100%(1)100% found this document useful (1 vote) 5K views42 pagesCCDC 24
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content,
claim it here.
Available Formats
Download as PDF or read online on Scribd
Standard construction document CCDC
Nee lio: (Deopog
a lelnnee Ble
eectster Feed
Prf rach vee
a guide to model forms
and support documents
(for use with CCDC 2 - 1994)
[cC [C B [C Canadian Construction Documents Committee‘Standard Construction Document CCDC 24 —
TABLE OF CONTENTS
Page
INTRODUCTION 1 CHANGE PROCESS
Proposed Change Form
~ Guideline
PREQUALIFICATION OF CONTRACTORS 2 boom
CContactor’s Qualifcation Statement Standard Fon 2 ~ Model Form
Speers ‘Change Onder Form
= a = Guidetine
= CCDC 11 (See Appendix A) ase
= Model Form
FINANCIAL INFORMATION REQUIRED OF THE Change Directive Form
OWNER 4 = Guideline
: ~ Checklist
Project Financial Information Standard Form
= Guideline ~ Model Form
= Checklist Summary of Changes Form
= CCDC 12 (See Appendix B) ~ Guideline
= Checklist
~ Model Form
ete 7 Combined Proposed Change and Change Order Form
Application For Payment Form 8 ~ Guideline
~ Guideline ~ Checklist
= Checktst = Model Form
= Model Form
Schedule of Values and Work Performed Foon 10
< NOTIFICATION PROCESS
= Checklist Notice Form
= Model Fon ~ Guidetine
~ Checklist
(Cerificate For Payment Form 3
~ Guideline ao
~ Checklist
Dome WARRANTY NOTIFICATION
Stnsor Decuton Sur Foms ee
Guide ~ Guideline
= CCDC 9A, 9B, and 9C (See Appendix C) coo
CCenificate of Substantial Performance 8 ~ Model Form
~ Guideline
Product Warranty Notice Fonm
See = Guideline
= Checklist
‘SUPPLEMENTAL INSTRUCTION PROCESS 9 a.
Supplemental instruction Form 19
~ Guideline APPENDIX
~ Checklist
‘A CCDC 11 — Contractor's Qualification
~ Model Fonn a
CBE
CCDC Copyright 1996
B CCDC 12 - Project Financial Information
C CCDC 9A, 9B, and 9C - Statutory
‘Declaration Forms
D Definitions In CCDC 2 - 1994
199¢
2
23
27
29
31
33
33
36,
38‘Standard Construction Document CCDC 24 ~ 1996
A GUIDE TO MODEL FORMS AND SUPPORT DOCUMENTS
(for use with CCDC 2 - 1994)
INTRODUCTION
The CCDC Stipulated Price Contract Form, CCDC 2 - 1994 (CCDC 2), refers either expressly
cr by implication to a number of administrative processes and forms. The purpose of this Guide
is to assist users of CCDC 2 in meeting the administrative requirements outlined in that standard
Contract Form by providing examples of model forms for these processes. For each model form
the Guide contains:
7 a brief explanation of each of the administrative processes involved,
+ a short narrative description to guide users of the form,
a a list of items which should be included in the form, and
+ an example of a model form.
Most of the administrative requirements contained in CCDC 2 are also common to both CCDC
3 — Cost Plus Contract Form and CCDC 4 — Unit Price Contract Form. The information in this
Guide therefore also may be of assistance to users of CCDC 3 and CCDC 4. The model forms
may require revision when used with CCDC 3 and CCDC 4 to ensure conformity with the
specific administrative requirements of those standard Contract Forms. The Committee
emphasizes that reference should be made to the actual Contract Form with respect to the
appropriate administrative requirements to be applied. For information as to use of CCDC
2 — 1994, refer to CCDC 20 - ‘A Guide to the Use of CCDC 2 - 1994"
With the exception of the Standard Forms CCDC 11 - ‘Contractor's Qualification Statement’
(Appendix A), CCDC 12 ~ ‘Project Financial Information’ (Appendix B), and CCDC 9A, 9B,
and 9C ~ ‘Statutory Declaration Forms’ (Appendix C), users may reproduce or reprint the Model
Forms for this purpose. Users may consider colour-coding the Model Forms for ease of
identification in contract administration,
Many Owners, Consultants, and Contractors successfully use their own administrative forms for
contract administration. The Committee encourages the use of forms which are compatible with
CCDC documents and contain the same information as outlined in this guide. The content of
existing forms should be reviewed to ensure that they contain the required information identified
in the checklist.
NOTE:
‘This Guide refers to capitalized and italicized terms which are defined in the DEFINITIONS in
CCDC 2 - 1994 and are reproduced in Appendix D.
CCDC 24 - 1996 1PREQUALIFICATION OF CONTRACTORS
For a Project involving complex work or a tight schedule, the Owner may call for
Prequalification prior to bid call by requesting Contractors to submit their qualifications. ‘This
allows preselection of those Contractors who are best qualified for the Project.
Contractor's Qualification Statement Standard Form
Guideline
Care should be taken when determining prequalification criteria to request information relevant
to the preselection review. The Owner may choose to request additional qualifications to those
specified in the Contractor's Qualification Statement in order to suit specific Project
requirements, These additional qualifications can be inserted in the space provided or in
additional pages if required. All the qualifications should be carefully investigated based on a
predetermined set of criteria,
‘The Contractor may indicate in the statement certified qualifications of the Contractor and the
Contractor's employees. These include quality management, quality assurance programs, and
construction safety programs or records.
CCDC 11 = ‘Contractor's Qualification Statement’, as shown in Appendix A, is the Standard
Form for obtaining information on capacity, skill, and experience of contractors bidding on
construction projects.
Checklist
‘The completed Contractor's Qualification Statement Standard Form includes:
* A statement:
— indicating that the document is intended to provide information on the capacity, skill,
and experience of the Contractor
= reminding the Contractor to supplement information requested with additional sheets if
required
+ Project number
+ Title and location of the Project
+ Name, address, and contact numbers of the Consultant receiving the qualification statement
+ Name, address, and contact numbers of the Contractor submitting the qualification statement
+ Legal structure of the Contractor:
— year established
~ joint venture or not
— corporation, partnership, registered, sole proprietor, or other.
— names and titles of officers, partners, or principal
Financial references from a bank:
name, address, and contact numbers
~— name of contact person(s)
2 CCDC 24 ~ 1996* Financial references from a bonding company:
— name, address, and contact numbers
~ name of contact person(s)
* A list of annual value of construction work for the past five years
«A list of principal projects completed in the past five years.
