Alexandria University
Faculty of Engineering
Structural Eng. Dept.
Post Graduate
Computer Applications in Construction Management
(02-523)
Final Exam (June, 2012)
QUESTION 1 (40%)
By using the feature of Primavera, Pg:
Time Allowed: 2 Hrs.
+ How to create the dictionary calendars based on the following information:
[Cat ‘Weekends Holidays Exceptions
T Sunday Zand 23 Jan. 2012 =
2 Friday 15 Feb. 2012 17 Feb. 2012
‘+ How to create suitable Enterprise Breakdown Structure “EBS”, for Arab Contractor Company?
‘+ How to insert successor activity using finish to finish relationship?
* How to create suitable Work Breakdown Structure “WBS”, for constructing a villa?
* How to create suitable Organizational Breakdown Structure “OBS”, for Arab Contractor Company?
‘+ Mention briefly the project management cycle and what are the phases used for Pe?
‘+ How to add the following Project information:
Project Name Pump Station
Planning Unit Day
Project Start Date | 4 Jan, 2012
‘Weekends Friday and Sunday
Project Finish Date | 23Feb.2012 |
QUESTION 2 (30%)
‘What is the difference between?
+ WBS & WPS;
+ OBS & EBS
‘© Hammock Activity & Milestone
+ Task Activity & Flag Activity;
* Free Float & Total Float;
Activitys
‘+ Interfering Float & Independent Float; and
‘+ Critical Activity & Dummy Activity.
QUESTION 3 (30%)
The following table illustrates the
ties of a small project:
Activity | _OD Typeof | Lag ] weekend | Holiday] Exception
TD | Days) | Predecessor | Retationship | Days)
A 10 = = =| Friday [18 an, 2012 | 20Tan, 2012
B 12 A 38 4 = [20Jan.2012 |
c 9 B FF 2 | Sunday [24 Jan. 2012 | 22 Jan, 3013
A SF 6
D 7 a SF 6 | Friday ~ | a7san.2012
* If project start date is Saturday 14 January 2012, find activity early and late dates?
Good Luck
1 Of 1 Page Dr. Remon F. Aziz~~ Faculty of Engineering
Structural Eng. Dept.
Alexandria University
Post Graduate
CONSTRUCTION ENGINEERING
Final Exam (January, 2012) (02-533) Time Allowed: 120 Min.
Qeesiuns 1 (20%)
‘What are the earthmoving duties? E
Mention the types of excavating; and loading Equipment?
Prove the formulas that give average value of an Equipment? .
What is meaning of job conditions; and management conditions?
What are the factors should be considered for selecting equipment?
eaore
Question 2 (30%)
Calculate the expected hourly cost scraper described below assuming straight line depreciation:
+ Initial cost is 94000 $;
© Useful life is 8 years;
* Salvage value is 6000 $
© Power is 200 HP;
* Crankcase capacity is 5 Gallon;
«Time between oil changes is 120 hours;
© Operating factor is 0.7;
© Unit cost of fuel is 1.35 S/gallon;
* Unit cost of lubrication is 4.55 $/gallon;
# Grease cost is 1.2 S/hr;
+ Tax, insurance, investments,.... ete. are 20%;
© Repairs and maintenances are 80% of annual depreciation;
* Tires cost is 30008;
«Tires life time is 3000 hrs; and
© Operating time is 1400 hrs.
Question 3 cow
‘A company purchases an equipment by 12000 §, it is estimated that equipment useful life = 4 years, and
salvage value = 4000 $.
It is required to find:
© Depreciation amount; and
«The book value of equipment a long life time using:
1, Suaight Line Method;
2. Sum of Year Method; and
3. Double Declining Balance Method.
Page 1 of 2 Dr. Remon €. Aziz,Structural Eng. Dept.
Post Graduate
Final Exam (January, 2012) (02-533)
Question 4 0%)
A hydraulic excavator, is required to excavate the basement, which is divided into 10 panels, the panel
dimensions equal to 20* 10 m? as shown in the Figure, knowing that:
* Excavator bucket capacity is 1.57 m°;
Material is sand;
Bucket fill factor is 0.8;
Average depth of cut is 4.5 m;
Maximum depth of cut is 6.4 m;
Angle of swing is 75 °;
Job efficiency is 48 min hr.;
Working hours per day are 8 hours:
Natural soil weights equal to 1500 kg/m’;
Loose soil weights 1350 kg/m; and
Compacted soil weights 2000 kg/m.
REQUIRED: How many days are taken to finish that work?
20m 20m 20m
3.9m) 28m) sm)
tom
29m) am) [2.0m) (2m
10m
1.4m) (10m)
22m) Kom) (4m)
10m
1.5 m) (1.0m)
f—______|sm) 0 mj
rein) (5m) Plan of Basement
10m
Lam) Lm)
(Excavation Depth in meter)
Standard cycles per hour for Excavator
; Small machine Medium machine Large machine
ete meus (0.74 m’) (0.75 m?: 1.75 m?) 1.76 m’)
Sand 250 200 150
Soft clay 200 160) 120
Rock 160 130 100
Swing ~ Depth factor for Excavator
Depth of cut “Angle of swing (degree)
(% of Max.) as _ 78 [ 90 120
30 133 1.26 21 Saari 1.08 |
30 128 121 116 1.10 1.03
70 1.16 110 1.05 1.00 0.94
39 1.04 100 | 095 — 0.95 0.85
Page 2 of 2 7 NTO Dt Remon Aciz