100% found this document useful (2 votes)
922 views14 pages

Safety in Design Report PDF

This safety in design report was prepared for the proposed Tuggerah Regional Sporting and Recreation Complex in Tuggerah, NSW. It identifies potential safety risks associated with the large number of pedestrians arriving by bus and moving around the facility. The report outlines steps taken in the design to reduce these risks, and requirements for operators to be compliant with workplace health and safety regulations. Examples of similar facilities demonstrate that comparable safety procedures are already in place elsewhere. Risk assessment matrices evaluate risks at different stages of the design, construction, operation, and demolition of the project.

Uploaded by

Selva Kumar C
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
100% found this document useful (2 votes)
922 views14 pages

Safety in Design Report PDF

This safety in design report was prepared for the proposed Tuggerah Regional Sporting and Recreation Complex in Tuggerah, NSW. It identifies potential safety risks associated with the large number of pedestrians arriving by bus and moving around the facility. The report outlines steps taken in the design to reduce these risks, and requirements for operators to be compliant with workplace health and safety regulations. Examples of similar facilities demonstrate that comparable safety procedures are already in place elsewhere. Risk assessment matrices evaluate risks at different stages of the design, construction, operation, and demolition of the project.

Uploaded by

Selva Kumar C
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd

Safety in Design Report

Tuggerah Regional Sporting and Recreation Centre


Lake Road, Tuggerah, NSW

Client: Wyong Shire Council

Date: 31.03.16

Revision: 02
 
 

Contents

Contents  ......................................................................................................................................................  2  
1.   Introduction  &  Approach  to  Safety  in  Design  ..........................................................................................  3  
2.   Safety  in  Design  Methodology  ...............................................................................................................  5  
3.   Risk  Management  -­‐  Safety  in  Design  .....................................................................................................  6  
4.   Safety-­‐In-­‐Design  Risk  Assessment  Matrix  -­‐  Design  .................................................................................  8  
5.   Safety-­‐In-­‐Design  Risk  Assessment  Matrix  -­‐  Construction  .....................................................................  10  
6.   Safety-­‐In-­‐Design  Risk  Assessment  Matrix  -­‐  Operation  .........................................................................  12  
7.   Safety-­‐In-­‐Design  Risk  Assessment  Matrix  -­‐  Demolition  ........................................................................  14  

 
  CKDS Architecture
  TRSRC Tuggerah Regional Sporting and Recreation Complex  
 
Page 2  
 
 
Principle1 People with control Safe design is everyone’s responsibility – ensuring safe
design rests with all parties influencing the design of a building
or structure.
1. Introduction & Approach to Safety in Design
Principle 2 The life cycle Safe design employs life cycle concepts – applying to every
phase in the life cycle of a building or structure, from conception
through to redevelopment and demolition.
1.1 Project Overview
This report has been prepared as part of the detail design and documentation of the proposed Tuggerah Regional Sporting and Principle 3 Risk management Safe design implements risk management – through
Recreation Complex at Tuggerah, NSW. systematically identifying, assessing and controlling hazards.

Through the design process a number of risks have been identified, particularly in regards to the design of the roads and vehicular
movement adjacent to the development, and the potential conflict with a large number of pedestrians.
Principle 4 Knowledge & capability Safe design requires knowledge and capability – which
In this report we aim to highlight potential risks and outline the steps taken to reduce or eliminate these. should be either demonstrated or accessed by any person
The key items addressed include: influencing design.

• The risks associated with the potential occurrence of a large number of pedestrians arriving by bus, and making their
way to various locations within the facility Principle 5 Information transfer Safe design relies on information – requiring effective
• The steps taken to reduce the associated risks through the design process. documentation and communication between everyone
• Requirements the operators will need to take into account in the future to be compliant under sections 17, 18 and 19 of involved in the life cycle of a building or structure.
the WHS Act.
• Safety for users of the amenities building.
• Examples of existing similar situations in other Council areas within the jurisdiction of the WHS Act, demonstrating that
similar procedures to that proposed are already in place.
• The steps taken to reduce the associated risks through the design process. Table 1: Principles of Safe Design
The Safety in Design matrix at the end of this document highlights the shared obligation of the designer and Council in managing
risk associated with their work systems.
The implementation of safe building design requires a thorough understanding of the WHS issues associated with each stage of a
building’s life cycle. These life cycle stages are summarised as below:
1.2 Background • Concept / schematic development

The proposed development has been designed to potentially accommodate a large number of participants and spectators. • Detailed design

