Artigo - RBI
Artigo - RBI
6ª Conferência sobre
Tecnologia de Equipamentos
1. INTRODUCTION
Risk-based inspection (RBI) is an integrated methodology that uses risk as a basis for
prioritising and managing in-service inspection. The potential benefits from using RBI
include: integrated cost-effective management of health, safety, and environmental and
business interruption risks; optimised inspection planning providing a higher level of
coverage for high-risk items; cost savings derived from extending inspection intervals
and increasing plant availability; and optimum repair and replacement scheduling.
This paper first considers the RBI process and identifies and describes some of the key
issues which must be addressed for its effective application including: user friendliness;
incorporation of damage mechanisms and failure scenarios; audit team approach;
systematic consideration of risk management measures; and linkage to inspection
frequency. It then provides a brief review the current status of RBI within the context of
existing regulatory framework and also in terms of American and European guidelines
for both RBI and assessment of inspection periodicity.
The paper goes on to present elements of the approach to risk-based inspection and
maintenance planning developed at TWI for integrity management in oil & gas
processing, pipeline and power industry sectors. The main features and implementation
procedures associated with TWI's RISKWISE TM and LIFEWISE TM software tools, and
PIPEWISE TM are given to illustrate semi-quantitative and quantitative methods. In
addition, Illustrative case studies are outlined.
The process of RBI should form part of an integrated strategy for managing the integrity
of all assets and systems throughout the plant or facility. RBI is a logical and systematic
process of evaluation and planning. The major steps within the process are:
For control purposes and to ensure best practice the plant manager should exercise a
'performance audit' on each of the above steps in the RBI process.
Sair
6ª Conferência sobre
Tecnologia de Equipamentos
Some of the main requirements and critical success factors for the effective
implementation of RBI are summarised below.
Increasingly, RBI is becoming a plant-based decision aid which forms an integral part
of an asset or plant manager's tool-box. It is essential that the tool is fully understood
and accepted by the user and, additionally, can be used easily without undue
complexity. Simplicity ensures rapid implementation and a fully transparent (rather than
'black-box') approach, which facilitates transfer of know-how. The incorporation of
local plant experience is also important in order to obtain 'buy in' to the product as well
as the results by plant personnel. Software tools simply will tend to 'sit on the shelf'
unless these issues are accommodated.
The RBI process must take account of all damage mechanisms and failure modes to a
level of state-of-the-art understanding. Failure databases derived from plant experience
together with available material models and associated databases are important input.
However, it should be recognised that comprehensive 'expert systems' or prescriptive
modules based on a knowledge of nominal service conditions, which purport to predict
all failure scenarios, do not currently exist. Expert judgement based on a combination of
operational process experience, design and material degradation issues is thus a key
element in identifying both existing and potential damage mechanisms and failure
modes.
The risk audit, the evaluation of risk management options and inspection planning
require multi-disciplinary input covering a range of competences. Therefore, it is best
performed by a team including plant personnel and technical expertise covering the
following areas:
- risk analysis,
- process hazards and business consequences,
- local safety management,
- plant design and materials degradation,
- operations, inspection and maintenance functions,
- inspection and NDE techniques.
The complexity of the plant or facility should determine the size of the team. Safety
implications should be addressed by individuals in the team who can demonstrate
professional competence. The team leader should preferably be remote from pressures
associated with plant production. Consensus is required on all major decisions and a
complete record must be kept of all judgements and decisions made. Auditability is
essential through all stages from plant data capture to inspection planning rationale.
Further benefits of an interactive audit team approach are the on-the-job training and
transference of assessment know-how, which are implicit within the approach.
Sair
6ª Conferência sobre
Tecnologia de Equipamentos
RBI tools, that only output a risk audit, no matter how comprehensive, do not
necessarily provide the solution that operators are looking for. A more holistic approach
is increasingly being required whereby the operator is systematically directed through a
series of risk-management options. These options should not be restricted to inspection
or maintenance actions but should also lead the operator to other measures such as,
design or engineering modifications, operational changes, etc. The impact of each risk
management action should be retained by the software so that cost/risk optimisation can
subsequently be undertaken.
