioned and the long-term profile. The comfort of the structure can be optimized by
adjusting the thickness of the surfacing. This may be adapted throughout the decades in which the structure is in
use.
It is essential that the chosen profile and the profile that is actually obtained are clearly defined in an
appropriately referenced document. Both of these elements must form part of the as-built file and shall be
included in the zero-point file for the structure.
For non-standard structures, these tests shall involve the systematic testing of all of the characteristic sections of
the structure, i.e. at least the sections on supports and the sections of greatest flexion on the span.
If the structure consists of a large number of almost identical spans, the testing of bearing sections can be
limited to just a few spans. However, it is important to carry out a load test on the middle of each span.
Although load tests involve no more than a simple observation, a number of special precautions must be taken.
When test trucks are used, it is important to start by loading the supports. The corresponding topographical
measurements are recorded for information purposes. A zero-point measurement is then taken which is used to
accurately determine the height differences between the supports and the middle of spans.
For box girder bridge decks, it may be beneficial to perform precise levelling measurements from inside the box
girder as this provides good measuring conditions and there is no interference from the trucks.
Before performing the measurements under load, it is necessary to wait for the structure to stabilize. This period
can be estimated at 10 minutes after the trucks have been positioned. In any event, the measurements cannot be
taken until the trucks’ engines have stopped.
The measurements are taken from points marked by studs or rivets with rounded heads which have been
carefully positioned and provide a single point of contact with the base of the levelling rod. Laser sightings may
also be performed.
The precise analysis of the results requires an adequate knowledge of the unladen thermal behavior of the
structure is established, which also allows the thermal effects to be dissociated from the combined effects of the
test loads.
The deflection values obtained during the tests are considered to be satisfactory when the measurements taken
coincide with the authorized range for the values calculated (1.1 times the probable values / 0.8 times the
probable values), allowing for the uncertainty of the measurement. This range, which conforms to the value
recommended by the "Guide des épreuves des ouvrages routiers" (Guide to Testing for Road Structures)
currently being prepared by Sétra, corresponds to a design-based approach that is more accurate than the current
methods.
The design assumptions must not be too conservative. Instead, they should be as realistic as possible as physical
quantities will be measured. In particular, it is important to account for:
• The law of the actual behavior of the materials derived from the testing of test samples
• The cracking of parts operating as reinforced concrete and the reduction of torsional inertia due to the
cracking
• The probable prestressing value (using the results of the measurements of transmission factors) for
partially prestressed structures
• The actual geometry of the structure, if on-site incidents have led to modifications.
If the deflection values are unsatisfactory, the results must be examined with a critical eye in order to find an
explanation for the anomalies: non-linearity of the behavior, abnormal changes in the deflections measured for a
non-standard section, etc. A new calculation must establish a range of theoretical values to be monitored on the
structure, based on realistic high and low assumptions made for the significant physical values.
In all cases, after performing a global analysis, the engineering office draws up a summary report. The Owner
decides whether or not the deflections are satisfactory according to the Construction Manager’s
recommendations.
Article 42 of this fascicule defines the role of the Chargé des Ouvrages Provisoires (Head of Temporary
Structures – COP).
It is important to emphasize that the COP cannot, under any circumstances, replace an external inspection
agency approved by the French Ministère du Travail (Ministry of Labour), either at the design stage or during
construction on site. This important point should be clearly explained in the STC (Special Technical Clauses).
The different phases in the inspection of a form traveler, from its design through to its use, are sequenced in the
following way:
• External inspection of the design calculations for the dimensioning of the form traveler focusing
particularly on the load-bearing elements.
• External inspection of the supporting beams using load testing to examine their elastic behavior and
evaluate their remanent deformations, to examine the welds after loading and to measure and monitor the
deflections.
These inspections are carried out by an organization approved by the Ministry of Labor such as french APAVE,
VERITAS, SOCOTEC, etc.
• External inspection by the Construction Manager who verifies that all documents guaranteeing the
traceability of the different inspections are available in accordance with the company’s Quality system
• Manufacturer’s inspection of the equipment in order to verify the conformity of the different
manufacturing stages
• External inspection of the conformity of the assembly of the form traveler on the segment on pier, carried
out by an approved organization upon completion of the assembly and before casting.
It should be emphasized that an inspection by an approved organization involves much more than a simple
visual inspection of the apparent condition of the equipment. This inspection must produce a general report,
confirming that all of the inspections required for the approval of the equipment have been performed and
guaranteeing that the construction is consistent with the design. It must be rounded off by a definitive
acceptance report attesting to the conformity of the equipment i.e. its fitness for use.
• Inspection by the COP of the conformity of the assembly of the equipment on the segment on pier,
performed upon completion of the assembly and before casting
• Inspection by the COP of the validity of the procedure used to move the form traveler forward. This
procedure will also be internally monitored on a systematic basis every time the equipment is moved
forward.
Before the first time the form traveler is properly used, it is essential to define the maximum number of times
the high-tensile steel bars forming the hangers can be used. This number shall be determined prior to the start of
work on site (see paragraph 7.5).
Finally, although this concerns the use to which the equipment is put rather than the form traveler itself, it is
important to mention that the contractor shall perform an internal inspection of the adjustment of the equipment
after it has been moved forward and before the reinforcements are installed.
This does not refer to an assembly carried out by the manufacturer of the equipment in the factory, but to a
“test” assembly that is normally carried out on site, in order to test the supporting beams, which are the main
structural components.
These beams are assembled on a flat surface, in opposition with the insertion of jacks. The resulting deflections
in these elements are verified under loads which increase progressively until the nominal load corresponding to
the forces encountered when the equipment is in service is reached.
7.3.3 - Centering
Chapter IV of fascicule 65A of the french CCTG covers temporary structures, with centering specifically
described in Article 45.
The testing of the bearing capacity of the soil for centering must be covered in the company’s QAP.
It is essential to verify the soil that will support the centering. To this end, it is possible to perform a static plate
load test defined by the standard NF P 94-117-1 of April 2000. This involves determining a value for the
modulus of the soil by subjecting it to the action of a plate whose diameter and stiffness are normalized
according to a standardized procedure, and then by measuring how far it sinks down.
Plate load testing provides a model, but the design verifications for centering are expressed in the form of
pressure exerted on the soil. For typical cases concerning 1 m x 1 m sole plates, with compaction limited to 3
mm and for soils with no underlying soft layers, the inspection of bearing capacity may be performed while
assuming that the value of the modulus at the plate Ev2 is 350 times greater than the permissible soil pressure.
In the case of vertical types of centering, it is important to be particularly attentive to the risk of differential
compaction due to the presence of a large number of supports and to the effects of successive compactions on
the geometry and stresses.
The inspection of the equipment used in the centering must be covered in the company’s QAP.
It is important to highlight the dangers that could be caused by any laxity with regard to the inspection of the
equipment in use. Any makeshift repairs could soon lead to a catastrophe. Therefore, the COP must certify that
all of the elements used in the centering are fully functional.
When inspecting the centering, two factors must be considered: the wear of the equipment and the extent of any
corrosion.
The wear of the equipment relates to its use on other sites. Fascicule 65A (Article 4 of Appendix B, in addition
to Article 44) uses a coefficient α in order to reduce the bearing capacity of the equipment. The value of this
coefficient can be as low as 0.75 for equipment with more than 10 consecutive uses.
In the same way, the corrosion of the equipment due to its different uses and periods of storage is determined in
the calculations using a reduction factor β equal to:
Corrosion condition β
Absence of corrosion 1
Slight corrosion (presence of oxide modifying 0.95
the color of the element)
Notable corrosion (small, thin particles of oxide) 0.85
Major corrosion: the element cannot be used
The inspection of the centering erection must be covered in the coontractor’s QAP.
The inspections must target the areas of greatest risk in the centering structures. Therefore, the following areas
and inspections must be covered:
• Verify that the manufacturer’s recommended runout ranges for the jacks are not exceeded
• Check that drainage has been installed on the platform in order to channel the runoff
• Make sure that improvised extensions and wedges are not used.
• Makes sure that the horizontal forces are correctly taken up.
• Verify that the structural beams or girders are correctly centred in the forks
• Make sure that any risk of accidental relative movement is avoided above the metal-to-metal contacts.
It is important to inspect any deformations of the centering throughout the entire casting phase and to monitor
the compaction of the supporting soils. A simple way to monitor this compaction consists of attaching vertical
bars under the centering which meet a fixed independent marker at ground level.
Article 23 of fascicule 65A describes the inspection procedures for the constituents. The following additional
points should also be noted.
The mixing water must conform to the standard P 18-303 of August 1999 which prescribes appearance tests,
chemical tests and defines the testing methods, the frequency of these tests and how to evaluate the conformity
of the water being tested.
Drinking water usually conforms to the standard. However, under specific climatic conditions, particularly in
tropical regions, drinking water may not conform to the requirements of the standard.
The acceptance inspection involving the rapid identification test defined by the standard P 15-466 of August
1983 is used by the contractor to verify the conformity of the cement at every delivery. Precautionary samples
are thus taken.
External monitoring tests in the framework of the standard P 15-300 of December 1981 enable to contractor to
confirm this conformity. For example, these tests may involve the following operations:
• Measurement of anhydride sulfurique SO3 content, or Na20 equivalent, or shrinkage test for cements
exposed to the action of deicing salts
• Measurement of hydration heat, tricalcium aluminate C3A content, or shrinkage test if these
characteristics are significant, etc.
External inspection tests are carried out by the Construction Checker and its laboratory.
Internal inspections must be carried out at two levels: by the producer and by the contractor. Their main
elements are:
The contractor’s external inspection consists of an acceptance inspection and possibly spot checks
corresponding to tests laid down in the standard P 18-540 of October 1997. Inspections of storage conditions for
the aggregates and additives may be added to these.
Monitoring the alkali reactivity potential of aggregates is a complex task which is covered in detail in the
“Recommandations pour la prévention des désordres dus à l’alcali-réaction" (Recommendations for the
Prevention of Problems Relating to Alkali Reactivity” published by the LCPC (Central Public Works Research
Laboratory) and in the appended document "Guide pour l’élaboration du dossier carrière" (Guide to the Creation
of the Quarry File).
Furthermore, Sétra’s "Guide pour la rédaction des pièces écrites des marchés" (Guide to the Drafting of Written
Documents for Contracts) concerning the "Prevention of Problems Relating to Alkali Reactivity" lists the
clauses to be inserted into the written documents for the DCE (Document de consultation des entreprises)
[Contactor Tender Document] and the contracts.
Considering these two documents, major structures are usually placed in category C. As a consequence, only
NR (non-reactive) or PRP (potentially reactive to pessium effect) aggregates shall be used in their construction.
Presentation
The deterioration of concrete due to sulfates has been known about since the beginning of the 20th century. It
may have internal or external origins.
If it has external origins, it is caused by industrial emissions, the presence of sea water or the action of
constituents of the soil in contact with the concrete (this applies to gypsum, for example). This is a known effect
and the recommendations of the standard NFP 18-011 of June 1992 help to control it via the choice of cements
and the concrete formulas.
If the problem has internal origins, it bring sulfates in the cement into play. These consituents are required for
slowing down the setting of the concrete. As the problem appeared relatively recently, less is known about it.
Indeed, its existence was only reported in 1986, concerning problems in prefabricated parts which look similar
to those caused by alkali reactivity, but which are, in fact, a different type of pathology.
This sulfate reaction of endogenous origin, which modifies the hydration reactions of concrete, has been
observed in many countries, although France has only recently started to pay serious attention to it. It is true that
it remains a limited phenomenon, as it only concerns around 10 structures in France at present. However, as
certain application conditions and certain current trends appear to be favorable to its appearance, it wouild
appear to be important to summarize the current levels of knowledge about this problem ([DIV 98] and [DIV
00]).
Parameters
While the alkali reactivity of concrete is governed by the three main parameters of moisture, alkali content and
reactive silica content, ettringite formation in concrete seems to be a more complex phenomenon.
Moisture is essential to the process. Parts of the structure which are subjected to alternate wetting and drying,
such as those exposed to differences in water level, are all the more vulnerable.
Temperature increases are equally important. Different authors suggest different upper limits, and their
recommendations relate more to a precautionary approach than to objective studies. However, this temperasture
range does depend on the type of cement used. A low sulfate and alkali content allows for a higher temperature
limit.
The composition of the cement is important in terms of the contents of three of its constituents: tricalcium
aluminate, sulfates and alkalis.
The type of aggregates must finally be mentioned. Indeed, with a limestone aggregate, the cement mixture has
better adhesive properties, which seems to prevent interstitial dissolution.
It is noticed that there is a greater number of parameters than for alkali reactivity. This indicates that it is a more
complex, though less frequent phenomenon.
• Construction systematically carried out during the summer, a period in which the temperature of the
concrete is higher
This demonstrates the importance of choosing the correct type of cement. Indeed, the clinkers in modern
cements are ground increasingly finely, rendering the mixture particularly volatile and subject to large increases
in temperature.
This risk seems to increase for the construction of bigger parts; in this case, particular care should be taken to
choose less exothermic cements.
There are certain statutory texts which cover this problem at least partially:
• Standard ENV 13 670-1 of September 1999 (construction of concrete structures). Paragraphe 8.5 "Cure et
protection des bétons coulés" (Curing and Protection of Cast Concrete) limits the temperature in large
parts to 65°C
• The European pre-standard Pr EN 13 369 of 1999, which requires testing and recommends very low
temperature limits.
In this respect, France is far behind many other industrialized nations. Based on the current state of knowledge,
it would seem to be advisable to check the moisture levels of the environment; in a dry environment, the risks
are obviously very small, but in a wet environment every precaution should be taken to ensure that the
temperature of the concrete does not exceed 65 to 70° C and to opt for cement with a low alkali content. Indeed
it would not be reasonable to allow concrete temperatures to reach 80 or 90° C as this could risk reducing the
life span of our structures.
The suitability test is used to verify the likelihood that the nominal formula of the concrete and its
implementation conditons satisfy the requirements of the contract in terms of its strength and the application
conditions. It is particularly useful for verifying the concrete resistance to frost and the effects of deicing salts,
where necessary. Article 77.1 of fascicule 65A provides information about the nature of this test.
The control test is used to verify the conformity of a batch of concrete. The control procedure is detailed in
Article 77.2 of fascicule 65A.
The aim of the information test is to verify that, under actual hardening conditions, especially with regard to
ambient temperatures, the strength achieved at an early age j, corresponding to a very precise phase of
construction, is above a predetermined value fcj .
This value fcj is establishjed after analysis in order to make sure that the strength of the concrete us compatible
with the construction procedures set out in the QAP, particularly in the casting program or prestressing program.
• Removal of formwork from lateral overhangs on the bridge deck cross section
• Stressing of certain tendons (generally cantilever tendons): in this case, the tensile strength value ftj is just
as important as fcj
The information test may also have other aims, e.g. to verify that the compactness of the concrete, a genuine
guarantee of durability, conforms to the expected values.
Additional tests are normally carried out as of the 7th day in order to make sure that the required level of strength
at is likely to be obtained at 28 days.
A third type of information test may be performed in order to obtain information about characteristics that are
not specified in the contract such as the modulus of elasticity, tensile strength (if this was not evaluated in the
main information test), long-term strength, creep effects, etc. In this case, these tests could be considered to be
control tests.
The test samples used fore the information tests shall be obtained and conserved in accordance with the
provisions of the standard P18-405, and of articles 1.5 and 6.3 of the P18-504 documentation booklet.
The concrete shall be cured in accordance with the recommendations of Article 74.6 of fascicule 65A.
7.4.3 - Maturometry
Maturometry is based on the existence of a relationship between the quantity of heat released by concrete when
setting and its mechanical properties.
If the same type of concrete is subjected to different thermal conditions but releases the same amount of heat
since the start of the manufacturing process, it will have the same mechanical strength.
In physical terms, this is shown by the fact that the hydration levels of the concrete will be identical.
Arrhenius’ Law is used to express the changes in the strength of concrete according to a temporal parameter: the
concept of equivalent age, which is independent of temperature. The concrete is characterized in an instrinsic
manner using a “reference curve”.
The reference curve is established by measuring the strength of standardized test samples stored at 20°C on
precise dates. The thermal monitoring of the concrete in these test samples is used to calculate an equivalent age
of this concrete at the desired reference temperature on each of the test dates at which the strength is tested until
breaking.
The apparent activation energy of the concrete must be known for this last operation. This depends on the type
of cement used and is adjusted according to the temperature.
In addition, thermistors linked to a central readout station are implanted in the concrete of the most recently cast
part of the structure and the temperature is recorded at regular intervals.
• Transform the actual age of the concrete into an equivalent age (time required for the concrete to develop the
same degree of hydration under isothermic conditions at 20° C)
• Read off the strength value corresponding to this equivalent age on the reference curve for the concrete.
This evaluation can be performed directly by the maturometer, which shows the level of strength obtained in the
concrete at the different positions where the thermistors have been implanted.
In practice, the temperature histories of the test samples used for the information tests are very different to those
of the concrete that forms part of the structure. Therefore, there is a risk that the strength measurements obtained
for these samples may not be representative of the actual situation.
Furthermore, the validity of the laboratory compression test is affected by the method used to remove the
samples from their container.
This illustrates the advantages of maturometry, because this process is not affected by different temperature
histories and only uses the total quantity of heat. It also shows the advantage to measure the maximum
temperature obtained in the middle of the concrete.
The significant reduction in the number of test samples required is also an advantage of this process, although it
is essential to use a sufficient number of samples to guarantee the validity of the measurements. For every five
findings by maturometry, one test sample shall be verified using a conventional information test.
The method requires the use of an activation energy value that corresponds to the type of cement, to any
additives used (e.g. extra fillers), and to the external ambient temperature. This activation energy will then be
confirmed or adjusted by referring to the strength/equivalent age curves obtained from the analysis of test
samples.
These tests are performed on samples stored at different temperatures, e.g. externally, in the laboratory, in an
isothermic box kept in the laboratory, etc.
Calibration may be quite a lengthy process; it will therefore be necessary to allow a sufficient period of time for
this process starting from when the concrete formula has been specified (3 to 4 months may be required). It
should also be noted that the maturometer must be recalibrated at regular intervals (see manufacturer’s
instructions).
As far as the measurements themselves are concerned, the first choice to be made is to determine the critical
areas of the structure in which the evolution of strength is representative of the operation to be tested.
If the aim is to determine the age at which the concrete is strong enough to resist the removal of formwork,
instruments will be placed in the area in which the last mix of concrete was added. It is also necessary to
position thermocouples so that information can be obtained for parts of the bridge deck box girder, for example.
Remote temperature sensing elements are used to evaluate the mass effect in the webs, which helps the maturing
process, and measure heat losses in the upper slab close to the edges. These can be positioned according to the
plan shown in Figure 7.11 below, for example.
7.4.4.1 - Application
For the construction of cast-in-situ segments, the planned sequence of operations generally starts at the same
side of the cantilever. This sequence of operations can be modified by reversing the order of casting if the
levelling measurements reveal a systematic discrepancy between the two sides of the balanced cantilever.
The inspection of the application of concrete must focus on the following points:
• The release of pressure from the jacks used to adjust the matched mold for segments prefabricated in the
prefabrication unit
• The conformity of the composition of the concrete shown by the information given on the delivery slip. It
is essential that the delivery slip shows the following information: the differences between the theoretical
weight and the actual weight of the constituents expressed as a percentage, and the water content of the
aggregates so that the total quantity of water can be recalculated
• The slump test and the estimate of entrained air. The slump test is difficult to perform when the concrete
is in liquid form: the wattmetric readings of the output of the mixer motor are therefore an important
source of information and these readings must be attached to the delivery slips. The presence of this
information will be verified during the acceptance inspections
• Compliance with the casting plan for the application of the concrete (fascicule 65A, Article 75.3):
maximum time from the end of the manufacturing process to the completion of casting, casting phases,
height of drop, vibration, floating of the upper face of the lower slab for which formwork was not used
• At the end of casting: surface condition, possible use of thermal protection devices, cleaning of starter
bars, and treatment of construction joint surfaces
It is particularly important to comply with the casting plan. Figure 7.12 above shows the main precautions to be
taken.
