Drawing Schedule- Blocks & Villas

Target Dates
Sl. No. Particulars
B-1
A Architectural Drawings
1 Architectural Complete Set (Plans, elevations & sections) Received
2 Toilet Details (Wall elevations, Plumbing & Fixtures details) 01/Oct/22
3 Balcony Railing 01/Nov/22
4 Stair railing 01/Nov/22
5 Flooring Pattern (Inside Flats) 01/Dec/22
6 Flooring pattern (Common Area & Lift Facia) 01/Dec/22
7 Flooring Pattern (Stilt Floor) 01/May/23
8 Wardrobes & Kitchen Cabinet Details 01/Jun/23
9 External Painting Color Scheme 01/Oct/23
10 Internal Signage Details 01/Oct/23
11 Concierge Details 01/Oct/23

B Structural Drawings
1 Foundation Plan and Details Received
2 Column Layout Received
3 Column Schedule Received
4 Plinth Beam Plan & Details Received
5 1st Floor framing Plan, Beam & Slab Details Received
6 2nd to 9th Floor framing Plan, Beam & Slab Details 01/Sep/22
7 10th to 12th Floor framing Plan, Beam & Slab Details 01/Oct/22
8 Terrace Floor framing Plan, Beam & Slab Details 01/Nov/22
9 Machine Room & Over Head Tank 01/Dec/22
10 Service Platform Detail 01/Feb/23

C Electrical Drawing
1 Electrical Plan Stilt floor Received
2 Electrical Plan Typical floor 01/Sep/22

D Plumbing Drawings
1 Sleeve detail 01/Sep/22
2 Plumbing Plan stilt floor 01/Oct/22
3 Plumbing Plan Typical floor 01/Oct/22
4 Terrace Floor Drainage Plan 01/Dec/22
5 OHT sleeve detail 01/Jan/23
6 Schematic Line Diagram (Downcomers/Uprisers) 01/Feb/23
7 Terrace Ring line 01/Feb/23
Date: 24/Aug/22
Target Dates
B-2 Villas

Received Received
01/Oct/22 01/Sep/22
01/Nov/22 Received
01/Nov/22 Received
01/Dec/22 01/Oct/22
01/Dec/22 NA
01/May/23 NA
01/Jun/23 Received
01/Oct/23 Received
01/Oct/23 NA
01/Oct/23 NA

Received Received
Received Received
Received Received
Received Received
Received Received
15/Sep/22 Received
15/Oct/22 NA
15/Nov/22 NA
01/Dec/22 NA
01/Feb/23 NA

Received Received
01/Sep/22 Received

01/Sep/22 Received
01/Oct/22 NA
01/Oct/22 Received
01/Dec/22 Received
01/Jan/23 NA
01/Feb/23 NA
01/Feb/23 NA
Drawing Schedule- Club House 24/Aug/22
Sl. No. Particulars Target Dates

A Architectural Drawings
1 Architectural Complete Set (Plans, elevations & sections) 01/Oct/22
2 Railings Details 01/Dec/22
3 Flooring Pattern 01/May/23
4 Specifications 01/May/23
5 HVAC Detail 01/Jun/23
6 Interior Drawings (Complete Set) 01/Jun/23
7 External Painting Color Scheme 01/Jul/23
8 Furniture Details 01/Oct/23
9 Gym & Games Equipment Details 01/Dec/23
10 Signage Details 01/Dec/23

B Structural Drawings
1 Foundation Plan and Details 01/Oct/22
2 Column Layout 01/Oct/22
3 Column Schedule 01/Oct/22
4 Plinth Beam Plan & Details 01/Oct/22
5 1st Floor framing Plan, Beam & Slab Details 01/Nov/22
6 Terrace Floor framing Plan, Beam & Slab Details 01/Dec/22
7 Machine Room & Over Head Tank 01/Jan/23

C Electrical Drawing
1 Electrical Plan Ground floor 01/Nov/22
2 Electrical Plan 1st floor 01/Nov/22
3 Electrical Plan Terrace floor 01/Dec/22

D Plumbing Drawings
1 Sleeve detail 01/Nov/22
2 Plumbing Plan Ground floor 01/Dec/22
3 Plumbing Plan 1st floor 01/Dec/22
4 Terrace Floor Drainage Plan 01/Jan/23
5 OHT sleeve detail 01/Jan/23
6 Schematic Line Diagram (Downcomers/Uprisers) 01/Feb/23
7 Terrace Ring line 01/Feb/23
Drawing Schedule- External Services 24/Aug/22
Sl. No. Particulars Target Dates

Landscape Drawings
1 Main Gate Received
2 Water Body Received
3 Landscape Setting out Plan 01/Jan/23
4 Lanscape Road, Pathway & Kerb setting out 01/Feb/23
5 Landscape Detail for Parks, Grading & Sections 01/Feb/23
6 Landscape Detail for Feature elements 01/Mar/23
7 Outdoor sports Activities 01/Apr/23
8 Amphitheatre Details 01/May/23
9 Swimming Pool Architecture Detail 01/Nov/23
10 Plantation Plan 01/Nov/23

Services
1 STP 01/May/23
2 UG Tank 01/Jul/23
3 Electrical Sub station 01/Jul/23
4 Sewage Disposal Plan 01/Jul/23
5 Storm water drainage with RWH Pits 01/Aug/23

Structure Drawings
1 Swimming Pool 01/Nov/23
2 Amphitheatre 01/May/23
3 STP 01/May/23
4 UG Tank 01/Jul/23
5 Electrical Substation 01/Jul/23

You might also like