Sewer Network Quality Manual
Sewer Network Quality Manual
Ltd and Yueyang Construction Engineering Group Co, Ltd Quality Control Manual
Quality Assurance
&Quality Control Plan
Construction of Kitime Sub-Catchment Primary, Secondary and Tertiary Sewer Network Construction – Lot I
1/26
JV CGCOC Group Co.Ltd and Yueyang Construction Engineering Group Co, Ltd Quality Control Manual
Contents
1 INTRODUCTION 4
2 REFERENCES 4
Construction of Kitime Sub-Catchment Primary, Secondary and Tertiary Sewer Network Construction – Lot I
2/26
JV CGCOC Group Co.Ltd and Yueyang Construction Engineering Group Co, Ltd Quality Control Manual
6 ANNEX 26
Construction of Kitime Sub-Catchment Primary, Secondary and Tertiary Sewer Network Construction – Lot I
3/26
JV CGCOC Group Co.Ltd and Yueyang Construction Engineering Group Co, Ltd Quality Control Manual
1 Introduction
This Quality Management System (QMS) defines the Management System that shall be applied by
JV CGCOC Group Co. Ltd and Yueyang Construction Engineering Group Co, Ltd Construction
and it is the Project’s main reference for all quality matters including objectives and targets set by
JV CGCOC Group Co. Ltd and Yueyang Construction Engineering Group Co, Ltd Construction
Management as well as the Employer.
In definition of the above statement, this QMP encompasses the Quality Management System, for
all Unique Construction’s activities for this project, which refers to or establishes procedures to
control and manage the various activities that may have an impact on product quality.
2 References
In this document as well as the attachments that must be read with this document the following
documents should be referred to:
Contractor’s Environmental & Social Management Plan (CESMP)
Health and Safety Management Plan (HSMP)
Traffic Control Plan (TCP)
Technical Specifications
BS British Standard
EN European Norm
PM Project Manager
SE Site Engineer
Construction of Kitime Sub-Catchment Primary, Secondary and Tertiary Sewer Network Construction – Lot I
4/26
JV CGCOC Group Co.Ltd and Yueyang Construction Engineering Group Co, Ltd Quality Control Manual
FM Foreman
RE Resident Engineer
The Project Manager reports directly to the Head Office and is responsible for:
Ensure key external and internal drivers are incorporated into strategy and reviewed
Ensure maintenance of standards
Preparing short and long term plans for contract management
Prevention of value destruction, ensuring that the contract are managed efficiently
and effectively, and sustainably.
Championing business and process improvements at all levels
Control and balancing of resources used and expenditures of the company
Develop and implement procedures for contract management and administration in
compliance with company policy.
Apply best practices for the project management and execution and develop tools
accordingly.
Assistant of PM
The APM reports to the Project Manager and is responsible for:
Management of Quality Assurance control
To make sure that all relevant construction Site engineer know what paperwork needs
to be done and also what controls (hold points etc.) are needed to be adhered to;
Construction of Kitime Sub-Catchment Primary, Secondary and Tertiary Sewer Network Construction – Lot I
5/26
JV CGCOC Group Co.Ltd and Yueyang Construction Engineering Group Co, Ltd Quality Control Manual
Site Engineer
The SE reports to the Assistant of Project Manager and is responsible for:
Management of Quality / Document Controller on site;
Completion of Inspection Test Requests and other test requests and handing in to
Document Controller Office;
To make sure that all relevant construction personnel know what paperwork needs to
be done and also what controls (hold points etc.) are needed to be adhered to;
To Record Employer inspections;
To do all relevant paperwork and file in data packs for handover to the Employer
when required;
To resubmit test request when failure occurs;
Control and Monitor corrective and preventive action requests;
Making sure that the NCR’s are closed in a reasonable time
Foreman (FM)
Foreman will report to the relevant Engineer
To ensure that the works area is ready for inspection by RE;
Conduct visual inspections of works with RE;
Ensure that Surveyor checks levels where applicable;
To review non-conformances for corrective / preventive actions to prevent recurrence
and also to make sure that mistakes/problems are recorded and repaired to the Employer’s
satisfaction. This will prevent rework as the Employer will not have any reservations about the
corrections;
Construction of Kitime Sub-Catchment Primary, Secondary and Tertiary Sewer Network Construction – Lot I
6/26
JV CGCOC Group Co.Ltd and Yueyang Construction Engineering Group Co, Ltd Quality Control Manual
Construction of Kitime Sub-Catchment Primary, Secondary and Tertiary Sewer Network Construction – Lot I
7/26
JV CGCOC Group Co.Ltd and Yueyang Construction Engineering Group Co, Ltd Quality Control Manual
Work towards the objective for more female employment in all job categories.