An addtional precaution to be taken for the casting of very tall segments is to use tubes which are designed to
reduce the height from which the concrete is supplied, therefore minimizing the risk of segregation. These tubes
can be shortened as the operation progresses.
For high-quality casting, the vibration of the concrete must be carefully controlled in order to eliminate
segregation and voids. The main precautions to be taken are summarized in Figure 7.13 below. It is particularly
important to make sure that vibration is not carried out in the immediate vicinity of prestressing ducts. As a
precaution, guide channels can be used in conjunction with the vibrating needle. These consist of expanded
metal mesh cylinders which are securely attached to the reinforcements.
• Verifying that the required levels of strength have been obtained before authorizing the removal of
formwork
• Performing a general inspection of the segment, either at the extremity of the cantilever or in the reception
area for a prefabricated segment.
After the inspection of a prefabricated segment in the reception area, a specific identification number is painted
onto the concrete of the web inside the box girder on the side of the mask.
Special conditions apply to the manufacture and application of concrete if the temperature recorded on the site
falls below 5°C or rises above 25°C. In this case, special provisions must be made to produce concrete at a
temperature of approximately 15 to 20°C. Upper and lower limits of 5°C and 40°C must not be exceeded during
the manufacturing process.
These provisions are described in detail in "Procédés généraux de construction - tome 1" (General Construction
Procedures-Information Document 1) by J. Mathivat and C. Boiteau, and "Le béton hydraulique - mise en
œuvre" (Hydraulic Concrete – Application) by J.M. Geoffray [GEO 96].
The recommendations of Article 74.3 of fascicule 65A must be followed for the treatment of construction joints.
It is always essential to construct a test segment. This may be reduced to a half-test segment for economic
reasons.
This element must be manufactured under actual site conditions in order to give an accurate picture of the
problems encountered in the casting of segments.
This element must be truly representative of the difficulties that are likely to be encountered on site. Therefore
the test piece will be artificially subjected to the full range of potential problems. Therefore, this segment will
normally be at least two meters long in order to include a prestress anchor block.
• The setting behavior of the fresh concrete in lower slabs without upper formwork
• The practicality of the implementation of internal ducts, transverse single-strand tendons and reinforcing
bars, particularly in problematical areas
• It will also be verified that the physical references for the adjustment of the alignment of prestress tendons
are accurate, unambiguous and fully understood by everyone working on site.
Differences and changes in temperature over time may also be recorded. Samples may also be extracted for
subsequent testing.
A specific procedure must be developed for the construction of the test segment.
A certain number of specific precautions must be taken with regard to the manufacture and application of high-
performance concrete.
The concrete plant must be capable of handling silica fume, and staff must be properly trained.
When transported in the truck mixer, the concrete behaves like a fluid, with the associated risks of spillage.
Vigilance is therefore required.
In view of the fluidity of HPC, the consistency of the fresh concrete must be inspected on site by measuring its
spread on a flow table in accordance with the P 18-432 and NF EN 12350-5 standards. Slump test
measurements are neither appropriate nor accurate for fluid concrete.
The application of the concrete requires completely leak-tight formwork, as the slightest loss of laitance could
result in segregation. The floating and levelling of the surfaces must be carried out by teams of workers aware of
the viscous and self-adhering behavior of this type of concrete.
In the case of a structure with variable inertia, the angle of the lower slab on segments close to the piers could be
steep enough to cause the concrete to slide down the slope. Formwork must then be erected on the extrados of
the slab. It may also be beneficial to use concrete of different consistencies for the webs and slabs. Full-scale
testing is required to verify this.
The curing of HPC must also be more meticulous and more intense than for ordinary concrete. HPC is more
sensitive to the effects of drying, because as the water contained within the concrete has been used up in the
hydration process, there is practically no more free water. While this constraint improves the durability of the
concrete, it also increases the risk of cracking in areas where shrinkage could be obstructed. Therefore, it is
important pay attention to the proportion and design of the non-prestressed reinforcements, using small
diameters and reduced center distances between the bars. This is particularly important for the construction of
cast-in-situ segments using the cantilever method.
• Numbers and indices of the plans used (which must be approved plans)
• Cleanliness of the work area and flushing out of the formwork bases before installation of reinforcements
• Systematic verification that any laitance deposits on construction joint surfaces have been purged and
cleaned prior to the closure of the formwork
• Condition of the equipment: structural condition, flatness of panels, absence of distortion at the edges
which form joints, leak-tightness of different seams and foam strips, cleanliness, elimination of traces of
laitance and oxidation, and oiling of outer skin
• Tolerances of panels for unevenness and the conformity of the dimensions in relation to plans
• Hydraulic jacks positioned under the segment acting as a matched mold - straightness, squareness of
application of load and performance of lock-nuts
• Conformity of inserts and fixings in relation to the plans: positioning, dimensions, type and number.
For the construction of cast-in-situ segments, it is very important to scrupulously observe the procedures
governing the movement of formwork tools and systematically inspect the supporting and attaching elements.
In particular, systematic visual inspections of the hangers are carried out in order to check for straightness and
the absence of impact marks or welding spots.
Checks shall also be performed to ensure that bolts are easy to tighten and that they act squarely on the plates. If
there are any doubts, the hanger is be scrapped – or better still, cut into one metre long pieces and replaced.
Furthermore, the hangers will be reused no more than 30 to 40 times and they will be automatically replaced
when this limit is reached. The number of uses could be painted on the hanger after each operation in order to
monitor their use. Needless to say, the hangers must be new at the start of construction on site.
• Acceptance inspection of the reinforcement bars: existence of the approval certificate, condition of the
bars (straightness, rust, dirt,), compliance with reinforcement bar list, welds
• Inspection of implementation: position, coating and setting, solidity of binding of blocks which must be
clean and made from concrete, absence of contact between these bindings and the near wall, length of
overlapping between the reinforcement bars and the starter bars
• Inspection of stability, rigidity and strength of the entire reinforcement cage with a view to casting. The
bar chairs should not be used to improve the rigidity of excessively flexible cages. It is better to use
frames to make stiffening trusses.
It is important to pay particular attention to the hooped reinforcements required due to the application of
concentrated forces. The accuracy of the positioning of the hoops on the prestress anchorages must be carefully
inspected. The centering on the trumplate must conform to its theoretical positioning, with the minimum
deviation allowed from this position. The scale of the plans used for these areas must be large enough to allow
for the precise management of the positions and sizes of the reinforcements. Three-dimensional modeling may
be used for certain critical areas. The test segment (see 7.4.4.2) will provide important information about the
feasibility of these arrangements.
For parts whose formwork has one or two lines of symmetry but whose reinforcements are asymmetrical, it is
important to verify that the reinforcement cage is not inverted.
The inserts designed for the structural element in question will also be inspected.
7.7.1.1 - Procurement
The delivery conditions for the prestress reinforcements conform to Article 5 of fascicule 4, Titre II. The
renewal of the protection is carried out in compliance with the stipulations of Article 66.2 of the supplement to
fascicule 65A.
The delivery of all of the components of the anchorages must be protected according to the provisions of Article
92.1.2 of fascicule 65A and Article 71.2 of its supplement. These conditions must also comply with the
provisions of Article 3-5 of Circular no. 86-64 of September 4 1986 concerning the delivery conditions for parts
and the checks to be performed.
7.7.1.2 - Storage
Storage procedures are defined in Article 92.1.3 of fascicule 65A and Article 76.2 of its supplement, and also in
Articles 4.1 to 4.3 of Circular 94-34 of April 19 1994). The storage conditions for prestressing elements must be
rigorously inspected and particular attention should be paid to the following points:
• The hard steel, factory-oiled prestressing cable reels must be stored in enclosed and well-ventilated
premises. They shall be placed on battens or pallets in order to keep the rims off the floor
• Prior to use, the parts can be stored temporarily under a shelter with a removable roof or under ventilated
tarpaulins, making sure there is no contact between the tarpaulin and metal. Wood with a high tannin
content must not be interposed between the reels, as this could affect the oiling
• Anchorages must be stored under a ventilated shelter and their crates or packaging are placed on battens
or platted to avoid contact with the ground. Key bolts are kept in their original packaging until use
• Ducts are stored in bundles under ventilated tarpaulins. They are also placed on battens or pallets to avoid
contact with the ground.
The accuracy of the installation of the prestress components is dependent on the methods used on site. It is
unrealistic to demand accuracy greater than 5 mm. The calculations and construction provisions must take
account of this.
The inspection of the installation of the ducts is a complex matter. Indeed, problems regularly arise on site due
to inadequate positioning.
This applies to the internal continuity tendons which may move during casting if they are incorrectly attached. It
may also result in the spalling of the lower slab due to delamination under the parasitic radial tendon forces that
are thus generated (Fig. 7.14 and 7.15).
Fig. 7.14 – Risks related to inaccurate duct geometry Fig. 7.15 – Spalling of the lower slab/Angled view from below
These problems must be borne in mind when designing the reinforcement plans, with regard to the systems used
to fix the internal continuity tendons in place and during the construction and implementation of these systems.
A spacing of approximately 0.75 m must be allowed between the ducts supports.
These systems are designed to align the ducts perfectly in accordance with the prestressing plans. Rigid sections
of ducts can be specified around joints with a view to maintaining the continuity of this alignment.
The same precautions must be taken for the cantilever tendons close to the facing on the upper slab.
Problems due to the incorrect geometrical positioning of the ducts are also observed on the external tendons.
These problems normally concern two phenomena: the localized spalling of the concrete due to parasitic forces
resulting from badly positioned deviators, or an excessively high number of breakages of single-strand tendons
when the structure is stressed and if parasitic angular cracks have developed close to the anchorages.
Fig. 7.16 – Spalling of a deviator when the structure is stressed Fig. 7.17 – The deviator after cleaning
To prevent these problems, it is first of all important to make sure that an efficient procedure exists for adjusting
the angle of the deviator tubes. As many basic errors are still committed on sites – e.g. inverting the deviators –
it is important to carry out general inspections and to take a regular overview.
It is also important to make sure that the beams situated at the base of the deviator beams are correctly
reinforced, including their edges, because the large-diameter bars which are commonly used require large
bending radii. Figures 7.16 and 7.17 show the problems caused by an incorrect reinforcement of one of these
edges on a deviator beam. These problems could have been minimized by the addition of small-diameter non-
prestressed reinforcement bars positioned close to the facings.
Finally, deviator tubes should be designed in such a way that the pressure exerted by the tendon on the concrete
is directed into the body of the structure and stops before the facings in the coating areas. Accordingly, the
concrete formwork tubes must be bell-mouthed so that the curvature of the tendon effectively starts around 10
cm from the facings (Fig. 7.18). The reader is advised to consult the Sétra document entitled "Précontrainte
extérieure" (External Prestressing), published in February 1990.
The geometrical accuracy of the ducts is very important. Therefore, in the contract documents, it is necessary to
designate a person in charge of monitoring the geometry of the prestress ducts before and after casting.
The following inspections must be performed during the installation of the prestressing elements:
• Verification that the sleeves of the thin metal ducts are correctly tightened: the prefabricated lengths of
ducts with sleeve extensions are designed to provide a satisfactory fit at the level of the facing
• Verification that the alignment of the ducts and their attachments conforms to the plan (Fig. 7.19)
• Verification that the ducts are in good condition and that there are no significant distorsions or out-of-
roundness
• Accurate inspections of the alignment of the ducts, particularly in the areas of deviation close to the
anchor block attachments (Fig. 7.20).
In general, this inspection must be carried out according to unambiguous physical references which are fully
understood by everyone working on the site. It is assumed that the plans show dimensions relating to existing
physical objects or lines marked out on site.
In areas of large deviations (emergence of tendon from anchor block, deviation area close to an anchorage, etc.),
in which it is better to use rigid tubes rather than thin steel ducts, it is possible to mark out the outline of the
curvature of the duct by making a light saw mark on the end sections of tube. This tip can also be applied to the
deviator tubes for the external prestressing ducts.
When completed, the installation of the ducts and the anchorages must be verified by a competent surveyor who
must check the following points:
• That stiffening devices are used to ensure a continuous alignment of the ducts around the joints, without
sudden changes of angle. These stiffening solutions may be used for the ducts throughout the entire length
of the segment to be cast; the angles at which the ducts emerge from the joint sections are inspected for
compliance with the values shown on the plans
• Use of coupling sleeves and the adhesive sealing of the sleeving joints
• Fixing of the trumplate to the formwork: verification of orientation, rigidity of the fixing and angle of the
injection hole
• Fitting of the duct in the end of the trumplate via a coupling sleeve
• Absence of sudden changes of angle, i.e. verification of the coaxiality of the different elements and of the
adhesive sealing
• Distribution of vents and the positioning of the vent outlets in the facings.
For the external prestressing, it is necessary to use temporary supports for the ducts in order to make sure that
the tendon is in the correct position before it is stressed (Fig. 7.21). The number and spacing of the supports will
depend on the number and strength of the prestressing units. A spacing of 4 to 5 m is typically used.
Should transverse prestressing be required, it is particularly important, given the thinness of the parts, to verify
the accuracy of the duct alignment and the presence of a support system designed to maintain this alignment
(Fig. 7.22). Furthermore, as tranverse reinforcement made from small-diameter bars is likely to be significantly t
distorted during casting, it is advisable to stiffen the reinforcement cages in order to make sure that the ducts
remain in the correct position.
Fig. 7.21 – Support system for HDPE ducts for external tendons
If the prestressing passes through the webs, the type and frequency of the tendon supports should be carefully
inspected in view of the forces exerted during casting; this also applies to the ducts left empty in reserve (Fig.
7.23).
It is also important to make sure that “removable” elements can actually be removed, especially when double
ducting is used on the deviators.
Finally, before casting, it is highly advisable to verify that the ductsducts have not been blocked by any foreign
objects: bottles, cans, tools, etc. This inspection can be carried out by flushing a ball through the sheath with
compressed air.
It is essential to reject strands showing signs of pitting due to oxidation, scratches, nicks or other defects likely
to affect their mechanical strength.
A corrosion table specifying up to five levels of corrosion, of which only the fifth level was unacceptable, was
once used by certain contractors. We consider this table to be far too lax and believe that corroded
reinforcements should never be accepted.
7.7.2.4 - Threading
Strand-by-strand threading is the most commonly-used threading method for bridges constructed by the
cantilever method. During this operation, it is particularly important to make sure that:
• The strands have been sufficiently well oiled in order to reduce the friction forces in the later phases
• The distance between the pay-off reel and the cable pusher is kept to a minimum and that, over this
distance, the strand is well protected by a tube or duct
• The cable reel has been placed in the static pay-off reel in such a way that the lay of the coil being
unwound lies in the same direction as lay of the stranding, so that the strand tends to pull itself tight while
is unwinding
• The additional length required for the stressing has been allowed for before the strand is cut to length
• The strand has not been marked by the rollers on the cable pusher; this particularly applies to the last
strands to be threaded, when the pressure of the rollers tends to increase
• A thick wooden shield is securely fitted over the strand outlet in order to protect staff
• Particular attention is paid to the threading of the last two strands of the tendon, as these are always the
most difficult to thread through the duct (for long tendons, i.e. over 50 m in length, speed of threading is
preferred to force in order to prevent the jamming of the last strands on the approach to the outlet)
• After the threading of every strand of an external prestressing tendon and the positioning of the
anchorages, it is important to verify that the entire tendon can move inside the duct. This helps to position
one strand in relation to another and also helps to check that there are no blockages.
Lubrication, oxidation and cleanliness play a vital role in the correct installation of a traditional strand-jaws
anchorage.
The anchorage must be properly lubricated if it is to work correctly and the lubrication conditions must be
specified in the internal procedures recommended by specialist distribution companies. The exact type of
lubricant to be used must also be specified.
Oxidation must not be considered to be acceptable in the mechanical assembly of the anchorage.
These three parameters are vital for the correct operation of the conical wedging of the strand-jaws in the
anchorage.
In addition to the fact that successful stressing depends on the quality of casting in the anchorage area, it is also
important to verify the following points when fitting the anchor head on the tendon:
• That they are disentangled if necessary, so that there are no brakages due to crossed strands near the
anchorage
• That the conical holes in the anchor head are clean and have no rust that cannot be wiped off.
It is also important to check that the jack is aligned concentrically on the anchor head and coaxially in relation to
the tendon.
An inspection plan must be drawn up prior to the start of the stressing operations. It specifies the types of
inspections, the frequency of the inspections and identifies the tendons to be inspected.
• Monitoring the position of tendons during threading in order to detect any possibility of crossed ducts.
They may also take the form of spot checks, e.g. when measuring transmission factors, which at first are
systematically verified for each family of tendons at the start of stressing operations, and then are checked at
random.
Before the jacks are threaded, it is advisable to cut all of the strands to the same length; this shows up any
problems with the jaws and reveals any broken strands. The marking of the strands at the back of the jack is
another, albeit less effective, solution.
Finally, before the start of operations, it is necessary to verify that engineering office has allowed for the
additional lengths of cable which are gripped by the jacks in their calculations of the extension of the tendons.
• Verify that the internal friction on the jacks and their anchorages has been correctly accounted for in the
interpretation of the pressure readings on the manometer
• Do not forget to correct the pressure reading in accordance with the calibration chart for the pump
manometer: the pressure is used as the reference measurement and not the extension, which is indicative
• Check that the correction for the compaction of the jaws has been properly allowed for in the
measurement of the extension on the piston of the jack.
Coefficients of friction are monitored by measuring the transmission factor. The principle behind this
measurement is described in detail in Article 95.4.2 of fascicule 65A and Appendix I of its supplement.
Before carrying out this measurement, it is essential to make sure that the jacks have been properly tared (using
a calibration chart). It is also important to verify the calibration chart for the manometers on the pumps (test
date).
During the construction of a cantilever with cast-in-situ segments, it is essential to verify that the value fcmin
which is mentioned on the french CIP (Commission Interministérielle de la Précontrainte-Interministry
Prestressing Committee] accreditation and in the construction design calculations has been achieved by the
concrete before stressing is carried out. The use of a sclerometer to perform this verification is strictly
prohibited.
The cantilever tendons are sometimes only stressed after the form traveler has been moved forward. This
operation, which is designed to shorten the segment construction cycle, means that the last segment to be cast
behaves as reinforced concrete with regard to the loads exerted by the form traveler. Normally, this poses no
problems in terms of general flexion, but particular vigilance is required with regard to the localized stresses
applied to the new concrete. This operation must be described in a detailed construction procedure and the
engineering office must apply specific design calculations to it.
7.7.4.1 - Injection
The combination of these three fundamental actions produces a permanent barrier against corrosion and
guarantees the longevity of the prestressing.
• Thixotropic grout: a traditional grout to which a thixotropifying agent is added at the end of the
manufacturing process.
The main characteristic of this second type of grout is its capacity to change from a gel when stationary to a
liquid when shaken. This has two advantages: the injection conditions remain the same as for a traditional grout,
and the front wall of the grout remains almost perpendicular to the duct and does not collapse as it passes
through high points. However, this property depends on the shearing threshold of the grout for a given slope and
on the steepness of the slope for a given grout.
Numerous tests must be performed on the grout. These are specified by European standards and are referenced
in Article 92.3 of fascicule 65A. They involve:
Testing using a transparent inclined tube, using the method described in Appendix 3.1 of Circular no. 99-54 of
August 20 1999, is essential in view of the representativeness of this test and the unsuitability of the other tests
with regard to the characterization of the in-situ stability of grout.
However, grouts may be used without preliminary testing if they have been given a favorable technical
evaluation report or a favorable provisional report by the CIP, except when testing is specifically requested by
the Construction Checker, provided that the components of the grout, the equipment used for their injection and
the temperature conditions for their application comply with the the conditions described in the technical
evaluation report. If just one of the conditions is not respected, it is essential to perform a new inclined tube test
on site.
