Qatar Building Permit Process Flow

sample for reference purposes only, i do not intend to own this document

Uploaded by

Trisha Salvador
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
3K views1 page

Qatar Building Permit Process Flow

sample for reference purposes only, i do not intend to own this document

Uploaded by

Trisha Salvador
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd

PERMITTING 

DETAILED PROCESS
PERMITTING PROCESS
FOURTH & FIFTH PRECINCTS
FOURTH PRECINCT
Design Consultant (DC) / Architect of Record (AoR) Ministry of Municipality & Environment Stakeholders’ Services Approval

Stakeho
PLANNING PERMIT PRE‐

Master Plan preparation and approval by Client
lders
APPLICATION

Submission of Master Plan to MMUUP
 Letter (Request for review of the development draft master plan)
 Explanatory Document KM – Electricity KM – Water
Planning Approval  Plumbing Drawing
 Conceptual Plans
Electricity service site plan with cable route  Plumbing Calculations
 Sustainability features and ratings Receive and review documents
 Development Phasing Plan
Substation Plans, civil details with dimensions 
and finishes.
 Illustrative Drawings HV (11kV) Single line diagram with HV cable 
 Comparison Table route.
 Broad Land Use Budget MV‐Panel and SMB Schematic diagrams with
cable sizes.
Voltage drop calculations.
Electrical Load Summary for each MV panels.
Submission: kWH Meters Summary
Civil Section Approval
 Letter (request for review of the development final master plan and issuance of 
Planning Permit and clearance to proceed in building permit) Reviewed / 
All above drawings in Planning Approval
specifically Civil Details
 All required information / Documents listed for Pre‐Application and corrected  Approved? Planning & Protection Approval
Drawings approved by Civil Section
PLANNING PERMIT APPLICATION

based on UPD review report.
 A0 Plan (3 copies) Installation Engineer Approval
All drawings approved by Planning &
N Y Protection Section

PEO
Compilation of the required documents “Package for Opening File”:  Hard copies of external elevations of the
 Copy of Ownership Document and Property Document (PD), certified by the  buildings excluding sections & details ASHGHAL – Drainage ASHGHAL – Roads
 Stamped drawings by PEO 

real estate registration (VL 6 months).
Copy of owner's ID or authorized person.  Another hard copy of the same contents an Item 
Drainage Drawing  Site drawings with road layout
 Hydraulic Calculation  TIS
 Establishment ID and commercial permit of the organization. 1 but on A3 or A4 size.
 Electronic copy of the full architectural drawings  Services Site Plan
 Housing department letter.
 Stability Certificate (for additional floor/s). in PDF format and AutoCAD
 Allocation letter (for government projects).  Electronic copy of the plot document, plot
number and plot ownership.
 Stability Certificate (for additional floor/s).
 No objection Letter from third parties such as the PEO, Supreme Council of 
 Hard copy of the perspectives and colored Planning Permit
presentation elevations QCDD ‐ Firefighting QCDD – Fire alarm
Health, AWQAF, etc. (please refer to the list beside this box)  
Hard and Electronic copy of the photos of the Detail Design Report (where (through QCD System)
 Copy of inquiry of planning and architectural regulations. existing buildings  applicable)  Detail Design Report (where
 Structural plans (for Rail).  A statement on the present status of the project  Fire Fighting system drawings (floor applicable)
 Street level site plan (from Ashghal).  A statement for the reasoning plans, elevations, sections)  Fire Alarm system drawings (floor
 Consultant’s authorization by owner.  Hard copy of any supporting document or  Schematic Diagrams plans, elevations, sections)
 Consultant Engineer Office Obligation. drawing you wish to add.  Fire Pump Rooms/Fire Water Storage   Schematic Diagrams with input‐
 Policy plan.  The elevations of all type of mosques,  (blow up plans required) output matrix
 Other Attachments. coordinated with the mosque sections in the   Calculation Reports (hydraulic,   Fire Command Center/Fire Pump
Ministry of Islamic Affair
manual, water) Rooms/Generator Rooms (if 
DC1, STAGE 1 OPENING FILE



ly
QCD Guidelines provided)
 Calculation Reports (battery load, 
audible/visible,lux)
Submission of the required documents: Reviewed /   QCD Guidelines
 Compiled “Package for Opening File” ‐ see above list. Internet
 Resubmission as requested by MMUP

Submission of the required documents:
N – (Additional information required)

Y
on
Approved?

