Conditions of Contract on Safety & Health end Environment, May 2019
f
| @ DELHI METRO RAIL CORPORATION LTD.
FURM No. : SE/23
PERMIT TO WORK - LIFTING PERMIT
‘SECTION — A: Details of Crew, Crane Configuration & Load Calculation
NAME OF CONTRACTOR CONTRACT NO.
PERMIT No. Date Time
Location, Activity being performed
Part - i
| Name of Lifting Engineer
| Name of Operators:
Names of Riggers:
[Name of Signal
(Bame of Signal man
Purt— 2; Crane Details
Crane Make, Model & Year: Max. Lifting Capacit
Maximum Boom Length: ‘Maximum Radius:
| Outrigger full extension (in mtr, Percentage of deratiun in crane capacity:
| Automatic Safe Load Indicator: Over Hoist Cut-off Limit Switch:
Part —3: Load Details
Description of the Load: Lifting points on Load:
Rigging Manner of load: Dimension of Load:
|Part—4: Load Calculation ( ‘% of Load chart referredifollowed)
| a) Crane Roam Length: b)Crane Boom Radius: __, ©) Rope Diameter(mm):
| d) No. of falls: + €) Deration in capaci £) Counter weight
. h) Weight of Load: ~__sh) Rigging We
) Total Weight to be lift:
(SWI. of crane on lifting configur
g) SWL (after deration
i) Hook Block Wei
) Safety margin in crane capa
}) Outriggers extension (in mtrs) _
[Part 5: Receipt
1 (Name of Lifting Engineer) hereby declare that the load calculation as mentioned in Part ~ 4 of this
permit shall not exceeds in any circumstances and work shall be carried out in safe manners. In addition,
the checklist along with lifting sketches as mentioned in section B of this permit shall be followed and also
attached. All measures have been adopted to ensure the stability & rigidity of the cranes as well as rigging.
All safety devices of the crane are in proper working order. Section A shall be treated as invalid without
| section B.
Name: Signed Time Date.
Part — 6: Clearance from Safety Department
(Name of Safety In-charge) also checked the above load calculation whicl
configuration for safe lifting operation.
— Load to be lifted),
within the erane lifting
Name: Signed Time Date‘Conditions of Contract on Safety & Health and Environment, May 2019
‘SECTION — B: Safety Checklist & Sketeh
Part - 7: Safety Measures Checklist
||S | Measures/particulars YesiNo/AviJother
No.
T | Crane use for lifting is suitable as per site condition and type of
| lining _
|[2 [Are lifting crew trained for lifting operation
| | 3___| Is crane set up on compacted and firm ground condition
(4 ‘Are crane outriggers fully extended and placed on metal plate
Are condition of lifting gears free from any type of defects
Ts condition of lifting appliance operator cabin in good condition | |
| | and wot 0 hi
adequate m
Is underground utilities presents, if yes, mentioned measures to
overcome & crane stability (mentioned in Method Statement)
9 | Is any power cable/OHE cable available, if yes, then measures to
| encounter that (mentioned in Method Statement)
10 | Safe means of access arranged
11 _| Safe working platform arranged
| [72 | Measures for working at height adopted
| 13__| ‘Traffic diversion along with provision of traffic marshal arranged
wdraunce Ww any
14 | Ts wind velocity check and under acceptable limit as recommended
by manufacturer
15 | Is copy of approved method statement available
16 | Is Automatic Safe Load Indicator working and cut off switch
provided & working
7 All certificate & document like TPI. Load chart etc. available
18 _ | Is proper arrangement of illumination done & level of lux
maintained
19 | Is rigging done by taking consideration of CG of load w.r.t crane.
hook
20 | Swing area of crane properly barricaded
21 | Other sysiem of crane like control lever, fail safe device, boom,
winch cte. are in good condition or working properly
22__| Is tag line to control the load is provided
“Any other measures
Part — 8: Lifting Sketch
(this sketch shall be site specific and reflects all hazards/obstruction along with dimension)
Consprtium of
a Mis Johnson Lifts
private Limited, India
‘and Mis SJEC
Corporation, ChinaConditions of Contract on Safety & Health and Environment, May 2019
a
Part 9 ; Final Authorization
| 1(ame of Lifting Engineer) hereby declare thatthe load ealelation as mentioned in Part ~ 4 of section
A and measures as mentioned in part 7 of section B shall be ensured. In addition, arrangement for safe
lifting, public safety, traffic diversion, working at height, means of access et has been adopted.
Name: Signed
Part - 10: Clearance from Safety Department.
1 (Name of Safety In-charge) certify that, measures for sae lifting have been adopted at site.
Name: Signed
PART 11; Clearance Certificate (By Lifting Engineer)
1 declare that all persons under my charge have been withdrawn and wamed that iti no tonger safe ro work at site,
| and that ll gear, toos and other equipment have been removed
ome Signed Time Date _ _
Part 12 : Cancellation (Being the Authorized Person)
| acknowledge receipt ofthe clearance of this Permit
This permit is now cancelled
Name: Signed Time Date
|
Ee
‘onsortium of
4 Johnson Lifts
Private Limited, India
and M/s SJEG.
Corporation, China