7.7.4.3 – Specific inspections and precautions during the injection of cement grout
Injection tests have shown that the appearance of pockets of air due to the collapse of the front wall of the grout
as it passes through high points can be prevented by optimizing the speed of advancement of the grout in
accordance with the alignments and the prestressing units used.
Furthermore, the phasing of the injection must be adapted to suit the alignment of the tendon in question. This
analysis must be carried out upstream of the process in order to make sure that the position of the vents is
consistent with this phasing.
Bleeder valves and vents are identified by marking or labeling according to the vent plan which must be
supplied by the contractor. During the construction of the bridge, these vents must be closed in order to prevent
water from seeping into the ducts. The bleeder valves are kept open.
Mixers and storage tanks must be protected from water penetration and prevented from drying out due to direct
sunshine.
An air compressor and a pressurized water inlet must be operational on the structure and kept ready in case of
problems during the injection process.
Pre-injection inspections
Before any injection takes place, it is compulsory to test the leak-tightness of the ducts in order to identify any
potential anomalies. This test can be carried out using compressed air or by creating a partial vacuum. This also
helps to check that the numbering of the ducts matches that of the vents. If the test shows the existence of any
connections between the ducts, the tendons concerned will be injected simultaneously.
Preparations for the injection must also take account of the weather forecast. The rheology of the grout must be
adapted to the ambient temperature and humidity.
Finally, it is important to remember to check the equipment and make sure that the necessary materials are
supplied in sufficient quantities.
During pressurized injection, the monitoring of the injection pressure is of paramount importance to the success
of the operation. The fundamental value to be considered is that the pressure in the duct must not exceed 1.5
MPa.
It is also necessary to perform systematic tests of the bleeding of the anchor caps and vents at the high points.
Fluidity and exudation tests are performed according to the recommendations of Article 95.5.l.B of fascicule
65A.
Post-injection inspections
After the injection, the different levels will be inspected in order to make sure that the ducts are properly filled.
This involves:
• A gammagraphic inspection, if allowed by the thickness of the concrete (e < 0.50 m).
Circular no. 2001-16 of February 28 2001 relative to the “Conception de la précontrainte extérieure au béton”
(The design of prestressing external concrete) describes the possible solutions used for the design of external
prestressing and mentions the risks involved in its removal. In practice, this leads to the use of protected and
sheathed single strands in a general duct injected with cement grout or ungalvanized strands in a general duct
injected with a flexible product, usually petroleum wax.
Wax
Wax is a malleable, crystallized solid material which is preferred to grease due to the absence of syneresis,
which improves its stability over time.
As wax must be injected at temperatures higher than its melting point, between 90 and 120° C, certain important
precautions must be taken.
Firstly, it is of paramount importance to consider the thermal exchanges with the adjacent materials and the
ambient temperature during the injection process. During cooling, the wax contracts significantly, to the order of
5 to 10 %, and this can lead to the creation of voids. Therefore, it is important to take special precautions such as
re-injecting the high points. However, in the case of the external prestressing, a large proportion of the shrinkage
of the wax is compensated for by the cooling of the HDPE duct, which was heated by the passage of the hot
wax.
It is absolutely essential to prevent any leakage of wax during the injections. If this happens, staff could be
burned and the surrounding concrete could be impregnated with wax, with disastrous consequences. To reduce
this risk to a minimum, it is important to only use materials which are resistant to high temperatures and to make
sure that the ducts and anchorages are perfectly leakproof by carrying out rigorous inpections and tests (As the
risks can never be entirely eliminated, it is important to ensure that everyone present is protected against the
risk of burning by the wax).
Grease
Because of its syneresis, it is prohibited to use grease for the protection of prestressing units that are not self-
shielded.
For self-shielded units such as those which are often used in transverse prestressing, the protection of
anchorages using grease must be carried out on site. The greatest care must be taken to ensure there are no leaks.
7.8.1.1 - Characteristics
The adhesive used for prefabricated segments consists of epoxy resins mixed with a hardener. Its main
properties are:
Adhesives bearing the "NF-Produits spéciaux destinés aux constructions en béton hydraulique" (French
Standard – Special products intended for hydraulic concrete structures) label in the structural adhesives
category, or products bearing an equivalent European label are highly recommended.
The term “adhesive” is not strictly accurate. In fact, results from the laboratory testing of concrete-to-concrete
bonding, structural demolitions and analyses of structural behavior show that under normal conditons on
construction sites, the joints are not actually bonded because tensile strength is not created in the joint.
• Filling the openings between joints caused by the differential shrinkage of different parts of the section of
the box-girder; these openings may reach 0.3 mm in size
• Partially correcting imperfections in joints because the adhesive has a similar compressive strength to the
concrete
• Lubricating the surfaces when the parts are brought together, minimizing the damage caused by the
inevitable minor impacts during handling operations
Before the segments are assembled and bonded, it is necessary to test the time taken for the adhesive to set, i.e.
the time between the start of the mixing of the components and the moment when the mixture no longer adheres
on contact. The following precautions must be taken when performing this test:
• The components of the test sample must be similar in quantity to the mixture that will be used on site in
practice
• Care must be taken to avoid trapping air when mixing the components of the glue
• The temperature and humidity conditions for the test must be representative of the actual conditions and
conform to the specifications.
• Ensure that if it rains, protective measures such as the sheeting of the bonding area and the creation of an
run-off barrier near the joint are implemented in order to prevent contact with rainwater run-off before and
after the bonding of the segments and until they are securely lashed together
• Verify that a sufficient amount of adhesive is applied to the joints of both segments to form a seam of
excess adhesive on the edges of the joints
• Verify that this seam has not been ground down after polymerization, except on the bridge deck extrados,
in order to facilitate the surfacing required for the application of the waterproofing layer.
It should be noted that the formation of a seam of adhesive as mentioned below simplifies inspections in the
short and long term by guaranteeing that the joint has not been been altered after the clamping of the parts.
A major bonding defect can only be repaired by an injection of resin according to a specific procedure adapted
to each case.
Resurfacing with cement mortar may make it harder to evaluate the type and extent of any defects. This
evaluation must imperatively be carried out before any repairs are made.
Minor defects such as impact damage to the concrete on the edge of a joint are better left exposed. If resurfacing
is necessary, a recess should first be created around the damaged area and an epoxy resin-based mortar should
be used for the repair.
The inspection of the general appearance of a segment concerns three criteria: shape, corresponding to the
different geometrical dimensions of the segment - texture, which is given by the formwork skin - and color,
which is governed by the concrete.
For example, color is quite difficult evaluate in isolation because it depends on how the surface reacts to the
light. In fact, the type of surface finish can attenuate differences in the color of the concrete. Color therefore
relates to texture. The color obtained also depends on the number of times the formwork is reused – which turn
depends on the resources allocated to the project.
Three factors play an important role in determining the color of the segment facings on structures built by the
cantilever method: the quality of the concrete, the formwork and vibration.
The final appearance of the segment facings should be considered when choosing the concrete formula because
the color depends on the rheology of the concrete. The amount of water used, the proportions of additives and
the temperature are the three key, interdependent factors which must be controlled. The additives and their
effects on the water and temperature are particularly important.
It is now known that changing the formula of the concrete to suit the season plays a key role in producing a
high-quality facing. Concrete for the construction of bridges built by the cantilever method is now manufactured
during several seasons. A reference formula for spring and autumn has to be changed to allow for higher
temperatures and lower rainfall in summer and is changed again in winter to account for the reversals of these
same parameters. It is particularly important to account for the variation in the water content of the components.
Only a detailed rheological study will satisfy this requirement.
Maturometry, which generalizes the evolution of the hydration parameters for concrete, helps to improve the
management of the quality of concrete. It is also a valuable indicator for the removal of formwork, as it can be
used to determine how long the formwork needs to remain on the part and this is one of the key factors in
determining the homogeneity of the facing.
This factor is particularly important for the prefabrication of segments in prefabrication units. The daily cycle
which leads to the removal of formwork in the morning, is actually quite hard to reconcile with the stoppage of
work at the weekend.
Today, the most widely used formwork is made of steel or bakelite plywood (film-faced plywood, which is less
expensive, may cause problems depending on the type of aggregates used). These materials are used primarily
for economic reasons and their characteristics are not ideal for the creation of high-quality facings.
A double formwork skin is better suited to this task. This consists of a thickness of no more than 10 mm of
ordinary plywood fixed to the standard formwork. In this case, the formation of bug holes can be prevented by
making sure that the wood fibres are aligned in the same direction as the pouring of the concrete.
The drawback to this technique relates to the time required for the assembly and the dismantling of the
formwork skin each time it is replaced, rather than the costs of the materials. Indeed, beveled vertical slats of
unfinished wood have already been used for this purpose.
Formwork skins, made from composite materials which can be reused at least three hundred times, are a new
arrival on the market. These materials are very expensive, however, and are not suitable for all shapes.
Another important contribution of the formwork skin to the creation of a high-quality facing is to dampen the
vibrations transmitted to the formwork during the vibration of the concrete, thanks to the column of air between
the formwork skin and the formwork itself.
7.8.2.3 - Vibration
A large number of defects are caused by incorrect vibration. Two pitfalls must be avoided:
• Over-vibration - meaning that part of a component has been vibrated for too long. On a constant cycle,
which is the most common situation, this means that another part of the component has not been vibrated
for long enough
• Post-vibration - involving the creation of secondary vibrations caused by the hard spots of the
reinforcements or formwork structures.
The importance of the type of formwork skin is illustrated by the fact different materials have different
capacities to absorb vibrations.
Flat vibration, e.g. of a slab, often creates intermittent vibrations in the reinforcements which act as secondary
vibrators when the concrete is tightly compacted.
To make sure that the upper section of a layer of freshly-poured concrete is sufficiently vibrated, it is necessary
to vibrate it for one to two minutes after air bubbles have ceased to emerge from the concrete.
Finally, it is important to follow a vibration plan corresponding to the shape of the component. This plan is
drawn up by a specialist or with specialist help (see paragraph 7.4.4 concerning the inspection of application).
Differences in the appearance of the facing can be reduced by the use of white cement or light-colored cement.
Clinker has a distinctive color and additives can be used to attenuate its impact. Therefore CHF-CEM III/A and
B, and CPJ-CEM Il/A and B cements produce light-colored facings.
The test segment is used to experiment with all of the aforementioned factors and eventually arrive at a
comprehensive solution for the production of high-quality facing. However, it is also necessary to anticipate
changes in the quality of the formwork skin. For example, if the skin is made from painted sheet metal, this
paint will gradually disappear, thus changing the final appearance.
As fascicule 65A does not address all of the issues relating to facings, the Construction Manager may also refer
to the Projet National Qualibé (National Concrete Quality Project) report for additional information.
The first French regulations applicable to prestressed concrete appeared on October 1 1953, (Circular no. 141
issued by the Ministère des Travaux Publics, des Transports et du Tourisme [Minsistry of Public Works,
Transport and Tourism] - a Provisional Instruction concerning the use of prestressed concrete). Essentially, it
recommended the use of fully compressed concrete (with minimum compression on one axis equal to at least
8% of the maximum compression), but it hinted at the use of partially prestressed structures.
This instruction recommended the inclusion of certain clauses in the Cahiers des prescriptions spéciales
(Special Conditions) [CPS]) relating to the composition of concrete (minimum cement batching of 400 kg/m3)
and the quality of prestressing reinforcements. It also made the use of strong sealed metal ducts compulsory for
prestressing by post-tensioning.
In 1965, Circular no.44 of August 12 1965, relating to the instruction provisoire (Provisional Instruction) for the
use of prestressed concrete (called “IPl”), replaced the 1953 Provisional Instruction. Complete prestressing
remained, but there was no lower compression limit (σmin ≥ 0). Cylinder strength at 28 days replaced cube
strength at 90 days. It should be noted that this circular was written primarly for bridges with prefabricated
girders. It incorporated the advances made since 1953, especially regarding the calculation of losses of tension
(e.g. formulae for relaxation losses).
1966 saw the publication of the Provisional Directive for the construction of prestressed concrete bridges. This
was intended to prevent accidents during the construction of bridges or on structures in use. It made changes to
the “construction” section of the IPl and insisted on:
• The use of APC (Artificial Portland Cement) 325 or CFA (Cement – Fly Ash) 400 cement, batched at 400
kg/m2 for the manufacture of concrete, in order to reduce the risks of corrosion (the use of PCS [Portland
Slag Cement] cement had to be approved by the LCPC)
• The almost total prohibition of admixtures after the collapse of a beam on the Guerville viaduct. This
accident was caused when an incorrect dose of an admixture prevented the concrete from hardening
properly; as a result, the bottom flange of the girder was crushed during prestressing
• Precautions for the storage of prestressing reinforcements on site, in order to reduce the risks of stress
corrosion
• The care to be taken over the injection of ducts and the need to allow a maximum period of 8 days
between the stressing and injection operations, again with a view to reducing the risks of stress corrosion
(only APC 325 cement was allowed for the injection grout and sealing mortar).
1971 saw the introduction of the Directives Communes relatives au Calcul des Constructions (DC71) [Common
Guidelines relating to Structural Design], which was the first document to cover the concept of limit states.
These guidelines were intended to be used as the basis for the creation of new design rules for metal, reinforced
concrete and prestressed concrete structures.
In the same year, the 1960 load regulation was replaced by Titre II of fascicule 61 of the Cahier des
Prescriptions Communes (CPC) [Common Conditions]. This regulation significantly reduced the intensity of
the distributed loads A (l) for bridges of moderate length (between 15 and 80 m) and introduced degressivity
factors according to the number of loaded lanes and the category of structure.
The Provisional Directive for the injection of ducts on prestressed concrete structures appeared on March 28
1973. This highly informative document covered the requirements for grouts (traditional and special), the
characteristics of study and suitability tests, the manufacturing conditions for grouts, the execution and
inspection of injected materials, accidents, etc. This directive led to real improvements in the quality of the
protection applied to prestress tendons.
In December 1972, Sétra published the first version of its Technical Bulletin on bridges built by the cantilever
method, called “BT7”. This document covered the history, engineering, design and construction of these
structures. Appendix I of this document featured a design example incorporating changes due to creep and
thermal gradients. Appendix II included a collection of 55 monographs on structures built between 1960 and
1972 in France and abroad.
In 1973, Circular no. 73-153 of August 13 1973 introduced Provisional Instruction no. 2 (called “IP2”) relating
to the use of prestressed concrete. This consisted of a design rule based on “limit states” methods. The IP2
introduced the use of:
• Types or classes of prestressing (from type I: no decompression of concrete, to type III: limitation of the
opening of cracks)
• Specific rules relating to end or support areas and to concentrated forces during post and pre-tensioning
• Rules to account for delayed deformations in concrete due to shrinkage, creep, etc.
During this period, private and public engineering firms were not ready to face up to the practical difficulties
relating to the application of this new regulation (complete overhaul of design programs, difficulty of applying
the range of characteristic values of the prestressing when there was a redistribution of efforts due to delayed
obstructed deformations, etc.). Therefore, the IPl, which remained valid, continued to be used except for the pre-
tensioning, the distribution of concentrated forces and for the precise calculation of delayed deformation effects.
Circular no. 74-60 of April 23 1974 made changes to the following articles of the IP1 in accordance with the
new Titre II in fascicule 4 of the CPC of March 5 1971, and March 26 1973:
• Article 10, relating to the calculation of relaxation losses in the prestressing reinforcements, established
relaxation at 3,000 hours
• The values of the coefficients of friction f and φ specified in the IP1 were used in the certificates of
approval, except for structures with numerous joints for which they were determined by the CPS (Special
Conditions).
The Direction des Routes et de la Circulation Routière (Department of Roads and Traffic) published a circular
on April 2 1975, after analyzing and determining the causes of cracking observed on a number of bridges built
by the cantilever method. This document was designed to supplement the IPl with regard to the following
points:
• Distribution of prestressing loads (concentrated forces) and the accumulation of shearing stresses with or
without transverse or vertical prestressing (stressed stirrups)
• Thermal gradients (5°C under rare combinations and 10°C under practically permanent combinations in
the sense of the BPEL 91, while taking account of the instantaneous deformation modulus of the concrete)
By introducing rules to allow for creep and the thermal gradient, this circular brought an end to the era of
second-generation bridges (see Chapter 1) and paved the way for a new generation of much better dimensioned
bridges.
8.1.4 - 1975-1982
This period saw the publication of new regulations which, on the one hand, incorporated the concept of quality
and on the other, abandoned the "allowable stresses" calculation in favor of "limit-states" calculations.
• Circular no. 79-23 of March 9 1979, which included the instruction of January 15 1979 relating to the
inspection of concrete quality (conditions for the execution and interpretation of study, suitability and
inspection tests which were not included in fascicule 65 of August 13 1969, and described in Circular no.
69-92, or in a usable form within Appendix B of the IP2)
• Circular no. 79-78 of August 16 1979 relating to the implementation of prestressing units, which
established:
– The values of the coefficients of friction f and φ (according to the radius of curvature, the
number of joints crossed and the type of tendons: smooth wires or strands)
– The moduli of elasticity of the wires (200,000 MPa) and strands (190,000 MPa)
– The measuring conditions for the transmission factors
– The choice of ducts (ducts and tubes), in addition to the diameters, radii of curvature and the
continuity of the ducts
– The limit of the initial stress to be 0.7 Frg for reinforcements with a small radius of curvature
(stressed stirrups)
– The strength of the concrete close to the anchorages and the minimum distances to the facings
of the anchor plates
– The conditions of execution for the tensioning
– The need and the implementation conditions for temporary protection and sealing
• Circular no. 79-121 of December 14 1979 concerning the reprint of the IPl, which incorporated the
modifications made by Circulars 74-60 of April 23 1974 and 77-67 of April 25 1977
• Circular no. 79-25 of March 13 1979 relating to the new Directives Communes pour le Calcul des
Constructions (D.C.C.C.79) [Common Guidelines for Structural Design]. These guidelines served as the
basis for the creation of BAEL and BPEL rules and the design rules for foundations.
A supplement to Technical Bulletin No.7 also appeared in April 1979, introducing the requirements of the
Circular of April 2 1975 and its implications concerning the quantities of materials, new design programs, the
stability of cantilevers under construction, design examples, construction advice (prefabricated segments,
measurement of transmission factors, form travelers, stressed stirrups, segregation of concrete, workability,
protection of anchorages, etc.).
This period was marked by the generalization of "limit states" design rules. The introduction of Quality
Assurance and the development of French and European standardization led to significant changes in the rules
relating to the construction of structures.
The development of “external prestressing” had a major impact on the development of prestressing procedures,
and much less of an influence on the development of prestressing reinforcements.
Significant changes were made to the design of large prestressed concrete structures, but construction
techniques remained very similar.
It should also be noted that the effects of Circular 82-50 of May 24 1982 began to felt. This involved the notions
of quality of use, the organization of quality, internal and external inspections and independent inspections, etc.
All of these notions concerning quality were applied to each of the texts relating to the construction of
structures.
In 1983, the regulations relating to the design of prestressed concrete bridges were revolutionized by the
appearance of fascicule 62 Titre l Section 11 of the french CCTG (General Technical Clauses, technical design
and calculation rules for prestressed concrete structures according to the limit states method, called the “BPEL
83”). It should be noted that the BPEL 83, the IPl and the IP2 were all applicable until December 31 1985
according to certain procedures established by decree.
• External prestressing
• The notion of verification categories for structures (Class I authorizes no traction and is mainly used for
prefabricated bridges; Class II, in which the tensile stresses are limited, is used for major bridges and large
standard bridges or those situated in harsh environments; Class III, covering “partial prestressing”, was
applied to prestressed concrete bridges built by the cantilever method, certain types of standard bridges in
reasonably benign environments (2nd and 3rd category road bridges) and for bridge slabs with transverse
prestressing
• A characteristic thermal gradient value of 12° C for verifications at service limit state
• The possibility of performing verifications with the probable prestressing Pm, instead of range
calculations using P1 and P2 (characteristic values).