This report outlines in detail potential risks, and proposed actions and controls to be put in place. The identification of Risks and • Construction
recommended actions have been nominated by Council and the design team. • Building occupation and operation
• Building maintenance & repair
1.3 What is Safety in Design (SiD) • Renovation &/or modification
• Demolition or demobilisation
Safety in Design (SiD) is a process defined as the integration of hazard identification and risk assessment methods early in
the design process to eliminate or minimise health and safety risks throughout the life of the product being designed.
Designers can achieve Safety in Design through a structured approach to identifying hazards & risks associated with the design. By
employing recognised risk management strategies, risks to users of a facility can be eliminated or significantly reduced through 1.4 Harmonised National Workplace Health & Safety
mitigation strategies and the implementation of design solutions based on risk assessments.
A sound approach to SiD includes assessment of risks during key phases of the design development, development of risk control As of the 1st of January 2012, the new harmonised National Workplace Health and Safety (WHS) legislation came into effect. As of
options and direction for safe construction, installation, commissioning, operation and maintenance of the completed facility. August 2013, seven jurisdictions the Commonwealth, NSW, QLD, SA, TAS, ACT, and the NT have enacted Work Health & Safety
The Code of Practice for Safe Design of Buildings and Structures developed by WorkCover NSW identifies five key principles for safe legislation. VIC has stated that it supports the principle of harmonisation but will not implement model WHS laws in their current
design. Table 1: Principles of Safe Design demonstrates these principles. form. The WHS model sets out new Codes of Practice aiming to regulate all the existing laws throughout the country, and create
a more consistent Work Health and Safety standard for all Australian employers and workers.

 
  CKDS Architecture
  TRSRC Tuggerah Regional Sporting and Recreation Complex  
 
Page 3  
 
 

Under the new Act, designers have a responsibility to ensure that their design of a building, plant and equipment eliminates and/or      
FACILITY L L   HEALTH & SAFETY   BENEFIT TO THE  
controls risks to the health and safety of people using them. Designers must also ensure that the facility is designed to eliminate or
minimise the need for any hazardous manual task to be carried out and give information to each person who is provided with the      

design about any features that eliminate the need for these task to be carried out. Design   Identification of potential risks.   Reduction of abortive design.  
   

Building designers must be familiar with section 22 of the Model WHS Act 2011. More specifically the content and requirements Elimination, reduction and control of risks.   Reduced need for post-­‐delivery retrofits.  
stated in regulations 61 and 294-296 of the WHS Regulation 2011 must be adhered to.      
Construction   Communication of residual risk to the   Reduction in contractor risk contingency.  
WorkCover NSW has developed the Code of Practice (CoP) for Safe Design of Buildings and Structures. The CoP was adopted in July contractor and sub-­‐contractors.    
2014, and is referenced as a guide to realising the standards of WHS under the act.   Greater time and cost certainty.  
Reduced likelihood of work site accidents
NSW has also adopted a number of other codes, most particularly the Code of Practice on Managing Workplace Risks. This code and injury.  
contains information on hazard identification and risk assessment.      
Operation   Increased health and safety for building Reduced operator WHS costs.
Of particular interest, designers of construction projects are required under the WHS legislation to provide a Safety in Design Report
occupants.  
(design risk assessment) to their client identifying the health and safety aspects of the design. Health and safety consideration should   Amplified organisational image.  
be given to those hazards or risks relating to areas such as access, site conditions, working environment, fall prevention, plant, Increased health and safety to members
Reduction in civil claims.  
structural safety, manual handling, amenities and facilities, fire and emergencies, hazardous substances, noise exposure and of the public.  
radiation.      
Maintenance   Safe practice for maintenance strategies.   Reduction in maintenance costs.  
This Safety in Design report will specify the hazards relating to the design of the structure and any control strategies recommended.    
Designers are required to develop and implement methods and processes to ensure safe design. In addition to this, when a design Reduced likelihood of workplace Streamlined maintenance strategies (time  
is altered, an additional review must be conducted to ensure that modifications do not present new risks. accidents and injury.   & cost benefits).  
Clients or organisations responsible for commissioning / managing designers on behalf of their clients must consult with their      
design team to ensure that any hazards and risks that may be present in the completed structure / workplace are addressed. Refurbishment / Communication of residual risk to the   Reduction in Contractor risk contingency.  
 
Additionally, clients are required to inform their designers of any risks and hazards that may exist in the area construction work is to Demolition   contractor and sub-­‐contractors.  
  Greater time and cost certainty.  
take place. Reduced likelihood of unplanned events.  
It is recommended that the SiD Report be passed onto any participant in the project who may extend the design or further develop
the design. This includes D&C Sub-contractors, designing fabricators, and specialist design consultants. In addition to this, the  
Table 2: Benefits of SiD Process
legislation recommends that the SiD Report be issued in parallel with the completed design documents to the principal contractor (if
not already involved in the design), associated authorities, building certifier, or agencies involved in the assessment or critique of the
design.
Clients and designers must consult with the project stakeholders who will be using the facility / workplace, during the planning phase 1.5 Objectives of the Safety in Design Process & Report
of the project, as their health and safety may be affected by the new design.

