Software Project Timeline Overview

This document outlines the tasks, durations, and timeline for a software development project from January 2019 through June 2019. The project includes tasks for scope, analysis, design, development, testing, training, documentation, pilot deployment, full deployment, and post implementation review, totaling 95.75 days in duration. Key milestones include completing the analysis by the end of February, design by mid-March, testing by mid-May, and a final software development template by the end of May.

Uploaded by

Fadli Badarudin
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
102 views1 page

Software Project Timeline Overview

This document outlines the tasks, durations, and timeline for a software development project from January 2019 through June 2019. The project includes tasks for scope, analysis, design, development, testing, training, documentation, pilot deployment, full deployment, and post implementation review, totaling 95.75 days in duration. Key milestones include completing the analysis by the end of February, design by mid-March, testing by mid-May, and a final software development template by the end of May.

Uploaded by

Fadli Badarudin
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd

ID Task Task Name Duration Jan '19 Feb '19 Mar '19 Apr '19 May '19 Jun

n '19 Feb '19 Mar '19 Apr '19 May '19 Jun '19
Mode 30 06 13 20 27 03 10 17 24 03 10 17 24 31 07 14 21 28 05 12 19 26 02 09
0 Software Development 95,75 days

1 Scope 3,5 days


7 Analysis/Software Requirements 14 days

17 Design 14,5 days


25 Development 21,75 days
32 Testing 48,75 days
48 Training 45,75 days
57 Documentation 30,5 days
67 Pilot 70,25 days
74 Deployment 5 days
81 Post Implementation Review 3 days

86 Software development template complete 0 days 29/05

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Software Development
Summary Manual Summary Rollup Progress
Date: Wed 16/01/19
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only