For each principal project include the following:
= title and location
description
project value
completion date
— name, contact person, and contact numbers of the owner
— name, contact person, and contact numbers of the consultant
© A list of similar or related projects completed.
For each related project include the following:
~ title and location
= description
— project value
— completion date
— name, contact person, and contact numbers of the owner
— name, contact person, and contact numbers of the consultant
© A list of major construction projects underway as of the date of submission,
For each project include the following:
— title and location
~ description
= project value
— scheduled completion date
— percent completed
name, contact person, and contact numbers of the owner
— name, contact person, and contact numbers of the consultant
© A list of key office personnel proposed for the Project attached with resumes of qualifications
and experience (e.g. principal in charge, project manager, estimator, etc.)
* A list of key site personnel proposed for the Project attached with resumes of qualifications
‘and experience (e.g. project manager, supervisor, foreman, etc.)
* Space for insertion of additional qualifications required by the Owner or certified
qualifications (e.g. quality management, quality assurance programs, construction
safety programs or records) indicated by the Contractor
‘* Signature of the Contractor declaring that the information provided is true and correct to the
best of the Contractor's knowledge
+ Date of the statement
CCDC 24 - 1996 3FINANCIAL INFORMATION REQUIRED OF THE OWNER
Paragraph 5.1.1 of GC 5.1 - FINANCIAL INFORMATION REQUIRED OF THE OWNER
entitles the Contractor, at the Contractor's discretion, to request the Owner to furnish reasonable
evidence that financial arrangements have been made to fulfill the Owner’ s obligations under the
Contract. Such request may be made prior to execution of the Agreement, and/or promptly from
time to time thereafter.
Paragraph 5.1.2 requires the Owner to notify the Contractor in writing of any material change
in the financial arrangements during the performance of the Contract.
GC 7.2 — CONTRACTOR'S RIGHT TO STOP THE WORK OR TERMINATE THE
CONTRACT entitles the Contractor to stop the Work or to terminate the Contract where the
Owner fails to comply with the requirements specified in GC 5.1. The Contractor, however,
must give 5 days’ written notice to the Owner, prior to taking any action, in order to allow the
Owner an opportunity to remedy the default.
Project Financial Information Standard Form
Guideline
In any contractual venture, each party has legitimate interest and responsibility in ascertaining
whether the other party is fully capable of performing all of its contractual obligations. In the
relationship between the Owner and the Contractor, the Owner may request financial statements
and bank references from a Contractor, and may require bonding which guarantees fulfilment of
both Project performance and payment obligations.
The proven ability to pay is just as important as a proven ability to perform. A Contractor,
therefore, has an equally valid interest in receiving assurances that an Owner has arranged
sufficient funds to make payments in accordance with the terms of the Contract.
Should financial commitment be required before signing the Contract, the Contractor has the
option of signing the Contract but not commencing the Work until the Owner provides acceptable
evidence of financial arrangements.
Evidence of financial arrangements should be not only for the total amount payable by the Owner
to the Contractor, but also for contingencies such as changes, If there is no financial
arrangement in the Contract for contingencies, then as changes or extras arise, the Contractor
may make a separate request for evidence of financial arrangements pertaining to the change.
The Owner should establish a procedure for notifying the lender of changes.
‘The Contractor may require the following types of information from the Owner:
‘Owner Information ~ Identify the Owner and its legal structure, i. the ultimate responsibility
for payment.
4 CCDC 24 ~ 1996Property Information — Identify whether the Owner holds legal ttle to the Project property. The
Contractor should have the correct name of the property owner and the legal description of the
property if a lien has to be filed.
Project Financing Information — Acceptable evidence of financial arrangements might include a
construction loan commitment that sets forth the conditions and requirements of the loan, a
lender's ‘set aside’ letter that represents the acknowledgement by the lender as to the amount
available for construction draws, a credit report, a corporate resolution or governmental
appropriation, or other equally positive documentation that the Owner has made provision for
sufficient funds to fulfill the Owner's obligation under the Contract.
CCDC 12 - ‘Project Financial Information’, as shown in Appendix B, provides a Standard Form
for obtaining information, which in most cases should be sufficient for permitting the Contractor
to ascertain the Owner's financial arrangement.
Checklist
‘The completed Project Financial Information Standard Form includes:
© Title of the Project
* Location of the Project
Owner Information
+ Legal name
+ Address and contact numbers
‘+ Name of contact person(s)
‘+ Legal structure (corporation/partnershipfindividual/other)
Property Information
* The Owner's interest in the property (fee simple, lease, etc.)
+ Name of party holding legal tile to the property (if other than the Owner)
‘© Legal description of the property
+ Legal structure of title holder (corporation/partnership/individual/other)
Project Financing Information
If financed by construction loans:
« Name, address, and contact numbers of the lender(s)
+ Name of contact person(s)
‘+ Type of loan(s)
+ Amount of loan(s)
* Terms of loan(s)
If financed by government funding (direct or government guaranteed):
+ Name, address, and contact numbers of the governmental agency
+ Name of contact person(s)
© Type of funding (grant/loan/debenture issue)
+ Program under which funding provided
+ Amount of funding
+ Terms of grant or loan
CCDC 24 - 1996 5If other sources of funds:
* Description (Owner's equity, syndication proceeds, etc)
If bank references are provided:
+ Name, address, and contact numbers
+ Name of contact person(s)
Support Information
At least one of the following should be provided:
© Construction loan agreement
+ Lender's ‘set-aside’ letter acknowledging amount of loan proceeds to be applied only to draw
for the construction contract
+ A bank letter evidencing financial arrangements made to fulfill the Owner's obligations under
the Contract
+ Owner's audited financial statement
* Other evidence of the source of funding
Information regarding comparable projects completed by the Owner or its related entities
Signature of the Owner declaring that:
— the information is true and correct to the best of the Owner’s knowledge
= the Contractor is entitled to rely upon the accuracy of such information
— the Owner shall notify the Contractor in writing of any material change in the Owner's
financial arrangements during the performance of the Contract
6 CCDC 24 - 1996PAYMENT PROCESS
ARTICLE A-5 — PAYMENT in CCDC 2 - 1994 states that the Owner shall make progress
payments to the Contractor on account of the Contract Price when due in the amount certified
by the Consultant,
GC 5.2 - APPLICATIONS FOR PROGRESS PAYMENT provides that the Contractor may
‘make applications for payment monthly to the Consultant. The requirements for applications are
described in that General Condition. The Contractor submits to the Consultant the completed
Application for Payment Form, along with the schedule of values and Work performed, and back-
up material required for certification.