The benefits of employing a design risk management process during the development of a design extend beyond the provisions of a The objectives of the SiD process and report is to ensure that safe design principles are undertaken by the company on each project
facility that can be constructed and operated safely. Table 2: Benefits id SiD Process demonstrates the positive outcomes achieved in alignment with WHS legislation.
via this process.
As building design impacts on the overall safety of a completed facility and often plays a significant role in determining operational
WHS within the built environment, the SiD process must be seen as an essential element in achieving best practice outcomes.
Employing the SiD process should result in minimisation of illness and injury to contractors, end users operating the facility, and
facilities staff maintaining the building.
Further to this, the SiD process presents positive commercial outcomes for designers, contractors and clients alike. The cost
associated with unsafe design can be generated through the need to retrofit additional building infrastructure, inefficient operations,
higher insurance premiums, and potentially litigation or civil action. It is substantially more economical to eliminate workplace safety
hazards through the implementation of a structured risk management process during the design phase.

 
 
  CKDS Architecture
  TRSRC Tuggerah Regional Sporting and Recreation Complex  
Page 4  
 
 

STEP 1: Discuss the project


The design team and client representative involved in the development of the design must collaboratively plan
2. Safety in Design Methodology and discuss the project to ensure the exchange of information. The designers and client must identify all operations
to take place in and around the facility to ensure the design can be tailored to the operational requirements.
These discussions will also help to identify the potential hazards and risk associated with the intended operations.

2.1 Safe Design Process STEP 2: Identify key stakeholders


The project team is to identify additional project stakeholders for inclusion in the consultation process. The
The following section of this report describes the methodology and implementation of the SiD process. operational expertise of the facilities users should be drawn upon to help develop functional design.

The safe design process should be engaged as early as possible in the development of the design. By considering SiD during the
very early concept design phase, fundamental decision-making can occur during preliminary design development. This will avoid STEP 3: Determine the consultation process
unnecessary reworks or abortive design. Once the design team has been established, the design manager should determine the approach to
The table below describes the eight steps associated with the delivery of safe design through the SiD process. communication and collaboration.

STEP 4: Prepare a risk and solutions register


STEPS DELIVERY OF SAFE DESIGN The design team should conduct a preliminary risk analysis in consultation with key project stakeholders. The
intention of this step is to identify all conceivable risks and hazards that are relevant to the facility and its intended
1 Discuss the project operations. All risks and hazards will be recorded in the risk register.
Once all risks and hazards have been identified, the design team is to identify the likelihood and consequence
associated with the risk. Commonly this is achieved through a quantitative assessment to establish a risk ranking.
2 Identify key stakeholders See section 3 of this report for the approach to risk assessment.
Once the risks are assessed the design team will develop solutions to each of the risks to either eliminate or
mitigate the effect of the risk. Each solution will be documented in the risk register. See Section 5 of this report for
3 Determine the consultation process instructions on the risk assessment process.

4 Prepare a risk and solutions register STEP 5: Prepare an initial report to the client
On completion of the risk assessment, a report to the client will be prepared to identify the intended design
solutions for review and approval.
5 Prepare an initial report to the client

STEP 6: Amend and finalise the design


Based on the client’s review and acceptance of the report, the design is to be updated in alignment with the
6 Amend and finalise the design
documented strategies.

7 Provide a final report to the client STEP 7: Provide a final report to the client and principle contractor
On completion of the design, a final SiD report is to be prepared and issued to the client and principle contractor
for construction. It is recommended that the final SiD report be passed onto the facility occupant to contribute to
their development of safe work practices and procedures.
8 Review the design
The report must identify any residual risk, so that further operational controls can be developed by the facility
operator.

STEP 8: Review the design


As design development in certain projects continues into the construction phase through the development of
workshop drawings and contractor proposed alternatives, it is important that any risk controls potentially affected
by these elements are re-assessed. Furthermore, if additional information with regard to facility operations
becomes available post completion of the design documentation, further assessment and development of controls
may be necessary.
 