An RBI tool, which only outputs a risk audit, also leaves the user with the problem of
selecting appropriate and safe inspection intervals.
Health and Safety regulations, e.g. the PSSR (see Section 4.1) do not specifically
prescribe inspection intervals. Rather, they requires the ‘Competent Person’ to use
judgement and experience. As mentioned under Section 4.3, the Institute of Petroleum
[1] and SAFed [2] have issued guidelines on maximum service intervals between
inspections. These should be used where necessary although the extent of operating
experience is often a key factor in avoiding excessive conservatism.
Notwithstanding the above, to be effective the RBI tool should offer formal guidance on
the inspection frequency based on the risk audit undertaken. Where risk management
measures are incorporated, the software should accordingly be able to guide the user to
the target inspection frequency by selecting the appropriate measures.
Nevertheless, since general and localised corrosion are often the most prolific damage
mechanisms in industrial installations, in many cases a formal approach based on
assessment of remaining life is potentially very useful. Calculations should implicitly
make conservative assumptions and issues such as inspection accuracy and process
stability need to be factored in.
The European Commission has introduced a series of European Health and Safety
Directives, which are law and are being implemented by every member state within the
European Union (EU). In the UK, implementation of these directives is within the
existing Health and Safety at Work etc Act, 1974 [4]. For pressure systems, the UK
Health and Safety Executive (HSE) provides the Pressure Systems Safety Regulations
(PSSR) [5] for steam raising plant together with an Approved Code of Practice (ACoP)
providing practical advice on compliance with the Regulations. The responsibility for
specifying the nature, extent and periodicity of inspection is placed with the 'Competent
Person' who must effectively perform a risk assessment before making
recommendations. The European Pressure Equipment Directive (PED) [6] considers all
pressurised fluid containment with the aim of conformity in design and manufacture.
The PED also has a requirement for supply of 'instructions for the user' giving all
necessary safety information for commissioning and during continued service. Risks are
considered in the form of hazards associated with release of stored energy. HSE
publications in the period 1998-2000 [7-9] have focused more on risk assessment yet
without being prescriptive in terms of methodology. The guidance given allows
flexibility, for example, it recognises that quantitative approaches are not always
necessary.
API and ASME have produced guidelines for establishing inspection focus based on
risk evaluation [10&3].
API 581 [10] was developed primarily for the oil refining and petrochemical industry. It
comprises qualitative and quantitative approaches. The qualitative approach is based on
determining a series of failure likelihood and failure consequence factors, which are
used to deliver, for every equipment item, a risk rating in the form of a position within a
five by five risk matrix. In the quantitative approach, the evaluation of likelihood (or
failure frequency) starts with a generic failure frequency for the type of equipment in
question. This value is then modified by two factors: FE (Equipment Modification
factor) takes account of items such as damage type, inspection effectiveness, condition,
design and fabrication and process control; and FM (Management System Evaluation
Factor) accommodates the potential impact on mechanical integrity of all process safety
management issues from API-RP 750. The factors FE and FM are obtained from an
exhaustive scoring system based on questionnaires or workbooks. The quantitative
assessment of failure consequence within API 581 is based on a systematic multi-stage
process to determine costs relating to instantaneous and continuous fluid release with
regard to flammable and toxic consequences, environmental clean-up, business
interruption etc.
Sair
6ª Conferência sobre
Tecnologia de Equipamentos
The ASME approach [3] has been developed for power (fossil and nuclear) and process
plant applications. Again it comprises a qualitative risk-ranking as well as a quantitative
assessment applied to individual components or equipment items. The quantitative
approach recommends that a full FMECA (Failure Modes Effects Criticality Analysis)
should be conducted. The use of operating experience databases and analytical damage
models together with their probabilistic applications is also recommended. The latter is
required for establishing inspection periods, although detailed examples of the
analytical process are not given.
