You are on page 1of 2

New Forms of Construction

Contracts – The JCT & NEC


Design
JCT 05
The Intermediate Building Contract 2005
The new JCT suite of contracts (main and
provides an obligation on the contractor to
sub contracts) are currently in the process of
use reasonable skill and care. This
being published and have been fully
obligation is that of a professional designer
redesigned and updated. The updates have
holding himself out as competent to carry
dramatically changed the JCT Contracts as
out such design work. The Minor Works
we know them with use of plainer English
with Contractor’s Design 2005 however, has
and a change in layout, numbering and
no mention of the level of skill required.
position of clauses.
The Design & Build contract includes a
Key Changes
clause which provides that any inadequacy
in design in the Employer’s Requirements is
The main change is the integration of the
not the responsibility of the contractor.
Private and Local Authorities form of
However, the contractor is still responsible
contract leaving just 3 Standard Building
for checking that the design complies with
Contracts:
any statutory requirements. Moreover, any
inadequacy that requires alteration will be
1. Standard with quantities
treated as a change.
2. Standard with approximate
quantities
Copyright
3. Standard without quantities
A new copyright provision has been
They can now be used by both private and
included which states that Copyright in all
local authority employers.
contractors design documents remain vested
in the contractor
There are a greater number of definitions
and some change of terminology. For
On payment of all monies to the contractor,
instance, ‘Determination’ is now
the employer obtains an irrevocable, non
‘Termination’, ‘Loss & Expense Matters’
exclusive licence to copy, use and reproduce
are now ‘Relevant Matters’ and ‘Defects
the contractors design documents for any
Liability Period’ is now ‘Rectification
purpose relating to the works (but not to
Period’.
reproduce them for an extension of the
works).
Supplements are a thing of the past as
fluctuations, sectional completion and
Payment
contractor’s design portion have all been
incorporated within the contract.
If no withholding notice is served, then the
employer pays the amount stated in the
Project specific information has moved to
payment notice. If no payment notice was
the ‘Contract Particulars’ which is found
served, the amount due is to be determined
immediately after the articles of agreement.
in accordance with the valuation provisions
of the contract.
Future amendments will not be issued
separately as before but incorporated
in the contract and a new version published Insurance
immediately.
The 1998 version usually included an
amendment requiring Professional
Indemnity Insurance. This has now been
incorporated into the contract as a new
clause 6. This new clause requires the NEC3 Framework Contract
contractor to take out Professional If the 8 week deadline is missed the
Indemnity insurance immediately following • A contract between an employer contractor is not entitled to a change in
contract execution. The amount of cover and a number of suppliers for a price, completion date or key dates.
required is listed in the Contract Particulars. period of time.
If no period for expiry is selected, it is 6 However, if the Project Manager failed to
years from the date of Practical Completion. Procurement & Contract Strategies notify the Contractor of his decision and the
Contractor had notified him of this and he
Third Party Rights & Collateral • A user’s guide for the NEC3 still failed to receive a decision, then the
Warranties contracts in various procurement Project Manager is treated as accepting the
and contract strategies. event as a compensation event and the
The employer can require the contractor to Contractor can then submit quotations.
enter into a collateral warranty or the New Clauses
Contract (Rights of Third Parties) Act can Termination
be used instead. If no choice is made, a Clause 25.2 states that any costs incurred by
schedule of third party rights is the employer due to the contractor not ‘Disputes & Termination’ is now known as
incorporated. JCT have also published a providing the services contained in the ‘Termination’. Disputes have been moved to
standard form for each collateral warranty. works information should be borne by the W1/W2. W1 for use where the Housing
contractor. Grants Construction and Regeneration Act
Termination does not apply and W2 where it does. The
Clause 43.4 provides for the Project new clause 19 covering ‘Prevention’ is also
In the 1998 versions, certain insolvency Manager to arrange access to the works for added as a new reason for termination.
events would result in automatic termination the contractor to correct defects. Once
but now the employer must serve notice access is provided, the defect correction Risk & Insurance
before any termination. period begins.
Although the employer still has to submit
Adjudication Clause 19 is a new clause inserted to deal his insurance policies and certificates as in
with rare events and how to prevent and NEC2, the contractor is now only obliged to
Adjudication is much simpler. The statutory deal with them. Such events are now also submit his insurance certificate signed by
adjudication scheme applies so Adjudication compensation events. the insurer.
is now carried out in accordance with the
Scheme for Construction Contracts. If the Secondary Option Clauses The contractor must have appropriate cover
Contract Particulars are not completed, the until a defects certificate or termination
default position is that disputes will be Secondary Option Clauses are now X certificate has been issued.
settled through litigation rather than clauses so that they can be used across the
arbitration as it was in the 1998 versions. whole suite of contracts. Conclusion

New Contract There are 2 new X clauses; Although the revisions of both contracts
have made them easier to use there have
The new Framework Agreement has been X18 Limitation of Liability which limits the been significant changes. Therefore, careful
designed for the procurement of Contractors liability for indirect and consideration of the Contracts and legal
construction and/or engineering works over consequential loss and also provides for an advice should still be sought prior to use as
a prescribed period of time and comes in a overall cap on liability. amendments may still be required.
legally binding and non binding form. It
covers how the parties should work together X20 Key Performance Indicators (KPI’s).
and how the framework agreement works This includes an incentive schedule which
with the underlying contract. sets out the amount to be paid to the CONTACT DETAILS
contractor if KPI’s are improved or For further information or
achieved. assistance contact Jonathan
NEC3 Hawkswell or David Kilvington
Payment
The NEC has also been completely revised Hawkswell Kilvington LLP
and updated with new clauses, terminology 17 Navigation Court
When assessing the amount due, the
and the introduction of new contracts. Calder Park
assessment interval runs from completion of
Wakefield
the whole of the works to four weeks after
As with JCT05, defined terms have WF2 7BJ
the issue of the defects certificate.
expanded and changed such as ‘Actual
Cost’ becoming ‘Defined Cost’, ‘Possession Tel: 01924 258719
Early Warnings
Date’ becoming ‘Access Date’ and the Fax: 01924 257666
addition of the terms ‘Key Dates’ and ‘Risk Email: enquiries@thkp.co.uk
A new risk register is to be maintained by
Register’. Web: www.thkp.co.uk
the Project Manager with all early warning
matters listed therein. The early warning This bulletin is not intended to be a
New Contracts
meetings referred to in NEC2 are now definitive analysis of the law and
referred to as Risk Reduction Meetings. professional advice should be taken before
NEC3 Term Service Contract any course of action is pursued.
© THKP 2003
Compensation Events
• Used to engage suppliers for
managing and providing a service
The period for notifying compensation
over a specific term (not just for
events has been extended from 2 weeks to 8
use in the construction industry).
weeks from becoming aware of the event.

You might also like