 
  CKDS Architecture
  TRSRC Tuggerah Regional Sporting and Recreation Complex  
Page 5  
 
 

3.2 Type of Risk


3. Risk Management - Safety in Design Safety risks present within the design of a facility can be categorised by the following:

3.1 Risk Management


TYPE DESCRIPTION

Designers, design managers & individuals involved in the production of building design should endeavour to eliminate any
R Reliability
foreseeable hazards that may arise from the design of a facility. As it is not always reasonably practical to eliminate all risks
associated with the built environment, designers and design managers must implement risk control measures through a structured
approach to risk management. A Accessibility

Risk management must form an integral part of the design development process. Ideally risk management should be M Maintainability
discussed regularly at design meetings, and through planned workshops to ensure key decision making and design development is
cognisant of the necessary risk controls required to deliver safe design.
B Buildability
The risk management process includes four key stages to developing and maintaining safe outcomes. These stages are described
below and further represented in Figure 1: Risk Management Process. O Operability

S Security
• Hazard identification – identification of potential hazardous situations that could result in injury or illness.

• Risk assessment – assessment of how likely the risk is and the associated consequence if the hazard occurs.

• Risk elimination / control – elimination or control of the risk through planned strategies and mitigation measures. 3.3 Hierarchy of Controls
• Evaluation and review – recurring review of risk controls and mitigation measures to ensure they remain current and
The two key definitions of risk controls are as follows:
appropriate.
Static controls – the physical components and electronic systems that form part of the built facility that will be handed over to the
end user. These controls are the responsibility of the project team, including the subcontractors, the architects, the
engineering designers and other sub-consultants on the project.
Dynamic controls – the administrative procedures to be implemented by the ‘tenant’ during the operation of the facility.

Risk mitigation strategies that form the outcome of the SiD process can be characterised by the following hierarchy of controls
shown in the Table 3: Hierarchy of Controls. The name ‘hierarchy of controls’ emphasises that elimination of a risk will always be
preferred to mitigation or reduction strategies where achievable.

Figure 1: Risk Management Process

 
 
  CKDS Architecture
  TRSRC Tuggerah Regional Sporting and Recreation Complex  
Page 6  
 
 

      Table 4: Severity of Consequences identifies the ascending severity of consequences. The greater the consequence the higher
L   L     numeric scores, for example, 1 represents an insignificant consequence, while 5 represents a catastrophic consequence.
     
1   Elimination   Design the hazard out of the building or structure.  
     
2   Substitution   Substitute less hazardous materials, fixtures, fittings, plant or
   
construction methods.      
     
   
3   Isolate   Use guards or barriers to limit access to the hazard.   1   Occurrence would have an insignificant impact on the operation of the facility and the health &  safety
      of the building occupants.  
4   Engineering   Minimise risk by engineering means, e.g. provide a permanent building
maintenance unit to maintain the external façade of the building.      
2   Occurrence would have a minor impact on the operation of the facility and the health & safety of
     
5   Administrative controls   Recommend the establishment of systems of work or signage, where the building occupants.  
required, to control residual risks.      

      3   Occurrence would have a moderate impact on the operation of the facility and the health & safety
6   Personal protective equipment   Recommend suitable personal protective equipment and training, where of the building occupants.  
required, to control residual risks.  
   
  Table 3: Hierarchy of Controls 4   Occurrence would have a major impact on the operation of the facility and the health & safety of
the building occupants.  
   
3.4 Risk Evaluation 5   Occurrence would have a significant impact on the operation of the facility and the health & safety
of the building occupants.  
Risks will be evaluated in alignment with the table below. High and extreme rated risks will require additional controls. The likelihood
allocation combined with the consequence score identifies the risk ranking as displayed in the matrix below.  

Table 4: Severity of Consequences


Determine the Consequence (C )

1 2 3 4 5

Insignificant Minor Moderate Major Catastrophic

A Almost Certain High High Extreme Extreme Extreme


Determine the Likelihood (L)

B Likely Moderate High High Extreme Extreme

C Possible Low Moderate High Extreme Extreme

D Unlikely Low Low Moderate High Extreme

E Rare Low Low Moderate High High

 
 
  CKDS Architecture
  TRSRC Tuggerah Regional Sporting and Recreation Complex  
Page 7  
 

4. Safety-In-Design Risk Assessment Matrix - Design

Risk Score before Controls Control Measures Risk Score after Controls
(Refer item 3 of guide) (Refer item 2 of guide) (Refer item 3 of guide)

Consequence

Consequence
Likelihood

Likelihood
Type Of Risk
Risk Additional Control

Risk Score

Risk Score
Issue (RAMBOS) Foreseeable Risk associated with the Issue
Control Control
ID Control Description/ Action Action by Required
Hierarchy Type
(static /
dynamic)