Paragraph 5.2.3 requires the Contractor to submit to the Consultant, prior to the first application
for payment, a schedule of values for the various parts of the Work to facilitate evaluation of
future applications for payments, In addition, paragraph 5.2.5 obligates the Contractor on each
application to submit a statement based upon this schedule. The schedule of values is a
‘breakdown of the Contract Price which assists the Consulzant and Owner in the systematic
review of the application and to complete the certificate required under paragraph 5.3.1 of GC
5.3 - PROGRESS PAYMENT.
Paragraph 5.2.2 of GC 5.2 - APPLICATIONS FOR PROGRESS PAYMENT provides that the
applications for progress payment shall be dated the last day of the agreed payment period, which
does not have to be the last day of a calendar month.
GC 5.5 - PAYMENT OF HOLDBACK UPON SUBSTANTIAL PERFORMANCE OF THE
WORK describes how the Contractor may apply for the payment of holdback amount after the
issuance of the Certificate of Substantial Performance of the Work. Paragraph 5.5.1 of GC 5.5,
~ PAYMENT OF HOLDBACK UPON SUBSTANTIAL PERFORMANCE OF THE WORK
states that together with an application for payment for the release of holdback monies, the
Contractor shall submit a swom statement that all accounts for labour, subcontracts, Products,
construction machinery and equipment, and other indebtedness which may have been incurred
by the Contractor in the Substantial Performance of the Work and for which the Owner might
in any way be held responsible have been paid in full, except for amounts properly retained as
a holdback or as an identified amount in dispute. Although not required in CCDC 2 - 1994,
some owners may request the Contractor to submit similar swom statements for the second and
subsequent applications for progress payment.
CCDC 24~ 1996 7Application For Payment Form
Guideline
‘The Contractor is required by the Contract to submit the application for progress payment to the
Consultant, The supporting documentation format must conform to the agreed schedule of
values. Documentation which adequately supports the claim allows the Consultant to compare
the values of Work performed to the schedule of values, and will facilitate the issuance of the
Certificate of Payment. The Consultant may require supplementary documentation or
breakdowns to justify the Contractor's claim.
‘The Contractor is advised to review the application for payment with the Consultant before
submission to expedite the application process. Agreement on format, categories, support
documentation, number of copies, and handling method, etc. will speed up the review process.
Checklist
‘The completed Application for Payment Form should include:
* Application number (which should be sequential)
+ Date of the application
‘* Time period covered by the application
* Reference number(s) (Owner, Consultant, or Contractor’s Project number or other reference)
* Name and address of the Contractor
*+ Contractor's registration number for Value Added Taxes such as the Goods and Services Tax
and the Quebec Sales Tax
Name and address of the Consultant
Name and address of the Owner
Title and location of the Work and Contract number if applicable
Total value of Work performed and Products delivered to the Place of the Work at the end
of the period covered by the application
Applicable statutory holdback rate
Total holdback amount
Holdback released
Holdback retained (Total holdback amount less holdback released)
Total amount claimed at the end of period covered by the application (Total value of Work
performed and Products delivered to the Place of the Work less holdback retained at tht end
Of the period covered)
* Total certified amount from the previous certificate for payment, noting the previous certificate
number and date of issuance
* Total amount claimed current period (Total amount claimed at the end of period
covered less total certified amount from the previous certificate for payment)
* Value Added Taxes
* Total amount payable current period including Value Added Taxes
+ Signature of the person submitting the application
8 CCDC 24 - 1996APPLICATION FOR PAYMENT
Contractor: Application number:
GST registration number:
Date:
Consultant:
Period covered:
from
‘Owner:
Reference number(s):
‘Work:
‘ile and Tation
Total value of Work performed and Prodycts delivered to the Place of
the Work at the end of period covered $s o
Total holdback at % $ ®
Holdback released $ »
Holdback retained a-» $s
3
Total amount claimed at the end of period covered a
Total certified amount from previous certificate for
payment __
manor and dae
Total amount claimed current period -
Value Added Taxes at _%
oe we
3
Total amount payable current period including Value Added Taxes c+
Submitted by the Contractor
eae ad ie of perio viring “ipatare
CCDC 24 - 1996 9Schedule of Values and Work Performed Form
Guideline
The Schedule of Values & Work Performed Form serves the following two purposes:
The Schedule of Values Form
The Contractor is required to submit to the Consultant, at least 14 days before the first
application for payment, a schedule of values for the parts of the Work. It breaks down the Work
to quantifiable elements with a total equal to the Contract Price. The Contractor prepares the
schedule of values by filling in the Description and Total Amount of each item, A cost
breakdown for mobilization, supervision, major trades, Products delivered to the Place of the
Work, mechanical and electrical works, as-built drawings, and maintenance work facilitates the
Consultant's review of the application for payment. When the Consultant accepts the schedule
of values, it is to be used as the basis for applications for payment.
‘The Schedule of Values and Work Performed Form
The Contractor is required to include a statement based on the schedule of values with each
application for payment. This includes the original breakdown for parts of the Work and items
such as Change Orders and Change Directives. The Contractor is required to provide the
percentage of the value of the Work performed for each item of the Work.
Checklist
‘The completed Schedule of Values Form should include:
* Name and address of the Contractor
+ Title and location of the Work and Contract number if applicable
+ A list of items and their numbers that form the Work
* For each individual item include the following:
— Description of item (section number)
~ Amount included in the Contract Price
+ Page numbering
The completed Schedule of Values and Work Performed Form should include:
+ Name and address of the Contractor
+ Title and location of the Work and Contract number if applicable
* A list of items by number (parts of the Work), Change Orders, and Change Directives covered
by the application
* For each individual item include the following:
— Item number (section number, Change Order number, or Change Directive number)
~ Description of item
‘Amount included in the Contract Price
Percentage of the value of the Work performed to end of period covered
Value of Work performed and Products delivered to the Place of the Work to end of
period covered
~ Value of the Work previously performed and Products previously delivered to the Place
of the Work
'
'
10 CCDC 24 - 1996— Current value of the Work performed and Products delivered to the Place of the Work
applied for
= Balance to complete (Optional: The amount included in the Contract Price less the
value of the Work previously performed and Products previously delivered to the Place
of the Work)
— Remarks may be used to show references and explanation of value claimed
© Application number
© Date of the application
‘+ Time period covered by the application
+ Page numbering
CCDC 24 ~ 1996 uny 20T 20 A
syemay [| oajdmoy owed peunopeg
Lo & sourreg, waar Aysnoraaig
‘waxy paronos porag
come
oquinu uorearddy
GaNdOAAd WOM ANV SANTVA JO FINGAHOS
CCDC 24 ~ 1996Certificate For Payment Form
Guideline
Paragraph 2.2.4 of GC 2.2 - ROLE OF THE CONSULTANT in CCDC 2 ~ 1994 states that the
Consultant will review the Contractor's applications for payment, determine the amounts due,
and issue a certificate for payment in the amount applied for or such other amount as the
Consultant determines is properly due.