• The first covered the anchoring strength of external prestress tendons in the event of overtension in order
to prevent the blockage of wedges by the cement grout
• The second dealt with the use of single and multi-strand couplers, the precautions to be taken with keyed
anchoring and problems relating to the use of “super” strands.
In February 1990, the CTOA (Centre des techniques d’ouvrages d’art - Center for Engineering Structure
Techniques), a division of Sétra, published a guide entitled "Précontrainte extérieure" (External Prestressing). It
gave additional information on subjects covered by the BPEL 83, with a particular emphasis on external
prestressing technology.
The BPEL 83 rules were replaced by the BPEL 91 rules at the start of 1992. The major modifications introduced
by this new version included:
• Extending the rules to concrete with characteristic strength of between 40 and 60 MPa
• Introducing a "θ" coefficient into the formula giving the value of the compression limit stress of concrete
at ULS, as a function of the duration of applied of loads
• Reduction of the 1983 shear limit stress which was considered to be too forgiving
• For coastal structures: increasing the depth of coating on non-prestressed reinforcements without
individual protection from 4 to 5 cm
• Appendix 3, which assigned numerical values to the coefficients of friction f and φ for tendons inside the
concrete, sheathed and protected strands and tendons outside the concrete.
It should be noted that the BAEL 83 rules were simultaneously replaced by the BAEL 91 rules.
At the end of the 1990s, the BPEL 83 was modified again, becoming the BPEL 91, revised in 1999. An
additional appendix (Appendix 14) was included in this new version, relating to concrete with a characteristic
strength of between 40 and 60 MPa.
The end of the 1990s was also marked by the appearance of two circulars relating to prestressing using post-
tensioning techniques:
• The first, dated August 20 1999, prohibited the washing of sheathed tendons with water, established a
number of new requirements for HDPE tubes and promoted the injection of external tendons with wax
• The second was published on February 28 2001 and imposed new requirements concerning the injection
of external prestress tendons (see paragraph 7.7.4.4).
The purpose of this section is to briefly outline the principal specific disorders that have been identified for these
structures and to describe the lessons that have been learnt with regard to the design of modern structures built
by the cantilever method. In the interests of relevance, we shall only cover problems with structural origins, as
problems caused by other factors (materials, use, maintenance, etc.) are not exclusive to the cantilever
construction method.
For more detailed information about problems affecting prestressed concrete structures, the reader is invited to
refer to Sub-Section 32.2 of the second part of the Instruction technique pour la surveillance et l’entretien des
ouvrages d’art (Technical Instruction for the Monitoring and Maintenance of Civil Engineering Structures),
published in 1979 and modified in 1995.
The appearance of significant deformations and/or cracks on prestressed concrete structures may be evidence of
structural disorders.
Not all of the cracks found on prestressed concrete structures are signs of defective behavior.
When analyzing the problems on a structure, it is important to consider all of the characteristics of the cracks
observed.
The opening and widening of cracks if they are active are obviously the first elements to consider. However, this
information is insufficient in itself to evaluate the condition of the structure.
Prestressed concrete structures built by the cantilever method are often only prestressed longitudinally. They
therefore behave like reinforced concrete in the transverse direction. As a result, fine longitudinal cracks may
develop and in most cases, these are evidence of normal transverse flexion behavior in reinforced concrete.
This applies to the fine cracks that can be observed in the upper slabs. It also applies to the fine cracks found in
the deviators on structures with external prestressing.
As a guide, it shall be considered that the opening of the cracks on elements behaving like reinforced concrete
must not exceed:
– 0.1 mm in the case of systematic cracking (multiple, evenly-distributed cracks), for the average width of all
of these cracks
– 0.2 mm for the average width of an individual crack
– 0.3 mm in localized cases for the width of an individual crack.
These openings are values under dead loads and were established in the framework of studies relating to the
penetration of corrosive agents into the concrete. For structures or parts of structures situated in relatively non-
corrosive environments, these values could therefore be increased.
Structures built according to the Instruction Provisoire n° 1 (Provisional Instruction no. 1) or the BPEL in Class
I were designed to be totally prestressed, as, in theory, no traction is allowed with regard to flexion when the
bridge is in service. As a result, minimal longitudinal reinforcement is used and this would be incapable of
compensating for any unforeseen tensile forces. On this type of structure, transverse cracks are usually evidence
of abnormal longitudinal flexion behavior. In particular, cracks crossed by prestress tendons are problematic
because of the risk of fatigue in the prestressing reinforcements.
On the other hand, tensile forces are allowed at the design level for structures dimensioned according to Classes
II or III of the BPEL. Efforts are made to keep the opening and widening of any cracks to acceptable levels in
order to:
– Prevent the risk of fatigue in the tendons crossing areas likely to be tensioned
– Limit the penetration of corrosive agents through the gaps caused by excessively wide cracks.
With this in mind, stresses or stress variations within the concrete and reinforcements are minimized and non-
prestressed longitudinal reinforcement bars are added to control the cracking.
These structures were built more recently and benefit from the lessons learnt on older structures. Fine transverse
cracks, which are closed when the structure is not loaded, are usually evidence of normal behaviour in
prestressed concrete, in accordance with the regulations. Excessive cracking (open cracks when the structure is
not loaded, etc.) is obviously a sign of abnormal behavior.
Problems arose during the construction the cantilevers on some of the first structures built using the cantilever
method and a spectacular accident occurred on the site of the Viosne viaduct on November 13 1970, when the
first cantilever tipped over, fortunately without any serious consequences (Fig. 8.1).
Fig. 8.1 – Tipping of the first cantilever of the viaduct over the Viosne
Accidents have also been caused by the collapse of prefabricated segments and form travelers, e.g. on the
bridges of Calix, in 1975 and Bellegarde in 1982.
Design rules governing the stability of cantilevers under construction were established and published in the
supplement to Technical Bulletin (BT) no. 7, published by Sétra in 1979. These rules, which are included in this
guide along with several additions, have now been successfully used for over twenty years. No cantilevers have
collapsed since their publication, despite the collapse of several form travelers.
The majority of structures built using the cantilever method prior to 1975 have suffered from transverse
cracking or the opening of joints in the lower slab, towards the middle of the central spans or in so-called “low
bending moment” zones (Fig. 8.2).
These cracks are evidence of insufficient resistance to longitudinal flexion. This type of cracking is particularly
serious given that the cracks or open joints are often crossed by continuity tendons inside the concrete, thus
exposing these reinforcements to the risk of fatigue.
These cracks have several causes which are often cumulative and include:
• The failure to account for the redistribution of forces due to the delayed obstructed deformation of
materials in the calculations. For simplicity’s sake, these forces are often put down to "redistribution by
creep" (in general, this error leads to the normal stress in the lower axis at the crown being overestimated
by 2 to 3 MPa)
• The failure to account for the thermal gradient in the calculations (in general, this omission also leads to
an overestimation of the normal stress in the lower horizontal plane at the crown of approximately 2 MPa
for a thermal gradient of 6° C)
• Parasitic forces locked into the structure when the closing segment is assembled due to adjustments made
on site (realignment of cantilevers, correction of reverse deflections, unforeseen site loads, incorrectly
controlled weight of the form traveler etc.).
The Circular of April 2 1975 and the supplement to the BT7 of April 1979 defined the design rules to be
adopted in response to redistributed forces due to the delayed obstructed deformation of materials and in
response to the thermal gradient. For structures dimensioned according to the IPl, this resulted in a significant
reduction in the recommended slenderness ratio at the crown, from l/50th to 1/40th, i.e. the bridge deck became
considerable thicker in this area.
With regard to the coefficients of losses by friction, the values adopted by the BPEL were more conservative
than those in the previous regulations. The BPEL paid particular attention to the case of tendons crossing
numerous joints, as happens on bridges built by the cantilever method. In addition, empty ducts allow for
additional prestressing to be used if the actual friction is greater than the friction values allowed for in the
design. Finally, the design allows for the use of additional prestressing (anchorages, deviator tubes, etc.) in order
to facilitate any future structural repairs or reinforcements (see the recommendations in Chapter 3 of this guide).
Two types of disorders may point to the existence of excessive radial tendon forces: longitudinal cracking in the
lower slab in the crown area and localized cracking, delamination or spalling of the concrete.
Longitudinal cracking in the lower slab is caused by downward thrusts in continuity tendons inside the concrete
in structures of variable depth and most commonly affects the central span (Fig. 8.3 and 8.4).
These problems affected first-generation structures because a large number of low-strength continuity tendons
were spread across the entire width of the lower slab, mainly in the central span. Also, many of these early
structures were built without gussets at the junction between the web and lower slab.
Localized cracks, delamination and the spalling of concrete are caused by the errors in the positioning of the
ducts such as the festooning of ducts between two joints, badly-positioned tendons, sudden changes in angle
close to the joints etc. These problems create radial tendon forces.
Gussets are now systematically used at the junction of the webs and the lower slab of box girders. Furthermore,
the practice of spreading the tendons across the full width of the lower slab has now been abandoned, especially
for bridge decks of variable depth. Tendons are now usually placed in the gussets or very close to them, which is
made easier by the fact that fewer internal continuity tendons are needed for mixed prestressing.
To combat problems caused by incorrectly positioned ducts, the Instruction Technique pour la Surveillance et
l’Entretien des Ouvrages d’Art (Technical Instruction for the Monitoring and Maintenance of Civil Engineering
Structures) recommends using a reinforcement plan that is designed to take up any parasitic radial tendon forces
due to angular fractures in proximity to the joints.
For information, we shall also mention two other important pathologies found on prestressed concrete bridges
built by the cantilever method:
Bridges built by the cantilever method are, of course, not immune to the more general problems affecting
prestressed concrete structures (distribution of concentrated prestressing forces, injection defects, corrosion of
tendons, etc.). It should be noted that the positioning of cantilever tendons inside poorly protected channels on
the extrados - a technique specific to bridges built by the cantilever method - proved to be particularly damaging
in terms of the corrosion of tendons and was quickly abandoned.
To round off this section, it should be mentioned that external prestress tendons have failed on several occasions
in recent years. This problem has affected tendons whose ducts were injected with a cement grout which had
failed to set properly in certain areas due to the phenomenon of settling (fresh grout).
The most commonly used repair technique consists of adding extra prestressing or replacing the original
prestressing. In the latter case, the original prestressing must be dismantled, which is a difficult process,
especially for tendons situated inside the concrete. It should be noted that these techniques are also used for
reinforcing operations.
Longitudinal prestressing
The tendon layout may be rectilinear or polygonal. In the latter case, it is angled by deviators added to the initial
structure (Fig. 8.6).
Fig. 8.6 – Additional longitudinal prestressing Fig. 8.7 – Anchor block for additional longitudinal
prestressing
The additional anchor blocks may be situated beyond the abutment, as on the Corbeil bridge, in Essonne, or
more conventionally, inside the box girder (Fig. 8.7 above).
Transverse prestressing
Transverse prestressing may be carried out on the lower slab (Fig. 8.8), the webs, or both (Fig. 8.9).
Further information on this subject is given by the following articles [RIC 93], [DEL 94], [BAR 94], [PER 94],
[JEH 94], [DEL 98], [BAR 98], [POI 99], [TAV 00], [BOUT 1] and [GIA 01] listed in the bibliography in the
appendix to this guide.
Other techniques are also used. For information, these include adjusting the height of the supports and adding
extra material, glued steel plate sheet or FRP (cf. article [POI 92]).
There is little information concerning repair design for prestressed concrete civil engineering structures.
However, the following documents provide useful information for anyone interested in the repair of prestressed
concrete bridges:
• Maintenance et réparation des ponts (Bridge Maintenance and Repair) [Presses de l’ENPC – 1997]
• Ponts en béton précontraint par post-tension (Post-tensioned Prestressed Concrete Bridges) [HA, Sétra,
TRL, LCPC]
• Annales de l’ITBTP n° 501 de février 1992 : Journées réparation et renforcement des structures de
bâtiments et d’ouvrages d’art (Annals of the ITBTP no. 501 of February 1992: Information Days for the
Repair and Reinforcement of Buildings and Civil Engineering Structures).
With these provisions in place, it must be possible to perform bridge management and maintenance operations
in accordance with labour legislation and particularly with regard to french Law no. 93-14-18 of December 31
1993, which introduced the Dossier d’Intervention Ultérieur sur Ouvrage (DIUO) [Post-Construction Works
File].
Finally, these access arrangements must not make the structure vulnerable to acts of vandalism.
Mixed prestressing has been used on the vast majority of large bridges built in recent years. This means that a
certain number of tendons are situated outside the concrete. To benefit fully from this technique, it must be
possible to replace these tendons without having to demolish any part of the structure.
The requirements concerning the tendons and their layout are set out in the Sétra guide entitled "Précontrainte
extérieure" (External Prestressing), published in 1979. It should be noted that a large number of the provisions
specified in this guide are included in Chapter 7 of the supplement to fascicule 65A of the french CCTG and
that, notwithstanding any contrary provisions in the STC, these provisions are compulsory.
The provisions concerning the injection of these tendons are defined by the french circular of February 2001
relating to the injection of prestress tendons situated outside the concrete. It should be remembered that this
circular only authorizes the use of non-adhesive products (factory-applied grease and wax), unless special
equipment capable of absorbing the energy of the tendon during its removal is used.
At a given moment in the life of a bridge, it may be decided to strengthen the prestressing. This may be due to a
pathology affecting the structure or to a change in its functional design. For a box-girder structure, it is
important to allow this possibility by building in the means to add additional external tendons if they are
required. This includes leaving room to pass formwork tubes housing an extra pair of tendons through cross
beams and deviators, and placing extra trumplates in the cross beams. It is also necessary to allow the forces
added by this extra pair of tendons when dimensioning the reinforcements for the deviators and cross beams.
The original type of tendons is used for the extra tendons and they are aligned according to the same rules. They
are then stressed according to the same procedures used for replacement external tendons. (Further information
on this point can be found in Article 64 of the supplement to fascicule 65A of the CCTG and its comments).
To allow for easy movement inside the box girder (Fig. 91), it is important to design bridge decks of sufficient
depth. For bridge decks of a constant depth, the problems caused by an insufficient depth could affect the entire
structure; therefore, it is recommended to fix the minimum total external depth at 2.20 m. For bridge decks of
variable depth, the access problems are occasional and only concern areas in the middle of the spans or close to
the abutments, so a minimum depth of 2 m can be accepted. It is important to note that these depths are given
for bridge decks without transverse ribs. For bridge decks with transverse ribs, it is necessary to add the internal
height of the ribs (usually 0.75 m to 1 meter) to the minimum depth.
In the majority of structures, there is sufficient room – at least 0.75 m – between the external tendons nearest to
the middle of the box girder to walk comfortably on the concrete surface of the lower slab. When this is not the
case, either because the lower slab is very narrow or because there are too many external tendons, it is possible
to install a gridded steel walkway over the tendons. This passageway may be cramped in the middle of the spans
due to tendons rising up close to the piers. (N.B. If the box girder is too narrow for normal maintenance, it is
possible to use completely internal prestressing, which is not as bulky as mixed prestressing).
Cross beams on modern box girder bridges always have access shafts to allow access for construction workers
and, when the bridge is in service, maintenance staff. For easy and, above all, risk-free movement through this
passageway, it is important to ensure that the height clearances in the shafts correspond to the values shown in
Figure 9.2.
Furthermore, if these deviators and crossbeams have low beams which hinder the movement of staff and
equipment – a common situation – it is advisable to install metal or concrete stairways or concrete ramps on
either side of these elements (Fig. 9.3). Important: if the vertical height exceeds 1.50 m, these elements must be
equipped with guard rails.
An access shaft must be made in line with each pier in order to allow access from the bridge deck to the piers
and vice-versa. For obvious reasons, this shaft must be positioned in line with the inspection pits in the pier head
units (see 9.3.2.1 below). In order to prevent this shaft from adversely affecting the mechanical behavior of the
slab or lower part of the cross beam, it should be circular in shape and 80 cm to 1 m in diameter. For safety
reasons, it is essential to keep this shaft closed under normal conditions, using a metal grid which cannot be
removed and closes automatically. An effective system consists of placing a square metal grid inside a square
rebate built into the top of round access hole.
All large prestressed concrete bridges must have an electrical system that is used to light the inside of the bridge
deck and to supply power for any tools required during maintenance operations (flood lights, power drills, etc.).
The lighting in the box girder must be powerful enough to allow staff to move around in complete safety (Fig.
9.4). For this purpose, bracket lights with spherical light bulbs or, more commonly, neon tubes or fluorescent
strip lights are used. These lights are positioned centrally underneath the upper slab with a longitudinal center-
to-center spacing of no more than fifteen meters and the high-risk areas around the cross beams and deviators
must be adequately lit. If the total length of the structure does not exceed 400 to 500 m, all of the bracket lights
can be operated simultaneously using 2 two-way switches situated at both ends of the bridge deck. For bridges
of over 500 m in length, it is recommended to organize the lighting system into sections of 300 to 400 m. In this
case, in addition to the two switches on the abutments, two-way switches must also be fitted at the ends of each
section N, in order to control the lighting for sections N and N+1. In the interests of economy, it is also possible
to fit a timer to the lighting system, but this must be set to stay on for a long time (at least 10 hours) in order to
avoid plunging workers into darkness when they are still inside the box girder.
Electricity is supplied by power sockets, which are usually positioned one meter above the lower slab, directly
below the light fittings. To allow for the use of power tools inside the box girder, a 220- volt system with a
frequency of 50 Hertz must be installed. In certain systems, these sockets are accompanied by safety sockets
supplying 24-volt current. In all cases, the power socket circuit in the box girder must be totally independent
from the lighting circuit, so that a problem with a tool does not suddenly extinguish the internal lighting.
The electrical system must comply with the general standards in force for low-voltage electrical systems (i.e. the
NF C 15-100 standard on the publication date of this guide). After installation, it must be approved by an
accredited organization.
There must be no risk of damaging the non-prestressed reinforcements or the prestress tendons during the
installation of the system.
9.2.3 - Miscellaneous
As explained in the Sétra “Précontrainte Extérieure” (External Prestressing) guide, it is necessary to examine
different ways of routing extra or replacement tendons through the bridge deck, and for transporting the
equipment needed for their installation. If it turns out to be impossible to route the tendons via the abutments,
another solution would involve making a 1 m x 0.80 m hole in the lower slab, directly in line with a road lane if
possible. Under normal conditions, this hole would be closed using a galvanized steel hatch (Fig. 9.5 and 9-6).
For further information about this point, the reader is recommended to refer to section 5.45 in the guide
mentioned above. These hatches may also be used to supply any other equipment, of course.
In the past, certain box-girder structures featured access hatches in the central part of the upper slab. As these
hatches cause maintenance and durability problems, this technique must be completely prohibited.
Water frequently penetrates into the box girder due to leaks in the structure or during maintenance operations. In
order to allow this water to drain away quickly, it is essential to leave holes of 10 to 15 cm in diameter in the
lower slab, equipped with a beveled tube extending through the intrados to form a drip groove. The longitudinal
positioning of theses holes must take account of the longitudinal profile of the top of the lower slab, which is
very different to the longitudinal profile of the road for a bridge deck of variable depth. It is also important to
consider the position of the cross beams and deviators, which form a barrier preventing the drainage of water.
Care must betaken to ensure that this configuration does cause water to run down the facing of the piers.
Transversally, it is also important to account for the transverse slope of the top of the lower slab and of the
tendons which might be installed there.
In order to facilitate the installation of networks inside the box-girder at some future date, it is common practice
to install anchor rails or couplings on the underside of the upper slab. Usually made from galvanized or
stainless steel, these fittings form the upper anchorages for the bars to which pipework, or a metal frame
supporting the networks, can be attached.
Fittings situated close to the tendon anchorages on piers may also be used for jack hoists, subject to their
nominal load being greater than 20 kN.