A-E

A-E
1-5

1-5
1. EGRESS & ACCESS
Access footpath to be sufficiently wide enough for large CKDS /
Bus to drop off large numbers of participants Safety of people adjacent bus traffic.
1.1 A,O A 4 Extreme numbers. Design Elimination Static E 1 Low -
during major events. Drivers not seeing children.
Clear Signage (for both traffic and pedestrians. Team

Clear signage for drop off. CKDS /


1.2 Internal drop-off zone. A,O Pedestrian / car conflict. B 2 High Design Substitution Static E 1 Low
Space for passing parked cars.
Team

Additional lane width to accommodate ease of bus CKDS /


External bus / car parking. Conflict between buses and cars. Elimination Static
1.3 A,O C 3 High Design B 2 High
movement.
Team

1.2 Obscured view to oncoming traffic. Design buildings that are well back from the corners giving CKDS Elimination
Vehicles entering and leaving the car park. A,O C 3 High Static B 2 Moderate
Conflict with pedestrians. good vision as per AS.2890. -
2. LANDSCAPED AREAS (General Access, Compliancy, Facilities, Users)
A,O Surfaces playable and safe for intended use. C 3 Detail of playing surface and substrate to enable intended
2.1 Field surface fit for use. Moderate use. Design Team Elimination Static B 1 Moderate -

A,O Obscured view to oncoming traffic. C 3 Selection of planting to enable clear view of road,
2.1 Vehicles entering and leaving the car park. Moderate footpaths and intersections. Design Team Elimination Static D 3 Moderate -

3. AMENITIES BUILDING (Security, Safety)


All access doors to be clearly visible from outside the
Safety for children to access and use the Access to public amenities to clearly visible for CKDS /
3.1 A,O C 5 High building. Elimination Static E 1 Low
amenities. passive surveillance, with no hidden recesses. Design Team

4. CIVIL WORKS

Due consideration of existing conditions and High Civil works to provide stable playing fields
4.1 Conformance with Geotechnical A,O A 4 Design Team Elimination Static E 1 Low
geotechnical recommendations in civil design

Layout of fields to be provide playing facilities in


Field setout in accordance with national field High Design Team Static E 1
4.2 Field Setout and Profile A,O A 4 accordance with Council requirements Elimination Low
dimension requirements including runoff areas.

Civil Works to accommodate return to play conditions as


Stormwater runoff to allow Client required timing High Design Team Static E 1
4.3 Stormwater runoff A,O A 4 required by council Elimination Low
between rain and return to play

5. IRRIGATION

Close coordination, good open and clear


communication and very accurate set out with Design Documentation to be co-ordination for minimal site
5.1 Co-ordination A,O particular attention to invert levels of the site A 4 High work discrepancies. Design Team Elimination Static E 1 Low
drainage and the intensive drainage system and final
finished surface levels is key to the designs success

    Page 8    
CKDS Architecture
TRSRC Tuggerah Regional Sporting and Recreation Complex  
 
 

The project is of significant size and there is minimal


fall across the site. This poses significant risk to the
overall success of the project. Preceding bulk earth Design Documentation to accommodate existing site
5.2 Response to Natural Topography A,O works and accuracy of subgrade levels and final A 4 High parameters. Design Team Elimination Static E 1 Low
levels and accurate grades of the imported final
growing soil will be  critical.  

Use of other than specified products and materials.


The design has taken into account materials that are
relatively common to the respective industries (
Irrigation and Intensive Drainage systems) however
both are quite small and unique complex industries on Design Documentation to meet current and appropriate
5.3 Material and Product Selection A,O projects of this size and scope. The irrigation design A 4 High standards, considerate of specific site conditions. Design Team Elimination Static E 1 Low
especially utilises computer modelling for watering
efficiency and the use of other products or material’s
could make significant impacts on the immediate and
long term result’s and costs to Council.

    Page 9    
CKDS Architecture
TRSRC Tuggerah Regional Sporting and Recreation Complex  
 
 

5. Safety-In-Design Risk Assessment Matrix - Construction

Risk Score before Controls Control Measures Risk Score after Controls
(Refer item 3 of guide) (Refer item 2 of guide) (Refer item 3 of guide)

Consequence

Consequence
Likelihood

Likelihood
Type Of Risk
Risk Additional Control

Risk Score

Risk Score
Issue (RAMBOS) Foreseeable Risk associated with the Issue
Control Control
ID Control Description/ Action Action by Required
Hierarchy Type
(static /
dynamic)

A-E

A-E
1-5

1-5
1. EGRESS & ACCESS
2. LANDSCAPED AREAS (General Access, Compliancy, Facilities, Users)
B.S Accessibility to landscaped zones which is located C 2 Site Management Plan required to regulate vehicle and
2.1 Delivery of materials adjacent field works. within field construction zone. Moderate pedestrian movement. Contractor Elimination Static D 3 Moderate

3. AMENITIES BUILDING (Security, Safety)


Site Management Plan required to regulate vehicle and
Accessibility to amenities site, which is located within Contractor Elimination Static E 1
3.1 Delivery of materials adjacent field works. B.S C 2 Moderate pedestrian movement. Low
field construction zone.