Monitor monthly targets for equal employment.
Prepare and submit on a monthly basis the labour returns
Work towards and ensure that hygienic conditions on site is of a high standard and
are being maintained.
Arise awareness with JV CGCOC Group Co. Ltd and Yueyang Construction Engineering
Group Co, Ltd and Ethiopia law regarding the No Human Traffic and Child Labor policies.
Construction of Kitime Sub-Catchment Primary, Secondary and Tertiary Sewer Network Construction – Lot I
8/26
JV CGCOC Group Co.Ltd and Yueyang Construction Engineering Group Co, Ltd Quality Control Manual
Organizational Chart
Director General of Overseas
Ltd.
General Manager of
Project Manager
Deputy Project
Manager
Office Engineering Construction Engineer Material /Quality Contract & Project Administrative and Environmental, Plant and
Safety
Quantity Surveyor Site Engineer Material Inspector Contract Casher Health and safety Mechanical Engineer
Administrator officer
Office Engineers Earth work foreman Laboratory Accountant Gender Officer Electrical Engineer
Technicians
Assistance Surveyors
Chainman
Construction of Kitime Sub-Catchment Primary, Secondary and Tertiary Sewer Network Construction – Lot I
9/26
JV CGCOC Group Co.Ltd and Yueyang Construction Engineering Group Co, Ltd Quality Control Manual
Construction of Kitime Sub-Catchment Primary, Secondary and Tertiary Sewer Network Construction – Lot I
10/26
JV CGCOC Group Co.Ltd and Yueyang Construction Engineering Group Co, Ltd Quality Control Manual
No. Project
Responsibility Duties Authority Availability
1 Quality Manager Deputy Director General Office manager Technical Part Time
Director
2 Quality Assurance Manager (QAO) Project Manager Professional Engineer Full Time
3 Assistant Quality Assurance Officer Deputy Project Manager Professional Engineer Full Time
(AQAO)
4 Quality Control Manager Material Engineer Professional Engineer Full Time
5 Quality Control officer Material Inspector Engineer Full Time
6 Quality control Executor All Foreman Technologist Full Time
7 S H E Compliance Officer SHE Expert do all SHE QC functions Environmental Management Full Time
8 Quality Controller (Mechanical Engineer) Do all mechanical QC functions Technologist Part Time
9 Quality Controller (Electrical engineer) Do all electrical QC functions Professional Technologist Part Time
The main team will carry out their functions with support from the following members who are located in Lusaka or Outside of Country.
Construction of Kitime Sub-Catchment Primary, Secondary and Tertiary Sewer Network Construction – Lot I
11/26
JV CGCOC Group Co.Ltd and Yueyang Construction Engineering Group Co, Ltd Quality Control Manual
The Contractor will supply the Engineer as well as the QA/QC with copies of all the
As far as possible, copies of the relevant specification will be included in the QCP for
In the absence of a referred standard or code the Contractor will submit another
international code or standard and will demonstrate the suitability and equivalence
Work at all times will comply with the minimum standard of quality of materials
and workmanship set by the designated Standard or Code and to the performance
The contract will be executed in compliance with the below listed directives and
compiled with if they are stricter or specify higher quality than the specifications or
Standards indicated in further sections of this specification are valid for design,
similar standards for the same subject, the priority of the standards will be as
follows:
EN
BS
DIN
ASTM
Construction of Kitime Sub-Catchment Primary, Secondary and Tertiary Sewer Network Construction – Lot I
12/26
JV CGCOC Group Co.Ltd and Yueyang Construction Engineering Group Co, Ltd Quality Control Manual
Earthworks;
EN 124: Gully tops and manhole tops for vehicular and pedestrian areas
management;
outside buildings;
reinforced;
Construction of Kitime Sub-Catchment Primary, Secondary and Tertiary Sewer Network Construction – Lot I
13/26
JV CGCOC Group Co.Ltd and Yueyang Construction Engineering Group Co, Ltd Quality Control Manual
characteristics;
Construction of Kitime Sub-Catchment Primary, Secondary and Tertiary Sewer Network Construction – Lot I
14/26
JV CGCOC Group Co.Ltd and Yueyang Construction Engineering Group Co, Ltd Quality Control Manual
ISO 12162: Thermoplastic materials for pipes and fittings for pressure
ISO 25780: Plastics piping systems for pressure and non-pressure water
jacking techniques;
aggregates.