QCDD – ACMV (through QCD System)



Detail Design Report (where
applicable)
ACMV system drawings (floor plans, 
elevations, sections)
 Approved Planning Permit (Master Plan) Reviewed / 

e
 Site Plan and Location Map Internet Schematic & Control Diagrams 
Approved?
 Architectural drawings( Floor Plans, Elevations, Sections) & schedule of   Pump Room/Generator Room
Accommodation/Area Statement Ventilation System (as required)
 Calculation Reports (smoke exhaust
nc

N
system, staircase & fire lift shaft 
Y
pressurization system, CFD Analysis )
 Stair & Lobby Pressurization (if
Submission of the required documents provided)
Kahramaa Building Permit Application (Electrical)  QCD Guidelines
 Bulk Application
re

Internet Manage and Transfer Internet


 Power layout (site plan)
Design Consultant)
N (Relay to the

 Single Line Diagram
 Substation Layout MOI Security
DC1, STAGE 2

 Official letter in Arabic director to
fe

SSD ‐ MoI.
 Copy of commercial registration with 
activity approved by SSD.
Submission of the required documents  Authorization letter in Arabic from
Qatar Civil Defense (QCD) the owner to the approved 
 Narrative/Fires safety report KM ‐ Electrical
re

QCD System QCD contractor/consultant.


 Floor Plans, Elevation, Sectional Drawings and Details  Copy of project contract.
 QCD Building Plan Guideline  Detailed list of all security
 Policy Plan surveillance equipment’s and devices 
BOQ.
QCD Approval  KM
N QCD System N  Detailed drawing of cameras
Approved? by MMUP Approved? locations for each floor.
r

 Cameras storage calculation details + 
Load calculation.
Fo

DC1 Approval  Control room design layout with all
TEMPORARY BUILDING 

security system equipment’s.
 Detailed schematic diagram drawing
Design beyond the end of Schematic Design till Final Building Permit by D&B Contractor of system.
PERMIT (BP)

 Technical specification of cameras
and security system devices.
 Copy of maintenance contract or
Submission periodical services level agreement 
 Temporary Building Permit request Reviewed & 
OOREDOO (SLA) (if available).
 DC1 Approval Approved?  Site Plan  Project time line plan details showing 
*SC’s support will be 
 Required undertaking letters / forms required  Ooredoo/telecom schematic the start & end dates.
 Ooredoo incomer details, Ooredoo 
N room details
Y
 Digital details of Ooredoo incomer
SERVICES’ APPROVAL

MOE
Temporary BP Obtained 
STAKEHOLDERS 

Approved EIA
Submission
 All required stakeholder design documents. Stake‐
 DC1 Approval form
MOT
 Approved DC1 Site Plan
holders  Approved TIS
 Other forms / documents
Services Approved
QCAA
QKLEEN  Building Plans

DC2 STAGE

 Site Plan shows garbage disposal  Elevations showing maximum height
Submission location  Policy Plan
 Updated Architectural documents
 Original approved services documents / drawings Reviewed & 
Y DC2 Approved
 Structural design Approved?
 3D modelling (as needed) QRAIL
 Other documents  Architectural, Location plan,
N Structural plans, Sections and 
WOQOD Elevations with QND (95) levels 
Y
BUILDING PERMIT 

 Brief Description of the Gas/liquid noted on all drawing including the 
fuel System required. loading design and foundation details
Building Permit Submission  Construction Layout (DWG)
 MMUP DC1 and DC2 Approval Notice  Proposed location of Fuel System
(BP)

 All Approved Drawings & Documents incorporated in the layout
 MMUP Form – Building Permit Request (with required fees if needed) Reviewed &   Detail drawings of the Fuel System
 MMUP Form – Consultant Engineering Office Obligation Approved?
Y Building Permit Obtained  Detail data of all Fuel System 
 MMUP Form – Contracting Company Obligation Equipment
 MMUP Form – Contracting Company Authorization
 MMUP Form – Owner Obligation
 MMUP Form – Engineering Consulting Office Authorization
N

LEGEND: