Project: Center for the Arts Contractor: Holder Date: 12/6/11 Report Number: 12 Day: Su M T W Th F S
Work Performed: At this point during the day it had been raining for a while. I noticed that there were not any workers on site at the time. The only work I saw being done happened to be an office modification.
Weather
Temp: 56 Degrees F Wind: Slight Condition: Heavy Rain Humidity: Little
Equipment at Site Dump Truck (1) Crane (1) Formwork All Terrain Forklift