4. CIVIL WORKS
B.S It is the responsibility of the Civil Contractor, Principal
Contractor and the Project Manager to ensure all works
Personal injury. relating to excavation for civil services are undertaken by Contractor Engineering Static C 3 Moderate
4.1 Excavations. Damage to existing services. C 3 High fully qualified professionals. A work risk assessment must
Safe operating procedures. be prepared for every excavation, hazards identified and a
work method statement provided and implemented.
B.S It is the responsibility of the Civil Contractor, Principal
Personal Injury. Contractor and the Project Manager to provide a safe
Working within an operational public working environment that is totally separated with solid Contractor Engineering Static C 3 Moderate
4.2 Damage to existing services. C 3 High
environment. fencing that will not allow access by the occupants of the
Safety of general public.
public to the site.
B.S It is the responsibility of the Civil Contractor, Principal
Contractor and the Project Manager to ensure all
Construction equipment and machinery. Personal Injury. construction equipment and machinery is in good working Contractor
4.3 C 3 High Engineering Static C 3 Moderate
Damage to equipment order, all electrical equipment is tested and tagged and all
personal safety equipment is working at all times.
B.S It is the responsibility of the Civil Contractor and Principal
Contractor to engage a qualified underground services Contractor Engineering Static C 3 Moderate
4.4 Existing underground services. Damage to existing services. C 3 High locator to identify all underground services prior to any
excavation occurring in all areas.
B.S It is the responsibility of the Civil Contractor, Principal
Contractor and the Project Manager to provide safe all
weather access to the site. All vehicles that need to cross
Personal injury.
Site access. any areas where school students or staff have access, Contractor Engineering Static C 3 Moderate
4.5 Safety of general public. C 3 High must be accompanied by an escort on foot to look out for
Safety of on site staff. and manage a clear safe passage for the vehicle.

B.S It is the responsibility of the Civil Contractor, Principal


Working with other trades; Contractor and the Project Manager to coordinate all work Contractor Engineering Static C 3 Moderate
4.6 Conflict of on site workers and equipment. C 3 High areas where multiple trades need to work in close proximity
and ensure safe work practices are implemented.

B.S The Civil Contractor, Principal Contractor and the Project


Manager are to adequately treat and/or dispose of any
Contaminated soils; Discovery of contaminated soils, and appropriate dangerous site materials including contaminated soils and Contractor Engineering Static C 3 Moderate
4.7 C 3 High
disposal. asbestos in accordance with the Authorities Regulations,
Industrial Standard and Practices.

    Page 10    
CKDS Architecture
TRSRC Tuggerah Regional Sporting and Recreation Complex  
 
 

It is the responsibility of the Civil Contractor, Principal


Contractor and the Project Manager to provide safe all
Environmental factors; Safety of persons on site, and equipment when weather conditions at the site. A work risk assessment Engineering
4.8 B.S
exposed to adverse environmental conditions.
C 3 High must be prepared for environmental factors (such as rain, Contractor Static C 3 Moderate
flooding, wind, snow, etc), hazards identified and a work
method statement provided and implemented.

It is the responsibility of the Civil Contractor, Principal


Temporary works. Safety of persons on site, and equipment during the Contractor and the Project Manager to provide temporary Engineering
4.9 B.S
undertaking of temporary works.
C 3 High works to provide access to the worksite or to support works Contractor Static C 3 Moderate
until they have been completed.

5. IRRIGATION      
Highly skilled specialist contractors are considered It is the responsibility of the Civil Contractor, Principal
critical to ensure best results and minimal long term Contractor and the Project Manager to provide and
5.1 Contractor Selection B.S issues. Again close coordination between all trades C 3 High monitor Work adequate Methods Statements and engage Contractor Engineering Static C 3 Moderate
on site with good communication skills will be key. appropriately qualified sub contractors to carry out the
works as programmed.
Prevention of damage to key irrigation and intensive
drainage components. During construction and
following construction any accidental damage to
wiring, piping, pumps filters or valves will be
It is the responsibility of the Civil Contractor, Principal
detrimental to reliable operation. Faulty repairs and
Contractor and the Project Manager to provide and
debris in pipelines pumps and filters is the fastest way
Damage to Irrigation and Drainage monitor Work adequate Methods Statements and engage
5.2 B.S to introduce problems into a new system. Any and all C 3 Contractor Engineering Static C 3 Moderate
Components High appropriately qualified sub contractors to carry out the
damage which may occur MUST be rectified only by
works as programmed.
specialist contractors and pipes fully flushed and
inspected and damage components plotted on the
survey Work as Executed drawings. During
construction all valve and drainage pits to be
protected