Paragraph 5.3.1 of GC 5.3 - PROGRESS PAYMENT provides that if the Consultant amends the
application, the Consultant is to notify the Contractor promptly in writing giving reasons for the
amendment.
‘The Certificate For Payment Form should provide the following distinct types of information for
the benefit of the Owner and the Contractor:
(1) the Consultant's certification in response to the Contractor's application for payment;
(2) information as to the status of the Contract Price informing the parties to the Contract;
(3) a payment summary informing the Owner of the amount payable to the Contractor for the
period covered; and
(4) optional: a place to record the Contractor’s acknowledgement of the receipt of payment.
The Contract Price may include a contingency allowance as described in GC 42 -
CONTINGENCY ALLOWANCE, At the outset of the Project, this is an amount in the Contract
to the benefit of the Owner, from which expenditures authorized by a Change Order may be
deducted. As there are many variations of accounting for this process, the Contract Summary
should be revised as necessary to document the adjustment of the contingency allowance and/or
Contract amount.
EXAMPLE:
Contract Summary
Original Contract Price $ w
Change Orders (numbers: )s ®
Current value of Change Directives
included in the certified amount $ oe
‘Contingency Allowance 8 ate
©
Value of changes less contingency allowance av~»
Value of Contract on the last day of the payment period «+5
Value Added Taxes at % o
Total amount payable for the construction of the Work including
Value Added Taxes «n $s ®
Alternatively, the Owner may add to the Contract amount by Change Order or Change Directive
rather than expending the contingency allowance.
CCDC 24 - 1996 13‘The Consultant forwards the completed Certificate for Payment Form to the Owner, in the
umber of copies required by the Owner, together with the corresponding Application for
Payment Form and the Schedule of Values and Work Performed Form as submitted or as
modified as the case may be.
It is recommended that copies of the completed Certificate for Payment Form be sent to the
Contractor and that the Contractor acknowledges receipt of payment highlighting the date and
amount by signing and returning copies of the certificate to the Consultant and the Owner for
record purposes.
‘Checklist
The completed Cerificate for Payment Form should include:
* Certificate number
Reference number(s) (Owner, Consultant, ot Contractor's Project number or other reference)
Name and address of the Consultant
Name and address of the Owner
Name and address of the Contractor
Title and location of the Work and Contract number if applicable
‘Statement by the Consultant to the Owner certifying the total value of Work performed
and Products delivered to the Place of the Work as of the valuation date (exclusive of Value
Added Taxes)
+ The signature (and in some jurisdictions the seal) of the Consultant
* The date of issue
* A Contract Summary showing:
— Original Contract Price
— Value of Change Orders issued
~ Current value of Change Directives included in the certified amount
— The value of Contract on the last day of the payment period
— Value Added Taxes
~ Total amount payable for the construction of the Work including Value Added Taxes
* A Centfication Summary showing:
= The value of Work performed and Products delivered to the Place of the Work as of the
valuation date
~ Applicable statutory holdback rate
— Total holdback amount
— Holdback released
— Holdback retained (Total holdback amount less holdback released)
— Amount (The value of Work performed and Products delivered to the Place of the Work
Jess holdback retained as of the valuation date)
— Amount from previous certificate for payment, noting the certificate number
~ Amount of Contract Price payable current period (The amount as of the valuation date
less the amount from previous certificate for payment)
~ Value Added Taxes
= Total amount payable current period including Value Added Taxes
* Optional: a place to indicate the balance to certify (The value of Contract on the last date of
the payment period less the value of Work performed and Products delivered to the Place of
the Work as of the valuation date)
4 CCDC 24 - 1996+ Optional: a place to indicate the Contractor's acknowledgement of receipt of payment
EXAMPLE
‘The Contractor acknowledges receipt of payment upon the __day of
in the amount of $
CCDC 24 - 1996
15CERTIFICATE FOR PAYMENT
Consultant: Certificate number:
Owner: Reference number(s):
Contractor: e
Work:
Tile ad Tcaton
This is to certify that the value of Work performed and Products delivered to the Place of the
Work as of is$ (exclusive of Value Added Taxes).
Certified by the Consultant
~ ‘name and title of person signing ‘signature date f leswe
Cen Rr
Contract Summary
Original Contract Price s_ ©
Change Orders (aumbers: ys ®
Current value of Change Directives
included in the certified amount $ o
Value of Contract on the last day of the payment period «2 $
Value Added Taxes at % $ o
Total amount payable for the construction of the Work including
Value Added Taxes 1s $
Certification Summary
‘Value of Work performed and Products delivered to the Place of the
Work s o
Total holdback at % s o
Holdback released 5 o
Holdback retained @-» $ 0
Amount (value of Work performed and Products delivered to the Place ofthe Work
Jess holdback retained) (7-1) $ an
Amount from previous certificate for payment (number: )s “
‘Amount of Contract Price payable current period «1-12 8 a
Value Added Taxes at % $ 0
Total amount payable current period including Value Added Taxes $ as,
16 CCDC 24 ~ 1996Statutory Declaration Standard Forms
Guideline
CCDC 9A - ‘Statutory Declaration’ (Accompanies Contractor's application. for release of
holdback, security deposit, or both) is the Standard Form for sworn statements made by the
Contractor as required in paragraph 5.5.1.2 of GC 5.5 - PAYMENT OF HOLDBACK UPON
SUBSTANTIAL PERFORMANCE OF THE WORK when the Contractor applies for payment
of the holdback amount after the issuance of the Certificate of Substantial Performance of the
Work.
CCDC 9B - ‘Statutory Declaration’ (Accompanies the Contractor's or a Subcontractor’s second
and subsequent progress claims) is the Standard Form for swom statements made by the
Contractor or a Subcontractor when applying for the second and subsequent progress payments.
The declaration confirms that all payment obligations incurred by the Contractor or a
Subcontractor in performing the Work or subcontract work, up to the last payment application
and for which the Owner might be held responsible, have been satisfied.
CCDC 9C ~ ‘Statutory Declaration’ (Accompanies a Subcontractor's application for release of
holdback, security deposit, or both) is the Standard Form for swom statements made by a
Subcontractor when applying for release of holdback, subcontract security deposit, or both. The
declaration confirms that all payment obligations incurred by the Subcontracior in performing
the subcontract work, and for which the Contractor or the Owner might be held responsible, have
been satisfied.
‘These forms are shown in Appendix C.
