Annexure - A 28
PROCEDURE TO GRANT LICENSE
Receiving Application
Evaluation
If requested by the
applicant, issue a no
1 week* objection letter
Request Commission approval to publish the intention
of granting a license in the newspapers
*if the applicant is failed to
provide all the required
information as specified in
the application, this
1 month
process takes more than 1
Receiving Commission approval and ratification to week.
publish the intention of granting a license and
publishing paper notice for representations (28 days will
be given to make any representations)
If any representation is raised,
1 month those have to be clarified from
relevant authorities before
If there are no representations, then request request commission approval,
Commission approval to grant the license which may takes another 2-3
weeks
Obtain physical progress and the current status of the
project from the applicant
1 month
Receiving Commission approval and ratification to grant
the license and requesting Minister’s concurrence to
grant license
3 weeks
Receive Minister’s concurrence to grant license
1 week Granting the license
1 week
Publish in the gazette