0% found this document useful (1 vote)
259 views6 pages

Taunsa Barrage Cofferdam Case Study

The document summarizes the construction of a cofferdam and dewatering process for the rehabilitation of the Taunsa Barrage project in India. A civil works contractor built half of the weir and rehabilitated half of the barrage bays by constructing a cofferdam upstream and downstream to isolate the work site. Over 300,000 cubic feet of stone and earth fill were used to construct the barrier, which had to withstand 300,000 cubic feet of flood water per second. Fifty to sixty tube wells and eight generators providing 3MW of power were used to dewater the site within four 700 foot wide enclosures. Heavy equipment like dump trucks, dozers, backhoes, and vibrating pile hammers

Uploaded by

jaideep
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (1 vote)
259 views6 pages

Taunsa Barrage Cofferdam Case Study

The document summarizes the construction of a cofferdam and dewatering process for the rehabilitation of the Taunsa Barrage project in India. A civil works contractor built half of the weir and rehabilitated half of the barrage bays by constructing a cofferdam upstream and downstream to isolate the work site. Over 300,000 cubic feet of stone and earth fill were used to construct the barrier, which had to withstand 300,000 cubic feet of flood water per second. Fifty to sixty tube wells and eight generators providing 3MW of power were used to dewater the site within four 700 foot wide enclosures. Heavy equipment like dump trucks, dozers, backhoes, and vibrating pile hammers

Uploaded by

jaideep
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd

CASE STUDY

COFFERDAM CONSTRUCTION AND DEWATERING TAUNSA BARRAGE


REHABILITATION PROJECT

INTRODUCTION
Taunsa Barrage is located on the river of Indus river in the region of Punjab, India. The irrigation system
is connected to all the rivers through a series, this process is done by diverting the river water in sequence
to barrages then releasing the water into main canals and eventually to the network where water is
distributed to small channels. The taunsa barrage was built in 1958 in such a way that four main canals
were constructed with two canals on either side of the barrage. The barrage consist of 65 gates which
were divided with a thickness of 7 feet piers with a total width of the structure constituting to 4,346 feet
and was designed in a way that 1,000,000 cusecs of flood can pass through the barrage.

Figure: Taunsa Barrage


PROJECT DESCRIPTION
The civil work contractor for the project was Descon Engineering Limited (DEL) in association with
China Gazooba Corporation (CGGC) and they were selected under international competitive bidding. The
process of rehabilitation was planned in a way such that in first year they construct half of the weir and
rehabilitate half bays of the barrage. This rehabilitation work consist of strengthening the old concrete at
chute and basin floor, for this the cofferdam was built on the upstream and downstream of the restoration
site.

Figure: Early stage of Construction

Figure: Construction of Cofferdam at front and back of the enclosure

It was constructed in such a way that the barrier across the barrage could resist to a greater maximum
observed flood of 300,000 cusecs for non-monsoon and monsoon seasons. Thus taking this kind of
precautions made all satisfactory factor of safety to divert and also the height of the cofferdam. There was
also a periodic monitoring of the rise of water level and flow of river, which made them to build the head
across the barrage within 15 ft and design head being at 24 ft across the barrage.

The major cost region of the project was estimated to be at $60 million and other works like maintenance
of dam and securing of water was estimated to be around $ 14 million. Rest all schedules and planning
was done to get all those materials and equipments to the site at right time.

CONSTRUCTION PROCESS OF COFFERDAM


In the initial stage of the construction materials like stone and earth fill was brought to the site to dump in
the upstream and downstream of the river in large quantities to construct the sub weir. In this kind of
construction the major equipments used are excavators, dozers and dumpers. These dumpers dump the
stone on top of the embankment whereas dozers move across the flowing water and also the earth fill
material was dumped from top so that it settles down. But during the built up of the cofferdam it should
be monitored keenly time to time thus to safe guard the area as well as to place the materials over the
settled area.
The major advantage while constructing the cofferdam was the continual supply of the materials like
stone and earth fill which were maintained at the site with a scheduled supply. As the construction work
approached the center of the river channel there was a constant rise in the velocity which required more
materials timely to make sure the progress was going in a planned way. This is because of having limited
time to build the cofferdam, activity of constructing the cofferdam became a major priority and no other
activity is carried out till the completion of the cofferdam.

Figure: Dumper unloading stones

Material quantities for constructing a cofferdam:


Stone

100,000 cft (3000m3)

Sheet piles

224,000 sft (Area), 35 40 ft (Depth)

Sand bags

60,000 No

Earth filling

11.46 M cft (324,394 m 3)

DEWATERING
In the process of construction of coffer dam, the next step is dewatering. Dewatering method requires a
lot of pumping of water with certain measures like maintain the water levels to a desired point. The main
equipments used for dewatering are tube wells, pumps and screens for concreting at required different
areas of the compound.
Sheet piles analysis and overall stability is calculated in a software called SEEP/W for cofferdam section
seepage. Thus a realistic model is available where for different parameters sensitivity analyses is done.
Eventually based on these results a sheet pile is installed.
In the primary phase of work, single enclosure for construction of sub weir has been planned. After a keen
analysis for the flow conditions across the barrage it was decided to construct a four 700 ft wide
enclosures instead of having a one single enclosure of 2800 ft length. Subsequently, to lower down the
water table 50 to 60 tube wells were required in each enclosure of 700 ft. Being large portioned area in
spite of having pumps and generators there was extra capacity provided for keeping the project to run
swiftly.
Generation of power supply being a challenged task, the pumps required 3 MW for which eight
generators of sets 375 kVA was provided. As two generators required for dewatering there was stand by
generator provided thus making sure that there is no interruption of power supply. Thus the pumped water
was directed to the surrounding water bodies.

Figure: Construction of Sub Weir

Figure: Cofferdam with sheet piles during dewatering

EQUIPMENTS USED
Heavy equipments were used during the construction of the cofferdams, such as

Loaders and Dump trucks


Dozers
Backhoe

Dewatering pumps tube wells along with pumps and screens


Vibrating pile hammer

Each machinery used constitute a weight around 10 15 tons which can move freely on newly
constructed embankment. Usually stone dump was built then was followed by earth fill dump. The stone
is dump in reverse on top of the embankment by the dumper during the construction.

You might also like