Construction of Kitime Sub-Catchment Primary, Secondary and Tertiary Sewer Network Construction – Lot I
15/26
JV CGCOC Group Co.Ltd and Yueyang Construction Engineering Group Co, Ltd Quality Control Manual
EN 197: Cement
EN 1008: Mixing water for concrete – Specification for sampling, testing and
containing structures;
EN 10080: Steel for the reinforcement of concrete. Weld able reinforcing steel;
commercial specifications;
Quality of Materials
All permanent materials using for this project should tested and get approved before
ordering. All materials will conform to the prescribed standards and specifications in
16/26
JV CGCOC Group Co.Ltd and Yueyang Construction Engineering Group Co, Ltd Quality Control Manual
The Contractor will maintain control over procurement and manufacturing sources
to ensure that all products and services conform to the specified requirements.
All installations will comply fully with the manufacturer’s installation and operation
Documents, the contractor will through the Engineer propose a solution which will
QA/QC testing will be conducted for each of the major items under construction.
Materials testing.
Storage on site
Pipe works – uPVC, PP, HDPE– welding, fittings and pressure testing;
Testing Services
(a) Tests on material proposed for the works will be the responsibility of UNIK who
will submit these results through the QAO to the Engineer for approval. Acceptance
from the Engineer of the laboratory service to be used will be obtained. The cost of
Construction of Kitime Sub-Catchment Primary, Secondary and Tertiary Sewer Network Construction – Lot I
17/26
JV CGCOC Group Co.Ltd and Yueyang Construction Engineering Group Co, Ltd Quality Control Manual
(a)The contractor shall establish, equip and maintain the QA/QC laboratory.
QA/QC quality control tests will be performed in the site laboratory as applicable.
CGCOC provides staff, they shall be managed by the named QA/QC agency. It was
agreed that the contractor would provide in their employment two suitably
of the QAO.
(c)QA/QC shall be responsible for the delivery of test samples to the field
laboratory.
Submittals
The contractor will submit QA/QC documentation Pre and Post the construction of
all activities. All Documentation will be submitted using a Transmittal form and will
All original documents will be kept at the site office of the contractor, Copy’s will be
The contractor will prior to all construction activities submit the relevant Method
o List of Material
Construction of Kitime Sub-Catchment Primary, Secondary and Tertiary Sewer Network Construction – Lot I
18/26
JV CGCOC Group Co.Ltd and Yueyang Construction Engineering Group Co, Ltd Quality Control Manual
7. Risk assessments
Construction Submittals
The contractor will during construction activities submit the relevant inspection
2. As Built Recordings
1. Completion Reports
2. Commissioning plans
4. As Built Drawings
7. Test results
Construction of Kitime Sub-Catchment Primary, Secondary and Tertiary Sewer Network Construction – Lot I
19/26
JV CGCOC Group Co.Ltd and Yueyang Construction Engineering Group Co, Ltd Quality Control Manual
No response from
Eng
Send Reminder
to Engineer Execute work as per
Site Instruction
Document Review
Documentation Control
All documents will be kept at the QCM to ensure a local point of origin and
A comprehensive register of the following documents but not limited to will be kept
on site:
Site instructions;
VO’s;
NCR’s.
Construction of Kitime Sub-Catchment Primary, Secondary and Tertiary Sewer Network Construction – Lot I
20/26
JV CGCOC Group Co.Ltd and Yueyang Construction Engineering Group Co, Ltd Quality Control Manual
Outgoing
Incoming
Documents
Documents
Document control/
QAM assign
reference and add
to document
register
PM evaluate and
assign to relevant
recipients
Drawings
All Drawings received on site shall be registered by QCM in the Drawing Register
The QCM will dispatch copies of the master drawings and these drawings will be
marked “controlled Copy”. Each recipient to sign on the transmittal note as proof of
receipt.