The API and ASME approaches are similar in that they both advocate progression from
a relatively simple qualitative risk-ranking method to a far more complex quantitative
method requiring significant effort and expertise to execute. Although the ASME
approach considers the time dependence of failure probability, neither approaches offers
clear and formal methods to translate risks into inspection frequencies.
In summary it can be said that where predictability exists there is scope for formal
methods for determining inspection periods based on reliability and remaining life
considerations. These are considered in Section 5.
This section presents TWI's RISKWISE TM and LIFEWISE TM software with emphasis
on estimation of inspection periodicity and replacement planning respectively, in
addition to PIPEWISE TM programme.
TWI's RISKWISE TM suite of software has been customised for several applications and
has been implemented worldwide in oil and gas process plants, power plant boilers,
pipelines, etc. The customised versions of RISKWISE TM have also been incorporated in
equipment-specific life management programmes, e.g. PIPEWISE TM and
TANKWISE TM for pipelines and above ground storage tanks respectively.
RISKWISE TM has been outlined in previous publications, e.g. [12]. Only those aspects
relevant to evaluation of inspection frequency will be detailed here.
The evaluation of failure likelihood within the software includes a Damage Mechanism
Factor (DMF) based on an assessment of whether failure is not credible (NC), unlikely
(UL) or likely (L) in each of three forward time frames, 1TA, 2TA and 3TA where TA
normally represents the current inspection or turnaround interval. This approach takes
account of uncertainties in plant inspection data as well as uncertainties in damage rules.
The RLI is derived on the basis of equivalence between damage and overall failure
likelihood rating and hence also between damage rate and likelihood change rate (LCR).
The LCR is obtained from the evolution of failure likelihood over the periods: 1TA,
2TA and 3TA. For example if it remains NC (i.e. NC/NC/NC) over these time periods
then the LCR is low. On the other hand if the failure likelihood changes from NC to L
then the LCR is high. For a given damage mechanism, e.g. corrosion, the numerical
values of DMF relating to NC, UL and L are derived from the generic form of the
associated cumulative failure probability curve.
value is output to the user to provide a formal basis for assigning future inspection
periods.
The reliability of the calculated RLI as a conservative tool for establishing inspection
intervals has been calibrated against calculated remaining lives. A typical comparison is
presented in Fig.1, which shows that in all cases, the RLI is equal to or more
conservative than the corresponding calculated remaining lives.
30
10
RLI values, tabulated on the RISKWISETM risk summary screen, enable improved
inspection or other risk mitigation actions to be evaluated in priority order. The
sensitivity of the RLI and hence, inspection period, to various risk mitigation or
inspection relaxation (focus/defocus) actions can subsequently be assessed thereby
enabling cost-risk optimisation.
LFEWISETM is applied in cases where continuous degradation occurs with time, e.g.
internal corrosion of pipelines. The input information includes a life model and
uncertainty distributions in the model input parameters, notably: damage status, future
operating conditions and relevant material damage kinetics data. The associated
uncertainty distributions are subjected to a Monte Carlo probabilistic analysis to yield
the failure probability as a function of forward time. A cost analysis is also performed
using input on the cost of a planned repair or replacement in net present worth terms,
Sair
6ª Conferência sobre
Tecnologia de Equipamentos
In cases where cost information is not readily available a limiting failure probability
approach can be adopted to discern the safe remaining lifetime.