The principal characteristics of these rails and bushes (position, orientation, length, nominal load, cross section,
etc.) must be determined according to a precise set of specifications for the networks they are designed to
support. This guarantees their suitability for their future tasks.
It is advisable to number the segments using indelible paint and a stencil according to the construction plans.
This type of identification prevents the use of different numbering systems in inspection reports carried out over
the years. On certain very large structures, it might also be useful to label cross beams on piers with the number
of their corresponding pier as this could facilitate the identification of certain works.
9.3 - Piers
9.3.1 - Space between the underside of the bridge deck and the top of piers
In order to facilitate monitoring and maintenance operations, it is recommended to leave a minimum space of
0.50 m between the top of the piers and the underside of the bridge deck.
If the height of the piers exceeds 8 to 10 m, it is recommended to build a pit into the pier head units. This pit,
resembling a bathtub in shape, allows work to be carried out "comfortably" in the pier head area, in spite of the
limited space between the top of the pier and the underside of the bridge deck (Fig. 9.7 and 9.8). These pits are
usually 0.80 to 1 m deep and one meter wide; their length depends on the center distance between the bearings.
A ∅ 100 mm drain hole is built into the pit for the drainage of any water that might enter, especially during
construction.
A bridge deck often has to be jacked up after commissioning in order to change the bearings, reset the slide
plates or make adjustments due to the subsidence of a pier or a geometrical defect. To prevent problems or
damage to the structure during jacking, it is necessary to determine the position of the jacking points at the
design stage.
The size and location of these jacking points depends on the amount of space available on the pier head unit. It
is also important to position the jacking point as close to the axis of the nearest web as possible. In general, two
jacking points are provided for each bearing. However, if the pier head unit is too short to accommodate two
jacking points per bearing, it is possible to allow two points between both bearings, i.e. one point per bearing.
These points will also be be situated as close to the webs as possible. Once these jacking points have been
determined, the next stage is to design and install the reinforcements or prestressing required to take up the
forces generated in the piers and bridge deck under these support conditions. It is also necessary to mark the
jacking points on the plans and identify their positions on the top of the pier. Support blocks (Fig. 9.9) are
usually used for this operation, although durable markers (studs, etc.) may be used if the geometry of the
structure prevents the use of blocks.
9.3.3.1 - Inspection
Hollow piers are usually equipped with a system of safety ladders and landings throughout their full height (Fig.
9.10) for use during internal monitoring and inspection operations. This system is allows for the regular
examination of the inside of piers with a level of accuracy that satisfies the requirements of scheduled
inspections. For more detailed inspections, it is possible to use binoculars or additional ladders if stairs are
fitted.
The dimensions of the system (height and depth of steps, frequency of landings) are determined according to the
standards in force relating to stairs in buildings. NF E 85-010 "Échelles métalliques fixes avec ou sans
crinolines" (Fixed Metal Stairs With or Without Safety Bows) was the applicable standard on the publication
date of this guide.
Considering the financial investment required for this type of equipment, precautions must be taken to guarantee
its longevity. Stairs or ladders must be made from hot galvanized steel thick enough to ensure that minor
corrosion does not affect the strength of these elements. Landings can be made from galvanized steel or the
same concrete that was used to construct the pier shafts.
In recent years, some Owners have decided to restrict the fittings inside hollow piers on large bridges to a single
metal gridded platform situated just underneath the crosshead and couplings to which harnesses can be attached
(Fig. 9.12). This creates a working platform from which inspectors equipped with climbing gear can operate.
This system reduces the initial investment costs and guarantees that inspections will be carried using the latest
totally compliant equipment. However, an inspection of the piers under these conditions requires more
equipment and more time, which also increases the cost of the operation, of course.
Fig. 9.10 – Safety ladders and landings inside a pier Fig. 9.11 – Access door to a pier or an abutment with
five-point safety lock
9.3.3.2 - Access
Whatever the context, it is necessary to allow access to hollow piers from the bridge deck. For this, a shaft is
usually created at the bottom of the inspection pit described in Paragraph 9.3.2.1. As before, this hole must
normally be closed using a metal grid or plate. It must also be offet in relation to the shaft built into the cross
beam on pier, to make sure that if someone falls from the bridge deck, they will not fall further than the bottom
of this pit.
In the majority of cases, a second access point is also provided via a metal door at the base of the pier.
Considering the risks of vandalism, it is necessary to use the same type of doors as those recommended for the
abutments (see 9.4.2 and Fig. 9.11). It is also possible to situate these doors three or four meters above ground
level, requiring a ladder for access. These doors are rarely aesthetically pleasing and it is important to make sure
that the architecture of the pier is as complimentary as possible.
If it is impossible to provide doors at the base of the piers (e.g. piers on the sea bed, risk of vandalism too great,
insufficient strength, etc.), it is necessary to create a reasonably large shaft leading from piers to the bridge deck.
Indeed, this passageway must be big enough to be used for transporting and removing maintenance equipment.
In the event of an accident during a maintenance operation, any victims will also have to be evacuated via this
single passageway.
9.3.3.3 - Lighting
Hollow piers must be equipped with a lighting system similar in design to the system used for the bridge deck.
9.4 - Abutments
9.4.1 - Access to abutments
Access points to the abutments must be designed and built with care. In general, access is gained from the
supported road, via the return walls of the abutments. However, it is also possible to enter abutments from
another road below the structure if parking spaces are provided. These access points must be created with care
(concrete surfacing, concrete or wooden stairs, guard rails if necessary, etc.). However, they must also be as
unobtrusive as possible in order to avoid attracting unwanted attention.
On large bridges built in recent years, the front face of an abutment is usually closed off by a concealing wall,
which is entered through a metal door. This system is highly recommended, as it denies access to unauthorized
persons and therefore prevents malicious damage to the bridge bearings, external continuity prestressing and the
guttering under the joints. This solution is also aesthetically pleasing, given that these walls hide the inside of
the abutments which are never very attractive. It is also important to fit high-quality locks on the doors. Five-
point safety locks bearing the "A2P trois étoiles" label awarded by the french APSAD (Assemblée Plénière des
Sociétés d’Assurances Dommage - Plenary Assembly of Damage Insurance Companies) are particularly suitable
for this task (see Fig. 9.11 on previous page).
In addition to this important provision, as little room as possible should be left between the concealing wall and
the outer edges of the box girder. No more than 15 cm should be allowed for this gap, including between the
underside of the bridge deck and the top of the central part of the concealing wall.
Although covering a much smaller area than a bridge deck, an abutment must have the same type of electrical
system (lighting and power sockets). It is important to fit a light switch next to the door mentioned in 9.4.2
above.
One of the essential requirements for changing the external prestressing is the ability to gain access to the
anchorages to stress the new tendons. As mentioned in section 5.42 of the "Précontrainte extérieure" (External
Prestressing) guide published by Sétra, the design of an abutment must incorporate a cable pulling chamber if
the external tendons are attached to stressed anchorages on the cross beam directly above the abutment. In order
to determine the effective length L of this chamber, i.e. the distance between the internal face of the abutment
wall and the end of the bridge deck, not including the corbel, it is necessary to consider the phase of the
replacement process which requires the most room. For external tendons injected with a flexible product (wax
or grease), this key phase in the design of this chamber is when the new tendons are in their ducts and the
tensioning jack is positioned at the end of the strands prior to “swallowing” them up (Fig. 9.13). In this phase,
the space required corresponds to the length of the jack Lv plus the length of the strands connected to the jack
prior to stressing Lt.
The following table gives the lengths Lv, Lt and (Lv+Lt) for the 19T15S, 27T15S and 37T15S types of tendons
used in certain French prestressing systems.
At the design stage, it can therefore be considered that the effective length L of the chambers must be at least
2.40 m for 19T15S cabling and 2.60 m for 27T15S or 37T15S cabling.
In certain very specific cases, cable pulling chambers may not be built into abutments. In this case, the
additional length described above is no longer required. However, the distance between the end of the bridge
deck and the abutment wall must not be reduced too much. A minimum distance of 0.80 m to 1 m is essential
for inspecting and correctly maintaining these parts of the structure.
Expansiont joints are fitted at the ends of almost all large modern bridges, and are therefore situated directly
above the abutments. Despite the care and attention devoted to their design and fitting, these joints are never
totally watertight. Therefore, it is necessary to collect any water that percolates through them in order to protect
the abutment crossheads, bridge bearings and the external prestressing anchorages situated at the ends of the
structure.
The best systems are shown in Figures 9.14 to 9.l6, consisting of a metal gutter positioned under the joint.
Supported by galvanized steel brackets, this gutter must be positioned centrally under the expansion joint, which
requires a corbel of 30 to 40 cm on the side of the bridge deck. In order to prevent splashes, it is necessary to
channel the water using vertical neoprene splash guards enclosing the space between the joint and the gutter.
These splash guards, which are usually different to those supplied with the joint, must be weighted for
maximum resistance to the draft of air created by passing trucks. To facilitate the cleaning of the gutter, it is
recommended to fit a water tap on the abutment, provided that the structure can be connected to the drinking
water network at reasonable cost. The pipes must then be protected from freezing.
Fig. 9.15 – Gutter under joint (the distance to the slab Fig. 9.16 – Gutter attachment
allows for easy cleaning)
9.4.6 - Space between the underside of the bridge deck and the top of the crossheads
As for the piers, it is advisable to leave a minimum gap of 0.50 m between the top of the abutment crossheads
and the underside of the bridge deck in order to facilitate maintenance operations.
Like piers, abutments must have jacking points for the bridge deck. These are determined according to the
procedures described in paragraph 9.3.2.2 above.
In most cases, the contract is not divided into tranches or packages. Very large projects, however, may
sometimes be broken down into tranches in order to stagger the financing of the works, although this system is
not be recommended because the tranches can rarely be considered in isolation.
Sub-group I contains the documents that make up the contract. It contains the frameworks for the tender
document, the price schedule, cost estimate, draft the Special Administrative Clauses (Cahier des Clauses
Administratives et Particulières [CCAP]), the Special Technical Clauses (STC), and occasionally, price
breakdowns and breakdown frameworks. It also includes a series of documents appended to the STC, including:
• Site plan
• Plan view
• Longitudinal cross-section
• Contractual part of the geotechnical survey, i.e. usually consisting of the borehole logs.
In certain cases, sub-group I also contains specific studies which have a direct influence on the design of the
structure: hydraulic studies, wind-effect study, etc. In other cases, certain architectural studies may also be
included in sub-group I in order to make the information relating exclusively to these studies contractually
binding (reference to a matrix for the bottom shuttering matrix, aggregates, etc.). Finally, if the structure has to
be built over or close to a traffic-bearing road, railway or waterway, sub-group I must also contain a document
listing the road, rail or water-related constraints facing the contractor during the works.
Sub-group II is made up of documents intended for information purposes only. For structures built by the
cantilever method, this sub-group usually includes the following items:
• Architectural study
• The non-contractual part of the geotechnical survey: usually the pre-design for the foundations produced
by the laboratory in charge of this survey.
In addition, sub-group II sometimes contains initial plans for the bridge deck reinforcements, along with design
calculations or miscellaneous studies containing information for contractors.
In recent years, sub-group II of certain Contractor Tender Documents has also included reports concerning the
formulation of concrete, including the results of specific studies carried out upstream by the Construction
Manager (HPC, alkali reactivity, frost and salt-resistant formulas, etc.)
Technical proposals are detailed precisions that contractors are obliged to include in their bid in addition to their
proposed basic solution. Article 2.3 b of the Tender regulations specifies the structural elements for which
technical proposals must be submitted. With regard to the bridge deck of a structure built using the cantilever
method, the following points must be covered in these proposals:
• Origin of the components, the composition and the application of the concrete
• Bridge bearings
• Prestressing processes
• Expansion joints.
The Owner may authorize contractors to offer variants with a view to encouraging competition. Contrary to the
technical proposals, these variants, if they are accepted, may require alterations to be made to the price schedule,
cost estimate and of course the Special Technical Clauses and the attached plans.
The permissible technical variants are listed in Article 2.3 of the Tender Regulations. The most common
variations include:
• The replacement of concrete webs with lightweight metal webs (for long span bridges)
• Substitution of the cantilever construction technique by the incremental launching method, with or
without pilings depending on the situation (for moderately long bridges of a constant depth)
The evaluation phase for the bids for a structure to be built by the cantilever method is often longer than for a
basic structure. Therefore, the first article of the tender document should specify a reasonably long period of
validity for the bids (a minimum of 180 days), or even longer if contractors are likely to propose major variants.
As we have already mentioned, construction surveys for structures built by the cantilever method are long and
complex. Sufficient time must also be allowed for Construction Managers to evaluate these surveys. For certain
structures, work on site may sometimes advance at a faster rate than the construction surveys can be carried out.
In order to prevent the interruption of work due to delays in the availability of construction plans that have been
approved by the Contruction Manager, it is essential to allow a sufficiently long preparation period in which the
engineering firms can reach a stage that is well ahead of the work carried out on site. The period required varies
from structure to structure, but the amount of time required is inversely proportional to the time allowed for the
construction of the piers.
For a structure built by the cantilever method, the list of general documents to be included in the contract
includes at least the following documents:
• Fascicule 61 Titre II of the french Cahier des Prescriptions Communes (Common Conditions) [CPC]) :
"Programme de charges et épreuves des ponts-routes" (Program of Loads and Tests for Road Bridges)
• Fascicule 61 Titre IV Section II of the french General Technical Clauses (GTC): “Actions de la neige sur
les constructions” (Effects of Snow on Structures) (DTU P 06-006 of September 1996)
• Fascicule 62 Titre I - Section I of the french GTC: "Règles techniques de conception et de calcul des
ouvrages et constructions en béton armé suivant la méthode des états limites" (Technical Rules for the
Engineering and Design of Reinforced Concrete Structures According to the Limit State Method) [BAEL
91 revised in 1999]
• Fascicule 62 Titre I - Section II of the french GTC: "Règles techniques de conception et de calcul des
ouvrages et constructions en béton précontraint suivant la méthode des états limites" (Technical Rules for
the Engineering and Design of Reinforced Concrete Structures According to the Limit State Method)
[BPEL 91 revised in 1999]
• Fascicule 65-A of the french GTC and its supplement: "Exécution des ouvrages de génie civil en béton
armé ou précontraint" (Construction of Reinforced and Prestressed Concrete Civil Engineering Structures)
in their updates published in August 2000
• Fascicule 62 Titre V of the french GTC: "Règles techniques de conception et de calcul des fondations des
ouvrages de génie civil" (Technical Rules for the Engineering and Design of Civil Engineering
Structures)
• Fascicule 68 of the french GTC: "Exécution des travaux de fondation des ouvrages de génie civil”
(Construction of the Foundations for Civil Engineering Structures).
• French Circular no. R/EG3 of July 20 1983 entitled "Transports exceptionnels, définition des convois
types et règles pour la vérification des ouvrages d’art" (Exceptionally Large Trucks: Definition of
Standard Loads and Rules for the Verification of Civil Engineering Structures), published by the
Direction des Routes (Highways Department), for structures supporting these types of vehicles.
• The AFPS 92 guide for the seismic protection of bridges, edited by the Association Française du Génie
Parasismique (AFPS) [French Seismic Engineering Association], published by the École Nationale des
Ponts et Chaussées (National School of Civil Engineering)
• The officially approved standard NF P 06-013, more commonly known as the "Règles de construction
parasismique - règles applicables aux bâtiments - PS92" (Antiseismic Construction Rules – Rules
Applicable to Buildings – PS92), with regard to the foundations
• Order no. 91-461 of May 14 1991 relating to the prevention of seismic risks and to the Decree of
September 15 1995 relating to the classification and rules for antiseismic constructions applicable to
bridges in the “normal risk” category.
Article 8.1 of the Special Administrative Clauses (Cahier des Clauses Administratives particulières [SAC])
specifies the length of the preparation period and indicates whether or not this is included in the contract period.
Further details concerning this point are given in article 10.4.2 of this chapter.
As conflicts between the Contractor and Construction Manager often arise over compliance with acceptance
deadlines, it is recommended that Article 8.2 of the Special Administrative Clauses should contain a text which
clearly mentions:
• The deadlines that the Construction Manager agrees to observe, in the framework of the first and
subsequent evaluations of the documents.
Although it could probably be improved, the following text could serve as an example for this text:
Many bridges are built immediately next to or even above other traffic-bearing routes. Under these conditions
and for safety reasons, it is necessary to wait until the traffic on these arteries has been interrupted before
carrying out certain operations.
As traffic can normally only be interrupted at certain times of the day, work on site may be disrupted. It is
important to mention these constraints clearly in articles 8.4 and 8.5 of the SAC, either by describing the
constraints directly in these articles, or by referring the reader to another of the documents included in the
Contractor Tender Document.
Article 91 of the SAC outlines the main hold points on the site as well as the time necessary for the Construction
Manager to cancel these hold points. The following table gives a non-exhaustive list of the hold points likely to
apply to the bridge deck of a structure built by the cantilever method in addition to the average delay before they
can be lifted.
Hold points Time required
Casting and formwork removal
Acceptance of the quality control element 1 day
Authorization for the casting of a part of the structure 1 day
Authorization to move form travelers forward 1 day
Authorization to remove falsework from a section of bridge deck 1 day
Prestressing
Authorization for tensioning of prestressing 1 day
Acceptance of tensioning before reinforcements are cut 1 day
Authorization for the injection of prestressing ducts 1 day
Bridge bearings
Acceptance of bearing blocks 1 day
Acceptance at moment of delivery 1 day
Acceptance of the fitting of bridge bearings (adjustment and positioning) 1 day
Fittings
Acceptance of waterproofing substrate 1 day
Acceptance of waterproofing; authorization to apply surfacing materials 1 day
Acceptance of a quality control element for the prefabricated concrete cornice 1 day
Acceptance of the adjustment of cornices before sealing 1 day
Acceptance of pavement joints before fixing or sealing 1 day
Acceptance of retaining systems before sealing 1 day
Testing
Authorization to perform loading tests 1 day
There now follows a list of points that must be clearly specified in the Special Technical Clauses (STC) for the
Contractor Tender Document.
These points may be broken down into two categories. The first concerns elements of additional information to
that provided in the GTC and by the applicable standards, either because these documents are incomplete, or
because none of them cover the field in question. The second category concerns the options proposed by these
texts.
In line with the standard STC included in the CAPT-DCE-OA software published by Sétra, none of these points
repeats the requirements laid down in the GTC and the applicable standards, because they are already binding
for the contractor.As these points concern conventional types of box girders built by the cantilever method,
additional information may be required for more sophisticated box girder designs.
As we have already mentioned, great care should be taken with regard to the quality and execution of the
surveys. With this in mind, it is advisable to include an article entitled “Programme des études d’exécution”
(Construction Survey Program) in the Special Technical Clauses. This can be worded in the following manner:
The list enumerates the documents that must be submitted for the construction of both temporary and permanent
structures. It shall be drawn up in accordance with the framework of surveys specified in the contract.
The provisional schedule includes the deadlines for the submission of documents and the fixed or tentative
deadlines for approval by the Construction Manager, in accordance with the minimum deadlines established by
Article 8.2 of the SAC. It presented in the form of a bar chart clearly showing the critical tasks and the time
allowed.
10.6.3-1 -Actions
The STC must state all of the actions to be considered in the verifying calculations for the structure.
Many of these actions are defined in fascicule 61 Titre II of the french CPC and in the BPEL 91 revised in
1999. These actions, which are normally listed and described in the STC are:
• Selfweight of the bridge deck (specify the unit mass of the concrete)
• Prestress forces
• Concrete shrinkage and creep (specify the area in which the structure is situated)
• Predicted overloads from road vehicles and pedestrians on the structure, including fatigue trucks, if used
These actions must be accompanied by certain actions which are specific to box girder bridge decks and the
method of construction. These must be specified in the STC and relate toconcern:
• Site overloads defined in Chapters 3 and 5 of this guide, only to be used for calculations in the
construction phase before the closure of a cantilever
• Specific site actions (e.g. an unbalanced segment, collapse of one of the form travelers, forces transmitted
by launch beam supports, etc.), also described in Chapter 5 of this guide.