The data pack will be assembled and kept up to date by the QCM and will be
One set of Data Packs will be handed over to the Employer on completion of the
contract.
Meetings
Community meetings
Prior to the start of work in any area a meeting with the leaders in the area will be
conducted. During the meeting the following will be conveyed to the community
leaders:
Community Involvement
Community safety
Construction of Kitime Sub-Catchment Primary, Secondary and Tertiary Sewer Network Construction – Lot I
21/26
JV CGCOC Group Co.Ltd and Yueyang Construction Engineering Group Co, Ltd Quality Control Manual
Progress meeting
Weekly
Weekly progress meetings will be held on site with the Site personnel.
Monthly
Monthly progress meetings will be held between the employer and the contractor.
Safety Meetings
Safety meetings will be held weekly with representatives from the local workers as
Quality meetings
Quality meetings will be held weekly between management of the contractor and
Recording of Meetings
All meetings held for Quality Safety and progress will be recorded.
Flow Chart for Detection of Deviations
De te ction of De te ction of
de via tion by the de via tion by the
Engine e r Contra ctor
Re port the
Notifica tion to
De via tion if
the contra ctor
ne ce sa ry issue
by the Engine e r
NCR
Corre ctive
proposa l by
Contra ctor
(Me thod
sta te me nt)
Approva l of
propose d
core ctive a ction
by the Engine e r
Ex e cution of the
corre ctive
a ction
Construction of Kitime Sub-Catchment Primary, Secondary and Tertiary Sewer Network Construction – Lot I
22/26
JV CGCOC Group Co.Ltd and Yueyang Construction Engineering Group Co, Ltd Quality Control Manual
Procurement
Overall responsibilities for the procurement for the project lies with the procurement
Should there be any deviation this deviation will be communicated to the engineer
prior to procurement.
Construction Aspects
Bench Marks and Survey Beacons
The preservation of bench marks will be the sole responsibility of the contractor.
Road Crossings
All road crossings will be done in accordance with the traffic control plan. Prior to
documentation concerning the road crossing. This documentation will consist of the
following:
After completion of the crossing the repair work to the crossing will be done within
Off-Site Inspection
Where required as per the project specification, specifically for pipes and equipment,
Preparatory Inspection
Before the start of any major activity a meeting will be held between the contractor
and the Engineer as to agree on the required documentation with this meeting and
Specific Drawings
Construction of Kitime Sub-Catchment Primary, Secondary and Tertiary Sewer Network Construction – Lot I
23/26
JV CGCOC Group Co.Ltd and Yueyang Construction Engineering Group Co, Ltd Quality Control Manual
On-Site Testing
Prior to the start of the any work pre-construction photos will be taken of the
A quality representative shall be on site to do sand bedding, soil and backfilling test
and collect the cube samples for destructive concrete testing. Results from these test
will be issued to the QCM for review. All tests on and off site will be performed as
Engineers inspection
On completion of tests done by the contractor and approval by the engineer the
original test results will be included in the data pack for final hand over.
Rejection of work
Should a test fail on any work or product that work or product will be rejected?
Where applicable to work that has been rejected, a NCR will be issued. If the product
failed, this product will be clearly marked and quarantined. If the QCP were not
Before the start of each major activity the following procedures will be followed:
The Contractor will notify the QAO and the Engineer at least 48 hours before
be conducted between contractor and QA/QC to plan and agree QCP’s and
which shall address how work will be performed, safety issues, schedule,
etc.
Construction of Kitime Sub-Catchment Primary, Secondary and Tertiary Sewer Network Construction – Lot I
24/26
JV CGCOC Group Co.Ltd and Yueyang Construction Engineering Group Co, Ltd Quality Control Manual
activity. Assure QA/QC inspections and testing are coordinated with construction
Before the start of a defined activity, all aspects documented during the
followed:
Check safety compliance and possible upgrade of safety program and activity
Officer Schedules.
Follow up Inspection
requirements.
The QA/QC and the Engineer shall conduct a final inspection of all stages of
construction work.
Construction of Kitime Sub-Catchment Primary, Secondary and Tertiary Sewer Network Construction – Lot I
25/26
JV CGCOC Group Co.Ltd and Yueyang Construction Engineering Group Co, Ltd Quality Control Manual
6 Annex
Construction of Kitime Sub-Catchment Primary, Secondary and Tertiary Sewer Network Construction – Lot I