Level 1:
Level 2:
Level 3:
6. CASE STUDIES
PIPEWISETM
Design, O&M, Identify corrosion/ damage
Inspection Data Capture types & available models
DELIVERABLE
Level 1
RISKWISETM
Risk/Life Audit - RISKWISEpipelinesTM
software
• Risk Audit
• Semi-quantitative likelihood (L), Summary
consequence (C) and likelihood change
Level 2
L
rate (LCR) analysis
• Remaining life indicator (RLI)
estimation
• Optimum risk mitigation/inspection
measures C
• Inspection,
maintenance
and replacement
schedules
• Statistically
optimised
inspection
Quantitative Analysis- LIFEWISEpipelinesTM
coverage plan
• High risk lines/line lengths
• Quantitative probabilistic assessment and • Refined
Level 3
Hot/Cold
Tank Oxygen Reactor Separato
Item type Total farm Stripper & Heater r
Accumulator 1 1
Column 1 2
Drum 1 1
Reactor 1 1
Heater 1 1
Piping 10 2 5 3
Sair
6ª Conferência sobre
Tecnologia de Equipamentos
S&T 18 16 2
Exchanger
Tanks 2 2
Total 35 2 3 23 7
6.1.2 Results
The results are summarised in Figures 4-5. Figure 4 shows a summary of the results of
the risk audit on a risk matrix with likelihood categories 1-5 and consequence categories
A-E.
The severity of consequence was found to be greatest for the piping and shell and tube
heat exchangers
12 100%
90%
10
80%
8 70%
No. of Equipment
Cumulative %
60%
6 50%
40%
4
30%
2 20%
10%
0 0%
0 48 84 90 96 240 480
RLI, mths
Based on the time dimension of failure likelihood, implicit in the software, values of the
Remaining Life Indicator (RLI) were automatically output for each item and each
damage mechanism (DM). Where more than one DM exists then the minimum RLI
value is output. These are shown in the form of a distribution covering all the selected
items in Figure 5. It is seen that the computed RLI varies from zero to 480 months. In
view of the currently adopted inspection periods (IP) given above and subject to process
controlled shutdowns and statutory requirements there was clearly scope for
optimisation.
Details of some selected equipment items, damage mechanisms (DM) results and
recommendations are summarised in Table 2.
A summary of the major findings and benefits of the study is given as follows:
− The study highlighted areas where imminent risk mitigation was needed (e.g.
replacement of vapour condenser bundles).
Sair
6ª Conferência sobre
Tecnologia de Equipamentos
Risk
Risk
RLI,
RLI.,
IP,
Focus-defocus
temperature
mechanisms
Operating
Material;
proposal
Damage
Initial
Initial
Initial
Class
Class
mths
mths
mths
Item
New
New
Vapour Carbon Oxygen 0 48 5A replace 48 2A
Condense steel; pitting, bundle at
r 38C water side earliest
(Bundle) opportunit
y
(or install
air cooler)
Charge 9Cr 1Mo Sulphidati 480 48 1E relax to 480 1E
Heater steel; on, Creep, visual
Tubes 357C Vanadate inspection
attack only at
next
planned
shutdown
Feed Carbon General & 84 84 2B internally 168 1B
Tank steel; 25C pitting coat tank
corrosion floor with
epoxy
resin at
next
opportunit
y
Reactor P11 & Sulphidati 90 48 2E increase 90 2E
12Cr on, inspection
steel; Creep interval
380C cracking, for
Hydrogen cracking
attack, H+ (only) to
embrittle 96 mths
ment
Hot Carbon General 90 48 2E defer next 90 2E
Separator steel; pitting internal
101C corrosion, inspection
HIC, for further
Stress 48 mths;
corrosion external
cracking UT
(only) at
normal
inspection
interval
(48 mths)
Sair
6ª Conferência sobre
Tecnologia de Equipamentos
The case study covers subsea pipelines used for oil production and water injection,
where the key problem was internal corrosion and limited inspection data. Both were
addressed in the study.
The objective of the study was to assess the useable remaining life of in excess of 260
oil production and water injection lines with an age in the range 1 to 39 years. The
internal damage mechanisms to be addressed included: CO2 corrosion, H2S corrosion,
microbial corrosion, oxygen induced corrosion, HIC and stress corrosion cracking.