Depending on the situation, it may also be necessary to mention certain additional actions such as:
• Seismic effects
• Etc.
The STC usually mentions the different combined actions that have to be considered. The combinations to be
used for the in-service verification of the structure are specified in the BPEL 91 revised in 1999. Combinations
to be used for verifying the structure with regard to the risks of cantilever instability are given in Chapter 5 of
this guide. It should be noted that they differ from those mentioned in the Directives Communes (Common
Guidelines) of 1979.
• The verification categories, as described in Article 1.3 of the BPEL 91 revised in 1999, used to verify the
longitudinal flexion of the bridge deck and the transverse flexion of the upper slab on structures with
transverse prestressing (see Paragraph 3.3.2)
• The cracking categories, as described in Article A 4.5.3 of the BAEL 91 revised in 1999, for the
verification of reinforced concrete parts (transverse flexion, deviators, cross beams, etc.)
• The thermal gradient and the thermal expansions to be adopted in the construction phase (see Paragraph
3.3.3.2).
As differences of opinion exist between Construction Managers, the STC must specify whether Article 6.1.2.3
of the BPEL 91 revised in 1999 is applicable in the strict sense, or whether different permissible stresses must
be adopted. (For example, Paragraph 3.3.3 of this guide recommends the application of the comment in Article
6.1.2.3 in construction situations).
The STC must also state whether it is compulsory to perform a range calculation for prestress effects. If not, the
STC must specify the values of k and k’ to be adopted for the application of Article 4.10 of the BPEL 91 revised
in 1999. These values are directly related to the requirements formulated by the Construction Manager with
regard to empty ducts and the measurement of transmission factors (see our recommendations in 3.2.3).
As the BPEL 91 revised in 1999 does not include any rules for the accumulation of non-prestressed
reinforcement bars designed to compensate for transverse flexion on the one hand, and the tangent general
flexion and distribution forces on the other, it is essential to include a rule of this type in the STC (see Chapter 4
of this guide). It would also be advisable to add a rule governing how to allow for different construction phases
in the calculation of stresses at the ULS (see our proposals in paragraph 3.3.5).
In accordance with Paragraph 3.2.5, it is important to note that an as-built calculation must be performed after
the completion of the construction work. This calculation takes account of the actual phasing of the work carried
out on a bridge built by the cantilever method, with the actual dates of casting and any incidents that occurred
on site (e.g. a broken strand that was not replaced). It may also consider the estimated coefficients of friction
given by measurements taken on site.
Finally, depending on the structure in question, the following requirements may also be specified in the STC:
• Allow for the curvature of the structure on the horizontal plane in the calculations of longitudinal flexion
• Perform a finite elements calculation for a specific part of the structure (segment on pier, segment on
abutment, ribs, etc.)
• Perform a second-order calculation for one or more piers if they are very slender (in this case, the STC
must specify the design assumptions for the horizontal forces in the pier heads)
• Etc.
Chapter 3 of this guide gives a lot of valuable advice on choosing the coefficients and rules mentioned in this
paragraph.
10.6.4.1 - Formwork
The STC must specify the category of facing to be used for the inner and outer surfaces of the box girder. This
category must conform to the definitions provided in Article 52 of Fascicule 65A of the french CCTG.
The STC must specify whether the contractor must manufacture a test segment for the suitability tests or
whether small control slabs or elements will suffice. In all cases, the STC must clearly mention:
• The ducts and non-prestressed reinforcement bars that they must contain.
Furthermore, the STC must clearly define the acceptance conditions for these tests: inspection of facings, core
sampling in the sheath areas, measurement of flatness of facings, etc.
It is advisable to establish a minimum strength requirement for the concrete at the moment the formwork is
removed. This must not be less than 15 MPa.
10.6.5 - Prestressing
The STC must precisely state the number and type of strands to be used for the cantilever tendons, along with
their strength and relaxation categories. It must also mention the type of duct and, of course, the type of
injection product to be used.
The characteristics mentioned in the STC for the continuity tendons must be the same as those specified for the
cantilever tendons. The Owner’s requirements for the permanent protection to be used on the anchorages (e.g.
conventional sealing, metal caps, etc.) must also be specified. Certain Construction Managers demand rigid
ducts for the ducts at the level of the anchor blocks, guaranteeing a consistent alignment without any
concentration of radial tendon forces.
If the project calls for the installation of transverse tendons in the upper slab or ribs, the STC must clearly state
the applicable requirements, which are identical to those for the continuity tendons.
The characteristics mentioned in the STC for the external tendons must be the same as those specified for the
cantilever tendons. The type of deviator tubes and corrosion inhibitors to be used in the structural deviators, in
addition to the types of anti-vibration systems to be adopted, if any, must also be specified. Finally, the Owner’s
requirements with regard to additional prestressing, and more specifically, to the capacity of this prestressing,
must also be specified.
As these fittings are not always clearly marked on the plans included in the Contractor Tender Document, the
STC must clearly describe the maintenance fittings that the Owner has requested for the structure. These fittings
include:
• The electrical system for the box girder, including the internal lighting
• Closing devices (doors, grids, plates, etc.) for the access points to the bridge deck (manholes in cross
beams on abutments, manholes in the lower slab, on piers or close to abutments)
• Anchor rails fixed to the upper slab or webs, which may be used for the immediate or subsequent
installation of networks in the box girder
• Handling rails fitted in the upper slab, in line with any hatches that may be built into the lower slab
• Rails used in the deployment of tensioning jacks for the external prestress tendons
Chapter 9 of this guide contains numerous guidelines for the drafting of the corresponding clauses.
As mentioned in Chapter 7, the inspection of work carried out on a structure built by the cantilever method is an
important and complex task which the Construction Manager must start to organize quite a long time in
advance.
The Contractor Tender Document (SAC, STC) must clearly specify these inspections, which usually correspond
to hold points for contractors.
In addition, it may not be possible for the Contract Manager and his or her laboratory to carry out certain
inspections. If this is the case, it will be necessary to use the services of an external inspection company. These
inspections must be clearly defined and paid for separately.
In addition to the prices normally shown in this appendix, the price schedule for a prestressed concrete structure
built by the cantilever method using cast-in-situ segments must also include prices for the following elements:
• Form travelers
The price for the cantilever stabilization system is normally given as a “fixed price” or a “fixed price per pier”,
covering the supply, installation, and eventual removal of the temporary stability blocks, the temporary
prestressing and, if necessary, the temporary pilings or cable-stays. The price also covers any jacking operations
required during construction, especially during the transfer onto permanent bearings.
The price for the form travelers usually includes the design, construction, transportation, adjustments,
successive movements during construction and the final dismantling of form travelers used on site, in addition
to cost of external inspections. This is either a fixed price or, for very large structures, a “per pair” price. In view
of the large sums of money involved, this price is normally paid in instalments as the work advances on site.
The price of the formwork tool for the segment on pier is given as a fixed or “fixed per pier” price. This
normally includes the design, construction, transportation, adjustments, successive movements during
construction and the final dismantling of structures used for centering and encasing the segments on piers, in
addition to the cost of external inspections.
The price for the centuring of end sections includes the design, assembly and removal of the centuring used for
the sections of bridge deck not built by form travelers, plus the costs of external inspections. Payment is often
on a fixed-price or fixed price per abutment basis, although a price per square meter may also be charged
according to the area of bridge deck to be shored up.
A1 Determination example
Example of the determination of a bridge deck built by the
cantilever method
This appendix presents an example of the calculation of the bridge deck for a structure built by the cantilever
method. It also provides information about specific aspects of the design.
Like the rest of this guide, this appendix has been drawn up in accordance with the BPEL 91 revised in 1999
and fascicule 61 Titre II of french CPC.
A1.1 - Reminders
A1.1.1 - Notation
d to be the minimum distance from the mean tendon to the upper axis in order to guarantee the adequate coating
of the tendons
d’ to be the minimal distance from the mean tendon to the lower axis in order to guarantee the adequate coating
of the tendons
Furthermore, we take:
I
ρ= to be the geometric output of the cross-section
Bvv '
c = ρv to be the ordinate (in relation to G) of the highest point of the central core
c’= ρv’ to be the ordinate of the lowest point of the central core
Ms1 and Ms2 to be the maximum and minimum extreme moments respectively (counted algebraically) due to the
imposed loads
Ml and M2 to be the maximum and minimum extreme moments respectively applied to a cross section
M = M 1 - M2
Finally, we use the same indices for shear forces (T) as for the moments.
(
- in traction: − σ t = − f tj − k f c )
Given that the hyperstatic forces due to prestressing are ignored, in each section we should have:
P P e0 + M 2
below Mmini = M2 σ sup = + v ≥ σ t (1)
B I
P P e0 + M 2
σ inf = − v ' ≤ σ c (2)
B I
P P e0 + M 1
below Mmaxi = M1 σ sup = + v ≤ σ c (3)
B I
P P e0 + M 1
σ inf = − v' ≥ σ t (4)
B I
M2 I σ t M I σt
− c' − − ≤ e0 ≤ c − 1 +
P v P ¨P v ' P
These are sections in which we are not restricted by the coating requirements for the tendons; P can therefore be
chosen so that:
M2 I σ t M I σt
− c' − − = c− 1+
P v P ¨P v ' P
so
ΔM M1 I σ t I σt
with − (v '−d ') ≤ e0 ≤ v − d
M
P= − Bσ t and e0 = c − + = − c' − 2 −
c + c' P v' P P v P
In so far as we can choose the thicknesses of the two members, we can choose them in such a way that
I I ΔM
= = (with Δσ being the range of stress variation σ c + σ t ).
v v' Δσ
Thus, under extreme loading cases, we may obtain the four limit stresses (Fig. A1.2a), but if an excessively
I ΔM
thick member is dictated (e.g. an upper member for which > normally applies) we will only be able to
v Δσ
obtain three limit stresses (Fig.A1.2b).
- σt 0 ²σ b 0
- σt ≤ σb
- σt σb σt σb
0 -
0
These are sections in which we are restricted by the coating requirements for the tendons. Based on compliance
with the minimum stress, this gives:
ΔM ΔM
P≥ − Bσ t = − Bσ t
c+c ' ρh
P must therefore be at least equal to the higher of the two values below (according to the structurally significant
moment):
M1 M2
and −
I I
c + v ' −d ' + σ t c' + v − d + σt
v v'
As in the previous situation, the number of limit stresses that can be obtained depends whether or not it is
possible to modify the thickness of the members. Let us consider the example of a section that is mainly
subjected to negative moments (e.g. a section on an intermediate support); therefore M2 (the minimum algebraic
value) is structurally significant. If we are able to modify the thickness of the upper structural member, it will be
possible to obtain three limit stresses (Fig. A1.3a), with:
M2 I ΔM
P=− and = (compliance with the change of stress σb, in the upper axis).
I
c' + v − d + σ t v Δσ
v'
If, as is usually the case, the size of the upper member is imposed (excessively thick), we will only be able to
obtain two limit stresses (Fig. A 1.3b) with:
M2
P=−
I
c' + v − d + σt
v'
-σt
0
σb -σt 0 ≤ σb
sous M1 sous M1
sous M2 sous M2
-σt σb
σb
0 0
(a) (b)
≥
Fig. A1.3 – Limit stress diagrams for an over-critical section
Using the notation adopted by M. Courbon, the focal point method consists of using the mechanical constants
ai, bi and ci for each span to calculate the focal point ratios for the left, (φi) and right, (φ’i). Both groups of
equations are given below:
ϕ1 ψ1 = 0 ϕ‘n = 0
b2 bn −1
= a2 + c1 - b1 ϕ1 = cn-1 + an - bn ϕ‘n
ϕ2 ϕ ' n −1
bi +1 bi
= ai+1 + ci - bi ϕi = ci + ai+1 - bi+1 ϕ‘i+1
ϕ i +1 ϕ 'i
bn b1
= an + cn-1 - bn-1 ϕn-1 = c1 + a2 - b2 ϕ‘2
ϕn ϕ '1
Having ascertained the the focal point ratios and the rotations ω’i and ω"i for the end of span i, which is
considered to be independent and subjected to the loading case in question, we can calculate the bending
moments on the supports Ai-1 and Ai when span Ai-1 Ai is loaded.
ω 'i
+ ω "i
ϕ 'i
Mi-1 =
1
bi ( − 1)
ϕ iϕ 'i
ω "i
ω 'i +
ϕi
Mi = -
1
bi ( − 1)
ϕ iϕ 'i
The moments on the other supports are determined by the following focal point ratios:
The following units of measurement are systematically used in this example (unless otherwise specified) :
The example involves the determination of a structure with three asymmetrical spans totaling 214.50 m between
the centers of the end supports. There are two end spans of 53.375 m and 63.375 m and one central span of
97.75 m. The bridge deck is cast in-situ due to its moderate length (Fig.A1.4).
Given the need to comply with clearance dimensions, the height of the box girder varies parabolically between:
The segments on piers are 8.00 m long and the closing segment for the central span is 2.00 m long.
(*) This is quite a low slenderness ratio but it is imposed due to the fact that this structure is designed to double
the capacity of an existing bridge.
The supported platform is illustrated in Figure A1.5. However, only one side of the traffic lanes is shown, as the
complete structure consists of two bridges fastened together.
According to fascicule 61 Titre II of french CCTG, the distributed overload A is given as:
a2 = 3.5/3.05 = 1.15
Considering the third comment in Article 4.21, the linear loads according to the length of loaded section is given
by:
36000
with A( ) = 230 + (A(l) in kg/m² and l in m - units used in fascicule 61 Titre II).
l + 12
- For the concrete: compressive strength fc28 = 35 MPa, for a permissible in-service compression stress = 0.6 x
35 = 21 MPa
- For the cantilever and continuity tendons, we use 12T15S prestress units, giving an effective mean in-service
force estimated at 1.95 MN; the overall diameter of the ducts is 80 mm
-For the external tendons, we use 19T15S prestress units, giving an effective mean in-service force estimated at
3.1 MN; the overall diameter of the ducts is 100 mm.
As the total width of the slab is equal to 10.95 m, including the longitudinal anchoring girders for the safety
barriers, it is logical to design a box girder with two webs positioned according to the findings of a summary
analysis of the transverse behavior. This analysis was also used to establish the thickness of the upper slab
between the webs at 25 cm, whereas the thickness of the webs (36 cm) is determined by the casting conditions,
allowing for the diameter of the ducts. Vertical webs were chosen for aesthetic reasons. The thickness of the
cantilevers varies between 25 cm on the BN4 side and 30 cm on the web side. The mean thickness of the upper
slab is therefore 27 cm. Figure Al.6 shows the cross-sections used as the basis for the first approximate
calculations.
Finally, we know that there must be room to accommodate gussets in the slabs. Although we do not yet know
the precise dimensions of the formwork for these elements, we must allow for them in our calculations. As an
initial estimate, we shall use the dimensions given in Figure A1.7.
In the central spans, the total height of the box girder varies parabolically according to following the law:
2
⎛ 2x ⎞
h(x) = h0 + (h1 - h0) ⎜ ⎟
⎝ l ⎠
In the end spans (Fig. A1.9), the total height varies parabolically at first (section closest to pier), and then it
becomes constant and equal to h0, close to CO and C3.
We then have to establish the thickness ε (x) of the lower slab; in fact, for this, we shall use a parabolic variation
law similar to the one used for h(x), with ε0 and ε1 the thicknesses at the crown and on the pier:
2
⎛ 2x ⎞
ε(x) = ε0 + (ε1 - ε0) ⎜ ⎟
⎝ l ⎠
As an initial estimate, we shall use ε0 = 24 cm: a value which is imposed by the casting conditions, and ε1 = 45
cm: a value chosen in view of the span lengths and the slenderness ratios.
A computerized calculation gives us the mechanical characteristics of the sections on pier and at the crown.
Section at the crown Section on pier
h(x) 2.300 m 5.300 m
ε(x) 0.240 m 0.450 m
B 6.0965 m2 9.3129 m2
v 0.860 m 2.420 m
v’ 1.440 m 2.880 m
I 4.620 m4 41.532 m4
ρ 0.612 0.640
In the following calculations, we shall use the sequence of construction operations shown below:
1 Construction of cantilever on P1
2 Construction of the cast-on-falsework section near to C0
3 Closure of C0-Pl, stressing of continuity tendons for C0-Pl and transition to permanent bearings for P1
4 Construction of cantilever on P2
5 Construction of cast-on-falsework section near to C3
6 Closure of P2-C3; stressing of tendons for P2-C3 and transition to permanent bearings for P2
7 Closure of P1-P2 and stressing of continuity tendons for Pl-P2
8 Stressing of external tendons
9 Installation of fittings and commissioning
The complete cantilever is shown in Figure A1.11 below. In order to simplify the calculations, we consider that
the bridge deck is supported on the centerline of the pier. The moment resulting from this assumption is slightly
higher than if the calculation were to be performed in line with the temporary stabilizing blocks.
Fig. A1.11 – Determination of the support moment during the casting of the final segments
⎡ ⎛ x ⎞ ⎤
2
⎡ ⎛ x ⎞ ⎤
2
Hence, with a unit mass of 2.5 t/m3, therefore a unit weight of 0.024525 MN/m3:
x
- Mg(x) = ∫ − T (ξ )dξ
0
g = 0.074995 x2 + 2.75.10-6 x4
For the section on pier, i.e. for x = 48.875 – 1.00 m (½ closing segment), this gives Mg = - 186.34 MNm.
At this moment Mg, it is necessary to add the moment due to the known site loads (Qc1) in addition to the
moment due to random site loads (Qc2 and Qc3).
Qc1 ÖMoment due to the weight of the form traveler, assumed to be equal to approximately 40 t, i.e. 0.40 MN,
and exerted at 3.00 m / 2 + 1 m = 2.5 m from the crown:
Qc3 Ö Moment due to a concentrated load of (50 + 5b) kN, with b being the width of the upper slab of the box
girder:
We can therefore consider that: Mg = - 186.34 – 18.55 – 2.51 – 4.70 = - 212.10 MNm. The shape of the moment
curve in cantilever Mg is shown in Figure A1.12 below.
Fig. A1.12 – Bending moment in the cantilever under selfweight + form traveler
Sheath diameter: 81 mm
Concrete: B35
We consider the bridge deck to be cast in-situ with certain precautions taken (presence of empty ducts,
measurement of transmission factors). The strength of the concrete in the segments on piers at the moment of
the casting of final pair of segments is taken to be fcj = 35 MPa. The allowable stress in the upper axis is
therefore:
σt = 0.7 x (0.6 + 0.06 x fcj) – 0.02 x fcj = 0.7 x (0.6 + 0.06 x 35) – 0.02 x 35 = 1.19 MPa
The force N developed by the cantilever tendons in the section on pier must satisfy the following condition:
N M v N e0 v
+ + ≥ σb
B I I
e0 = 2.258 m Öposition of the mean tendon supposing its distribution over two beds
e0 = v - 2 φg with φg = 0.081 m
Mv 212.10 x 2.42
−σb − − 1.19 +
N ≥ I = 41.532 = 46.74 MN
1 e0 v 1 2.258 x 2.42
+ +
B I 9.3129 41.532
46.74
n tendons ≥ ≈ 24 tendons
1.95
to which we add two tendons in order to prestress the final pair of segments.
We therefore have 13 pairs of 12T15S tendons, allowing us to divide the cantilever into 2 x 13 standard
segments of 3.375 m in length (see Figure A1.13 below).
The shape of the moment curve in the cantilever under selfweight and prestressing is given in Figure A1.14
below.
At this stage in the design, it is advisable to make sure that the cantilever tendons are strong enough to take up
the weight of the bridge deck and form traveler during the construction of the central closing segment. To this
end, two vertical forces are applied in a downward direction at each end of the cantilevers (figure A1.15). These
forces represent the effect of the weight of the form traveler and the concrete for the closing segment when still
wet. These forces are exerted on two independent and isostatic structures because, at this stage, the two halves
of the bridge have not yet been connected.
