1) What is real time operating system(RTOS) and explain how to choose an RTOS?
2) What is difference between general purpose Kernal and real time keral
3) Give difference between assembly language programming and C programming?
4) Short note on GNU debugger? 5
5) Write black box and white box testing? 5
----------------------------------------------------------------------------------------------------------------
Mahatma Education Society's
Pillai HOC College Of Engineering & Technology, Rasayani
Department of Electrical Engineering
UNIT TEST-II
Date:
TE(ETRX)/VII ESD Duration:1 Hr.
(a) FIRST question is compulsory
(b) Attempt any THREE out of remaining FOUR questions Marks: 20
1) What is real time operating system(RTOS) and explain how to choose an RTOS?
2) What is difference between general purpose Kernal and real time keral
3) Give difference between assembly language programming and C programming?
4) Short note on GNU debugger? 5
5) Write black box and white box testing? 5
Mahatma Education Society's
Pillai HOC College Of Engineering & Technology, Rasayani
Department of Electrical Engineering
UNIT TEST-II
Date:
TE(ELE)/V CE Duration:1 Hr.
(a) FIRST question is compulsory
(b) Attempt any THREE out of remaining FOUR questions Marks: 20
1) Discuss the Role of Project Manager? 5
2) What is the difference between Market and Demand? 5
3) Explain Project Life Cycle in brief? 5
4) Explain SWOT Analysis with help of suitable example? 5
5) Explain Break-Even-Analysis? 5
--------------------------------------------------------------------------------------------------------------------------------------
Mahatma Education Society's
Pillai HOC College Of Engineering & Technology, Rasayani
Department of Electrical Engineering
UNIT TEST-II
Date:
TE(ELE)/V CE Duration:1 Hr.
(a) FIRST question is compulsory
(b) Attempt any THREE out of remaining FOUR questions Marks: 20
1) Discuss the Role of Project Manager? 5
2) What is the difference between Market and Demand? 5
3) Explain Project Life Cycle in brief? 5
4) Explain SWOT Analysis with help of suitable example? 5
5) Explain Break-Even-Analysis? 5