Calculate corrosion
rate using
Process Database Predict Consequence
Assessment
Diameter
Grade Determine cumulative
Nom WT corrosion rate
Age
from flow data
Assign a prevailing
corrosion rate
(future)
RISKWISEpipelinesTM
Figure 8: PIPEWISE TM Level 2 remaining life ranking procedure for oil production
lines
In view of the paucity of inspection data it was necessary to use corrosion modelling
tools such as PREDICT software. The RISKWISEpipelinesTM software was used to
establish failure likelihood factors which were centred on current line condition
Sair
6ª Conferência sobre
Tecnologia de Equipamentos
(cumulative corrosion), likelihood of failure within forward time frames (e.g. 5, 10 and
15 years) and inspection effectiveness.
Level 3 was aimed at the quantitative estimation of the useable remaining life of
selected lines using TWI's LIFEWISEpipelinesTM probabilistic approach. It involved:
- calculation of the probability of corroded thickness being less than the minimum
required thickness.
It was generally found that, where line-specific thickness data were available or could
be obtained, assessed lives could be extended by up to 16 years above estimates made in
the absence of such data. The useable remaining life was based upon the exceedence of
target reliability levels, which were selected from pipeline standards. A target reliability
value of 10-5 was used for the high safety-class oil production lines and a value of 10-2
was adopted for the low safety-class water injection lines.
The output enabled the operator to formalise a pipeline inspection and replacement plan
with associated savings resulting from reduced business interruption, deferred capital
spend and minimised liability uncertainties.
7. CONCLUDING REMARKS
The key issues for effective implementation of semi-quantitative RBI tools have been
addressed. These include: the need to retain application efficiency and user friendliness,
as levels of sophistication increase; expert judgement in identifying existing and
potential damage mechanisms (based on a combination of operational process
experience and design and material degradation issues); an audit team approach to RBI
implementation providing multi-disciplinary input and facilitating on-the-job training
and transfer of assessment know-how; consideration of risk management measures such
Sair
6ª Conferência sobre
Tecnologia de Equipamentos
The status of RBI within existing regulatory framework has been reviewed in addition
to relevant guidelines for the application of RBI and assessment of inspection
periodicity. Both the API and ASME approaches advocate progression from a relatively
simple qualitative risk-ranking method to a far more complex quantitative method
requiring significant effort and expertise to execute. However, neither approaches offers
clear and formal methods to translate risks into inspection frequencies.
The scope for formal methods for determining inspection periods, based on reliability
and remaining life considerations, is dependant on whether degradation mechanisms are
predictable and can be incorporated in predictive models. It has been shown that the
semi-quantitative Remaining Life Indicator (RLI), as incorporated in RISKWISE TM
software, can be sufficient for plant-wide inspection planning as well as establishing
risk management measures. This approach has been illustrated for in a case study on a
Naphta HDS unit within an oil refinery. If a more refined analysis is required, e.g. for
critical equipment, fully quantitative assessment tools can be used. This has been
illustrated in a case study on sub-sea pipelines using the LIFEWISE TM software and
PIPEWISE TM programme.
8. ACKNOWLEDGMENTS
9. REFERENCES
4 The Health and Safety at Work etc, Act 1974. A guide to the Health and Safety
at Work etc. Act,1974, 4th Edition. 1990, ISBN 0 7176 0441 1.
5 Pressure Systems Safety Regulations 2000 (SI 2000 No. 128): Safety of pressure
systems. Approved code of practice L 122. HSE Books 2000, ISBN 0 7176
1767X.
8 The Provision and Use of Work Equipment Regulations 1998. Approved Code
of Practice and Guidance l22 (Second Edition). HSE Books, ISBN 0 7176 1626
6.
10 Risk based Inspection Base Resource Document, 2000 API Publication 581,
Primary Draft, American Petroleum Institute, May 2000.