Gantt Chart Project Schedule

The document outlines a project schedule consisting of 5 main jobs with dependencies between sub-jobs. Job 2 involves getting materials from January 10-12, with 2 sub-jobs to obtain materials for parts A and B. Job 3 involves lathe work from January 13-19, including turning parts A and B on the lathe from January 13-16 and polishing part B from January 15-19. Job 4 assembles parts A and B on January 20-22, once their prerequisites are complete.

Uploaded by

Myiel Angel
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
75 views3 pages

Gantt Chart Project Schedule

The document outlines a project schedule consisting of 5 main jobs with dependencies between sub-jobs. Job 2 involves getting materials from January 10-12, with 2 sub-jobs to obtain materials for parts A and B. Job 3 involves lathe work from January 13-19, including turning parts A and B on the lathe from January 13-16 and polishing part B from January 15-19. Job 4 assembles parts A and B on January 20-22, once their prerequisites are complete.

Uploaded by

Myiel Angel
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd

Immediate Time Alloted

Job No. Activity Start Date End Date


Predecessors (days)
1 Start 0
2 Get Materials 2 1/10/2023 1/12/2023
2.1 Get Materials for A a 1 1/10/2023 1/11/2023
2.2 Get Materials for B a 2 1/10/2023 1/12/2023
3 Lathe 6 1/13/2023 1/19/2023
3.1 Turn A on lathe b,c 3 1/13/2023 1/16/2023
3.2 Polish B e 4 1/15/2023 1/19/2023
3.2.1 Turn B on lathe b,c 2 1/13/2023 1/15/2023
4 Assemble A and B d,f 2 1/20/2023 1/22/2023
5 Finish g 0

Legend:
Major Activity
Minor Activity
Sub Activity
Slack Time

Status
Ongoing
Completed
At Risk
Delayed
Not Started
Status
October
1/10/2023 1/11/2023 1/12/2023 1/13/2023 1/14/2023 1/15/2023 1/16/2023
Ongoing
Not Started
Not Started
Not Started
Not Started
Not Started
Not Started
Not Started
November
1/17/2023 1/18/2023 1/19/2023 1/20/2023 1/21/2023 1/22/2023