Work As Executed drawings. The system should be


witnessed and surveyed independently for verification
of correct materials and record of completed works at
It is the responsibility of the Civil Contractor, Principal
stages during construction to ensure quality is
Contractor and the Project Manager to manage and
5.3 Work as Executed Drawings M maintained and the design is followed. Any necessary E 2 Low Contractor Engineering Static E 1 Low
review the production of Work as executed drawings.
site changes which may become apparent can then
also be confirmed and assured as to their correct
placement and authenticity.

    Page 11    
CKDS Architecture
TRSRC Tuggerah Regional Sporting and Recreation Complex  
 
 

6. Safety-In-Design Risk Assessment Matrix - Operation

Risk Score before Controls Control Measures Risk Score after Controls
(Refer item 3 of guide) (Refer item 2 of guide) (Refer item 3 of guide)

Consequence

Consequence
Likelihood

Likelihood
Type Of Risk
Risk Additional Control

Risk Score

Risk Score
Issue (RAMBOS) Foreseeable Risk associated with the Issue
Control Control
ID Control Description/ Action Action by Required
Hierarchy Type
(static /
dynamic)

A-E

A-E
1-5

1-5
1. EGRESS & ACCESS
Directional Signage and Management Plan to Administrative
Bus drop of large numbers of participants Safety of people adjacent bus traffic. implemented by facility management. Facility
1.1 A,O B 3 High Dynamic E 1 Low
during major events. Drivers not seeing children. Management

Directional Signage and Management Plan to


Internal drop off zone. Pedestrian / car conflict implemented by Facility management. Facility Administrative Dynamic
1.2 A,O B 3 High Management
E 1 Low

Directional Signage and Management Plan to


Facility Administrative
1.3 External bus / car parking. A,O Conflict between buses and cars. B 3 High implemented by Facility management. Dynamic C 3 Moderate
Management

Traffic Management Plan to be implemented and


1.2 A,O. Obscured view to oncoming traffic. monitored by facility management to maintain security Facility Administrative
Vehicles entering and leaving the car park. C 3 High systems and landscaping to maintain safe vehicle / Dynamic C 3 Moderate
S Conflict with pedestrians. Management
pedestrian movement.

2. LANDSCAPED AREAS (General Access, Compliancy, Facilities, Users)


Maintenance plans to be developed based on design
Maintenance of soft landscaping and playing R,O Playing fields maintained for safe usage. C 3 documents to be implemented and monitored by facility Wyong Council Administrative v E 1
2.1 High Low
fields. management.
3. OPERATIONS & MAINTENANCE (Maintenance/Repair, Cleaning, Waste Management Inspection/Testing, Documentation, Security, Safety)
Directional Signage and Management Plan to be co-
Administrative
M,O ordinated with Waste Contractor and Council to Wyong Council Dynamic E 1
3.1 Safe operation of garbage collection vehicles. Conflict of common paved areas with facility users. C 3 High Low
.S implemented by Facility management

On Site Traffic management Plan to be implemented by


M. Facility Management Wyong Council Dynamic E 1 .
3.2 Safe operation of maintenance vehicles. Conflict of common paved areas with facility users. C 3 High Administrative Low
A,O

4. AMENITIES BUILDING (Security, Safety)


Signage and safe working of doors latches etc. to be
maintained by facility management. Administrative
Safety for children to access and use the A,O Safe access, and clear surveillance of amenities Wyong Council Dynamic E 1
3.1 C 3 High Removal of obstructions to maintain clear visual access Low
amenities. .S access points.
to entrances to be maintained.

4. CIVIL WORKS Clear .


5. IRRIGATION
Maintenance. For the longevity and reliability of the
systems, each should respectively be serviced and
maintained by trained personnel in accordance and at
intervals as recommended by industry common or Provision of Maintenance Manuals. Maintenance plans
best practise and manufacture’s or the contractors
High to be developed based on design documents to be Wyong Council Administrative Dynamic E 1
5.1 General Maintenance R.M recommendations as to be supplied in the operation C 3 Low
manuals should be closely followed. The control implemented and monitored by facility management.
system on the irrigation and the pump system is quite
a specific specialised part of the system which can be
easily misunderstood by untrained persons.

