Hotel Pre‐opening Checklist
Bali Hospitality Professional Services ‐ agustinus.aguspurwanto@ehotelier.com
TIME CONTROL
Line
Task Name Duration Actual Finish Followed Up By:
No.
Start Date Finish Date
26 Sales Tax Permit 30 days
27 Third Party Agreements 116 days
28 Leases 116 days
29 Retail 116 days
30 Develop Standards of Performance 10 days
31 Develop RFP 1 days
32 Release RFP
Release RFP 10 days
33 RFP Deadline 45 days
34 Lesee Selected 10 days
35 Lease executed 30 days
36 Employee Orientation 10 days
37 F & B 116 days
38 Develop Standards of Performance 10 days
39 Develop RFP 1 days
40 Release RFP 10 days
41 RFP Deadline 45 days
42 Lesee Selected 10 days
43 Lease executed 30 days
44 Employee Orientation 10 days
45 Financial Reporting 30 days
46 Daily Revenue Report 5 days
47 Daily Labor Report 5 days
48 Period Financial Statements 10 days
49 Peiod Ending Management Report 30 days
50 Planning 90 days
Agustinus Agus Purwanto
Hotel Pre‐opening Checklist
Bali Hospitality Professional Services ‐ agustinus.aguspurwanto@ehotelier.com
TIME CONTROL
Line
Task Name Duration Actual Finish Followed Up By:
No.
Start Date Finish Date
51 Proforma 30 days
52 Annual Strategic Plan 30 days
53 Complete First Year Operating Budget 30 days
54 Complete Pre‐opening Budget 30 days
55 Develop forecasting program 30 days
56 3 days Forecast (Rooms) 5 days
57 10 days Forecast (Rooms and F & B)
10 days Forecast (Rooms and F & B) 5 days
58 Weekly Forecast (Total Property) 30 days
59 I.T 146 days
60 Manual Back Up ‐ S.O.P's 66 days
61 Timekeeping System 10 days
62 Telephone System 10 days
63 Simplex 10 days
64 Payroll System 10 days
65 OCV 10 days
66 Back Office System 10 days
67 Sales & Reservation System 10 days
68 PMS 10 days
69 POS 10 days
70 System 146 days
71 PMS 146 days
72 Develop RFP 20 days
73 Develop Business Process 10 days
74 Determine Workstation: Amount and Location 5 days
75 Determine Budget 5 days
Agustinus Agus Purwanto
Hotel Pre‐opening Checklist
Bali Hospitality Professional Services ‐ agustinus.aguspurwanto@ehotelier.com
TIME CONTROL
Line
Task Name Duration Actual Finish Followed Up By:
No.
Start Date Finish Date
76 Release RFP 1 days
77 RFP Deadline 30 days
78 System Selected 5 days
79 System Specifications Determined 5 days
80 System Installed & Tested 75 days
81 System Training 10 days
82 POS 146 days
83 Develop RFP 20 days
84 Develop Business Process 10 days
85 Determine Workstation: Amount and Location 5 days
86 Determine Budget 5 days
87 Release RFP 1 days
88 RFP Deadline 30 days
89 System Selected 5 days
90 System Specifications Determined 5 days
91 System Installed & Tested 75 days
92 System Training 10 days
93 Keylock System 146 days
94 Develop RFP 20 days
95 Develop Business Process 10 days
96 Determine Workstation: Amount and Location 5 days
97 Determine Budget 5 days
98 Release RFP 1 days
99 RFP Deadline 30 days
100 System Selected 5 days
Agustinus Agus Purwanto
Hotel Pre‐opening Checklist
Bali Hospitality Professional Services ‐ agustinus.aguspurwanto@ehotelier.com
TIME CONTROL
Line
Task Name Duration Actual Finish Followed Up By:
No.
Start Date Finish Date