CCDC 24 - 1996 ”Certificate of Substantial Performance
Guideline
‘Substantial Performance of the Work is defined in the CCDC standard Contract Form to be
‘... a8 defined in the lien legislation applicable to the Place of the Work. If such legislation is
not in force or does not contain such definition, Substantial Performance of the Work shall have
been reached when the Work is ready for use or is being used for the purpose intended and is
$0 certified by the Consultant’.
‘The applicable lien legislation may prescribe the form to be used for the certification of
substantial performance. In that event, the statutory prescribed form should be used.
Checklist
‘The completed certificate should include:
+ Name and address of the Contractor
Name and address of the Owner
Name and address of the Consultant
Title and location of the Work and Contract number if applicable
‘The Contract date
‘A statement that the Work of the Contract was substantially performed on a certain date
Description of the Work not yet performed at the date of Substantial Performance of the Work
‘Signature of the authorized person acting on behalf of the Consultant or Contractor as
specified in the applicable lien legislation
Name and title of the person signing
© Date of signing
+ The legal description of the property and any other information or statement that may be
required by the lien legislation applicable to the Place of the Work
‘+ Professional seal if required by the legislation applicable to the Place of the Work
1B CCDC 24 - 1996SUPPLEMENTAL INSTRUCTION PROCESS
Paragraph 2.2.9 of GC 2.2 - ROLE OF THE CONSULTANT describes the circumstances in
which Supplemental Instructions are used.
Supplemental Instructions are issued to record clarifications or interpretations in the Contract
Documents or to give direction on a problem which evolves during the course of the Work. They
may not be used if the instruction affects the Contract Price or Contract Time. Changes to the
Contract Price and Contract Time are dealt with by Change Orders or Change Directives as
provided in GC 6.2 - CHANGE ORDER and GC 6.3 - CHANGE DIRECTIVE.
Supplemental Instruction Form
Guideline
The Supplemental Instruction is to be issued by the Consultant to the Contractor and a copy is
sent to the Owner and other consultants,
If the Contractor is of the opinion that the instruction affects the Contract Price or Contract
Time, the Contractor must notify the Consultant in writing.
Checklist
The completed Supplemental Instruction Form should include;
Instruction number
Date of the instruction
Reference number(s) (Owner, Consultant, or Contractor's Project number or other reference)
Name and address of the Consultant
Name and address of the Contractor
Name and address of the Owner
Title and location of the Work and Contract number if applicable
A statement:
= referring to paragraph 2.2.9 of GC 2.2 - ROLE OF THE CONSULTANT in CCDC 2
= 1994 which authorizes the issuance of the Supplemental Instruction
— indicating that if the Contractor proceeds to work in accordance with this Supplemental
Instruction, the Contractor acknowledges that there will be no change in the Contract
Price and Contract Time
= requiring the Contractor to promptly notify the Consultant if the Contractor believes
that this Supplemental Instruction affects the Contract Price and Contract Time
* Description of the Supplemental Instruction and list of attached specifications and drawings,
if any
+ Signature of the Consultant issuing the Supplemental Instruction
* Distribution list (Contractor, Consultant, Owner, other consultants, and file)
CCDC 24 - 1996 19SUPPLEMENTAL INSTRUCTION
Consultant: Instruction number: :
Contractor: Date:
Owner: Reference number(s):
Work:
Tile and Toation
The following instruction is issued to the Contractor in accordance with Paragraph 2.2.9 of GC
2.2 - ROLE OF THE CONSULTANT in CCDC 2 - 1994. Proceeding with work in accordance
with these instructions indicates the Contractor's acknowledgment that there will be no change
in the Contract Price and Contract Time. If the Contractor believes that this instruction affects
the Contract Price or Contract Time, the Contractor shall promptly notify the Consultant,
Description:
Issued by the Consultant
ae ad le of eran signing aan
distributed to:
20 CCDC 24 - 1996(CHANGE PROCESS
GC 6.1 - CHANGES "in CCDC 2 ~ 1994 allows the Owner, through the Consultant, to make
changes in the Work by Change Order ot Change Directive. The following forms will facilitate
this process in accordance with CCDC 2 — 1994, It is extremely important to identify properly
and document changes in the Work with respect to both the Contract Price and Contract Time
in all the forms mentioned below.
Proposed Change Form
‘This Form is a request to the Contractor to indicate the changes in the Contract Price and
Contract Time as a result of proposed changes in the Work. If the Owner does not accept the
Contractor's proposal for changes in the Contract Price and Contract Time, the Owner may issue
a Change Directive if the proposed changes are within the general scope of the Contract
Documents, Proposed changes in the Work must be identified, properly documented, and
administered in accordance with the Contract Documents and should be tracked and cross-
referenced with Change Orders.
Change Order Form
This Form is signed by the Owner and the Contractor recording their agreement upon a change
in the Work, the amount or method of any adjustment in the Contract Price and the extent of any
adjustment in the Contract Time. The specific additions, deletions, or other revisions to the Work
must be accurately identified,
This Form is also used to record agreement for:
(1) an expenditure under a contingency allowance;
(2) the adjustment to the Contract Price against the difference between the actual expenditure
and the contingency allowance; and
(3) the adjustment to the Contract Price against the difference between the actual cost and
each cash allowance.
Change Directive Form
‘This Form is a signed instruction issued by the Owner directing a change in the Work within the
‘general scope of the Contract Documents. It is issued to require the Contractor to proceed with
a change in the Work prior to the Owner and the Contractor agreeing upon the adjustment in
Contract Price and Contract Time.
‘The specific additions, deletions, or other revisions to the Work must be accurately identified.
‘After the Change Directive is issued, the parties may continue to negotiate and subsequently
agree on the adjustment to the Contract Price and Contract Time, recording such agreement by
a Change Order.
CCDC 24 - 1996 aSummary of changes
This Form is intended for summarizing proposed and recorded changes to the Contract Price and
Contract Time for the information of the Owner, Contractor, and Consultant. It reflects the
status of the changes in the Work.
Combined Proposed Change and Change Order Form
This combined Form includes:
(1) a request from the Owner to the Contractor to indicate the changes to the Contract Price
and Contract Time as a result of proposed changes in the Work;
(2) a reply outlining the Contractor's proposal for changes in the Contract Price and
Contract Time; and
(3) an agreement signed by the Owner and the Contractor for a change in the Work, the
amount of any adjustment in the Contract Price and the extent of any adjustment in the
Contract Time,
This Form will be very useful for small or clearly delineated changes required by the Owner or
for substitutions proposed by the Contractor. Support documentation can be attached and
referenced in the form.
