AUTHORIZATION FLOW CHART .
FACILITY-CENTRE NOTIFICATION TO TAEC
REGULATORY STAFF ASSIGNED
No
REPORT AND COVERING LETTER TO INCLUDE MISSING INFORMATION
ARE ALL NECESSSARY INFORMATIONS INCLUDED?
Yes
REGULATOR EVALUATE
PERSON AT RISK
RADIATION HAZARDS
MEASURES IN PLACE
DOCUMENT FINDINGS
REVIEW AND AMEND
REGULATOR ASSESS IF INSPECTION IS NECESSARY
No
INSPECTION REQUIRED?
Yes
NOTIFY THE CLIENT INSPECTION AND NECESSARY CHARGE REGULATORY REPORT
FACILITY PAY NECESSARY CHARGES
TECHNICAL COMMITEE INSPECTION AT FACILITY REGULATOR FILL THE LICENCE FORM DIRECTOR APPROVE THE LICENCE LICENCE SENT TO CLIENT
PRE AUTHORIZATION INSPECTION AT FACILITY
TANZANIA ATOMIC ENERGY COMMISSION |RADIATION CONTROL DIROCTORATE | Eng ABDALAH KILEO