Standard Sales Order from Stock (VA01) CS01
Purpose
Use this procedure to create a Material BOM
Trigger
None
Prerequisites
Bill of material structure is required for a material.
Material number should exist for the BOM to be created.
Menu Path
Use the following menu path(s) to begin this transaction:
SAP Menu à Logistics à Production à Master Data à Bills of MaterialàBill of
MaterialàMaterial BOM àCS01 - Create
Type in CS01 in the command line.
Transaction Code
CS01
Helpful Hints
Note:
R/O/C in the field tables represents Required, Optional, or Conditional field entries.
• Optional field: you may enter information in an optional field, but an entry is not required for the
completion of the transaction.
• Conditional field: an entry that becomes required as a result of entering something previous to it,
which then deems it required.
Version: Preliminary Last Modified: 12/8/2011 11:32:00 AM Page 1 / 125
DIC Global SAP Program
Title: Create material BOM (CS01)
Process: Plan to fulfill
Sub-Process: plan to fulfill Process
Procedure
1. Start the transaction using the menu path or transaction code.
2. As required, complete/review the following fields:
Field Name R/O/C Description
Transaction Code R Description of the Transaction Code.
Example: CS01
Version: Preliminary Last Modified: 12/8/2011 11:32:00 AM Page 2 / 125
DIC Global SAP Program
Title: Create material BOM (CS01)
Process: Plan to fulfill
Sub-Process: plan to fulfill Process
Create material BOM: Initial Screen
3. As required, complete/review the following fields:
Field Name R/O/C Description
Material R SAP Code. In the Material field, enter the material for which
you want to create the BOM.
Example: 100000000010
Plant R Plant in which this BOM is valid
Enter plant identifier
Example: EE11
Note: If left blank, this becomes a group BOM. Make sure to
enter a plant.
BOM Usage R The manner in which this BOM is to be used
Use 1 for Production, 9 For Rework and R for Reactive
(Pigments Division)
Version: Preliminary Last Modified: 12/8/2011 11:32:00 AM Page 3 / 125
DIC Global SAP Program
Title: Create material BOM (CS01)
Process: Plan to fulfill
Sub-Process: plan to fulfill Process
Field Name R/O/C Description
Alternative BOM O Identifies which BOM for this material is to be
created/selected
Enter alternative if desired
Note: The system will check to see if it exists. Otherwise, the
system will automatically allocate the number.
Valid From R Date from which change is effective
Enter effective date
Note: Defaults to current date.
Version: Preliminary Last Modified: 12/8/2011 11:32:00 AM Page 4 / 125
DIC Global SAP Program
Title: Create material BOM (CS01)
Process: Plan to fulfill
Sub-Process: plan to fulfill Process
Create material BOM: General Item Overview
4. Update the following Required, Optional, and Conditional fields, as needed:
Field R/O/C Description/Action
Component R Material number
Enter material number.
Example: E.g. 320000000051 and
320000000052
Quantity R Quantity of the component required to make the
base quantity of the material
Enter the required quantity.
Example:
Un O Unit of measure. Defaults from material master.
Enter if different from base UOM.
Example: KG, EA
Ict R Item category
L for Stock Items
N for non-stock items
Version: Preliminary Last Modified: 12/8/2011 11:32:00 AM Page 5 / 125
DIC Global SAP Program
Title: Create material BOM (CS01)
Process: Plan to fulfill
Sub-Process: plan to fulfill Process
Press enter for each of the different warning messages.
Highlight each line as follows:
Click on Item for the component details.
Use Next Item to move through the components.
Version: Preliminary Last Modified: 12/8/2011 11:32:00 AM Page 6 / 125
DIC Global SAP Program
Title: Create material BOM (CS01)
Process: Plan to fulfill
Sub-Process: plan to fulfill Process
Create material BOM: Item: All data
Field R/O/C Description/Action
Recursion allowed O Flag allowing the material to consume itself during
the production process. It controls whether the
system checks the BOM for recursiveness.
Set if needed
Version: Preliminary Last Modified: 12/8/2011 11:32:00 AM Page 7 / 125
DIC Global SAP Program
Title: Create material BOM (CS01)
Process: Plan to fulfill
Sub-Process: plan to fulfill Process
Click on the tab.
Note the costing relevancy field. X means it is 100% relevant to costing – this must be used for all
components, except for ZPIP materials (e.g. water).
Use Next Item and Previous Item to move forward and backwards through the components.
Version: Preliminary Last Modified: 12/8/2011 11:32:00 AM Page 8 / 125
DIC Global SAP Program
Title: Create material BOM (CS01)
Process: Plan to fulfill
Sub-Process: plan to fulfill Process
5. Select Go to Header F6.
6. As required, complete/review the following fields:
Field R/O/C Description/Action
Version: Preliminary Last Modified: 12/8/2011 11:32:00 AM Page 9 / 125
DIC Global SAP Program
Title: Create material BOM (CS01)
Process: Plan to fulfill
Sub-Process: plan to fulfill Process
BOM & Alternate text O Enter if there are alternates for ease of selecting the correct
BOM later
Enter descriptive text
Base Quantity R Quantity to which all component quantities in a BOM relate.
System defaults to one unless otherwise configured
Enter base quantity if different from default
BOM Status R 1: Active
2: Inactive
Select active if the BOM can be used, inactive if not
7. Click on the BOM status drop down:
Double-click
Version: Preliminary Last Modified: 12/8/2011 11:32:00 AM Page 10 / 125
DIC Global SAP Program
Title: Create material BOM (CS01)
Process: Plan to fulfill
Sub-Process: plan to fulfill Process
Create material BOM: Header Overview
7. Click
Version: Preliminary Last Modified: 12/8/2011 11:32:00 AM Page 11 / 125
DIC Global SAP Program
Title: Create material BOM (CS01)
Process: Plan to fulfill
Sub-Process: plan to fulfill Process
Create material BOM: Initial Screen
Version: Preliminary Last Modified: 12/8/2011 11:32:00 AM Page 12 / 125
DIC Global SAP Program
Title: Create material BOM (CS01)
Process: Plan to fulfill
Sub-Process: plan to fulfill Process
Version: Preliminary Last Modified: 12/8/2011 11:32:00 AM Page 13 / 125
DIC Global SAP Program
Title: Create material BOM (CS01)
Process: Plan to fulfill
Sub-Process: plan to fulfill Process
The system displays the message, “ ."
8. You have completed this transaction.
Result
You have created a material BOM.
Version: Preliminary Last Modified: 12/8/2011 11:32:00 AM Page 14 / 125