2 CCDC 24- 1996Proposed Change Form
Guideline
Proposed changes need to be presented to the Contractor in a timely manner and in sufficient
copies for distribution. It is important for the Consultant to provide a clear and complete
description of the proposed changes.
Sufficient time should be allowed for the Contractor to estimate the changes to the Contract
Price and Contract Time for the proposed change in the Work.
‘The Proposed Change Form should be sent by the Consultant to the Contractor and copied to
the Owner and other consultants,
‘Checklist
‘The completed Proposed Change Form should include:
Proposed change number
Issue date of the proposed change
Reference number(s) (Owner, Consultant, or Contractor's Project number or other reference)
Name and address of the Consultant
Name and address of the Contractor
‘Name and address of the Owner
Title and location of the Work and Contract number if applicable
A statement:
— referring to paragraph 6.2.1 of GC 6.2 in CCDC 2 — 1994 which authorizes a request
for proposed change
~ requiring within a certain number of days a quotation from the Contractor conceming
adjustments to the Contract Price and Contract Time
~ indicating that the Contractor shall not proceed with the proposed change unless a
‘Change Order or Change Directive authorizing a change in the Work is issued
+ Description of the proposed change, including where appropriate, the reason for and the origin
of the proposed change
«+ Signature of the Consultant preparing the proposed change
+ Distribution list (Owner, Contractor, Consultant, other consultants, and file)
CCDC 24 ~ 1996 a= PROPOSED CHANGE
Consultant: = Proposed change number:
CC ee
Owner: Reference number(s):
Work:
cad Tcaton
Pursuant to paragraph 6.2.1 of GC 6.2 - CHANGE ORDER in CCDC 2 - 1994, indicate
within ____ days of the above date the changes to the Contract Price and Contract Time for
the following proposed change in the Work. Do not proceed with the change without a
Change Order ot Change Directive authorizing a change in the Work.
Description:
7
Prepared by the Consultant
Te ad ef prion ging ipa
distributed to:
mw CCDC 24 - 1996Change Order Form
Guideline
‘When the monetary consideration of a Change Order is to be applied against a contingency
allowance, the Contract Price shall be:
(1) unchanged, if the expenditures authorized against a contingency allowance are less than
the amount stated in the Contract Documents; or
(2) adjusted by such difference, if the expenditures authorized against a contingency
allowance exceed the amount stated in the Contract Documents.
Should the Contract Price not include a contingency allowance, delete or strike out the line and
record the changes in Contract Price.
‘The Consultant prepares and signs three copies of the Change Order for the Owner to sign. The
Owner signs these copies and retums them to the Consultant, who then sends them to the
Contractor. After signing, the Contractor returns two copies to the Consultant, who then
transmits one copy to the Owner.
Checklist
‘The completed Change Order Form should include:
Change Order number
Date of the Change Order
Reference number(s) (Owner, Consultant, or Contractor's Project number or other reference)
Name and address of the Consultant
Name and address of the Owner
‘Name and address of the Contractor
Title and location of the Work and Contract number if applicable
‘A statement referring to paragraph 6.2.2 of GC 6.2 - CHANGE ORDER in CCDC 2 - 1994
which describes a Change Order as an amendment to the Contract stating the agreement
between the Owner and the Contractor upon a change in the Work and the adjustments in the
Contract Price and Contract Time
+ Description of the change to be made in the Contract by the Change Order, including
reference to specifications, drawings, or other supporting data (reference to proposed change
ot Change Directive) to clarify the scope of the change
Contingency allowance adjustment, if applicable
Contract Price adjustment
Contract Time adjustment
Signature of the Consultant recommending the change in the Contract
‘Signature of the Owner approving the change in the Contract
Signature of the Contractor approving the change in the Contract
CCDC 24 ~ 1996 2sCHANGE ORDER
Consottant: Change Order number:
Owners Date:
Commacto: (Reference number(s):
Work:
a a —___. —
Pursuant to paragraph 6.2.2 of GC 6.2 - CHANGE ORDER in CCDC 2 ~ 1994, the following
is an amendment to the Contract stating the agreement between the Owner and the Contractor
upon a change in the Work and the adjustments in the Contract Price and Contract Time.
Description:
‘The contingency allowance is increased/decreased by the sum of $
‘The Contract Price is increased/decreased by the sum of $
‘The Contract Time is increased/decreased by Working Days
a
‘Recommended by the Consultant
"nae nd tle of person iging “ature daz
Approved by the Owner
"ne ad a f person gring “atone dae
Approved by the Contractor
Wane and eof prac signing nature date
6 CCDC 24 - 1996‘Change Directive Form
Guideline
It is recommended that the Consultant prepare thsee copies of Change Directive for the Owner
1 sign. These copies are then sent to the Contractor for acknowledgement. The Contractor is
to retain a copy and retum the other two signed copies to the Consultant. The Consultant, in
turn, sends a copy signed by all parties to the Owner.
Checldist
The completed Change Directive Form should include:
* Change Directive number
Date of the Change Directive
Reference number(s) (Owner, Consultant, or Contractor's Project nueabet or other reference)
Name and address of the Consultant
Name and address of the Owner
‘Name and address of the Contractor
Title and location of the Work and Contract number if necessary
A statement:
— referring to GC 6.3 - CHANGE DIRECTIVE in CCDC 2 - 1994 which authorizes the
Owner to direct changes in the Contract
— indicating that the adjustment to Contract Price will be established according to the
provisions of paragraphs 6.3.2, 6.3.3, and 6,3.4 and the adjustment to Contract Time sill
be established according to the provisions of paragraph 63.6
* Description of the change to be made in the Contract by the Change Directive, including
reference to specifications, drawings, or other supporting data to clarify the scope of the
change
* Signature of the Consultant preparing the Change Directive
« Signature of the Owner issuing the Change Directive
+ Signature of the Contractor acknowledging the receipt of the Change Direcsive
CeDe 24 - 1996 a(ConmMan eee
Owner:
Contractor:
Work:
Tile ad Toaton
CHANGE DIRECTIVE
Change Directive number:
Date:
Reference number(s):
As provided in GC 6.3 - CHANGE DIRECTIVE in CCDC 2 - 1994, the Owner directs the
Contractor to make the following changes in the Contract. ‘The adjustment to Contract Price
will be established according to the provisions of paragraphs 6.3.2, 6.3.3, and 6.3.4 of GC 63
and adjustment to Contract Time will be established according to the provisions of paragraph
6.3.6 of GC 6.3.
