BOQ For 2 Storied Building
BOQ For 2 Storied Building
Tender No: 01
Component: 2-Story Administration Building and a Guardhouse
Original Issue: November 07, 2010
Pos. Description of Work/Items Project Schedules Ref. Unit Quantity Unit Cost Total Cost
1. General
1.1 Preliminaries 1.1 Occupied Areas, 1.1 Existing
Services Schedule and 1.1 Items
to be supplied schedules
2. Site
2.0 Deal with Graves 2.1 Identified hazardous materials
and 2.3 Earthwork schedules
1/12
Currency: US Dollars
Tender No: 01
Component: 2-Story Administration Building and a Guardhouse
Original Issue: November 07, 2010
Pos. Description of Work/Items Project Schedules Ref. Unit Quantity Unit Cost Total Cost
6 Soil backfilling on and around foundation septic
tank up to ground level. This includes supplying
of needed materials. See drawings and
schedules for levels/dimensions and details.
CU.M 45.00 -
7 Soil backfilling on and around foundation of
guard room up to ground level. This includes
supplying of needed materials. See drawings
and schedules for levels/dimensions and details.
CU.M 10.00 -
8 Gravel compaction, Class 2, at any places
shown for main building foundations, floors and
its sidewalk/ramp. The cost includes leveling
and compaction of ground surface, and
supplying of needed materials and its
compaction. See drawing and project schedules
for dimensions and details.
CU.M 43.00 -
9 Gravel compaction, Class 2, for entire
parking/walkway areas at the yard. The cost
includes leveling and compaction of ground
surface, and supplying of needed materials and
its compaction. See drawing and project
schedules for dimensions and details.
CU.M 30.00 -
10 Gravel compaction, Class 2, for septic tank. The
cost includes leveling and compaction of ground
surface, and supplying of needed materials and
its compaction. See drawing and project
schedules for dimensions and details.
CU.M 15.00 -
11 Gravel compaction, Class 2, for guard room.
The cost includes leveling and compaction of
ground surface, and supplying of needed
materials and its compaction. See drawing and
project schedules for dimensions and details.
CU.M 12.00 -
2.4 Service Trenching 2.1 Identified hazardous materials,
2.1 Salvaged Materials for Re-use
and 2.3 Earthwork schedules
3. Structure
3.1 Concrete-General 3.1 Non reinforced concrete, 3.1
Reinforced concrete and 3.2
Concrete- Integral Finishes
schedules
NOTE: Cost for concrete items in this section includes
reinforcement, steel anchorage embedded in
concrete, shuttering, concrete, concrete curing and all
to the complete job.
2/12
Currency: US Dollars
Tender No: 01
Component: 2-Story Administration Building and a Guardhouse
Original Issue: November 07, 2010
Pos. Description of Work/Items Project Schedules Ref. Unit Quantity Unit Cost Total Cost
2 RCC (20 Mpa) at the foundtions of 2-story main
building. The quantity includes RCC at
foundations and tie beams under the ground. CU.M 18.00 -
3 RCC (20 Mpa) at the columns of first story of
main building. CU.M 13.00 -
4 RCC (20 Mpa) at the columns of second story of
main building. CU.M 11.00 -
5 RCC (20 Mpa) at the beams of first story of main
building. CU.M 10.00 -
6 RCC (20 Mpa) at the beams of second story of
main building. CU.M 10.00 -
7 RCC (20 Mpa) at the slabs of first story of main
building. CU.M 20.00 -
8 RCC (20 Mpa) at the slabs of second story of
main building. CU.M 19.00 -
9 RCC (20 Mpa) at the RCC stair case inside
main building. CU.M 4.00 -
10 RCC (20 Mpa) at the parapet of main building.
CU.M 4.00 -
11 RCC (20 Mpa) at the entire guard room. The
quantity includes RCC at foundations, floors,
columns, beams, ring beams, lintels, etc. CU.M 6.00 -
12 RCC (20 Mpa) at entire septic tank and its
manhole. The cost for RCCs here includes wall
mounted fixed ladder inside the septic tank as
well. CU.M 15.00 -
13 PCC (20 Mpa) at the floors, roofs, side walks,
ramps, window sills, kerbs, PCC pavements,
flowerpots, septic tank, yard, and any other
places shown as PCC in the drawings for main
building, guard room and the septic tank.
