NNN CONSTRUCTION SERVICES

10/20/2023
CONSTRUCTION SITE DIARY DATE (MM/DD/YYYY)
Project Name: Weather at [Time am/pm]
Location: [Condition ofWeather]
Prepared By: [Temperature]
Project No. Reference No.:
Contractor : Weather at [Time am/pm]
Ground Conditions: (Dry, Wet, Frooze,Damp) [Condition ofWeather]
[Temperature]
SITE ATTENDACE No. of Men PROJECT STATUS

Record any changes or problems affecting the work:


Equipments on Job No. Units

COMMENTS

___________________________ Site Manager: _________________________


Signature
Date: _________________________
NNN CONSTRUCTION SERVICES
10/20/2023
CONSTRUCTION SITE DIARY DATE (MM/DD/YYYY)

Project Name: Glass Doors and Windows Installation Weather at 8:00 am


Location: Punta 110 Building, Punta Princesa, Cebu City, 6000 Possible light Rain
Prepared By: Eng. Nikki Marie A. Cabahug Temperature: 27° C
Project No. 116-23B Reference No.: 10-227-23
Contractor : Weather at 4:00 pm
Ground Conditions: (Dry, Wet, Frooze,Damp) Mostly Sunny
Dry Temperature: 32° C
SITE ATTENDACE No. of Men PROJECT STATUS
Site Manager 1
Installer 5
1. Windows installed on the ground floor, proceeding as planned
Supervisor 1
2. Glassdoor frames assembled and ready for installation
Glazier 3
3. Weather conditions delayed exterior window installation
Helper 2
4. Half of the windows are glazed and sealed for airtightness
Safety Coordinator 1
5. On-site glass cutter repaired and back to work
Masons 4

Record any changes or problems affecting the work:


Equipments on Job No. Units
DELAYS
Scissors Lift 1 Type Description Time
Boom Lift 1 Adversed Installation postponed due to
Glass Handling Equip. 1 Weather extreme weather conditions like Two-hours lost
Glass Cutter 4 Conditions heavy rain or high winds.
Sealant Guns 3 URGENT ITEMS
Power Drills 5 Type Description Time
Scaffolding 10 Window Frame Run out 10:50 am
Scaffolding Lacking of scaffolds to 2F 2:10 pm

SAFETY INSPECTION
COMMENTS Yes No Incident
/ Inadequte Weather Conditions
/ Noise Pollution
*The scaffold stability issue was / Equipment Malfunction
resolved quickly. SITE VISITORS
*Safety reminder meeting held Names Purpose
following an incident. visit the site to inspect the progress and ensure that
Owner the installation of glass doors and windows aligns
with their expectations and requirements.

___________________________ Site Manager: Engr. Nikki Marie A. Cabahug


Signature
Date: 10/20/2023
NNN CONSTRUCTION SERVICES
10/18/2023
CONSTRUCTION SITE DIARY DATE (MM/DD/YYYY)
Project Name: Glass doors and windows Installation Weather at 8:00 am
Location: Punta 110 Building, Punta Princesa, Cebu City, 6000 Sunny
Prepared By: Engr. Nemey Gian D. Arnado Temperature: 32° C
Project No. 116-23B Reference No.: 10-227-23
Contractor : Weather at 4:00 pm
Ground Conditions: (Dry, Wet, Frooze,Damp) Mostly Sunny
Dry Temperature: 30° C
SITE ATTENDACE No. of Men PROJECT STATUS
Site Manager 1
Architect 2
Foreman 1 • Glass Windows for ground floor is ready for installation.
Installer 4 • Discussion for possible redesigning for second floor.
• Scaffolding ready for assembly.
Safety Officer 1
Helper 2
Driver 1

Equipments on Job No. Units Record any changes or problems affecting the work:
WORK STOPPAGE
Glass Cutter 2 Requested by:
Glass Handling Equip. 1 Client – Ms. Alaine Tess Cabije
Power Drills Set 4 Approved by:
Project Manager – Engr. Nemey Gian D. Arnado
Scissor Lift 1
CHANGE ORDERS
Old Order New Order
Installation of Glass Windows for Reassessing of installment location
Ground Floor and redesigning of plans for second
floor with Client.
INSUFFICIENT MATERIALS/TOOLS
COMMENTS No. of Materials
Materials/Tools
On-Site Needed
Glass Cutter 2
• Meeting will be needed for Glass Handling Equip. 1
the discussion of new Power Drills Set 4
plans. Scissor Lift 1
• More manpower to catch up Measuring Tools 1 Set
delays.

_ Site Manager: Engr. Nemey Gian Arnado


Signature
Date: October 18, 2023
NNN CONSTRUCTION SERVICES
CONSTRUCTION SITE DIARY 10/19/2023
DATE (MM/DD/YYYY)

Project Name: Glass Door and Windows Installation Weather at 8:00 am


Location: Punta 110 Builing, Punta Princesa, Cebu City, 6000 Possible light rain
Prepared By: Engr. Niña Rosette Agarin Temperature: 25° C
Project No. 116-23B Reference No.: 10-227-23 Weather at 4:00 pm
Contractor : Mostly Sunny
Temperature: 31° C
Ground Conditions: (Dry, Wet, Frooze,Damp)
Dry
SITE ATTENDANCE No. of Men PROJECT STATUS
Site Engineer 1
Foreman 1 1. The client's onsite management office declined to stop the operation
within the affected area of the project.
Technician 1
2. Worker accidentally damages a project material; the reimbursement
Helper 2
process is underway.
3. The preceding project failed in commissioning and is currently under
investigation and processing for reimbursement under project insurance.

Record any changes or problems affecting the work:


Equipments on Job No. Units
Delay Client Management Approval
Caulking gun with sealant 1 Confliction Type Description Resolution
Power drill 2 Opposition Have different views Meeting with client's
Pry bar 1 about temporarily management to meet halfway.
Putty knife 2 stopping operations.
Safety Glasses 5 Work Material Damage
Unit Material Will be reimbursed?
1 Glass Panel Yes

Failed Project Commisioning


Is project done to
COMMENTS Casualties Resolution
standard?
Client's onsite management office has to Project continuity will depend
understand the contractor's side to have a Labor and
Yes on the results of the
smooth and safe project execution. materials
investigation.

Site Manager: Engr. Niña Rosette Agarin


Signature
Date: 10/19/2023___