Description:
Prepared by the Consultant
“ae cad leo ero ing “ign dae
Issued by the Owner
Tae ad ile of porn ing anatare dae
‘Acknowledged by the Contractor
Te a Tf pan ing Tipe = wae
28
CCDC 24 - 1996‘Summary of Changes Form
Guideline
‘The Consultant, as the administrator of the Contract, should maintain this form and review the
status at the regular (monthly) application for payment meetings 0 incorporate the updated
information in the Schedule of Values and Work Performed.
This form or this type of information should be updated and distributed regularly upon the
issuance of a Proposed Change, Change Directive, or Change Order.
Checklist
‘The completed Summary of Changes Form should includ
+ Name and address of the Consultant
* Name and address of the Contractor
+ Name and address of the Owner
* Title and location of the Work and Contract number if applicable
+ Updated number of the current version of the summary
Date of the updated summary
Reference number(s) (Owner, Consultant, ot Contractor's Project number ot other reference)
A list of Proposed Changes, Change Directives, and the numbered references
For each individual Proposed Change or Change Directive include the following:
— Reference number
— Description of the Proposed Change or Change Directive
— Contractor's proposal for a change in Contract Price
~ Contractor's proposal for a change in Contract Time
— Change Order number if applicable
Date of the Change Order if applicable
Agreed value of Change Order if applicable
— Changes in Contract Time as recorded in the Change Order if applicable
+ Remarks may be used to show references and deadlines for amounts committed.
'
CCDC 24 1996 2»—
evarony | 2reaiouy sapson
un, wesmuey | soug oes a)
2710 somo | aqua, ee so Bury)
spewo; ‘un, suey suey 2p ur aduey © jondussag | pasodosg
weno | 30 on yoong | sammy 303 psodong 5 2019eOD sou FY
a SPO
> :@qunu 2oua1a}oy = 20
oma saowenuey
~~ stequinu Areurans |
CCDC 24 - 1996Combined Proposed Change and Change Order Form
Guideline
This combined Form is designed for proposed changes that can be easily defined. It may be used
to record an agreement for:
Q) an expenditure under a contingency allowance;
(2) the adjustment to the Contract Price against the difference between the actual expenditure
and the contingency allowance;
(3) the adjustment to the Contract Price against the difference between the actual cost and
each cash allowance; and
(4) the Contractor's proposed substitutions.
This Form can also satisfy the specific administrative requirements of some Owners who need
a proposed change from the Contractor before processing a Change Order.
Checklist
‘The completed Combined Proposed Change and Change Order Form should include:
Proposed change and Change Order number
Issue date of the proposed change
Reference number(s) (Owner, Consultant, or Contractor's Project number or other reference)
Name and address of the Consultant
Name and address of the Contractor
Name and address of the Owner
Title and location of the Work and Contract number if applicable
A statement:
~ referring to paragraph 6.2.1 of GC 6.2 in CCDC 2 - 1994 which authorizes a request
for proposed change
~ requiring within a certain number of days a quotation from the Contractor concerning
adjustments to the Contract Price and Contract Time
~ indicating that the Contractor shall not proceed with the proposed change until this form
has been signed by the Owner
* Description of the proposed change, including where appropriate, the reason for and the origin
of the proposed change
Signature of the Consultant preparing the proposed change
The Contractor's proposed adjustment in the contingency allowance, if applicable
‘The Contractor's proposed adjustment in the Contract Price
The Contractor's proposed adjustment in the Contract Time
Signature of the Contractor proposing the adjustment
‘Signature of the Consultant recommending the change in the Contract
Signature of the Owner approving the change in the Contract
Signature of the Contractor approving the change in the Contract
CCDC 24 ~ 1996 a1COMBINED PROPOSED CHANGE
AND CHANGE ORDER
Consultant: oe Proposed change and Change Order
number:
Contractor: —
Owner: Reference number(s):
Work:
Tile and Tocaion
Pursuant to paragraph 6.2.1 of GC 6.2 - CHANGE ORDER in CCDC 2 - 1994, indicate
within __ days of the above-noted date the changes to the Contract Price and Contract Time
for the following proposed change in the Work. Do not proceed with the changes until this
form has been signed by the Owner.
Prepared by the Consultant
‘ae ad HE of person sling iat
Contractor's Proposal
‘The contingency allowance is increased/decreased by the sum of $
‘The Contract Price is increased/decreased by the sum of $
‘The Contract Time is increased/decreased by Working Days
Proposed by the Contractor
Ta a Teo rion ig gare we
Recommended by the Consultant
‘name and title of person signing ‘signature dae
Approved by the Owner
Thame ad le of person sing ‘iature Tate
Approved by the Contractor
‘nae and eof person vighing ipnaiure aie
32 CCDC 24 - 1996NOTIFICATION PROCESS
CCDC 2 requires the parties to give notice under certain circumstances. The Notice Form will
facilitate this process. It assists the parties in giving notice in accordance with the Contract
Documents and serves to record same,
Notice Form
Guideline
The parties should read carefully and refer in the Notice Form to the pertinent provision that
requires notification. Consultation with legal counsel may be necessary to ensure full compliance
with the Contract Documents.