Fig. A1.15 – Effects of the weight of the form traveler and of the closing segment
In this new phase, the forces and stress in the upper horizontal plane along the centerline of the piers can be
expressed as follows:
We have seen in A1.2.7 that the closing segments were constructed in the following order:
The continuity tendons must be determined in reverse order. By starting at the final closing segment, the
hyperstatic effect of the continuity tendons stressed during the previous closing operations is not an unknown.
The continuity tendons for the span P1-P2 must take up the selfweight of the closing segment, the forces
resulting from the removal of the form traveler and the effects of the thermal gradient. In contrast to the other
continuity tendons, they develop both isostatic and hyperstatic moments. Figure Al. 16 below represents the
structure at the moment of the P1-P2 closure.
In order to determine the number of tendons necessary for the closing segment in the central span, we shall
study each phase of the closure and determine its effect on the structure.
A1.4.1.1 - Effect of the selfweight of the closing segment and the form traveler
As mentioned previously, the first stage of the closure can be simulated by applying two vertical forces in a
downward direction at each end of the cantilevers (figure A1.15). In this phase, the bridge deck still consists of
two independent isostatic structures. Therefore, this phase has no bearing on the calculation of the continuity
tendons.
This phase can be broken down into two parts. In the first part, two vertical forces are applied in an upward
direction at each end of the cantilevers (Figure A1.17). These forces represent the effect of the removal of the
form traveler and the concrete used for the closing segment (fresh concrete). In the second part, these forces will
be replaced with a uniformly distributed load directed in a downward direction and representing the set concrete
(Figure A1.18). In this phase, the structure is hyperstatic.
Fig. A1.17 – Diagram of moments due to the removal of the form traveler
At the end of these two stages, the moment to be considered for the calculation of the continuity tendons for the
span P1-P2 is:
Figure A1.19 below represents the bending moment due to a thermal gradient of 12° C.
The value of the moment at the crown used for the calculation of the continuity tendons for P1-P2 is therefore:
The isostatic moment is an unknown and is proportional to the prestressing that is used (Figure A1.20). The
isostatic moment is calculated in the following way:
Miso = N . e0 with N = normal force due to the tendons in the section and e0 = offsetting of the mean tendon
As the structure is hyperstatic when the continuity tendons are stressed, a hyperstatic moment is set up in the
central span which is of the opposite sign to the isostatic moment developed by the tendons. This hyperstatic
moment is an unknown and depends on the intensity and the distribution of the prestressing in the span
(alignment and length of tendons) and on the characteristics of the structure in question (whether or not there is
variation of inertia). The diagram for this is shown in Figure Al.21 below.
Fig. A1.21 – Diagram of the moments due exclusively to the hyperstatic effect of the P1-P2 continuity tendons
At the pre-design stage, it is possible to use a simplification which consists of considering the span to be
embedded on its supports (Figure Al.22). In this case, the hyperstatic moment can be evaluated in the following
way:
Fig. A1.22 – Diagram of moments exclusively due to the hyperstatic effect of the continuity tendons according to a simplified
calculation
Sheath diameter: 81 mm
Concrete: B35
As before, we consider the bridge deck to be cast in-situ with certain precautions taken (presence of empty
ducts, measurement of transmission factors). The strength of the concrete in the segments on piers at the
moment of the removal of the form traveler used for the closing segment is taken to be fcj = 16 MPa. The
allowable stress in the bottom axis is therefore:
σ b = 0.7 x (0.6 + 0.06 x fcj) – 0.02 x fcj = 0.7 x (0.6 + 0.06 x 16) – 0.02 x 16 = 0.77 Mpa
The force N developed by the continuity tendons in line with the closing segment must satisfy the following
condition:
As we do not know the number of tendons required, we also do not know their position in the box girder or their
isostatic moment diagram. Therefore, an iterative calculation is performed, starting with a single pair of tendons
22.25 m long, spanning six segments of 3.375 m and the closing segment of 2 m.
The distribution of the prestressing produces an isostatic moment which is distributed almost uniformly if a
single pair of tendons is used (subject to the variation in e0 and the variation of inertia of the section). The
hyperstatic moment is therefore:
ntendons = 2 fu = 1.95 MN
Fp = 3.90 MN
L = 97.75 m
lc = 22.25 m
In the event of one pair of tendons being insufficient, it would be necessary to repeat the calculation with two
pairs of tendons and recalculate the hyperstatic moment with the newly tendons arrangement.
The continuity tendons for the span C0-Pl must take up the selfweight of the cast-on-falsework section. Figure
Al.23 below shows the structure at the moment the span is closed.
Fig. A1.23 – Detail of the structure during placement of the closing segment on the C0 side
As the cross-section of the bridge deck is 6.0965 m² close to the abutments (h = 2.30 m), the load due to the
selfweight of the cast-on-falsework section is equal to Q = 6.0965 x 0.02453 = 0.14955 MN/m.
As the structure in question is isostatic, we can easily calculate the support reactions and the longitudinal
bending moment using static equations (Fig.A1.24):
Fig. A1.24 – Determination of the forces on the C0 side due to the closure of the span
Support reactions:
⎡∑ F = 0
⎢ M =0 ⇒ RP1 = 0.04238 MN and RC0 = 0.78015 MN
⎣∑
For the 5.50 m long section between C0 and the closing segment, the bending moment is equal to:
Q . x2
M(x) = R C0 . x − so for x = 5.217 m ⇒ M = 2.03 MN.m
2
Fig. A1.26 – Bending moment on C0 side due to the closure of the span
Duct diameter: 81 mm
Concrete: B35
As before, the bridge deck is considered to be cast in place with certain precautions taken (presence of empty
ducts and measurement of transmission factor) and the strength of the concrete is taken to be the value obtained
when the falsework is removed fcj = 16 MPa. The allowable stress in the lower axis is thus:
= 0.7 x (0.6 + 0.06 x fcj) – 0.02 x fcj = 0.7 x (0.6 + 0.06 x 16) – 0.02 x 16 = 0.77 Mpa
The force N developed by the continuity tendons in line with the closing segment must satisfy the following
condition:
N M v' N e0 v '
− − ≥ −σ b
B I I
In principle, no tendons are necessary. However, in order to prevent any cracking due to parasitic phenomena
(obstructed shrinkage, etc.), we shall specify one pair of 12T15S tendons.
The calculation that we have just performed is intended to determine the amount of continuity cabling needed to
consolidate the structure after the removal of falsework from the cast-on falsework section. However, somewhat
higher forces develop in this area after the closure of P1-P2. Indeed, as the structure is now hyperstatic, the
bridge deck becomes sensitive to the effects of thermal gradients, to which is added the hyperstatic effect of the
continuity tendons for P1-P2.
In this new phase, the forces and stress in the lower axis are:
Mg = 2.03 MN
The continuity tendons for the P2-C3 span must take up the selfweight of the cast-on-falsework section. Figure
A1.27 below represents the structure at the step when the span is closed.
Fig. A1.27 – Determination of forces on C3 side due to the closure of the span
A calculation similar to the one performed for the C0-Pl closing segment gives the support reactions and the
bending moment:
⎡∑ F = 0
⎢ M =0 ⇒ RP2 = 0.28374 MN et RC3 = 2.03456 MN
⎣∑
M = 13.57 MN.m
The force N developed by the continuity tendons in line with the closing segment must satisfy the following
condition:
N M v' N e0 v '
− − ≥ −σ b
B I I
6.07
n tendons ≥ ≈ 3
1.95
As before, prior to the stressing of the external tendons, it is important to verify the suitability of the cabling
after the closure of the span P1-P2 and the stressing of the continuity tendons for P1-P2. In this new phase, the
forces and stressing in the lower horizontal plane are:
Mg= 3.57 MN
The external prestress tendons must take up the forces due to the fittings, traffic loads A(l), thermal gradient and
creep. In order to calculate the number of tendons required, we shall proceed in stages:
- Determination of prestressing.
For an initial estimation, we can use certain rules to define the mean alignment of the external prestress tendons.
Longitudinally, we shall place the intermediate deviators for the central span one third of the way along the
span, i.e. at 32.583 m from the centerline of the piers. We shall also place a deviator on the end spans, also at
32.583 m from the centerline of the piers (Fig. Al.28). Remember that the deviators on piers position the
external prestress tendons as close as possible to the upper axis of the bridge deck (negative longitudinal
bending moment, whereas the intermediate deviators position these same tendons close to the lower axis
(positive longitudinal bending moment).
Fig. A1.28 – Longitudinal geometry of alignment for external tendons at end of segments
Transversally on the section on pier, we shall make the minimum distance from the mean tendon to the upper
axis equal to the thickness of the upper slab, i.e. 0.25 m. For the section at the crown, the minimum distance
from the mean tendon to the lower axis shall be equal to the thickness of the lower slab plus 0.15 m. This value
allows a gap of 0.10 m to be left between the sheath of the prestressing tendon and the top of the lower slab
(Fig.A1.29).
A computerized calculation gives us the envelope of the longitudinal moments due to the imposed loads A(1)
(Fig.A1.30).
The characteristic values of the enveloped curve below are used to determine the dimensioning sections and the
verification sections for the external prestressing (Fig.A1.31).
Fig. A1.31 – Position of the sections used to analyze the external prestressing
The following table summarizes the forces due to A(l) and the type of calculation to be performed in each
section.
Sections Moments Type of calculation
Min Max
Σ1 Closing segment C0-P1 - 4.75 MN.m 8.39 MN.m dimensioning
Σ2 - 19.23 MN.m 19.87 MN.m verification
Σ3 Pier P1 - 45.71 MN.m 11.41 MN.m verification
Σ4 Closing segment P1-P2 - 6.36 MN.m 21.62 MN.m dimensioning
Σ5 Pier P2 - 43.50 MN.m 6.40 MN.m verification
Σ6 - 15.50 MN.m 23.63 MN.m verification
Σ7 Closing segment P2-C3 - 9.42 MN.m 19.59 MN.m dimensioning
A1.5.1.3 - Fittings
A computerized calculation is used to obtain the curve of the bending moment due to the fittings. (Remember
that the linear weight of the fittings is equal to q = 47.4 kN/lm).
Fig. A1.32 – Diagram of the moments due to the weight of the fittings
The table on the left summarizes the forces due to the fittings in each section.
Sections Moments
A computerized calculation is again used to obtain the curve of the bending moment due to the thermal gradient
of 12° C.
The table below summarizes the forces due to the thermal gradient in each section.
Sections Moments
A1.5.1.5 - Creep
As an initial estimate, we reserve a margin of 2 MPa for the stress in the lower axis. This reserve is used to
calculate a creep moment in the central span:
M v' I
σb = − ⇒ M = − σb
I v'
4.62
Thus, for the section Σ4: v’ = 1.44 m I = 4.62 m4 M creep = 2 x = 6.42 MN.m
1.44
In the end spans, the moment corresponding to this compression reserve will be determined by a linear
interpolation between M = 0 MN.m on the abutment and M = 6.42 MN.m on the pier.
As the calculations are similar and repetitive, we shall only dimension the external tendons close to the closing
segment sections.
Moment MG1 (state after construction, see Figures Al.17 and A1.18) Ö MG1 = - 4.35 MN.m
Overload A(1) Ö MA(1) min = -6.36 MN.m and M MA(1) max = 21.62 MN.m
Calculation of MQ
MQ =1.2 MA(1) + 0.5 MΔt or MQ = MΔt with the values above gives:
6.73
x = x 32.583 = 21.958 m
6.73 + 3.26
7.067 . n
7.067.n Ö M hyper = − = − 0.072 . n
97.75
Calculation of stress:
σi =
N
−
M .v ' P + Pext
= ecl
M
− max
.v '
−
(
M Pecl + M Pext .v ' )
B I B I I
σi =
(2 x 1.95) + 3.1. n −
47.31 x 1.44
−
[(− 5.14 + 1.17 ) + (− 3.33. n )] x 1.44 σi = (1.546 .n) – 12.87
6.0965 4.620 4.620
Moment MG1 (state after construction - see figures A 1.17,18) Ö MG1 = 0.58 MN.m
Calculation of MQ
MQ =1.2 MA(1) + 0.5 MΔt or MQ = MΔt, which gives the following with the values above:
5.50 5.50
Mhyper = 1.17 − 0.576 = 0.06 MN.m for the continuity and exterior tendons of the span
53.375 53.375
P1-P2
e2 = 2.420-0.25 = 2.17 m
Fig. A1.37 – Isostatic moment diagram for external tendons in span C0-P1
3.26
x = x 32.583 = 10.625 m
3.26 + 6.73
2.163 . n . 2
S3 = (3.26. n .15.292) = - 49.755 . n Ö M hyper = = 0.081 . n
53.375
-2.163 .n
0.081× 5.50 . n
M hyper (Σ1 ) = = 0.008 . n
53.375
Calculation of stress in Σ1
σi =
N
−
M .v ' P + Pext
= ecl
M
− max
.v '
−
(
M Pecl + M Pext .v ' )
B I B I I
σi =
(2 x 1.95) + 3.1. n −
13.88 x 1.44
−
[(− 5.14 + 0.09) + (− 3.25. n )] x 1.44
6.0965 4.620 4.620
σi = (l.524.n)-5.26
Moment MG1 (state after construction - see Figures A1.17 and A1.18)Ö MG1 = 1.11 MN.m
Calculation of MQ
MQ=1.2 MA(1) + 0.5 MΔt or MQ = MΔt which, using the values above, gives:
15.50 15.50
Mhyper = 1.17 − 0.576 = 0.145 MN.m for the continuity and exterior tendons of the span
63.375 63.375
P1-P2
Fig. A1.39 – Isostatic moment diagram of the external tendons in span P2-C3
3.26
x = x 32.583 = 10.625 m
3.26 + 6.73
18.417 . n . 2
S3 = (3.26. n .15.292) = - 49.755 . n Ö M hyper = = 0.581 . n
63.375
-18.417 . n
0.581. 15.50 . n
M hyper (Σ 7 ) = = 0.142 . n
63.375
Calculation of stress
σi =
N
−
M .v ' P + Pext
= ecl
M
− max
.v '
−
(
M Pecl + M Pext .v ' )
B I B I I
σi =
(4 x 1.95) + 3.1. n −
34.18 x 1.44
−
[(− 10.28) + (− 3.113. n )] x 1.44
6.0965 4.620 4.620
σi = (l.480.n)-8.404
The structure consists of two independent bridge decks with a height difference of approximately 6
m. Deep pile foundation shafts (P5: four Ø 2.40 m shafts) or cast-in-situ piles (P2, P3, P4 & P6:
four piles of Ø 1.20 m to Ø 1.50 m)
Internal prestressing
with possibility of
adding extra external
prestressing.
Bourran La
viaduct at Technique
Rodez Française du
Béton
Précontraint,
Contractor:
12th FIP
DODIN Sud
(International
Aug. 1989 - June
Prestressing
1991
Federation)
Congress,
A11 Washington
1994
Revue
Travaux Oct. Engineering geology: risk of landslides
1991 July Deep pile foundation shafts: one Ø3 m or Ø4 m shaft for each pier sunk to depths of 11 to 15 m.
1992
Bridge over La
the Saint- Technique
Denis river on Française du
Béton
Reunion
Précontraint,
Island 12th FIP
(International
Contractor:
Prestressing
SBTPC
Federation)
Aug.1989 - Aug.
Congress,
1991
Washington
A12 1994
Revue Abutment C0, situated directly above a rocky spur embedded in the sand, is supported by two Ø2
Travaux July m deep pile foundation shafts, one of which is extended by micropiles.
1992 The three piers are built on superficial footings.
The ground had to be injected under P1.
A14
A17
A18
A21
Standard segments
built using “from
below” type of form
travelers.
Construction of - On support: Prestressing:
central span in half- h= 11 m - cantilever
cantilevers using s= 1/12 tendons in the
successive 3.60 m - At the crown: upper slab;
long cantilever h = 3.50 m - continuity
segments using form s = 1/39 tendons outside
travelers into which the concrete
the prefabricated stretching from
webs were placed. abutment to
These are of variable abutment;
depth and angle, due - internal
to the variation in continuity
width of the lower tendons in central
slab. span;
- prestressing bar
in web panels.
A23
SECTION ON PIER PILE SECTION AT CROWN Cast-in-situ - On pier: For the bridge deck:
segments. h = 9.00 m - Concrete: 13,900 m3
Length of standard - At the crown: - Non-stressed
segments: 3.30m for h = 3.50 m reinforcement bars:
the 96 m span and 1,711,000 kg (124
3.60 m for the other kg/m3)
spans. - Prestressing:
External 241 t
Internal 728 t
Temporary 22 t
A3 Bibliography
This appendix firstly mentions all of the official french texts relating to the engineering and design of bridges
built by the cantilever method. It then goes on to list a large number of documents and articles dedicated to this
technique.
- Fascicule 61 Titre II of the french CPC: "Programme de charges et épreuves des ponts-routes" (Loading and
testing program for road bridges).
- Circular no. R/EG3 of July 20 1983 entitled "Transports exceptionnels, définition des convois types et règles
pour la vérification des ouvrages d’art" (Oversize loads, definition of standard convoys and rules for the
verification of civil engineering structures) published by the Direction des Routes (Highways Department), for
structures supporting these types of vehicles
- Fascicule 6l Titre IV Section II of the french CCTG: "Actions de la neige sur les constructions" (Effects of
snow on constructions) (DTU P 06-006 of September 1996)
- Fascicule 62 Titre I - Section I of the french CCTG: "Règles techniques de conception et de calcul des
ouvrages et constructions en béton armé suivant la méthode des états limites" (Technical engineering and design
rules for reinforced concrete structures and constructions according to the limit states method) [BAEL 91
revised in 1999)]
- Fascicule62 Titre I - Section II of the french CCTG: "Règles techniques de conception et de calcul des
ouvrages et constructions en béton précontraint suivant la méthode des états limites" (Technical engineering and
design rules for prestressed concrete structures and constructions according to the limit states method) (BPEL
91 revised in 1999)
- Fascicule 65-A of the french CCTG and its supplement: "Exécution des ouvrages de génie civil en béton armé
ou précontraint" (Construction of reinforced or prestressed concrete civil engineering structures)
- Fascicule62 Titre V of the french CCTG: "Règles techniques de conception et de calcul des fondations des
ouvrages de génie civil" (Technical engineering and design rules for the foundations of civil engineering
structures)
- Fascicule 68 of the french CCTG: "Exécution des travaux de fondation des ouvrages de génie civil"
(Construction of the foundations for civil engineering structures)
- Standard NFP 95-104: "Réparation et renforcement des ouvrages en béton et en maçonnerie; spécifications
relatives à la technique de précontrainte additionnelle" (Repair and reinforcement of concrete and masonry
structures; specifications relating to the additional prestressing technique)
- Decree no. 91-461 of May 14 1991 relating to the prevention of earthquake risks and the Order of September
15 1995 relating to the classification and rules for antiseismic constructions applicable to bridges in the “normal
risk” category
- Guide AFPS 92 for the seismic protection of bridges, edited by the Association Française du Génie
Parasismique (French Seismic Engineering Association), published on the presses of the École Nationale des
Ponts et Chaussées (National School of Civil Engineering)
- The french standard NE P 06-013, more commonly called the "Règles de construction parasismique – règles
applicables aux bâtiments - PS92" (Seismic Construction Rules – Rules Applicable to Buildings – PS92), with
regard to foundations.
- Sétra Technical Guide "Appareils d’appui en caoutchouc fretté" (Laminated rubber pot bearings)
- Sétra Technical Guide "Appareils d’appui à pot de caoutchouc" (Rubber pot bearings)
- The guide to the ordering and management of studies for civil engineering bridges
- Fascicule 32.2 of the technical instruction for the monitoring and maintenance of civil engineering structures,
published in 1979 and modified in 1995
- The document entitled "l’Image de la Qualité des Ouvrages d’Art (Iqoa); catalogue des principaux défauts,
aide à leur classification - ponts à poutre caisson en béton précontraint" (Image of the quality of civil
engineering structures [IQOA]; catalog of the major defects and support for their classification – prestressed
concrete box girder bridges) published by Sétra in 1997.