CU.M 63.00 -
3.5 Brickwork 3.5 Brickwork construction
schedule
1 Second Class Brick masonry with mortar for
main building. This includes all brick walls/ brick
masonry in the entire building. CU.M 110.00 -
2 Second Class Brick masonry with mortar for
guard room. This includes all brick walls/ brick
masonry in the entire building. CU.M 18.00 -
3.6 Stonework
1 Stone masonry with mortar at the foundations
and/or any places shown in the drawings for
main building. See drawing and schedule for
details. CU.M 50.00 -
2 Stone masonry with mortar at the foundations
and/or any places shown in the drawings for
guard room. See drawing and schedule for
details. CU.M 13.00 -
3.10 Concrete Unit Masonry 3.10 Concrete Unit Masonry
4. Enclosure
4.1 Waterproofing 4.1 Waterproofing system schedule
3/12
Currency: US Dollars
Tender No: 01
Component: 2-Story Administration Building and a Guardhouse
Original Issue: November 07, 2010
Pos. Description of Work/Items Project Schedules Ref. Unit Quantity Unit Cost Total Cost
1 Single layer bitumen membrane (Isogam) at the
floor and walls of toilets/kitchen and at the
ground floors of main building and as well as
guard room. This includes preparation of base
layers shown on the drawings. Refer to
schedule/drawing for details.
SQ.M 255.00 -
4.2 Roofing 4.2 Roofing materials, and 4.2
Gutter and Down pipe Schedules
1 Flat roof for the main building. The cost for this
item includes all roof layers shown such as rigid
foam insulation layer, brick powder layer, PCC
beneath Isogam layer, Isogam layer and the
protective PCC layer on the Isogam. See
drawings for details. The cost also includes
Isogam and flashings needed for the parapet
around the roof.
SQ.M 160.00 -
2 GI corrugated roof for water tank enclosure on
the roof of the building. The cost for this item
includes all roof layers such as GI sheet, steel
profiles for purlins, steel C-shape channels as
the supporting members, mineral wool layer and
the steel mesh supporting the mineral wool
layer, and as well as all needed materials and
accessories required for complete installation of
a functioning roof.
SQ.M 10.00 -
3 GI flat K-span roof for guard room. The cost for
this item includes all roof layers such as GI
sheet standing seam and mineral wool
insulation layer and all needed materials,
accessories, connections required for complete
installation of a functioning roof.
SQ.M 51.00 -
4 Down pipes, PVC pipe class-B. This includes all
accessories such as over flow and stuff-holder
required for complete installation such as
supplying, fixing and others as per drawing and
schedules.
Lin M 40.00 -
4.3 Windows and Window Hardware 4.3 Window, 4.3 Window
Hardware, 4.5 Annealed Glasses,
and 4.6 Glassblock work
schedules
NOTE: Prior to work, samples must be approved by
UNOPS Engineer.
4/12
Currency: US Dollars
Tender No: 01
Component: 2-Story Administration Building and a Guardhouse
Original Issue: November 07, 2010
Pos. Description of Work/Items Project Schedules Ref. Unit Quantity Unit Cost Total Cost
NOTE: Cost for steel related items in this section
includes supplying materials, accessories,
connections, welding, any works, painting according
to the schedules and specifications for steel member
painting, which is at least on coat of anti-rust followed
by 2 other coats of oil-based painting for all surfaces.
SQ.M 0.80 -
4 Steel doors [the access way to the roof of main
building] plus steel type fixed ladder at first floor
hall. The work and the cost includes
construction and complete installation of inner
steel door to the ceiling of the first floor, and
installation of outer steel plate pane at the roof,
and as well as wall mounted steel ladder as
shown. The cost also includes all
hardware/accessories/works/materials needed
to a complete and functioning job. The cost also
includes one coat anti-rust followed by 2 other
coats of oil-based painting to all non-galvanized
steel surfaces as per given specs and full
satisfaction of UNOPS engineer.
LS 1.00 -
4.5 Glazing 4.5 Mirrors schedules
5. Interior
5.4 Suspended Ceiling 5.4 Suspended Ceiling Schedule
5/12
Currency: US Dollars
Tender No: 01
Component: 2-Story Administration Building and a Guardhouse
Original Issue: November 07, 2010
Pos. Description of Work/Items Project Schedules Ref. Unit Quantity Unit Cost Total Cost
2 Aluminum frame with 60x60 gypsum board
suspended ceiling for guard room. The cost
includes fixings, accessories, materials, works,
etc for a complete job to the full satisfaction of
Engineer.
SQ M 28.00 -
5.5 Joinery 5.5 Joinery fixtures schedule
LS 1.00 -
4 Wooden frame, MDF finish, floor mounted
cupboard at the kitchen for guard room. See
drawings for details. The cost includes making,
installation, framing, finish, hardware, stone
table top, splash back, 3 coats oil-based
painting and all to the complete job.
LS 1.00 -
5.6 Metalwork 5.6 Metal Fixtures Schedule
Lin M 8.00 -
3 Metal guardrails at stair's landing for main
building. This includes any needed work for
complete installation and also includes painting
as per schedule and specification for metallic
surface painting. See drawing for details.