‘The Notice Form should be used whenever notice is given under CCDC 2 including but not
limited to the following provisions of the Contract:
* Paragraph 2.2.7 of GC 2.2 - ROLE OF THE CONSULTANT
Written Notice of claims, disputes, and other matters in questions
* Paragraph 2.3.2 of GC 2.3 - REVIEW AND INSPECTION OF THE WORK
Notice of tests, inspection, or approvals
* Paragraph 3.2.3.4 of GC 3.2 - CONSTRUCTION BY OWNER OR OTHER CONTRACTORS
Report of affected work
+ Paragraph 3.4.1 of GC 3.4 ~ DOCUMENT REVIEW
Report of error in the Contract Documents
* Paragraph 3.11.6 of GC 3.11 - SHOP DRAWINGS
Written Notice of revisions to the resubmission of shop drawings
* Paragraph 5.1.2 of GC 5.1 - FINANCING INFORMATION REQUIRED OF THE OWNER
‘Written Notice of material change in the Owner’s financial arrangements
+ Paragraph 5.3.1 of GC 5.3 - PROGRESS PAYMENT
Written Notice of amendment to the application for progress payment
+ Paragraph 6.4.1 of GC 6.4 - CONCEALED OR UNKNOWN CONDITIONS
‘Written Notice of materially different concealed or unknown conditions
+ Paragraph 6.5.4 of GC 6.5 - DELAYS
Written Notice of claim
+ Part 7 DEFAULT NOTICE
Default Notice (because of the importance of this General Condition, the Owner and the
Contractor should consult their legal and financial advisors on all matters before any action
is taken under Part 7)
+ Paragraph 8.2.1.2 of GC 8.2 - NEGOTIATION, MEDIATION, AND ARBITRATION
‘Written Notice requesting the appointment of Project Mediator
‘+ Paragraph 8.2.2 of GC 8.2 - NEGOTIATION, MEDIATION, AND ARBITRATION
‘Written Notice of dispute against the Consultant's finding and reply of the responding party
+ Paragraph 8.2.5 of GC 8.2 - NEGOTIATION, MEDIATION, AND ARBITRATION
Written Notice terminating the Mediation
* Paragraph 8.2.6 of GC 8.2 - NEGOTIATION, MEDIATION, AND ARBITRATION
‘Written Notice requesting the dispute be finally resolved by Arbitration
‘CCDC 24 ~ 1996 33* Paragraph 8.2.8 of GC 8.2 - NEGOTIATION, MEDIATION, AND ARBITRATION
Written Notice requiring the dispute to be arbitrated immediately
+ Paragraph 9.2.2 of GC 9.2 - DAMAGES AND MUTUAL RESPONSIBILITY
Claim in writing for damage related to the other party
* Paragraph 9.2.3 of GC 9.2 - DAMAGES AND MUTUAL RESPONSIBILITY
Notification requiring the Contractor to defend a claim by another contractor
* GC 11.1 - INSURANCE
Written Notice of cancellation, change, or amendment restricting coverage
GC 12.3 - WARRANTY
Written Notice of observed defects and deficiencies that occur during the warranty period
Cheeldist
The completed Notice Form should include:
Name of the party that issues the notice (Owner, Contractor, or Consultant)
Name of the party to whom the notice is addressed (Owner, Contractor, or Consultant)
‘Address of the addressce (Owner, Contractor, or Consultant)
Title and location of the Work and Contract number if applicable
A statement referring to Article A-6 of the Agreement - RECEIPT OF AND ADDRESSES
FOR NOTICES and to the particular General Conditions of the Contract between the Owner
and the Contractor which authorize or reference the notice.
Signature of the party issuing the notice (strike out as appropriate)
Name and title of the person signing
Date of signing
Distribution list (Contractor, Owner, Consultant, other consultants, and file)
4 CCDC 24 - 1996From:
‘Over 7 Contvacion 7 Conant *
To: _ Address:
‘nner 7 Coniractor 7 Consaian *
Work:
Tie ad Tain
Pursuant to Article A-6 of the Agreement - RECEIPT OF AND ADDRESSES FOR NOTICES
and General Conditions of the Contract dated
between
and :
notice is hereby given that:
(Particulars)
Issued by the Contractor / Owner / Consultant +
"hae aid ile of perio vgning “atare ate
distributed to:
* strike out as appropriate
CCDC 24 ~ 1996 35WARRANTY NOTIFICATION
Paragraph 12.3.3 of GC 12.3 - WARRANTY states that, except for the provisions of paragraph
12.3.6 and subject to paragraph 12.3.2, the Contractor shall correct, at the Contractor's expense,
defects or deficiencies in the Work which appear prior to and during the warranty periods
specified in the Contract Documents,
Paragraph 12.3.4 requires the Owner to give written notice, through the Consultant, to the
Contractor of any observed defect or deficiency which occurs during the defined warranty period
in the Contract.
Paragraph 12.3.6 specifies that Product warranties be issued by the manufacturer to the benefit
of the Owner. During the warranty period, the Owner should give writen notice to the
‘manufacturer of any observed defect or deficiency in an item warranted under a Product
warranty.
Warranty Notice Form
Guideline
‘Sufficient time should be allowed for the Contractor to commence the remedy of defects. The
identification and numbering of warranty items will allow proper tracking. Before the end of the
warranty period, the warranted items should be reviewed in the warranty inspection.
Checklist
The completed Warranty Notice Form should include:
‘+ Warranty notice number
* Name of the Owner / Consultant (strike out as appropriate)
+ Name of the Contractor
+ Address of the Contractor
+ Title and location of the Work and Contract number if applicable
+ A statement:
— referring to paragraph 12.3.4 of GC 12.3 in CCDC 2 ~ 1994 which requires the Owner
to give written notice of observed defects and deficiencies that occur during the
warranty period
— requiring the Contractor to commence the correction of defects within certain number
of days
— requesting the Contractor to notify the Owner and Consultant upon completion of
correction of defects
Description of the observed defect or deficiency
Signature of the Consultant / Owner issuing the notice (strike out as appropriate)
Date of signing
Distribution list (Contractor, Owner, Consultant, other consultants, and file)
36 CCDC 24 ~ 1996WARRANTY NOTICE
From: - Notice number:
‘Over 7 Consahaat *
To: Address:
Contractor
Work:
Tie a Tocaton
Pursuant to paragraph 12.3.4 of GC 12.3 - WARRANTY of the Contract dated :
between _
and __ _
notice is hereby given of an observed defect or deficiency in the Work as outlined below.
‘Commence correction of the said defect or deficiency within days, and notify the Owner
and Consultant upon completion.
Description:
a
Issued by the Owner / Consultant +
Tae and ile of person gning “ipature aie
distributed to:
* strike out as appropriate
CCDC 24 - 1996 37Product Warranty Notice Form
Guideline
Sufficient time should be allowed for the manufacturer to reply to the Owner. ‘The identification
and numbering of warranty items will allow proper tracking. Before the end of the warranty
Period, the warranted items should be reviewed in the warranty inspection, The Owner is advised
to show the manufacturer GC 12 - WARRANTY of CCDC 2 and the Product ‘warranty obtained
from the manufacturer to expedite the process.
Checklist
‘The completed Product Warranty Notice Form should include:
* Product warranty notice number
+ Name of the Owner / Consultant (strike out as appropriate)
* Name of the manufacturer
* Address of the manufacturer
* Title and location of the Work and Contract number if applicable
* A statement:
~ referring to the manufacturer's Product warranty
— notifying the manufacturer of an observed defect or deficiency in the Product
requesting the manufacturer to respond within a certain number of days
Description of the observed defect or deficiency
Signature of the Consultant / Owner issuing the notice (strike out as appropriate)
Date of signing
Distribution list (Contractor, Owner, Consultant, other consultants, and file)
38 cep 24~ 1996PRODUCT WARRANTY NOTICE
From: Notice number:
‘Owner 7 Comsat *
To: Address:
Contractor
Work:
Tile and Tain
Pursuant to your Product warranty dated notice is hereby given of an observed
defect or deficiency in the Product as described below. Please respond within days.
Description:
Issued by the Owner / Consultant +
"ae ad ile of pron Waning “imaiure ae
distributed to:
* strike out as appropriate
CCDC 24 - 1996 39