- Analyse structurale des tabliers de ponts (Structural analysis of bridge decks) [J.A. Calgaro and M.Virlogeux]
- Ponts en béton précontraint par post tension (Post-tensioned prestressed concrete bridges) HA - TRL - LCPC –
Sétra
La collection de l’Irex
- Projet National Qualité (National Quality Project) - Opération du Plan Génie Civil (Operation of the Civil
Engineering Plan) – Documentation booklet "Parements en béton" (Concrete facings)
Éditions Eyrolles
- Procédés généraux de construction (General construction process ) – Vol.1 (J. Mathivat and C. Boiteau)
Research, calculations
) Materials
- [MOS 90] J. Mossot: Le viaduc du Champs du Comte, La technique française du béton précontraint (The
Champs du Comte viaduct, The French Prestressed Concrete Technique), Hamburg (1990) U
- [BOU 90] J. Boudot: Le viaduc de Sylans et des Glacières - Les structures triangulées en béton précontraint,
La technique française du béton précontraint (The Sylans et Glacières viaducts – Triangulated structures made
from prestressed concrete, The French Prestressed Concrete Technique), Hamburg (1990) S
- [SER 90] C. Servant, R Gallet, Ph. Lecroq, R Barras: Le viaduc de l’Arrêt-Darré, La technique française du
béton précontraint (The Arrêt-Darré viaduct, The French Prestressed Concrete Technique), Hamburg (1990) S
- [VIR 90.2] M. Virlogeux, G. Lacoste, M. Legall, RY. Bot, J-R Runigo, J. Combault, M. Duviard, G. Suinot
and P. Fraleu: Le pont sur le Loch d Auray, La technique française du béton précontraint (The bridge over the
Loch d’Auray, The French Prestressed Concrete Technique), Hamburg (1990) U
- [VIR 94] M. Virlogeux, E. Bouchon, J.C. Martin, J. Lefevre, Y. Maury, T. Guyot, M. Pottier, A. Heusse, P.
Fraleu, J. Ryckaert, J. Mathivat and B. Lenoir : Pont de Cheviré, La technique française du béton précontraint
(The Cheviré bridge, The French Prestressing Concrete Technique), Washington (1994) U
- [FUZ 94] J-R Fuzier, C. Adib: Poutres de lancement: le pont de Baldwin, La technique française du béton
précontraint (Launch beams: the Baldwin bridge, The French Prestressed Concrete Technique), Washington
(1994) S
- [BOU 94.2] E. Bouchon, E. Conti, D. de Matteis, E Pero, M. Virlogeux, R. Damour, A. Abastado, E Edon, M.
Tassone, A. Demozay, P. Jacques, F. Veyres, C. Lavigne: Le pont de la rivière Saint-Denis à la Réunion (Océan
Indien), La technique française du béton précontraint (The bridge over the Saint-Denis river on Reunion Island
[Indian Ocean], The French Prestressed Concrete Technique), Washington (1994) U
- [CHA 94] P. Chassagnette, J.J. Lagane: Doublement du pont sur la Seine à Gennevilliers, La technique
française du béton précontraint (Doubling the width of the bridge over the River Seine at Gennevilliers, The
French Prestressed Concrete Technique), Washington (1994) U
- [CRO 94] A. Crocherie, G. Gillet, B. Canitrot, F. Edon, P. Kirschner, B. Fournier, F. Renaud, T. Thibaux, P.
Doguet : Les viaducs du Piou et du Rioulong, La technique française du béton précontraint (The Piou and
Rioulong viaducts, The French Prestressed Concrete Technique), Washington (1994) U
- [CAN 94] B. Canitrot, G. Gillet, B. Bouvy, A. Palacci, B. Raspaud: Le pont de l’autoroute A75 sur la Truyère
à Garabit, La technique française du béton précontraint (The A75 highway bridge over the Truyère at Garabit,
The French Prestressed Concrete Technique), Washington (1994) U
- [LEB 94] J-D Lebon, A. Leveille: Le pont de la Corniche à Dôle, La technique française du béton
précontraint (The Corniche bridge at Dôle, The French Prestressed Concrete Technique), Washington (1994) U
- [COM 94] J. Combault, J.P Teyssandier, N.D. Haste, P Richard, M.S. Fletcher, Y. Maury, J. Mac Farlane: Le
second pont sur la Severn, La technique française du béton précontraint (The second Severn Bridge, The
French Prestressed Concrete Technique), Washington (1994) S
- [MUL 94] J. Muller, G. Causse: Le pont à voussoirs préfabriqués de l’autoroute H3 à Hawaï, La technique
française du béton précontraint (The H3 highway bridge made from prefabricated segments in Hawaï, The
French Prestressed Concrete Technique), Washington (1994) S
- [GAS 94] C. Gasaignes, J. Boudot, O. Martin: Ponts à voussoirs préfabriqués en Asie - L’exemple du projet du
KwunTong By-Pass, La technique française du béton précontraint (Bridges built from prefabricated segments in
Asia – The example of the KwunTong By-Pass project, The French Prestressed Concrete Technique,
Washington (1994) S
- [ABE 94] H. Abel, G. Causse, C. Outteryck, D. de Matteis, H. Capdessus, J. Bouillot, B. Grezes, G. Perez, J.
Combault, A. Leveille,Y. Faup, F. Zirk: Le pont d’Arcins sur la Garonne à Bordeaux, La technique française
du béton précontraint (The Arcins bridge over the Garonne in Bordeaux, The French Prestressed Concrete
Technique), Washington (1994) S
- [BAR 94] P. Barras, D. Poineau: Réparation du pont de Blagnac - Études, projet et suivi des travaux, La
technique française du béton précontraint (Repair of the Blagnac bridge – Studies, design and monitoring of
works, The French Prestressed Concrete Technique), Washington (1994) ´
- [VIR 96] M.Virlogeux, J.M. Lacombe, A. Le Bourdonnec: Practical design of cantilever tendons in bridges
built by the balanced cantilever method, FIP Symposium, London (1996)
- [SER 98] C. Servant (Serf), E. Bouchon (Sétra), R. Gachiteguy (Aveyron DDE [Departmental Public Works
Directorate]), J.J. Lagane, P. Chassagnette, V. Preyssas (Spie-BatignoUes TP): Record de portée dans la vallée
du Viaur, La technique française du béton précontraint (Span length record in the Viaur valley, The French
Prestressed Concrete Technique), Amsterdam (1998) U
- [COM 98] J. Combault (Dumez-GTM): Le pont de la Confédération (Ile du prince Edouard - Canada), La
technique française du béton précontraint (The Confederation Bridge [Prince Edward Island - Canada], The
French Prestressed Concrete Technique, Amsterdam (1998) U/S
- [JAC 98] P Jacquet, M. Duviard: Le viaduc de Rogerville, La technique française du béton précontraint (The
Rogerville viaduct, The French Prestressed Concrete Technique), Amsterdam (1998) S
- [MEU 98] P. Meurisse, X. Pham, K. Gharbi, J.P. Viallon: Une nouvelle génération de ponts mixtes: les
viaducs du Boulonnais, La technique française du béton précontraint (A new generation of composite bridges:
viaducts in the Boulogne area, The French Prestressed Concrete Technique), Amsterdam (1998) S
- [BOUS 98.1] C. Bousquet, J.M. Cussac, A. Fauvelle, B. Radiguet : TGV Méditerranée - Lot 2H -Viaducs sur
le Rhône, La technique française du béton précontraint (The TGV Méditerranée high-speed rail line – Package
2H – Viaducts over the Rhône, The French prestressed Concrete Technique), Amsterdam (1998) S
- [BOUS 98.2] C. Bousquet, J.P. Jung, F. Valotaire: Le viaduc TGV de Vernegues, La technique française du
béton précontraint (The Vernegues TGV high-speed rail line viaduct, The French Prestressed Concrete
Technique), Amsterdam (1998) SU
- [DEWI 98] M. De Wissocq, L. Paulik, M. Placidi, J. Vassord: Pont du Vecchio, La technique française du
béton précontraint (The Vecchio bridge, The French Prestressed Concrete Technique), Amsterdam (1998) U
Revue travaux
- [VIR 91.2] M. Virlogeux, G. Lacoste, P Fraleu, M. Legall, P.Y. Bot , J.P Runigo, J. Combault, M. Duviard, G.
Suinot, M. Le Corre: Le pont sur le Loch d’Auray (The bridge over the Loch d’Auray) (June 1991) U
- [JOU 91] A. Jouanno, G. Gillet, B. Bouvy, J.C. Foucriat, J. Goyet: Autoroute A75 dans le Cantal: Les études
du pont sur la Truyère (Studies for the bridge over the Truyère) (October 1991) U
- [BOU 92] E. Bouchon, E. Conti, D. de Matteis, E Vacher, M. Virlogeux, R. Damour, A. Abastado, E. Edon,
M.Tassone, M. Bustamante, A. Demozay, P.Jacques, E Veyres, C. Lavigne: Le pont de la rivière Saint-Denis à
la Réunion (The bridge over the Saint-Denis river on Reunion Island) (July-August 1992) U
- [RIC 93] C. Ricard, J.Jouves, B. Bouvy, Ph. Dhiver: Remise en état du pont de la RD220 sur le canal
d’amenée de la chute de Bourg-lès-Valence (Renovation of the RD220 road bridge over the head race canal for
the Bourg-lès-Valence waterfall) (November 1993) ´
- [HUM 93] E. Humbert, J. Hooghe, X. Durand, Y. Picard: Le viaduc de Limay, Yvelines (The Limay viaduct,
Yvelines) (1993) U
- [BER 95] A. Bernardo: Le pont du Rambler Channel à Hong Kong (The Rambler Channel bridge in Hong
Kong) (April 1995) S
- [CON 95] E. Conti, H. Oudin-Hograindleur: Passerelle tournée sur l’autoroute A4 à Noisy-le-Grand (Rotated
footbridge on the A4 highway at Noisy-le-Grand) (April 1995) U
- [RIC 96] D. Richard, G. Frantz, R Jacquet: Le viaduc de Rogerville (The Rogerville Viaduct) (April 1996) S
- [COM 96] J. Combault, J. Hervet, V.Vesval: Le second franchissement de l’estuaire de la Severn (The second
crossing of the Severn estuary) (April 1996) S
- [BOI 96] A. Boisset, J. Combault, M. Lefebvre, D. Maire: Le pont de l’île du Prince-Edouard (The Prince
Edward Island Bridge) (July and August 1996) U/S
- [MAG 97] H. Magnon-Pujo, B. Deberle: Le viaduc de la Rivoire (Isère). Une construction anticipée pour
faciliter la circulation de chantier (The Rivoire viaduct [Isère] Anticipatory construction in order to facilitate
the movement of site traffic). (July-August 1997) U
- [DEL 98] G. Delfosse, P. Eaure, G. Perez: Confortement par précontrainte additionnelle du pont de la Seudre
en Charente-Maritime (Reinforcement of the Seudre bridge in the Charente-Maritime by additional
prestressing) (February 1998) ´
- [QUI 98] D. Quivy, Y. Deleporte, B.Vincent: A39 - Les viaducs sur le Doubs et la Loue (A39 Highway –
viaducts over the Doubs and the Loue) (February 1998) U
- [DOG 98] P. Doguet: Un grand ouvrage sur l’Agout - Le viaduc de Castres (A major structure over the Agout
– the Castres viaduct) (February 1998) U
- [MON 99] J.Y. Mondon: Le Hung Hom by-pass à Hong Kong (The Hung Hom by-pass in Hong Kong)
(January 1999) S
- [PAU 00] L. Paulik: Le pont du Vecchio en Corse (The Vecchio Bridge in Corsica) (January 2000) U
- [DIEU 00] R Dieuaide: Le viaduc de Digoin (The Digoin viaduct) (January 2000) U
- [DEM 00] A. Demare, G.Tréffot: Le projet du second pont sur le Rhin au sud de Strasbourg (The design of the
second bridge over the Rhine to the south of Strasbourg) (January 2000) U
- [JAE 00] J.M. Jaeger, S. Nunez, JJ. Blanchi, D. Primault: A10 - Le viaduc de la Dordogne (A10 Highway –
The Dordogne viaduct) (January 2000) S
- [DEW 01] V. Dewilde, E. Dallot, E. Tavakoli, D. Guio, D. de Matteis: Passage à l’Euro(code) pour le second
viaduc de Pont Salomon (Transition to the Eurocode for the second Pont Salomon viaduct) (January 2001) U
- [DEM 01.1] A. Demare, G.Tréffot: Second pont sur le Rhin au sud de Strasbourg: Les travaux sont
commencés (Second bridge over the Rhine to the south of Strasbourg: Work has begun) (May 2001) U
- [POR 01] T. Portefaix, C. Roude, L. Rosset: Le viaduc sur la Medway (The Medway viaduct) (December
2001) U
- [BOUT 01] L. Boutonnet: Kingston Bridge à Glasgow (The Kingston Bridge in Glasgow) (December 2001) ´
- [CAY 01] F. Cayron, P. Cote: Un nouveau viaduc ferroviaire dans les nouveaux territoires de Hong Kong (A
new railroad viaduct in the New Territories of Hong Kong) (December 2001) U
- [LAC 02] J.J. Lacaze, D. Giacomelli, M. Duviard, V. Vesval, P. Charlon, C. Sandre: A89 - Le viaduc du Pays
de Tulle (A89 Highway – The Pays de Tulle viaduct) (January 2002) U
- [CHU 02] J.R Chuniaud, T. Jamet, J.M.Tanis, F. Menuel, E. Barlet, R Chatelard, J.R Viailon: Le pont sur le
Bras de la Plaine (Ile de la Réunion): un ouvrage d’exception dans un site grandiose (The bridge over the Bras
de la Plaine [Reunion Island]: an exceptional structure in a magnificent setting) (January 2002) U
- [DEM 02] A. Demare, G.Tréffot: Second pont sur le Rhin au Sud de Strasbourg: La grande travée au-dessus
du fleuve est achevée (Second bridge over the Rhine to the south of Strasbourg: The large span above the river is
finished) (February 2002) U
- [ABE 91] H. Abel-Michel, C. Outteryck, B. Grèzes, G. Ferez: L’exécution du pont d’Arcins (The construction
of the Arcins bridge) (July 1991) S
- [LEC 92] D. Lecointre, D. Lefaucheur: Ferraillage passif des bossages (Non-prestressed reinforcement of
anchor blocks) (January 1992)
- [VIO 93] P.Vion: L’exécution du pont de Villeneuve-sur-Lot (Construction of the Villeneuve-sur-Lot bridge)
(July 1993) U
- [COM 93] J. Combault, B. Flourens: Le pont de la corniche à Dole, de nouveaux plis dans le Jura (The
Corniche bridge at Dole, new undulations in the Jura) (March 1993) U
- [BAR 93] R Barras: La réparation du pont de Blagnac: études, projet et suivi des travaux (Repair of the
Blagnac bridge: studies, design and monitoring of work) (November 1993) ´
- [GIL 93] G. Gillet, B. Canitrot,A. Palacci, D. Froissac, P. Gernigon, B. Bouvy,J. Goyet: Le pont sur la Truyère
à Garabit (The bridge over the Truyère at Garabit) (November 1993) U
- [PER 94] G. Ferez, B.Taimiot: Le renforcement du pont de Bergerac (The reinforcement of Bergerac bridge)
(July 1994) ´
- [JEH 94] J.C.Jehan, J.L. Bernard: La démolition du pont de Beaucaire sur le Rhône (Demolition of the
Beaucaire bridge over the Rhône) (July 1994) ´
- [BOU 94.3] E. Bouchon, J. Lefevre: Pont de Tanus, les effets du vent (Wind effects on the Tanus Bridge)
(November 1994)
- [REl 94] J.M. Reinhard: Le Pont de la corniche à Dole (The Corniche Bridge at Dole) (November 1994) U
- [DEL 94] G. Delfosse, G. Ferez: Renforcement par précontrainte extérieure (Reinforcement via external
prestressing) (November 1994) ´
- [GIL 96] G. Gillet: Contournement de Marvejols: les viaducs du Piou, du Rioulong et de la Planchette (The
Marvejols By-pass: the Piou, Rioulong and Planchette viaducts) (July 1996) U
- [JAC 96] R Jacquet: Le viaduc de Rogerville sur l’autoroute A29 (The Rogerville viaduct on the A29
highway) (July 1996) S
- [TAV 96] F.Tavakoli: Modélisation STl d’un pont construit par encorbellements successifs (STL modeling of
a bridge built by the cantilever method) (November 1996)
- [GAC 98] R. Gachiteguy, G.Viossanges: Le viaduc du Viaur, des fléaux sous haute surveillance (The Viaur
viaduct: cantilevers under close surveillance) (March 1998) U
- [BAR 98] P. Barras: Réparation de l’ouvrage sur le quai Deschamps à Bordeaux (Structural repair on the
Quai Deschamps in Bordeaux) (August 1998) ´
- [PAU 98] L. Paulik: Le pont sur le Vecchio (The bridge over the Vecchio) (December 1998) U
- [DAL 00] F. Dallot, D. de Matteis, V. Dewilde, F.Tavakoli: Passage à l’Euro(code) pour le second viaduc de
Pont Salomon (Transition to the Eurocode for the second Pont Salomon viaduct) (August 2000) U
- [GOD 00] B. Godart, L. Divet: Une nouvelle réaction de gonflement interne des bétons: la réaction sulfatique
(A new internal swelling reaction in concrete: ettringite formation) (May 2000) )
- [TAV 00] F. Tavakoli: Renforcement du pont sur la Saône à Lyon (Reinforcement of the bridge over the
Saône in Lyon) (December 2000) ´
- [DEM 01.2] A. Demare, G.Tréffot: Second pont sur le Rhin au Sud de Strasbourg: études de faisabilité des
BHP (Second bridge over the Rhine to the south of Strasbourg: HPC feasibility studies) (March 2001) )
- [DEM 01.3] A. Demare, G. Tréffot: Second pont sur le Rhin au Sud de Strasbourg: des piles et des fondations
profondes dans le fleuve pour résister aux séismes et aux chocs de bateaux (Second bridge over the Rhine to the
south of Strasbourg: piers and deep foundations in the river to resist earthquakes and impacts from boats) (June
2001) U
- [LEF 02] D. Le Faucheur: Cumul des aciers de cisaillement et des aciers de flexion (Cumulation of shear and
flexion reinforcements) (July 2002)
- [DIV 00] L. Divet: État des connaissances sur les causes possibles des réactions sulfatiques internes au béton
(Extent of the understanding of the possible causes of ettringite formation in concrete) (July-August 2000) )
- [POI 92] D. Poineau, J. Theillout, F. Cusin: Réparation et renforcement des structures de bâtiments et
d’ouvrages d’art; application des techniques de tôles collées et de précontrainte additionnelle (Structural repair
and reinforcement of buildings and civil engineering structures) (February 1992) ´
Techniques de l’ingénieur
- [GEO 96] J.M. Geoffray: Le béton hydraulique - Mise en œuvre (Hydraulic concrete – Application) (May
1996) )
P CI JOURNAL
- [SCH 95] J. Schlaich, K. Schaefer, M. Jennewein: Temperature induced deformations in match cast segments
(July-August 1995)
- [ROB 97] C.L. Roberts-Woolman, J.E. Brein, M.E. Kregle: Towards a consistent design for structural concrete
(May-June 1997)
- [ITA 99] Ing. Salvatore Giuseppe Italiano: II ponte sul fiume Ticino nei pressi di Pavia (January 1999) S
- [ROS 00] Marco Rosignoli: Ponti in C.A.P. ad anime reticolani (May 2000)
- [REN 00] Ing. Marco Renga: Il ponte di Chivaso sulla S.S. 458 di Casalborgone (Torino) (July-August 2000)
S