    Page 12    
CKDS Architecture
TRSRC Tuggerah Regional Sporting and Recreation Complex  
 
 

Any shift or site equipment may impact significantly


on either the subsurface drainage system and or the
irrigation system. The shift or a light pole, pathway, Provision of Maintenance Manuals. Development of
building, drain, filed extension or reduction, kerb, goal Work Procedures and training of Stafff. Maintenance
High Wyong Council Administrative Dynamic E 1
5.2 General Site works and movements R.M post, section of planting or even he placement of a C 3 plans to be developed based on design documents to Low
garbage bin or site signage, could significantly impact be implemented and monitored by facility management.
the systems operation or efficiency. WAE plans and
the designers should always be consulted prior to the
addition of, or shift of anything on site.

The intensive drainage system is particularly prone to Development of Maintenance Work Procedures and
long term failure if pipes are damaged and not training of Stafff. Maintenance plans to be developed
High Wyong Council Administrative Dynamic E 1
5.3 Maintenance R.M correctly restored and or the incorrect drainage C 3 based on design documents to be implemented and Low
medium is replaced. monitored by facility management.

On going top dressing and or turf maintenance and


management, aeration and or coring etc can impact Development of Maintenance Work Procedures and
significantly the irrigation sprinklers and the intensive training of Stafff. Maintenance plans to be developed
drainage system. Only trained maintenance staff or High Wyong Council Administrative Dynamic E 1
5.4 Maintenance of top soil R.M C 3 based on design documents to be implemented and Low
specialists using the correct top dressing media monitored by facility management.
should be engaged for field renovation work to ensure
the longevity and reliability of all systems.

    Page 13    
CKDS Architecture
TRSRC Tuggerah Regional Sporting and Recreation Complex  
 
 

7. Safety-In-Design Risk Assessment Matrix - Demolition

Risk Score before Controls Control Measures Risk Score after Controls
(Refer item 3 of guide) (Refer item 2 of guide) (Refer item 3 of guide)

Consequence

Consequence
Likelihood

Likelihood
Type Of Risk
Risk Additional Control

Risk Score

Risk Score
Issue (RAMBOS) Foreseeable Risk associated with the Issue
Control Control
ID Control Description/ Action Action by Required
Hierarchy Type
(static /
dynamic)

A-E

A-E
1-5

1-5
1. EGRESS & ACCESS
2. LANDSCAPED AREAS (General Access, Compliancy, Facilities, Users)
3. AMENITIES BUILDING (Security, Safety)
Treat all materials for construction to comply with AS****
Hazardous materials encountered during Contractor Elimination Static B 1
3.1 Hazardous materials M C 4 Moderate so no known hazardous materials will be used in Low
demolition.
construction.
4. CIVIL WORKS

    Page 14    
CKDS Architecture
TRSRC Tuggerah Regional Sporting and Recreation Complex  
 

Safety in Design Report 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Tuggerah Regional Sporting and Recreation Centre
Page 2	
  
CKDS Architecture 
TRSRC Tuggerah Regional Sporting and Recreation Complex 	
  
	
  
	
  
	
  
	
  
	
  
	
  
Page 3	
  
CKDS Architecture 
TRSRC Tuggerah Regional Sporting and Recreation Complex 	
  
	
  
	
  
	
  
	
  
	
  
	
  
Page 4	
  
CKDS Architecture 
TRSRC Tuggerah Regional Sporting and Recreation Complex 	
  
	
  
	
  
	
  
	
  
	
  
	
  
	
  
Page 5	
  
CKDS Architecture 
TRSRC Tuggerah Regional Sporting and Recreation Complex 	
  
	
  
	
  
	
  
	
  
	
  
	
  
Page 6	
  
CKDS Architecture 
TRSRC Tuggerah Regional Sporting and Recreation Complex 	
  
	
  
	
  
	
  
	
  
	
  
	
  
3.
Page 7	
  
CKDS Architecture 
TRSRC Tuggerah Regional Sporting and Recreation Complex 	
  
	
  
	
  
	
  
	
  
	
  
	
  
	
  
CKDS Architecture 
TRSRC Tuggerah Regional Sporting and Recreation Complex 	
  
	
  
Page 8	
  
	
  
	
  
	
  
	
  
 
4. Safe
CKDS Architecture 
TRSRC Tuggerah Regional Sporting and Recreation Complex 	
  
	
  
Page 9	
  
	
  
	
  
	
  
	
  
5.2 
Resp
CKDS Architecture 
TRSRC Tuggerah Regional Sporting and Recreation Complex 	
  
	
  
Page 10	
  
	
  
	
  
	
  
	
  
5. Safet

You might also like