Lin M 2.20 -
4 Metal handrails, balustrades, infill and moldings
to concrete for ramp. This includes any needed
work for complete installation and also includes
painting as per schedule and specification for
metallic surface painting. See drawing for
details.
Lin M 11.00 -
5 Toilet roll holders for main building and guard
room. This also includes installation. No 7.00 -
6 Grab rail for handicap toilet. One complete set.
This includes supplying and complete
installation. LS 1.00 -
6/12
Currency: US Dollars
Tender No: 01
Component: 2-Story Administration Building and a Guardhouse
Original Issue: November 07, 2010
Pos. Description of Work/Items Project Schedules Ref. Unit Quantity Unit Cost Total Cost
7 Soap dishes for main building and guard room.
This also includes installation. No 7.00 -
5.8 Fire Extinguishers and Blankets 5.8 Fire Extinguishers Schedule
1 Extinguishers at main building and guard room,
wall mounted, powder-type (9kg). No 3.00 -
Subtotal Interior
-
6. Finish
6.1 Plastering 6.1 Plastering Schedule
7/12
Currency: US Dollars
Tender No: 01
Component: 2-Story Administration Building and a Guardhouse
Original Issue: November 07, 2010
Pos. Description of Work/Items Project Schedules Ref. Unit Quantity Unit Cost Total Cost
Internal surfaces
SQ.M 1,450.00 -
2 Flat water based: Interior, on all surfaces that
receive cement plaster for guard room. The cost
includes wall putty (gypsum filling) layer before
painting and all needed preparation of the
surfaces for painting. See schedule for detail on
this paint system
SQ.M 105.00 -
External surfaces
SQ.M 490.00 -
4 Flat water based: Exterior, on all surfaces that
receive cement plaster for guard room. The cost
includes wall putty (gypsum filling) layer before
painting and all needed preparation of the
surfaces for painting. See schedule for detail on
this paint system
SQ.M 95.00 -
Subtotal Finishes
-
8. Water Services
8.1 Water Services 8.1 Water services samples, 8.1
Water system piping, 8.1 Sanitary
fixtures, 8.1 Water heater
schedules and 8.1 Water Services
Testing schedules
8/12
Currency: US Dollars
Tender No: 01
Component: 2-Story Administration Building and a Guardhouse
Original Issue: November 07, 2010
Pos. Description of Work/Items Project Schedules Ref. Unit Quantity Unit Cost Total Cost
8 Damp proof Insulation rubber tape for all GI
Piping. Lin M 200.00 -
9 Water supply inspection manhole less than
1200mm deep. This includes excavation and
any needed work to make the manhole as per
drawings and schedule. No 1.00 -
Sanitation Piping
9/12
Currency: US Dollars
Tender No: 01
Component: 2-Story Administration Building and a Guardhouse
Original Issue: November 07, 2010
Pos. Description of Work/Items Project Schedules Ref. Unit Quantity Unit Cost Total Cost
31 Service Sink, including supply and installation.
No 2.00 -
32 Electrical water boiler with capacity of 50 Liter,
including supply and installation. No 3.00 -
33 Electrical water boiler with capacity of 30 Liter,
including supply and installation. No 2.00 -
34 PVC Reservoir capacity of 2000 Liter, including
supply and installation. No 1.00 -
35 Grease Trap less than 1200mm deep. This
includes excavation and any needed work to
make the manhole according to the drawings
and schedules. No 2.00 -
Tube well:
Borehole
No 1.00 -
Subtotal Water Services
-
9. Electrical Services
10/12
Currency: US Dollars
Tender No: 01
Component: 2-Story Administration Building and a Guardhouse
Original Issue: November 07, 2010
Pos. Description of Work/Items Project Schedules Ref. Unit Quantity Unit Cost Total Cost
9.1 Electrical Services 9.1 Electrical systems, 9.1
Electrical supply mains, 9.1
Electrical switchboard design, 9.1
Main 380VAC Distribution System,
9.1 Panel Construction, 9.1 Power
accessories, 9.1 Lighting control
and fittings, 9.1 Fire Detection
Equipment Schedule Schedules
and the Attachments
11/12
Currency: US Dollars
Tender No: 01
Component: 2-Story Administration Building and a Guardhouse
Original Issue: November 07, 2010
Pos. Description of Work/Items Project Schedules Ref. Unit Quantity Unit Cost Total Cost
16 2(1C x 2.5mm²) + 2.5mm² GND wires pulled in
PVC conduit, assorted colors as per phase
requirement RST/UVW, white color is for neutral
and green color for grounding, the duct should
not be filled more than 50%.
Lin M 260.00 -
Fittings/Fixtures
12/12